Upload
khangminh22
View
0
Download
0
Embed Size (px)
Citation preview
BOSA project
Comments and Response Report for the Proposed Botswana-South Africa (BOSA) Transmission Interconnection Project Southern African Power Pool (SAPP)
112581 27 February 2018
Project 112581 File 112581_BOSA_CRR_Phase 1to 3 27 February 2018
Document control record Document prepared by:
Aurecon South Africa (Pty) Ltd
1977/003711/07
Aurecon Centre Lynnwood Bridge Office Park 4 Daventry Street Lynnwood Manor 0081
PO Box 74381
Lynnwood Ridge 0040 South Africa
T
F
E
W
+27 12 427 2000
+27 86 556 0521
aurecongroup.com
A person using Aurecon documents or data accepts the risk of:
a) Using the documents or data in electronic form without requesting and checking them for accuracy against the original hard copy version.
b) Using the documents or data for any purpose not agreed to in writing by Aurecon.
Document control
Report title Comments and Response Report (CRR)
Document ID CRR_EIA phase Project number 112581
File path P:Projects\112581 Botswana-South Africa (BOSA) Transm\03PRJ Del\REP\07 Environment\8 Final ESIA for Approval\Ann_CRR
Client SAPP Client contact D Erasmus
Rev Date Revision details/status Prepared by
Author Verifier Approver
0 27 January 2017 Comments and Response Report
A Visagie A Visagie D Erasmus D Erasmus
1 15 June 2017 Comments and Response Report
A Visagie A Visagie D Erasmus D Erasmus
2 4 August 2017 Comments and Response Report
A Visagie A Visagie D Erasmus D Erasmus
3 27 February 2018 Comments and Response Report
A Visagie A Visagie D Erasmus D Erasmus
Current revision 3
Approval
Author signature Approver signature
Name A Visagie Name D Erasmus
Title Project Manager Socio Economic Development
Title Project lead
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018 Page i
Contents 1 Issues and Comments received during the Initial Notification Period ......................................................................................... 4
2 Issues and Comments received during the Scoping Phase ..................................................................................................... 10
3 Issues and Comments received during the Draft ESIA Phase ................................................................................................. 27
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
1 Issues and Comments received during the Initial Notification Period
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
Kindly provide us with a detailed arial map showing the exact
GPS points where the proposed electrical lines will cross the all
dirt & tar roads in Nietverdient area.
Willie Gunther for Pat Roos
Farmer: Putfontein 2 portion 4.
Email SA 28 December
2016
Maps for the Putfontein 2 farm, were
forwarded, as requested. The Nieverdient
Area is on the right of the R49, and the farm
Putfontein 2 is on the left, and the maps have
been prepared to indicate that area. Mr
Gunther was invited to indicate if he required
maps for the whole Nietverdient area. It was
also noted that the southern part of the
alignment may change, depending on the
confirmed new location for the proposed
Watershed B substation. This information will
be forwarded to all I&APs when available.
Pat Loots owns on Putfontein 2 portion 4. He indicated that he is
a game farmer (has lions and crocodiles etc.) and he has a
private air strip on his farm. He wanted to understand the
possibilities that the transmission line will go through or be close
to his property. He stated he will lose his accreditation for game
farming if the lines are visible to his guests and he is worried that
the aeroplanes won’t be able to land on the farm anymore.
He requires an urgent response as he is also looking at
investment opportunities from a BBBEE partner (they came to
Pat Loots
Farmer: Putfontein 2 portion 4.
Meeting with
Project team
SA 4 April 2017 An internal project meeting was held to
discuss the alignment and feedback was given
as indicated below.
Email SA 11 April 2107
The original response was to thank Mr Loots
for sharing his perspective on the potential
constraints on his land and the surrounding
area with the project team.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
see him yesterday) and he needs to inform them of the different
possibilities. He says he needs to be open with them but don’t
want to tell them if the possibilities are low.
He stated he was positive about changes and will be willing to negotiate but he needed to know in order to make decisions rather sooner than later.
The project team indicated that we are
currently in the feasibility phase of the project,
so we are still a minimum of twelve months
away from a decision as to whether to
construct the line or not. This decision will be
taken by SAPP CC, as the client, as well as
the two Sponsor utilities. As the appointed
Transaction Advisor, Aurecon is actively
engaging with affected stakeholders and
considering potential impacts on the proposed
line route. At this early stage of the project, the
first step in this instance is to review the line
route in light of the specific constraints that
you have brought to our attention. The
outcome of this review will be communicated
in due course.
Is there currently any maps available indicating whether the
transmission line will cross railway or pipeline servitude(s) in the
area?
The Transnet stakeholder that will register will depend on which
servitudes is being impacted.
Biance Schoeman
Transnet
Email SA 9 January
2017
The original response was that the information
would be provided in the Scoping Report.
Maps are provided in the Scoping Report of
known servitudes.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
The line servitude within the affected Woodland vegetation types
(Dwaalboom Thornveld, Madikwe dolomite, Zeerust Thuornveld,
Dwarsberg-Swartruggens Mountain Bushveld and Mafikeng
Bushveld) will affect various protected tree species – mostly
Combretum imberbe, Vachellia erioloba, Sclerocarya birea and
Boscia albitrunca. These veld types are listed as least
threatened and one as vulnerable, but most are under-protected.
The latter factor is taken into consideration should therefore be a
decision that a biodiversity off-set should be considered. The
protected tree species are abundant, but they are listed as
protected because of their keystone species value, and various
threats that need to be controlled by licensing.
The number of mature protected trees to be affected by the
proposed activities must be estimated (sometimes done by
extrapolation of tree numbers from benchmark sites). If more
than 2000 mature protected trees are affected within the
servitude, then investigation would then focus on the veld types
affecte4d their protected area targets and to what extent the
targets have been met, the relative biodiversity value, rarity of the
veld type and threat status, before it is decided whether an off-
set might be necessary.
The application in terms of Section 15 of the NFA has to be
made for a licence destroy protected tree species, and in that
Ms Mulalo Sundani
Department of
Agriculture,
Forestry and
Fisheries
Email SA 3 February
2017
Information will be verified by the biophysical
specialist and a response provided when
available.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
licence application more detail will have to be provided, such as
the number of mature trees to be affected.
You have sent a letter to Francina Petronella Johanna Elizabet
Jansen, PO Box 2, Shelly Beach as a Land Owner.
Please let me know where you got this information as their
property (Mrs Jansen and her late husband- my father and
mother in law), which is a portion of the Farm Groenvallei, was
sold during December 2000 and the property transferred into the
new owner's name. She has relocated during December 2000 to
Shelly Beach.
Andre Nel
JA Nel and
Associates for FPJE
Jansen
Email SA 10 January
2017
Information was obtained from a deeds
search. The project team will try to locate the
details of the new owner.
Please send the BID documents to the relevant regions as they
are to be notified.
Wietsche Roets
Department of
Water and
Sanitation (DWS)
Email SA 15
December
2016
The necessary BID document were sent to
North West DWS office.
The Department requested that a draft hard copy be sent to the
relevant officer as indicated in their letter.
Ellis Thebe
Rural,
Environmental and
Agricultural
Development read
Email SA 16 January
2017
Once the Scoping Report is available a copy
will be sent to Ms Oitseng Moholo
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
Water use authorisation to be obtained. Why is the border line
option not an option? There is already safety and a disturbed
flora corridor. I think the fence will also be upgraded as like all
other SA border fences.
Pieter Ackerman
Department of
Water and
Sanitation
(DWS)
Email SA 9 January
2017
A detailed process was followed to select the
best route from an environmental, social and
technical perspective, which is detailed in the
Scoping Report. A process will be followed in
the next phase of the project to obtain a WUL.
We will wait for the presentation in order to comment. Can you consider Appendix D2 of GA 509 in the meantime?
