VIVENCIO B. PACHOROPosition Desired: QC Civil Inspector
Email Address: [email protected]
Mobile No. : +97455240653/+97455129440
Home Contact No. : +6324777643
Address: 42 Sta.Rosa Street Barangay Kapitolyo
Pasig City Philippine
Key Qualifications:
Fourteen ( 14 ) years of combined experience in Civil Engineering and Construction. Almost eight ( 8 ) years in QA/QC and six ( 6 ) years in construction supervision. Involved in Gas to Liquid Project in Qatar Shell, both Early Site Works ( ESW ) and Main Works for Barzan Onshore Project Qatar, Vertical and Horizontal Projects such as Residential, Roads, Land Development, Gasoline Stations and Oil Refinery at Philippine.
Nationality: Filipino
Date Of Birth: May 04, 1980
Educational Attainment: Bachelor of Science in Civil Engineering (1997 to 2002)
School Graduated: Polytechnic University of the Philippines Manila
Work Experience:
March 2016 – Present: QC Civil Inspector
Consolidated Contractors Group ( Offshore )/
Teyseer Contracting Company JV
Doha, Qatar
Project: Water Mega Reservoir Project A
Duties and Responsibilities:
- Maintain a frequent technical inspection to all civil and building works, piling works ( macro piles and micro piles ), testing, earthworks and waterproofing
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Ensure that the works is carried out according to approved Inspection Test Plan and method statements.
- Maintain site diary, labor plans and other records.
- Maintain coordination between the contractors in charge
- Monitor the work progress of all parts of the project in all trades and submit report to the QC Engineer
- Inspect Contractors Resources and manpower on site
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
- Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
October 2011 to March 2016: QC Civil Inspector
Consolidated Contractors Group ( Offshore ) /
Teyseer Contracting Company JV
Doha, Qatar
Project: Barzan Onshore Project
RasLaffan Industrial City, Qatar
Duties and Responsibilities:
- Maintain a frequent technical inspection to all civil and building works, bored piling works, testing, earthworks, waterproofing, fireproofing, grouting, leak test and system test for underground pipes, pavement works and asphalt works.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Ensure that the works is carried out according to approved Inspection Test Plan and method statements.
- Maintain site diary, labor plans and other records.
- Maintain coordination between the contractors in charge
- Monitor the work progress of all parts of the project in all trades and submit report to the QC Engineer
- Inspect Contractors Resources and manpower on site
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
July 2010 to September 2011: QC Civil Inspector
Consolidated Contractors Group ( Offshore ) /
Teyseer Contracting Company JV
Doha, Qatar
Project: Early Site Works Barzan Onshore Project
RasLaffan Industrial City, Qatar
Duties and Responsibilities:
- Maintain a frequent technical inspection to all civil, testing, earthworks, groutingand asphalt works.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Ensure that the works is carried out according to approved Inspection Test Plan and method statements.
- Maintain site diary, labor plans and other records.
- Maintain coordination between the contractors in charge
- Monitor the work progress of all parts of the project in all trades and submit report to the QC Engineer
- Inspect Contractors Resources and manpower on site
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
July 2008 to June 2010: QC Civil Inspector
Consolidated Contractors Group ( Offshore ) /
Teyseer Contracting Company JV
Doha, Qatar
Project: Qatar Shell Gas To Liquid Project ( GTL )
RasLaffan Industrial City, Qatar
Duties and Responsibilities:
- Maintain a frequent technical inspection to all Precast, civil and building works, testing, earthworks, waterproofing, fireproofing, grouting, leak test for manholes and underground pipes, pavement works and asphalt works.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Ensure that the works is carried out according to approved Inspection Test Plan and method statements.
- Maintain site diary, labor plans and other records.
- Maintain coordination between the contractors in charge
- Monitor the work progress of all parts of the project in all trades and submit report to the QC Engineer
- Inspect Contractors Resources and manpower on site
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
February 2008 to June 2008: Site Engineer
Jeff James Incorporated
Binangonan, Rizal Philippine
Project: -British Embassy Building Project ( Steel Structure ) at
Taguig Metro Manila, Philippine
-St. Lukes Medical Center( Steel Structure ) at
Bonifacio Global City, Philippine
Duties and Responsibilities:
- Ensuring the works was done according to plans and scheduled time frame
- On site management and supervision
- Keep a site diary recording significant events, verbal instruction, telephone conversations and weather conditions
- Arrange minor design modification and corrections
- Remind the Construction Manager of monthly reports, reports action taken and instruction received
- Attend to correspondence as delegated by the Construction Manager
- Bring to Construction Manager attention any outstanding matter or unanswered correspondence
- Supervise in the fabrication and installation of steel structure accessories
- Supervision of structural works, layout, foundation
- Prepares material procurements needed
- Coordinates, prepares and present daily scheduled reports. Coordinates fieldworks, project controls, monitoringand conducting QA/QC Inspection.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Maintain site diary, labor plans and other records.
