Inter-Company STO: STO with SD with Delivery and with Billing Supplying Vendor: DC01 ( Plant) Receiving Plant: INC1 1) Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME--->PO---> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure, In Customer Master, sales Area Tab: you are maintaining shipping condition) 1

STO process with config 5th method

Embed Size (px)

Citation preview

Page 1: STO  process with config 5th method

Inter-Company STO: STO with SD with Delivery and with Billing

Supplying Vendor: DC01 ( Plant)Receiving Plant: INC1

1) Create one Customer Master in XD01 with respect to Supplying Plant Sales Area and assign this Customer no with Receiving Plant in OLME--->PO---> set up STO->Define shipping data for plant and for the supplying Plant assign the above sales area.( Make sure, In Customer Master, sales Area Tab: you are maintaining shipping condition)

1

Page 2: STO  process with config 5th method

In Customer Master:

2

Page 3: STO  process with config 5th method

2) OLME--->PO---> Set up STO------> Assign Delivery Type and Checking Rule For your supplying plant assign document type NB, Delivery type NLCC and Checking Rule RP or ZS

3) Assign Document Type, One-Step Procedure, Underdelivery ToleranceThen For your supplying Plant and receiving Plant assign Document type NB

3

Page 4: STO  process with config 5th method

3) Make sure you are maintaining Sales View for the material at supplying Plant and in Sales /Gen plant Data view maintain Availability check, Loading group and Transportation group.

4) In SPRO---->Logistics execution----> Shipping--->Basic shipping functions--->Shipping point Determination---->assign shipping points---> For your Loading group, Shipping Condition and Supplying plant combination, Assign shipping point these are the configuration settings you have to do in background.

4

Page 5: STO  process with config 5th method

5) For Receiving Plant Pur. Org and Co.Code Combination create Vendor master in XK01 and in this vendor master assign the Supplying plant in Pur.Org.Data screen--->Extras----> Add.Pur.data

5

Page 6: STO  process with config 5th method

Now create STO: NB

Process:

1. PR2. PO with Document type NB, Vendor as supplying Plant…

shipping tab will appear in item level3. Send PO to Supplying Plant4. Create outbound Delivery using VL10D/VL10B (Purchase

order history will created & Outbound delivery will update)5. Do Post Goods Issue(PGI) using VL02N. System will create

a Material Document with 643 Movement type.6. Create Billing Using VF01 w.r.t outbound delivery

document7. Do GR using MIGO…Goods Receipt w.r.t Outbound

Delivery number. 101 will trigger8. MIRO for both Material & delivery cost.