Pieter Ackerman
Department of
Water and
Sanitation
(DWS)
Email SA 10 July 2017 The Botswana –South Africa Transmission
Interconnection Project will undertake the
relevant authorisation in term of the National
Water Act (Act 36 of 1998). A pre application
meeting was held with the Mahikeng DWS
Regional office on the 28 February 2017 with
Clement Makwela. Water uses that are
identified for authorisation includes the
following:
• Section 21 (c and i) water uses for
construction of pylon within the
500m buffer of wetland or within the
1:100 year flood line of the water
course or within a
wetland/watercourse.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
• Section 21 (a) for abstraction of
water form a water resource for
construction
The application has not yet been submitted to
DWS Mahikeng office and currently being
compiled by Aurecon
Please note that SAHRA does not accept posted, emailed,
hardcopy or website links as official submissions. Please create a
case on the South African Heritage Resources Information
System (SAHRIS). Please see step-by-step tutorial videos on the
SAHRIS home page (http://sahra.org.za/sahris/). Please
inform me when this has been completed and reference the
Case ID number.
Natasha Higgitt
SAHRA
Email SA 14
December
2016
Noted, thank you
Impact on birds. Location of key biodiversity area /IBAS in
relation the project. Bird migrating paths in relation to the
powerlines. Who will monitor the impact of the powerlines on
birds? What periods/ who pays?
Which bird species will be affected? Taxomic groups?
What migration measures are projected with evidence that those
migration measures do work.
Dr J Senatso
Birdlife Botswana
Fax Botswana 20 January
2017
These concerns will be addressed by the bird
specialist and mitigation measures detailed in
the Environmental and Social Impact Report
(EIR).
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
The Department of Tourism is not affected by the proposed
project. Please note the Department of Tourism is responsible for
policy making, licensing the tourism enterprises and further
ensuring compliance to Tourism Statutes by licensed operators.
O.Mahlala
(Dept of Tourism)
Post Botswana 14 February
2017
Noted, thank you
We have no comments on issues of environmental assessment
which has no Archaeological Impact Assessment. If your report
had a portion on AIA our comments would suffice from there.
Louis Moroka
(Botswana National
Museum)
Post Botswana 14 February
2017
A baseline description of the heritage resources
that may be affected is provided in the Scoping
Report. This will be investigated in more detail
in the EIR.
The Department of Waste Management and Pollution advises
ensuring compliance to the following policy and legal instruments
1) Waste Management Act 1998; 2) Waste Water and Sanitation
Policy, 2001; 3) Air Pollution Preventative act 1971; 4) Botswana
National Master Plan for Waste Water and Sanitation 2003; 5)
Botswana Waste Management 1998; 6) Waste Water Discharge
Standard BOS 93
K. Mokokwe
(DWMPC)
Post Botswana 17 January
2017
Noted – this will be addressed in the process.
Please be advised that the council views and concerns
(consultation stage) can only be done during the submission /
presentation of the Draft Scoping Report. We will be looking
forward to receiving the Scoping Report from you on the same for
our input.
L.O .Chezuva
(Kgatleng District
Council)
Email Botswana 27 January
2017
Noted – the Scoping Report is currently out for
public comment.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
The following issues must be considered in EIA process
protected tree species – Spirostachys African (morukuru);
Sclerocarya berria (morula). The following interested and
affected parties must be added to the mailing list: Kgatleng Land
Board, Wildlife and National Parks, District Commissioner –
Economic Planning Council - Economic Planning
Kennedy
Thatayaone
Mathame(Departme
nt of Forestry and
Range Resources
(Mochudi)
Fax Botswana 17/03/2017 Noted – the Scoping Report is currently out for
public comment.
Minimum disturbance of grazing areas must be considered. Ministry Of Agriculture-Animal production
Mr Moswela
Email Botswana 18/04/2017 Noted – this will be included in the
recommendations.
It is difficult to see from the attached maps the exact location of
the proposed routes. The coordinates or shape files of the routes
would enable us to overlay it with our maps and see exactly what
we have in that area. However the following are possible
impacts of the project on agricultural land and production and
should be looked into.
Positive Impacts
• Marketing of Agricultural produce – during construction the presence of contractors in the area may create a market for Agricultural produce.
• Creation of employment during off seasons
Crop Production Email Botrswana 10/04/2017 Noted – these impacts have been identified in
the Scoping Report is currently out for public
comment and will be assessed in more details
in the EIR.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
ISSUES AND COMMENTS RAISED DURING THE INITIAL NOTIFICATION PERIOD
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa or Botswana
DATE RECEIVED
RESPONSE
• Creation of access road to farmland
Negative impacts
• Change in land use (displacement of people/fields, taking part of the productive fields, ranches or grazing areas etc.). This will lower Agricultural production
• Loss of Productive land- displaced farmers may find alternative fields in less productive areas.
• Clearing of a large piece of land may affects the rangeland for livestock grazing
• Labour competition. People may opt to abandon crop production during construction for temporary jobs.
• Waste disposal. If waste is not managed properly it may be a health hazard to both farmers and livestock
• Transmission lines can negatively affect field operations
e.g. aerial spraying, spray irrigation and future land development.
Disturbance of the soil during clearing of right of way and use of
big trucks and machinery during construction (can cause erosion
or compaction)
• Noise during construction
• Encroachment of certain plant species due to disturbance of the area.
• Safety of both farmers and livestock is not guaranteed at all times
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
2 Issues and Comments received during the Scoping Phase
ISSUES AND COMMENTS RAISED DURING THE SCOPING PHASE
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE South Africa
or Botswana
DATE
RECEIVED
RESPONSE
What will happen to the family graves that will be affected by the
proposed power line?
Mr. G.S Moremedi
Tribal Authority
representative
Focus
Group
meeting
SA
21 July 2107
It was explained to Mr. Moremedi and Tribal
Authority Council that a Heritage specialist has
been appointed as part of the ESIA process to
investigate the potential impacts on the heritage
resources along the alignment.
In accordance with the NHRA of South Africa,
the developer is not allowed to remove or
destroy graves without following statutory
procedures.
A 1 km corridor is being assessed to allow the
team to move towers to avoid graves should
these be in the way of the currently proposed
route. Although this will not be required, in the
event of graves being relocated for any project,
the developer may not remove or destroy the
graves without a formal process being followed
and permission being granted by authorities
and communication with the affected families to
allow for the necessary rituals.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
According to community understanding and the requirements of
the municipality, the affected communities should benefit from
local projects inform of jobs opportunities and empowering local
SMMEs etc.
What sorts of benefits can they expect from this project?
Follow-up comment:
Companies like Vodacom and MTN built a network tower in their
community and as part of their benefits these companies pay the
Chief a certain amount of money per annum.
The project is still in the feasibility stage. A decision as to
whether to construct the line or not has not been made.
Mr. Monamodi
Driefontein Ward
Cllr & Chief
Moiloanyane
Focus
Group
meeting
SA
21 July 2107
The ESIA is still scoping issues and will look in
detail at the benefits and mitigation of impacts
from the projects in the next phase of the
project. The benefits for the affected
communities will still be addressed in more
detail, informed by comments received from the
community during the stakeholder engagement
process.
More detailed information on this aspect will be
communicated to the communities during the
next public meetings (ESIA Phase).
Will the electricity be supplied to the communities from the
Mafikeng substation?
Mr. G.S Moremedi
Tribal Authority
representative
The line will link to substations and will feed
electricity directly to the national grid of each
country. There will be no take-off to local
communities. Furthermore, there is currently no
regional supply demand balance at risk. The
project is aimed to facilitate trade flexibility and
create an additional route to be potentially
utilized.
Based on the outcomes of the feasibility
studies, a decision as to whether to construct
the line or not will be made.
All communication must go through the Farmer’s Union and they
will disseminate the information. They will contact Aurecon if they
think of any other issue or comment.
Klippan Farmers
Association
Public
Meeting
SA 17 July 2017 Noted
Please contact Amelia Visagie
Fax: +27 (0) 86 538 6115
Tel: +27(12) 427 3149
Email: [email protected]
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Please send an updated zoomed in map of the preferred line and
affected land owners.
Aurecon: Noted and will send as soon as
available.
Will the land owners be compensated? Eskom: Yes, the landowners will be
compensated for land lost. There will be an
assessment undertaken with Eskom and the
amount will be agreed upon.
Will the area be rehabilitated after construction? Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Aurecon: The pylon structures that will be
used have a very small footprint and no
trenching will be required as this is an
overhead transmission line. All the impacted or
disturbed areas will be rehabilitated after
construction.
What is the social responsibility of project, and how will it benefit
the affected communities?
Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Eskom: Eskom normally has a community
support initiative for all their community-based
projects. The community initiative for this
particular project will be discussed and agreed
upon with the relevant traditional authorities,
councillors and local municipality as they have
a better understanding of the community
needs.