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
June 2007 to January 2008: Site Engineer
Savona States Inc.
Alabang, Muntinlupa Philippine
Project: -Roads and Drainage System of Savona State Village at
Barangay MabatoBatangas
Duties and Responsibilities:
- Ensuring the works was done according to plans and scheduled time frame
- Review plans for modification of existing structures prior to construction of the new drainage system
- On site management and supervision
- Keep a site diary recording significant events, verbal instruction, telephone conversations and weather conditions
- Supervise with surveyor team for layouting
- Remind the Construction Manager of monthly reports, reports action taken and instruction received
- Attend to correspondence as delegated by the Construction Manager
- Bring to Construction Manager attention any outstanding matter or unanswered correspondence
- Supervise and check road preparations ( earthworks,
Sub-grade, sub-base )
- Supervision of Asphalt laying
- Prepares plans for grading operations as related to heavy equipments, haul distances and access roads to quarries.
- Prepares realistic and achievable schedules
- Preparing scope of works including detailed work breakdown for different structures.
- Prepares material procurements needed
- Coordinates, prepares and present daily scheduled reports. Coordinates fieldworks, project controls, monitoringand conducting QA/QC Inspection.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Maintain site diary, labor plans and other records.
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
February 2005 to February 2007: Site Engineer
JNLC Construction Inc.
Cainta, Rizal Philippine
Project: -Condominium Units at
Skyway Twin Tower Pasig City Phillipine
-Construction Union Banks Branches at
Metro Manila Philippine
-Construction Mini Stop Convenience Outlets at
Metro Manila and Laguna Philippine
Duties and Responsibilities:
- Ensuring the works was done according to plans and scheduled time frame
- Review plans for modification of existing structures prior to construction
- On site management and supervision
- Keep a site diary recording significant events, verbal instruction, telephone conversations and weather conditions
- Remind the Construction Manager of monthly reports, reports action taken and instruction received
- Attend to correspondence as delegated by the Construction Manager
- Bring to Construction Manager attention any outstanding matter or unanswered correspondence
- Prepares realistic and achievable schedules
- Preparing scope of works including detailed work breakdown for different structures.
- Prepares material procurements needed
- Coordinates, prepares and present daily scheduled reports. Coordinates fieldworks, project controls, monitoringand conducting QA/QC Inspection.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Maintain site diary, labor plans and other records.
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
June 2007 to January 2008: Site Engineer
Aljorence Construction and Development Corporation
Quezon City Philippine
Project: -Residential, Land development, Roads and Drainage
System of South Forbes Park Village at
Cavite, Philippine
Duties and Responsibilities:
- Ensuring the works was done according to plans and scheduled time frame
- Review plans for modification of existing structures prior to construction of the new drainage system
- On site management and supervision
- Keep a site diary recording significant events, verbal instruction, telephone conversations and weather conditions
- Supervise with surveyor team for layouting
- Remind the Construction Manager of monthly reports, reports action taken and instruction received
- Attend to correspondence as delegated by the Construction Manager
- Bring to Construction Manager attention any outstanding matter or unanswered correspondence
- Supervise and check road preparations ( earthworks,
Sub-grade, sub-base )
- Supervision of Pavement laying
- Prepares plans for grading operations as related to heavy equipments, haul distances and access roads to quarries.
- Prepares realistic and achievable schedules
- Preparing scope of works including detailed work breakdown for different structures.
- Prepares material procurements needed
- Coordinates, prepares and present daily scheduled reports. Coordinates fieldworks, project controls, monitoringand conducting QA/QC Inspection.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Maintain site diary, labor plans and other records.
- Maintain control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
March 2002 to March 2003: Site Engineer
RUSAMA Construction Inc.
