This document contains SC Railing Company proprietary information. Disclosure is prohibited without the prior written permission of SC Railing Company. 7008 Northland Drive, Suite 150 Minneapolis, Minnesota 55428 p: 1-877-215-RAIL(7245) w: sc-railing.com Staircases called for optional side-mounted posts Top-mounted Vista railing Balconies and overlooks called for top- mounted posts Long runs of Vista railing create separation with a dramatic, yet minimal aesthetic Our Vista railing is perfect when an unobstructed view is preferred Free-standing handrails accompany the Vista railing on interior stairs Project: Meadow Glen Middle School Location: Lexington, SC Architect: Hussey, Gay, Bell, & DeYoung International GC: Adolfson & Peterson Construction Completion: December 2012 Scope: This project called for 850 linear feet of Vista stainless and glass railing and 2-line free-standing stainless handrail. Revered for its simple, yet sturdy design, our Vista railing does not incorporate a top cap, giving an air of openness, allowing the eye to see well beyond the railing. Its strength lends itself to high-traffic spaces. Project Information Public Middle School Case Study: Meadow Glen Middle School

Meadow Glen Middle School - Stainless & Glass Railings

Embed Size (px)

Citation preview

This document contains SC Railing Company proprietary information. Disclosure is prohibited without the prior written permission of SC Railing Company.

7008 Northland Drive, Suite 150 Minneapolis, Minnesota 55428 p: 1-877-215-RAIL(7245) w: sc-railing.com

Staircases called for optional side-mounted posts

Top-mounted Vista railing

Balconies and overlooks called for top-mounted posts

Long runs of Vista railing create separation with a dramatic, yet minimal aesthetic

Our Vista railing is perfect when an unobstructed view is preferred

Free-standing handrails accompany the Vista railing on interior stairs

Project: Meadow Glen Middle School

Location: Lexington, SC

Architect: Hussey, Gay, Bell, & DeYoung International

GC: Adolfson & Peterson Construction

Completion: December 2012

Scope: This project called for 850 linear feet of Vista stainless and glass

railing and 2-line free-standing stainless handrail. Revered for its

simple, yet sturdy design, our Vista railing does not incorporate

a top cap, giving an air of openness, allowing the eye to see well

beyond the railing. Its strength lends itself to high-traffic spaces.

Project Information

Public Middle School

Case Study: Meadow Glen Middle School