Electricity companies need the land to construct the powerline
but there is not always proper consultation. There is a need for
proper consultation.
Aurecon: These public meetings form part
stakeholder engagement process for the ESIA
process and stakeholders will be consulted
throughout this ESIA process. Outside of the
ESIA process, a stakeholder facilitator will be
engaged and a Steering Committee will be
formed that comprise of: traditional leaders,
municipal leaders, Eskom, and other important
stakeholder groupings. The steering
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
committee will be used to disseminate
information, manage concerns and to make
decisions that involve the local affected
communities.
What are the timeframes of the project? Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Aurecon: The project length in South Africa is
about 140 km. The project is depended on
another project (Watershed B substation) that
still needs to be finalised, but it is estimated
that the construction will last approximately 2
years once the approvals are in place.
Will there be an information board that informs the community
about the project, including construction company, date etc.
Aurecon: The construction will be a rolling
process and at every section there will be a
construction message board with all relevant
information.
Information will also be disseminated through
the Community Steering Committee. The
committee members will be member from the
various communities. Therefore, every
community will be represented in the
committee.
In what manner will the labour be sourced from the local
community
Aurecon: Recommendations from the social
specialist include that the contractor should be
required to employ local labour, where
possible. The requirement for the employment
of local labour should be formalised by
incorporating it into the contractor’s contract.
Quotas for local employment should be set
based on the availability of appropriate local
skills as indicated in the skills databases.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Opportunities should be investigated for
encouraging indirect employment creation in
the informal sector.
Eskom: Labour will be sourced from the local
communities through the Steering Committee.
What is the principle employed for appointing contractors and
sub-contractors?
Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Eskom: The bidding process will be advertised
on the Eskom tender website, and the
contractor will be chosen through that formal
tender process.
The distribution of work by contractor will be
decided by the Steering Committee.
What is the amount of money that will be spent on the project,
what is the project worth?
Eskom: This amount is not yet available as we
are still in a feasibility stage, but a rough
estimate will be available in the ESIA phase.
As Eskom will need land for the project what long-term benefit
will the community obtain from the project? Compensation vs the
long-term benefit for the community.
Eskom: Eskom is governed by the Electricity
Act and the community will be compensated
for the land lost as well as for livelihood
restoration. Eskom would also take part in
Corporate Social Investment (CSI) initiatives in
the area and after consultation with the local
leaders (traditional and municipal) Eskom will
decide which initiatives to take forward.
The owner will be compensated for the land
acquired permanently by Eskom. Farmers will
still be able to use most of the land for grazing
and/or other farming activities.
Will current and future uses of the land be taken into
consideration in the compensation?
Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Eskom: Eskom will compensate for the land
lost and also for current land uses. The future
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
land use potential will be looked at on a case
by case basis and where there is a formal plan
in place to assess this aspect.
All the project activities conducted within the village must adhere
to the protocol in the area. This must be done in consultation with
all the tribal authorities.
Aurecon: Noted. Effort was made to meet
some of the tribal authorities prior to this
meeting. This will continue throughout the
process.
There was limited or no input from the traditional leaders at the
start of the project.
Aurecon: The project is still in the feasibility
stage and the input from the traditional leaders
is crucial to the success of the project. This
consultation process is the first stage of
consultation at the earliest possible stage of
the project. Ongoing communication and
engagement will continue throughout the
duration of the project.
Effort was made to meet some of the tribal
authorities prior to this meeting.
It has been requested that there be a meeting with the traditional
leaders of the area, to explain the project in detail, this will assist
the leaders to deal with complaints and issues raised by
community members.
Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Aurecon: Noted and a meeting will be
scheduled.
Please provide the exact location of the project on a map also
indicating the landowners.
Aurecon: Noted and will send as soon as
available.
The hope was raised that the electricity challenge in the area will
be addressed through this project.
Aurecon: The primary objective is to facilitate
trade and ensure improved security of supply
on a regional basis. The project will also
improve power pool stability between strong
and weak systems, system control, reliability
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
and regional trading as well as alleviate
potential congestion. It will not however,
provide electricity on a local level to
communities.
The traditional leaders must be informed before the specialists
visit the area.
Lehurutshe Tribal
Council
Public
Meeting
SA 17 July 2017 Aurecon: Noted and protocol will be followed.
What is the duration of the proposed project construction? Serake / Driefontein
Tribal Authority
Public
Meeting
SA 18 July 2017 Eskom: The project is depended on another
project (proposed Watershed B substation
near Mahikeng) that still needs to be finalised,
but it is estimated that the construction will last
approximately 2 years after the approvals are
in place.
Does the proposed project affect the Serake village; if so, how
will the community benefit and project’s social responsibility?
Eskom:
Employment benefit
Some of the labour will be sourced from the
affected villages. The appointed contractor will
appoint the local labourers and local SMMEs
(Sub-contractors) through the established
Project Steering Committee.
Community benefits
Eskom considers community support initiatives
for all their community-based projects. The
community initiative for this particular project
will be discussed and agreed upon with the
relevant tribal authority representatives,
affected local municipality (ward committee),
main contractor and other important
community structures.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Community initiatives will be in line with the
Integrated Development Plan (IDP) future
community projects of the affected villages.
Compensation
Eskom is governed by the Electricity Act; a
once-off compensation is paid before
construction phase based on the required land
for servitude of the proposed powerline.
Skills development
Eskom encourages the contractors to provide
training opportunities to train local semi-skilled
labourers and certificates. Some trained
labourers end up receiving permanent
employment opportunities with the main
appointed contractor after the project is
complete.
Community requested Eskom to replace tower lights not working
at the Serake village
Serake / Driefontein
Tribal Authority
Public
Meeting
SA 18 July 2017 Eskom:
The proposed project is under the Eskom
Transmission Division. Communities should
report any local electrical fault to Eskom
Distribution, which is the division responsible
for transporting electricity to the villages. The
National Sharecall Number is 086 00 37566.
Will the project provide job opportunities to the local community? Supingstad Tribal
Authority
Public
Meeting
SA 18 July 2017 Eskom:
Yes, the project will create an opportunity for
the local labour pool to participate. More semi-
skilled and unskilled job opportunities will be
made available to the local community.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
What other benefits will the project have for the local community? Eskom:
Eskom will take part in CSI initiatives in the
area and after consultation with the local
leaders (traditional and municipal) Eskom will
decide what initiatives to take forward.
The information given today will be taken to Chief Suping where
after he will invite Eskom and Aurecon for a meeting.
Aurecon and Eskom: Noted and await
notification.
Tree species such as Vachelia erioloba, Combretum Imberbe,
Scierocarya birrea and Boscia albitrunca, protected under the
National Forest Act of 1998, will be affected by the proposed
activities. Application must be made to DAFF for the removal of
such species under Section 15 of the National Forest Act.
Once information on the tree species, their number and habitats
affected have been received with the licence application, further
investigation will be done to decide whether a biodiversity off-set
should be considered, which focuses on the following:
• The protected area targets;
• To what extent the targets have been met;
• The relative biodiversity value;
• Rarity of the veld type; and
• Threat status.
Ms Mulalo Sundani
Department of
Agriculture, Forestry
and Fisheries
Email SA 1 August
2017
The assessment of the unique or protected species, habitats including vegetation listed vegetation units forms part of the EIA phase aquatic and terrestrial ecological assessment. The main focus of the ecological assessment will be to determine the best alternative alignment that will minimise the potential impacts through avoidance of areas that contain large numbers of protected species or intact portions (high ecological value) of habitat. Furthermore the ecological assessment will also provide recommendations on the final placement of pylons and the process that should be followed during the Search and Rescue operation (if required). This will then be linked to rehabilitation and monitoring specifications once construction has been completed to ensure that important species and habitats will remain in a stable state. Data will be provided to fulfil the DAFF requirements in order to determine if any offsets will be required, however it is the intention of the proponent to avoid any high value areas.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Several types of heritage resources have been identified to be
located within and around the proposed powerline routes. These
include Palaeo-Arthropological sites, Stone Age Iron Age sites,
Rock Art sites, battlefields, cerneteries, historic farmlands,
historic rural towns, historic institutions, and scenic routes.