Las Pinas City Philippine
Project: -Pilipinas Shell Gasoline Stations Renovations at
Oriental Mindoro
-Construction of Pilipinas Shell Gasoline Station at
Metro Manila Philippine
-Renovation of Staff House at
Poro Point La Union Oil Depot Philippine
-Construction of Linear Park at
Pilipinas Shell Petroleum Company Pandacan Oil Depot
Manila Philippine
-Construction of New Perimeter Wall at
Pilipinas Shell Petroleum Company Pandacan Oil Depot
Manila Philippine
-Construction of New Buffer Wall at Tank Farm at
Pilipinas Shell Petroleum Company Pandacan Oil Depot
Manila Philippine
-Construction of Guard House at
Pilipinas Shell Petroleum Company Pandacan Oil Depot
Manila Philippine
-Dismantling and Hauling of Storage Tanks at Tank Farm
at Pilipinas Shell Petroleum Company Pandacan Depot
Manila Philippine
-Painting Works for Storage Tanks
at Pilipinas Shell Petroleum Company Pandacan Depot
Manila Philippine
-Painting Works Inside Chemical Storage Warehouse at
Pilipinas Shell Petroleum Company Pandacan Oil Depot
Manila Philippine
-Renovation Works for Staff Cafeteria at
Pilipinas Shell Petroleum ComapnyPandacan Oil Depot
Manila Philippine
Duties and Responsibilities:
- Ensuring the works was done according to plans and scheduled time frame
- Review plans for modification of existing structures prior to construction
- On site management and supervision
- Keep a site diary recording significant events, verbal instruction, telephone conversations and weather conditions
- Remind the Construction Manager of monthly reports, reports action taken and instruction received
- Attend to correspondence as delegated by the Construction Manager
- Bring to Construction Manager attention any outstanding matter or unanswered correspondence
- Prepares realistic and achievable schedules
- Preparing scope of works including detailed work breakdown for different structures.
- Prepares material procurements needed
- Coordinates, prepares and present daily scheduled reports. Coordinates fieldworks, project controls, monitoringand conducting QA/QC Inspection.
- Ensure each piece of construction carried out at site is constructed, completed and maintained in accordance with the drawings, specifications and conditions of contract or site instructions.
- Maintain site diary, labor plans and other records.
- Maintain strict control on safety measures and all statutory and contractual obligations on contractors
- Keep progress drawing current
Be present throughout all major activities on site like concrete pouring, testing etc. To supervise and control the quality of materials and workmanship.
Testing at site: -Dynamic Load Test ( High Strain ) using Pile Driving
Analyzer( PDA ), Dynamic Hammer, Stain Transducers,
Acceleration Transducers
-Pile Integrity Test ( Low Strain ) using Small Hand
Hammer, Wave Velocity Graphic Display Monitor
-Cross hole Sonic Logging Test using CSL Tube, Impulse
Generator, Winch, Data Acquisition Display System
-Caliper Logging Test using Three arm Probe, Winch,
Caliper Data Logger
-Compression Load Test
Tension Load Test
Lateral Load Test
Plate Load Test
CBR Test
Compaction Test ( Sand Cone and Nuclear Method )
Coating Thickness ( using Elcometer or WFT Gauge )
Concrete slump Test
Pin hole Holiday Test, Vacuum Test ( For Integrity Waterproofing membrane )
Rebound Hammer Test – to measure the elastic properties or strength of concrete or rock, mainly surface hardness and penetration resistance
SEMINARS ATTENDED:
Incident Injury Free Seminars at Qatar Shell Gas To Liquid Project Qatar
Safety Management and Leadership at Barzan Onshore Project Qatar
Supervisory Skills and Knowledge at Barzan Early Site Works Project Qatar
Introduction to HSSE and Leadership at Qatar Shell Gas To Liquid Project Qatar
Practical Leadership at Qatar Shell Gas To Liquid Project Qatar
Cultural Awareness at Qatar Shell Gas To Liquid Project Qatar
Quality Control at Qatar Shell Gas To Liquid Project Qatar
Productivity through Planning and Organising at Qatar Shell Gas To Liquid
Project Qatar
PERSONAL INFORMATION:
Place of Birth: Manila, Philippine
Sex: Male
Civil Status: Married
Citizenship: Filipino
Languages: Filipino, English
Weight: 180lbs
Height: 5ft. 7in.
Passport No. : EB6190198
Date Issued: August 23, 2012
Date Expired: August 22, 2017
Place Issued: Philippine Embassy Doha Qatar
REFERENCES:
Rolando Mendez
QA/QC Manager
+97455876324
Consolidated Contractors Group ( Offshore ) / Teyseer Contracting Company JV
EngelbertValdoz
Sr. QA/QC Engineer
+97466042628
Consolidated Contractors Group ( Offshore ) / Teyseercontracring Company
Vivencio B. Pachoro
Applicant