Recommendations provided include that the final alignment of
the Watershed B to BOSA connecting lines be subject to a
Heritage Walk-down to ensure that it will not impact on historic
battle sites associated with the Siege of Mafikeng. It is also
recommended that a Heritage Impact Assessment (HIA) be
conducted that will include desktop data collection, field surveys,
oral interviews and public consultation.
The SAHRA Archaeology, Palaeontology and Meteorites (APM)
Unit requests that an HIA must be conducted for the section of
the proposed development located in South Africa. The HIA
must assess all heritage resources as defined in section 3(3) of
the National Heritage Resources Act, Act 25 of 1999 (NHRA) and
the HIA must comply with section 28(3) of the NHRA. The Visual
Impact of the proposed development on heritage resources and
any comments provided by the public regarding resources must
be taken into account during the HIA. The HIA must be
submitted to SAHRA during the Public Review period as per the
NEMA EIA 2014 Regulations.
Ms Natasha Higget
South African
Heritage Resources
Agency (SAHRA)
Letter SA 10 August
2017
Information will be collected by the specialist
and a response provided when available.
The comment is noted and an HIA has been commissioned in compliance with section 38(3) of the NHRA. The visual impacts of the proposed development on heritage resources and the comments from the public regarding heritage resources will be taken into consideration in the HIA. The compiled HIA will be submitted to SAHRA as the commenting authority during the public comment period as per the NEMA EIA 2014 Regulations (as amended).
The Department would like to know if the file is still open because since we received the notice for EIA process on 12 January 2017 we haven't received anything report until now. Please let us know if the file is still active or not.
Obitseng Moholo E-mail SA 4 September
2017
Thank you for the email you submitted
regarding the above-mentioned project.
Please note that the Competent Authority for
this project is the National Department of
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Environmental Affairs (DEA Ref
14/12/16/3/3/2/1020).
All the information/ notifications about the
availability of the report for comments was
communicated with Portia Krisjan from your
provincial department. The report was placed
in the public domain, including on our website
(http://www.aurecongroup.com/en.aspx -
Listed under Public Participation) and the
stakeholders were requested to notify us if
they needed a soft copy (CD) to be submitted
to them.
Kgosi Lentswe requested the name of all affected villages. Lehurutshe
Traditional Office
Public
Meeting
SA 23 August
2017
(10H00am)
Aurecon: A locality map of the proposed
project was circulated around the table. It
was also indicated that a detailed aerial map
will be presented during the ESIA phase.
Aurecon requested permission from the Traditional Authority
Council to conduct project awareness, public meetings and site
visits at the proposed powerline project.
Traditional Authority: Permission was granted.
Aurecon should liaise with Mrs. Mogwera from
the Tribal Office fourteen (14) days before any
event take place at any Tribal Authority land.
It was queried whether the proposed powerline was a special line
different from the normal transmission line in the area and if it
would feed into the local grid.
Eskom: The proposed powerline is a big
transmission line with a capacity of 400 kV.
This line be transmitting power from
Watershed B in Mahikeng to Isang substation
in Botswana. The Watershed B substation in
turn will be receiving its power supply from a
proposed 400kV powerline coming from Pluto
Substation in Carltonville, Johannesburg,
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
The power from Watershed B substation in
Mafikeng will be distributed to smaller
distribution substations in the area via 132kV
powerlines. The distribution substations then
supply households and businesses through
smaller 88kV/11kV powerlines. This line
would therefore not benefit the community
directly but there will be services for the
community from other proposed projects.
It was queried whether the project would solve the problem
of load shedding in the area. The capacity of the powerline
in the area is very weak and windy conditions easily cause
power outages in the area. This has a negative impact on
the current and potential local businesses.
Lehurutshe
Traditional Office
Public
Meeting
SA 23 August
2017
(10H00am)
Eskom: The existing Watershed substation
located in Lichtenburg that supplies electricity
to Lehurutshe and Zeerust is currently being
upgraded with an addition of a transformer. It
is anticipated that the upgrade will be
completed within the next 6 months. After the
upgrades, the capacity should improve and
area should get a more stable power supply.
The purpose of the proposed BOSA project is
to improve the power supply and trade
electricity with Botswana.
What are the predicted environmental impacts of the proposed
project and how are they going to be managed?
Aurecon: During the scoping phase of the
project, both the environmental and social
impacts were identified on a desktop level.
Some of the impacts identified include impacts
on the heritage features (i.e. graves),
vegetation, wetland or rivers and birds.
During the ESIA phase, the specialists assess
the significance of the anticipated impacts
after they have undertaken fieldwork. All the
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
potential impacts are identified and potential
mitigation measures to minimise the impacts
will be documented in an Environmental
Management Programme (EMPr) and an
Environmental Impact Report (EIR). The
documents will be made available to the public
for comments. This information will also be
communicated during the public meeting with
the affected communities.
These documents are also submitted to the
Department of Environmental Affairs (DEA) for
approval. During the construction of the
project, the EMPr is used by the appointed
contractor and associated sub-contractors to
manage the impacts associated with
construction activities on a day-to-day basis.
Was the local municipality consulted or informed about the
project?
Lehurutshe
Traditional Office
Public
Meeting
SA 23 August
2017
(10H00am)
Aurecon: Aurecon Public Participation Office
have notified all the potential stakeholders
including the local municipalities regarding the
proposed project.
Aurecon did not receive responses from any of
the affected municipalities.
Most people were happy that BPC saw it fit to consult with the
Dikwididi residents and were happy with the upcoming
developments.
They Acknowledged that the project may affect them both
positively and negatively and hopes the residents of Dikwididi will
benefit in terms of employment.
Dikwididi
Community
Public
Meeting
Botswana 21st August
2017 at
08h00
Digby Wells: Noted. Feedback will be given
during the EIA phase.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
They wanted to know if they can carry on with farming during the
construction phase.
The following concerns and questions were raised:
• They wanted to know the exact line route.
• The community were concerned that there will be no
further consultation during the project.
• They wanted to know if they will be compensated if their
fields are affected.
Modipane
Community
Public
Meeting
Botswana 22nd August
2017, 09h00
Digby Wells: Noted. Feedback will be given
during the EIA phase.
The following concerns and questions were raised:
• Enquired about fields which are not fenced nor
developed, and wanted to know if they will still be
compensated.
• They appreciated the consultation and the upcoming
development.
• Urged that they should be first priority in terms of
employment creation.
Mokatse
Community
Public
Meeting
Botswana 22nd August
2017 at
11h00
Digby Wells: Noted. Feedback will be given
during the EIA phase.
No issues were raised by community members. The community
were of an opinion that it will be better for them to ask questions
in the next phase of public consultation when they know the
value of the project and the number of job opportunities that will
be created.
Ramotshere Moiloa
Mayor
Public
Meeting
SA 23 August
2017
(13H30)
Digby Wells: Noted. Feedback will be given
during the EIA phase.
The following concerns and questions were raised: Molotwane
Community
Public
Meeting
Botswana 25th August
2017 at
Digby Wells: Noted. Feedback will be given
during the EIA phase.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
• Who will uphold the contractors to their agreements on
hiring local people and the corporate social
responsibility?
• The locals were happy with the consultation process?
• Will they carry on with developing their fields (farming)?
• Requested that hiring be done at the kgotla with
knowledge of the village administrators.
11h00.
The locals were happy with the consultation process. Their main
concern was electric cables theft that is in the rising in the village.
Questions raised were as follows:
• How will land use be affected together with the
agricultural lands?
• Will there be any employment opportunities for the
village residents?
• Will electricity supply in the village improve?
Sikwane
Community
Public
Meeting
Botswana 25th August
2017 at
08h00
Digby Wells: Noted. Feedback will be given
during the EIA phase.
The following concerns and questions were raised:
• Will there be any employment opportunities for the
village residents?
• Will electricity supply in the village improve?
• Will the project help lower the electricity installation
prices?
• Who will be doing the environmental auditing to make
sure contractors uphold their agreements?
Mochudi
Community
Public
Meeting
Botswana 29th August
2017 at
08h00
Digby Wells: Noted. Feedback will be given
during the EIA phase.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
• Requested for feedback and consultation as the project
progresses?
The following concerns and questions were raised:
• Compensation arrangements (who will be compensating
them when affected)?
• Will there be any employment opportunities for the
Mabalane residents?
• Will they carry on with developing their fields (farming)?
• How will the grazing areas be affected?
• Will the burial sites be affected?
Mabalane
Community
Public
Meeting
Botswana 5th of
September
2017 at
08h30
Digby Wells: Noted. Feedback will be given
during the EIA phase.
The following concerns and questions were raised:
• What will happen if the line crosses the river and what
measures are put into place?
• Compensation arrangements (village locals say
compensation fees are way too small and the process is
not transparent)
• Who will uphold the contractors to their agreements on
hiring local people and the corporate social
responsibility?
• How will land use be affected together with the
agricultural lands?
• The village locals do not attend kgotla meetings and if
the Ipelegeng program (kgotla volunteer program) was
to cease operation all the kgotla meetings would fail and
there is no one from the tribal administration taking
Oodi Community Public
Meeting
Botswana 6th
September
2017 at
08h30.
Digby Wells: Noted. Feedback will be given
during the EIA phase.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
minutes and they have long raised these issues since
2013.
• Village locals say employment for projects and
developments are never transparent and hope this
project will be different.
The following concerns and questions were raised:
• Compensation arrangements (who will be compensating
them when affected).
• Will there be any employment opportunities for the
Ramonaka residents?
• Will they carry on with developing their fields (farming)?
• How will the grazing areas be affected?
• Will the burial sites be affected?
Ramonaka
Community
Public
Meeting
Botswana 31st
September
2017 at
08h30
Digby Wells: Noted. Feedback will be given
during the EIA phase.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
3 Issues and Comments received during the Draft ESIA Phase ISSUES AND COMMENTS RAISED DURING THE ESIA PHASE
ISSUES AND COMMENTS RAISED COMMENTATOR/S SOURCE SA or
Botswana
DATE
RECEIVED
RESPONSE
What are the benefits of the project? Miga Community Public Meeting SA 13 February
2018
Aurecon:
This proposed project will not bring electricity directly to the area.
It is a 400kv cross border transmission power line which is
intended to share and increase the power capacity in both
countries and provide benefit on a national scale. However, there
is a commitment from Eskom to support local projects in the
communities affected by the proposed project.
In addition, employment opportunities will be available for the local
communities during construction. Eskom will communicate the
logistics of the employment strategy with the relevant local
authorities in the affected areas at the time the project
commences. A Project Steering Committee (PSC) will be
established to disseminate information, facilitate recruitment
process, skills development and local SMMEs empowerment.
What is the project duration? Miga Community Public Meeting SA 13 February
2018
Eskom:
The BOSA project is dependent other projects (i.e. the proposed
Mahikeng substation and Pluto Powerline from Carletonville)
whose planning processes are still underway. However, Eskom
anticipates that all the necessary authorisations for construction
to commence will be in place by the end of 2020 for all the
projects. It is estimated that the construction of the proposed
BOSA project will last approximately 2 years once all the
approvals in place.
SAPP:
Project negotiations with the Minister of Energy are part of
acquiring necessary approvals. In addition to the ESIA process,
feasibility studies will be required, funding must be obtained; land
acquired and competent contractors appointed.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
What are the Terms of Reference for SAPP in
this project?
Miga Community Public Meeting SA 13 February
2018
Eskom and SAPP:
SAPP is an organisation responsible to coordinating the
development of transmission powerlines across Southern African
Development Communities. (SADC) to reduce power congestion.
The SAPP was established over 20 years with offices across
Southern Region and the head office is in Zimbabwe. The
organisation requests funding from organisations such as DBSA
and the World Bank to improve electricity in Africa. SAPP projects
currently underway:
• Ongoing powerline studies connecting SA and Mozambique
• Angola to Namibia powerline studies
• BOSA – connecting South Africa and Botswana
• Powerline studies connecting Botswana, Namibia and Zambia
The organisation is also coordinating other projects in East and
West Africa.
SAPP works closely with utilities (Eskom and BPC in this case) to
implement these cross-border projects. Eskom in South Africa will
commission the necessary studies to be undertaken for the
project to be approved for construction. They will also undertake
tender processes to appoint the contractor and oversee
appointment of sub-contractors.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Will be the affected households be consulted
and compensated?
Miga Community Public Meeting SA 13 February
2018
Aurecon:
Yes; Aurecon conducted a survey for the Resettlement Policy
Framework (RPF) / Relocation Action Plan (RAP) to assess
livelihoods impacts of the proposed project. The RPF / RAP
looked at how the loss of assets should be managed and how the
people should be compensated if needed. The study revealed that
about 77 farms are directly affected and two household at
Dinokana village should be resettled.
Necessary relocation process and compensation agreements will
only take place the project has all the approvals and funding to
start construction. At this stage, no agreements have been made
with the affected landowners.
How will Eskom accommodate the affected
landowners who have future plans for their
land and will they be compensated monthly
because their properties will be permanently
owned by Eskom?
Miga Community Public Meeting SA 13 February
2018
Eskom:
No compensation for future plans will be considered. The
compensation process used by Eskom is governed by the
Electricity Act and the compensation is a once off payment. The
compensation amount will vary depending on land use, affected
infrastructure or the value of the land (i.e. business / cultivation).
Once a servitude has been bought out by Eskom, certain activities
will not be allowed within the registered servitude, for example
building houses.
Is NERSA involved in the project? Miga Community Public Meeting SA 13 February
2018
Eskom:
Yes, the implementation of the project needs to meet the
requirements set by the National Energy Regulator of South Africa
(NERSA).
If the servitude is identified on our properties,
can we continue building or undertaking
planned developments within the servitude?
Miga Community Public Meeting SA 13 February
2018
Eskom:
After the identification of the servitude, building of any structures
within the servitude will be prohibited. Eskom will not compensate
any structure built after marking the servitude.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Is there any written agreement between the
consultants and landowners that will be
directly affected?
Miga Community Public Meeting SA 13 February
2018
Eskom:
No agreements will be signed at this stage until the project has
the funds approved and all necessary approvals to construct are
in place.
The proposed project has more negative
impacts than positive impacts? How will the
residual environmental impacts be addressed
after construction?
Miga Community Public Meeting SA 13 February
2018
Aurecon:
Environmental studies have been done to avoid most sensitive
impacts (i.e. social, heritage and biodiversity) during the design
phase of the project.
An Environmental and Social Management Plan (ESMP) has
been compiled as part of the ESIA. This is a legal document to
manage and/or mitigate the negative impacts of the project during
construction and operation of the project. This document will be
implemented by the appointed contractor on a day-to-day basis
and Eskom has the overall responsibility to monitor the contractor.
An independent Environmental Control Officer will be appointed
by Eskom to oversee the implementation of the ESMP.
The pylon structures that will be used have a small footprint and
no trenching will be required as this is an overhead transmission
line. All the impacted or disturbed areas will be rehabilitated after
construction as per the rehabilitation plan. Follow up inspections
or monitoring will be done until the ensure efficiency of
rehabilitation.
The project should empower local supply and
skill development in the affected areas.
Miga Community Public Meeting SA 13 February
2018
Eskom:
There will be opportunities for local SMMEs during construction
and the programme of developing local labourers from unskilled
to semi-skilled for the duration of the project and beyond. Some
individuals might get permanent employment opportunities by
contractors.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Will the electricity come to the people in the
area?
Khunotswana
Community
Public Meeting SA 13 February
2018
Eskom:
Electricity from the BOSA line is of high voltage (400 kV) which
will be linked to the two substations and fed to the national grid of
each country. High voltage electricity needs to be reduced in a
substation before it is distributed to households.
However, there is a separate project currently underway which will
assist with electricity supply in the area. The existing Watershed
substation located in Lichtenburg that supplies electricity to
Lehurutshe and Zeerust is currently being upgraded with an
addition of a transformer. It is anticipated that the upgrade will be
completed very soon. After the upgrades, the capacity should
improve and area should get a more stable power supply.
Will the project ensure that females also get
jobs from the opportunities created?
Khunotswana
Community
Public Meeting SA 13 February
2018
Aurecon:
Each community will have a Project Steering Committee (PSC)
which is made up of the community members representing their
communities. They will assist and facilitate a transparent
recruitment process to ensure equal opportunities for all, including
females and the youth.
Will the contractor bring in their own
employees in the project?
Khunotswana
Community
Public Meeting SA 13 February
2018
Aurecon and Eskom:
Powerline projects are not labour intensive, and few skilled and
unskilled workers are required during construction. However,
necessary measures will be place to the monitor recruitment
process and ensure labourers are sourced locally to the greatest
extent possible. This will be done through establishment of PSC
which comprises of community members, traditional leaders, local
municipality, Eskom and other important stakeholder groupings.
A Khunotswana community member requested
that the Project Steering Committee should be
selected during the meeting to ensure fairness
of employment process to accommodate
females.
Khunotswana
Community
Public Meeting SA 13 February
2018
Aurecon and Eskom:
The aim of the public meetings is to inform the public about the
project and the ESIA process being undertaken to authorisation
the project. The Project Steering Committee will only be selected
prior to construction once the project has been approved and
cannot be done at this stage of the project
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
The community raised concern about other
unsuccessful community projects:
Electricity project: Eskom installed electric
boxes / main switch to some sections of
Khunotswana village without connecting
power.
Water pipeline project: the budget was finished
before installing water pipes to the
households.
Khunotswana
Community
Public Meeting SA 13 February
2018
Eskom:
Eskom noted the issue and it was indicated to the community
that the proposed BOSA project falls under the Eskom
Transmission Division. Any unsuccessful project or any local
electrical fault should be reported to Eskom Distribution Division.
Eskom Transmission representatives will invite local Distribution
stakeholder personnel to respond to local distribution issues.
Where will contractor’s camp site (workers
accommodation) be established during
construction phase?
De Putten Farmers
Focus Group SA 14 February
2018
Aurecon:
The camp site will not be located on the farms. There will be
specific site camps away from the affected farmers, which will be
linked to available resources and confirmed by the contractor
prior to the commencement of construction.
The farmers suggested the following should be
monitored during construction:
• Access - access to the farms by
contractors must be clearly stipulated to
avoid stock theft
• Eskom should appoint 24/7 Security
company throughout project completion.
• The contractor should fence the
construction site for safety of livestock,
workers and households.
• There should be ablution services on site
for contractors to avoid environmental
pollution.
• The farmers requested that there should
be identification mechanism in place for
contractors.
De Putten Farmers
Focus Group SA 14 February
2018
Aurecon:
The suggested measures will be taken into consideration during
construction. Before construction, these measures will be
communicated and agreed upon (between Eskom, contractor
and landowners)
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
What will be the compensation for the affected
land owners farming (livestock, land used for
grazing)?
De Putten Farmers
Focus Group SA 14 February
2018
Eskom:
Compensation for the affected landowners / farmers, will be
assessed by independent land evaluator (specialist who have
working experience in the area). The cost for the servitude will be
calculated according to the state of the properties. Land use (i.e.
land used for cultivation and business purposes) will be
considered when calculating the total cost. Livestock farmers can
still use the affected land for activities such as cattle grazing and
cultivation after the erection of Eskom pylons, using low irrigation
systems. However, building of any structures under or within 50
m from powerline pylons is prohibited. Eskom will not fence the
powerline towers after construction.
The area has poor electricity supply, which is
affected by wind. Expensive electricity bills for
farmers have been reported to the local Eskom
offices. No assistance has been rendered to
them.
De Putten Farmers
Focus Group SA 14 February
2018
Eskom:
There is a separate project currently underway which will assist
with electricity supply in the area. The existing Watershed
substation located in Lichtenburg that supplies electricity to
Zeerust and the surroundings is currently being upgraded with an
addition of a transformer. It is anticipated that the upgrade will be
completed very soon. After the upgrades, the capacity should
improve and area should get a more stable power supply.
The proposed BOSA project is under the Eskom Transmission
Division responsible to transmission of power. Local landowners
should report electrical fault to Eskom Distribution, which is the
division responsible for distributing the electricity to residents.
Part of compensation request by directly
affected farmers is to get free power supply
from Eskom.
De Putten Farmers
Focus Group SA 14 February
2018
Eskom:
Eskom will only compensate for the land lost and for current land
usage. The RPF / RAP has considered assets (including crops
and buildings on the affected land). No free electricity can be
given to the directly affected parties.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
What is the purpose of implementing the
BOSA project?
Lehurutshe
Community
Public Meeting SA 14 February
2018
Aurecon:
The purpose of the proposed BOSA project is to improve the
power supply and trade electricity between South Africa and
Botswana.
What is the required servitude to construct the
proposed powerlines?
Lehurutshe
Community
Public Meeting SA 14 February
2018
Eskom:
The servitude differs according to the powerlines voltage. The
proposed project is a 400 kV which requires 55 m buffer zone.
This is the size of the servitude that will be registered on the title
deed.
The respective Ward Councillors should be
involved in the project
Lehurutshe
Community
Public Meeting SA 14 February
2018
Aurecon:
The stakeholder engagement team have engaged the district and
affected Local Municipality; hence there were representatives
from the Mayor’s office present.
How will affected community farm owners
benefit from the proposed project?
Serake / Driefontein
Community
Public Meeting SA 15 February
2018
Eskom:
Compensation for the affected landowners / farmers, will be
assessed by independent land evaluator (specialist who has
working experience in the area). The cost for the servitude will be
calculated according to the state of the properties. Land use (i.e.
land used for cultivation and business purposes) will be
considered when calculating the total cost. Livestock farmers can
still use the affected land for activities such as cattle grazing and
cultivation after the erection of Eskom pylons using low irrigation
system, however building of any structure under or within 50 m
from powerline pylons is prohibited. Eskom will not fence the
powerline towers after construction.
A RPF / RAP has been developed specifically for the identified
corridor to assist with resettlement of the affected houses.
Further communication and logistics or the resettlement process
will be negotiated with the relevant affected parties.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
According to community understanding and
the requirements of the Municipality, the
affected communities should benefit from local
projects and be informed of job opportunities
and empowering local SMME’s.
• What sort of benefits can they
expect?
• What jobs will be available?
• How will the chiefs benefit from this
project?
Serake / Driefontein
Community
Public Meeting SA 15 February
2018
Aurecon and Eskom:
This proposed project will not bring electricity directly to the area.
It is a 400 kV cross border transmission line which is intended to
share and increase the power capacity in both countries.
However, there is a commitment from Eskom to support local
projects in the communities affected by the proposed project.
In addition, employment opportunities will be available for the
local communities during construction. Eskom will communicate
the logistics of the employment strategy with the relevant local
authorities in the affected areas. Project Steering Committee
(PSC) will be established to disseminate information, facilitate
recruitment process, skills development and local SMMEs
empowerment.
Will the proposed project benefit young people
in terms of skills transfer?
Serake / Driefontein
Community
Public Meeting SA 15 February
2018
Eskom:
There will be job opportunities for the affected communities and
the principle will be to ensure opportunities also benefit young
people, woman and people with disabilities during construction
phase. General workers will receive necessary training skills to
be semi-skilled labourers and semi-skilled labourers will receive
necessary training skills required by the project, that can then be
used on other projects.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
How will community benefit from the proposed
project?
Supingstad
Community
Public Meeting SA 16 February
2018
Aurecon and Eskom:
This proposed project will not bring electricity directly to the area.
It is a 400 kV cross border transmission line which is intended to
share and increase the power capacity in both countries.
However, there is a commitment from Eskom to support local
projects in the communities affected by the proposed project.
In addition, employment opportunities will be available for the
local communities during construction. Eskom will communicate
the logistics of the employment strategy with the relevant local
authorities in the affected areas. A Project Steering Committee
(PSC) will be established to disseminate information, facilitate
recruitment process, skills development and local SMMEs
empowerment.
I see no water use authorisation required. Pieter Ackerman
Department of
Water and
Sanitation
(DWS)
E-mail SA 25 January
2018
Aurecon:
Several aquatic systems were confirmed within the study area,
therefore a water use authorisation will be required. The
application will be submitted to the relevant provincial authority
once the detailed design is complete and precise water crossings
are known.
Will there be access road watercourse
crossings, road drains? Will they adhere to
SANRAL drainage manual? Is that
sufficient? Will maintenance include
erosion/sedimentation issues?
Pieter Ackerman
Department of
Water and
Sanitation
(DWS)
E-mail SA 25 January
2018
Aurecon:
The project is still in the early stages of design, road crossings
have not yet been identified or designed and tower positions have
not yet been confirmed, hence we have not submitted the
application with the DWS. We do however we anticipate that
some of the access roads and towers might be within 500 m of
the watercourses which will trigger Section 21c and an
application. Application will be made once authority once the
detailed design is complete and precise water crossings are
known.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Will there be Plant Species Plans drawn up as
part of rehabilitation?
Pieter Ackerman
Department of
Water and
Sanitation
(DWS)
E-mail SA 25 January
2018
Aurecon:
Yes, the plant species plan will be incorporated in the
rehabilitation plan.
Pat Loots visited at Aurecon and discussed the alignment of the line close to his farm. He stated that he is very grateful that the stakeholders and landowners can provide input into the process. He looked at the new alignment and provided the following input:
• The line will still be visible from his lion hunting camp and this will have an impact on his accreditation;
• He suggested the following alignment (see kml attached);
• He wants to buy, if not possible, rent Putfontein Portion 3 and 4, to expand his operations;
• The proposed alignment will still cross Portion 3 and 4 but he is happy with what he proposed, as it will not be visible from his hunting camps.
Pat Loots Farmer Focus Group
meeting
SA 14 February
2018
Aurecon:
The suggestions incorporated into the updated design.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
The proposed line is located in areas of very high to low palaeontological sensitivity. It must be noted that Fig. 29 and 30 do not show the proposed line over the palaeontological sensitivity map. A desktop palaeontological must be conducted by a qualified palaeontologist for the proposed project. The desktop study must comply with the 2012 Minimum Standards: Palaeontological Component for Heritage Impact Assessments. A map/s showing the areas surveyed in relation to the proposed powerline must be submitted. SAHRA does not accept the statement in 2.5 of the HIA. Additionally, the Lidar data and aerial photographs used to survey the line must be provided. Photographs of the Iron Age pottery must be supplied
Natasha Nigitt Email SA 19 February
2018
Aurecon:
It was indicated that the comments were still being addressed by
the Heritage Specialist.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
The Vachelia erioloba, Boscia albitrunca and
Prunus Africana trees are protected under the
National Forest Act of 1998. Therefore,
license application for removal, disturb and
damage of the above protected trees will have
to be made with the Northwest Regional office.
Page 17 and 19 of the Aquatic and Terrestrial
Ecological Assessment report reported that a
small population of protected tree species
such as Vachellia erioloba and Boscia
albitrunca has been identified in the study
area, the number of such protected trees to be
affected need to be indicated as well as the
area where such trees will be removed (this
must be indicated on a suitable scale aerial
image showing an overlay of the powerline
servitude and line position). This might lead to
further investigation on whether a biodiversity
offset should be considered.
Ms Mulalo Sundani
Department of
Agriculture,
Forestry and
Fisheries
E-mail SA 28 February
2018
Aurecon:
A detailed walkdown by an appropriately qualified specialist will
be undertaken before the final placement of pylons prior to
construction, to avoid affecting protected trees. As the footprint
of the pylons is small it is expected that this should be achieved,
However, should any Vachellia erioloba, Boscia Albitrunca or
Prunus Africana trees be affected, a licence for removal or
disturbance of such species will be made at the Northwest
Regional office at the time and the implications in terms of
numbers will need to be considered. The Northwest Regional
Office of the Department of Agriculture, Forestry and Fisheries
will be kept involved in the process should any protected trees be
affected.
Mr Helm could not attend the public sessions
and asked that the documentations that was
handed out at the meetings must be forwarded
to him.
Andries Helm Farmer
Telephone and
SA 8 March 2018
Aurecon:
An email with all relevant documents was sent to Mr Helm.
Project 112581 File 112581_BOSA_CRR_FSR_vers3.docx 27 February 2018
Aurecon South Africa (Pty) Ltd 1977/003711/07 Aurecon Centre Lynnwood Bridge Office Park 4 Daventry Street Lynnwood Manor 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa T +27 12 427 2000 F +27 86 556 0521 E [email protected] W aurecongroup.com
Aurecon offices are located in: Angola, Australia, Botswana, China, Ghana, Hong Kong, Indonesia, Kenya, Lesotho, Macau, Mozambique, Namibia, New Zealand, Nigeria, Philippines, Qatar, Singapore, South Africa, Swaziland, Tanzania, Thailand, Uganda, United Arab Emirates, Vietnam.
1
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
2
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
3
Amelia VisagieFrom: Microsoft OutlookTo: Diane ErasmusSent: Wednesday, December 14, 2016 4:05 PMSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Your message has been delivered to the following recipients: Diane Erasmus ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
4
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
5
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
6
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
7
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
8
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
9
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
10
Amelia VisagieFrom: Microsoft OutlookTo: Diane ErasmusSent: Wednesday, December 14, 2016 4:04 PMSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Your message has been delivered to the following recipients: Diane Erasmus ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
11
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mail1.nwpg.gov.za. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system <[email protected]>: delivery via 0.mx.nwpg.gov.za.internal[10.145.142.11]:25:
250 Ok
12
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 4:29 PMTo: Amelia VisagieSubject: Read report : NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Green Category
Recipient: [email protected] Time of reading : 2016/12/14 04:28 PM Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Proje
13
Amelia VisagieFrom: Natasha Higgitt <[email protected]>Sent: Wednesday, December 14, 2016 4:25 PMTo: Amelia VisagieSubject: Re: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: image001.png; image002.png; image003.png; image004.png; image005.png; image006.png; image007.pngCategories: Purple Category
Good afternoon, Thank you for notifying SAHRA of the proposed development. Please note that SAHRA does not accept posted, emailed, hardcopy or website links as official submissions. Please create a case on the South African Heritage Resources Information System (SAHRIS). Please see step-by-step tutorial videos on the SAHRIS home page (http://sahra.org.za/sahris/). Please inform me when this has been completed and reference the Case ID number. Kind Regards, Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502 | F: +27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town www.sahra.org.za Please note that SAHRA will be closed for the Festive Season from the 26th to the 30th December 2016. Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502| C:+27 82 507 0378| F:+27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town | 8001 www.sahra.org.za
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.SAHRA Logo
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.SAHRA Values
From: "Amelia Visagie" To: "tiro seleka" , [email protected], "gaoruiwe matlawe" , [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], "mosenki lemme" , [email protected], "Pieter Swart" , [email protected], [email protected], "Biance Schoeman" , [email protected], [email protected], "alpheus matseke" , "Litha Mnqojana" , "nietverdiend sc" , [email protected] Sent: Wednesday, 14 December, 2016 4:11:50 PM
14
Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Project. The attached Background Information Document (BID) and notification letter will give you some background information about the project. Please send the relevant contact person’s information through to:
The Public Participation Office Aurecon South Africa (Pty) Ltd Attention: Ms Amelia Visagie Fax: +27 86 538 6115 Tel: +27 12 427 3149 Email: [email protected]
Please inform any other person that might be interested to register on the project. Kind regards, Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER This electronic communication and its content(s) are subject to a disclaimer which can be accessed here: http://mail.sahra.org.za/disclaimer.html
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.Break The Corruption Chain
15
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 4:36 PMSubject: Undeliverable: Change of email address.
This is the mail system at host relay.mailchannels.net. I'm sorry to have to inform you that your message could not be delivered to one or more recipients. It's attached below. For further assistance, please send mail to postmaster. If you do so, please include this problem report. You can delete your own text from the attached returned message. The mail system <[email protected]>: host fw2a.nwpb.org.za[196.220.62.2] said: 550 23.83.214.25 is not allowed to send mail from aurecongroup.com. Please see http://www.openspf.net/Why?scope=mfrom;[email protected];ip=23.83.214.25 (in reply to end of DATA command)
16
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 6:04 PMTo: Amelia VisagieSubject: Read report : NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Green Category
Recipient: [email protected] Time of reading : 14/12/2016 06:04 pm Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission P
17
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 7:21 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mx1.wmi2.net. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system
<[email protected]>: delivery via dovelmtp: delivered via dovelmtp service
18
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 7:19 PMTo: Amelia VisagieSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: ATT00001Categories: Green Category
Your message was delivered to the recipient. Sent via my BlackBerry from Vodacom - let your email find you!
19
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Thursday, December 15, 2016 3:38 AMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mx2.wmi2.net. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system
<[email protected]>: delivery via dovelmtp: delivered via dovelmtp service
1
Amelia VisagieFrom: Amelia VisagieSent: Thursday, December 15, 2016 9:34 AMTo: 'Roets Wietsche'Subject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Yellow Category, Green Category
Thank you for your mail We have already informed the regions yesterday. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Roets Wietsche [mailto:[email protected]] Sent: Thursday, December 15, 2016 7:04 AM To: Amelia Visagie <[email protected]> Subject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Please send this to the relevant regions as they are to be notified. Kind regards Wietsche From: Amelia Visagie [mailto:[email protected]] Sent: 14 December 2016 04:12 PM To: [email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN); Makwela Clement (MMB); Ackerman Pieter; Roets Wietsche; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Project. The attached Background Information Document (BID) and notification letter will give you some background information about the project. Please send the relevant contact person’s information through to:
The Public Participation Office Aurecon South Africa (Pty) Ltd Attention: Ms Amelia Visagie
2
Fax: +27 86 538 6115 Tel: +27 12 427 3149 Email: [email protected]
Please inform any other person that might be interested to register on the project. Kind regards, Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use, alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e-mail, nor for any consequence of its use or storage.
3
Amelia VisagieFrom: Amelia VisagieSent: Tuesday, January 10, 2017 3:15 PMTo: 'IzakVDM'Cc: Diane ErasmusSubject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Yellow Category
Thank you Izak. I will ensure to update our database with the relevant information. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: IzakVDM [mailto:[email protected]] Sent: Tuesday, January 10, 2017 2:57 PM To: Amelia Visagie <[email protected]> Subject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Amelia Your principal contact at DAFF for the above project is Ms Mulalo Sundani with contact details given below. I will be involved on providing her with technical advice where necessary. Kind regards Izak van der Merwe Forestry Scientific Services Department of Agriculture, Forestry and Fisheries Tel 012-3095771 Cell 0849102604 Email: [email protected] From: MulaloSU Sent: 10 January 2017 12:42 PM To: [email protected] Cc: RennyM; IzakVDM; ShumaniD Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Good Day Ms Amelia Visagie
4
The Department of Agriculture , Forestry and Fisheries is hereby acknowledge the receipt of the above-mentioned Notification of the Environmental Impacts Assessment Report for the proposed Botswana –South Africa Transmission Interconnection Project. For more information on the matter, kindly contact Ms Mulalo Sundani at [email protected] : (012) 309 5865 , Ms Shumani Dzivhani at [email protected] : (012) 3095765 or Mr Izak van der Merwe at [email protected]: (012) 309 5771 Regards Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Tel: 012 309 5865 E-mail: [email protected] [email protected]
5
Amelia VisagieFrom: Amelia VisagieSent: Tuesday, January 10, 2017 3:19 PMTo: 'MulaloSU'Cc: RennyM; IzakVDM; ShumaniD; Diane Erasmus; Wendy MlotshwaSubject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Yellow Category
Thank you Mr Sundani I Acknowledge receipt of your mail and will ensure to update the BOSA database accordingly. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: MulaloSU [mailto:[email protected]] Sent: Tuesday, January 10, 2017 12:42 PM To: Amelia Visagie <[email protected]> Cc: RennyM <[email protected]>; IzakVDM <[email protected]>; ShumaniD <[email protected]> Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Good Day Ms Amelia Visagie The Department of Agriculture , Forestry and Fisheries is hereby acknowledge the receipt of the above-mentioned Notification of the Environmental Impacts Assessment Report for the proposed Botswana –South Africa Transmission Interconnection Project. For more information on the matter, kindly contact Ms Mulalo Sundani at [email protected] : (012) 309 5865 , Ms Shumani Dzivhani at [email protected] : (012) 3095765 or Mr Izak van der Merwe at [email protected]: (012) 309 5771 Regards Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Tel: 012 309 5865 E-mail: [email protected] [email protected]
7
Amelia VisagieFrom: Amelia VisagieSent: Wednesday, January 11, 2017 12:20 PMTo: 'Biance Schoeman Transnet Group Capital'Cc: Diane Erasmus; Wendy Mlotshwa; Richard ArtheySubject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Yellow Category, Green Category
Good day Biance, Thank you for your mail. This mail is to inform you that the information you requested will be given in the scoping report. We will inform you when the report is ready for comments. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Biance Schoeman Transnet Group Capital [mailto:[email protected]] Sent: Monday, January 9, 2017 8:31 AM To: Amelia Visagie <[email protected]> Subject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Amelia, Thank you for the BID and Stakeholder letter. Is there currently any maps available indicating whether the transmission line will cross railway or pipeline servitude(s) in the area? The Transnet stakeholder that will register will depend on which servitudes is being impacted. Kind regards,
Biance Schoeman Environmental Specialist SACNASP Candidate Natural Scientist Transnet Group Capital - 40th floor T: +27 (011) 308-4708 / M: +27 (0)78 099 0369 Carlton Centre, 150 Commissioner Street, Johannesburg
From: Amelia Visagie [mailto:[email protected]] Sent: 14 December 2016 04:12 PM To: [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected];
8
[email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Biance Schoeman Transnet Group Capital; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Project. The attached Background Information Document (BID) and notification letter will give you some background information about the project. Please send the relevant contact person’s information through to:
The Public Participation Office Aurecon South Africa (Pty) Ltd Attention: Ms Amelia Visagie Fax: +27 86 538 6115 Tel: +27 12 427 3149 Email: [email protected]
Please inform any other person that might be interested to register on the project. Kind regards, Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
10
Amelia VisagieFrom: Willie Gunther | Avenatus <[email protected]>Sent: Wednesday, January 11, 2017 2:12 PMTo: Amelia VisagieCc: 'Pat Loots'; 'Andre Friedman'Subject: RE: FW: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Yellow Category
Thanks Amelia WILLIE GUNTHER SEL/CEL 0829245514
From: Amelia Visagie [mailto:[email protected]] Sent: Wednesday, 11 January 2017 1:55 PM To: Willie Gunther | Avenatus Cc: 'Pat Loots'; 'Andre Friedman'; Diane Erasmus; Wendy Mlotshwa; Richard Arthey; Kagiso Sakarea Subject: RE: FW: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Good day Willie, Thank you for your mail. I acknowledge receipt and will forward the maps to you as soon as our people are back from leave. It probably be somewhere next week. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Willie Gunther | Avenatus [mailto:[email protected]] Sent: Wednesday, January 11, 2017 1:16 PM To: Amelia Visagie <[email protected]> Cc: 'Pat Loots' <[email protected]>; 'Andre Friedman' <[email protected]> Subject: FW: FW: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Amelia My e/mail dd. 28December 2016 has reference. Kindly provide me with the requested information and acknowledge receipt of my mail
11
regards WILLIE GUNTHER SEL/CEL 0829245514
From: Willie Gunther | Avenatus [mailto:[email protected]] Sent: Wednesday, 28 December 2016 10:54 PM To: '[email protected]' Cc: '[email protected]' Subject: FW: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Amelia & Other NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT With reference to you mail dd. 14/12/2016 Herewith the required interested party form Kindly provide us with a detailed arial map showing the exact GPS points where the proposed electrical lines will cross the all dirt & tar roads in Nietverdient area. Kindly ensure that you forward any communication to in to both e/mails [email protected] [email protected] regards WILLIE GUNTHER SEL/CEL 0829245514
12
This email has been checked for viruses by Avast antivirus software. www.avast.com
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.
This email has been checked for viruses by Avast antivirus software. www.avast.com
13
Amelia VisagieFrom: PPP AurecongroupSent: Friday, January 20, 2017 12:01 PMTo: 'Andre Nel'; PPP AurecongroupCc: Diane Erasmus; Wendy MlotshwaSubject: RE: EIA BOSA Transmission interconnection ProjectCategories: Yellow Category, Green Category
Good morning Andre We have done a deeds search and got the information from there. Will you be able to assist me with the new owners contact detail please? I will then be able to update the database with the correct information. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Andre Nel [mailto:[email protected]] Sent: Tuesday, January 10, 2017 4:58 PM To: PPP Aurecongroup <[email protected]> Subject: EIA BOSA Transmission interconnection Project Good day, You have sent a letter to Francina Petronella Johanna Elizabet Jansen, PO Box 2, Shelly Beach as a Land Owner. Please let me know where you got this information as their property(Mrs Jansen and her late husband- my father and mother in law), which is a portion of the Farm Groenvallei, was sold during December 2000 and the property transferred into the new owner's name. She has relocated during December 2000 to Shelly Beach. Thank you and best regards. --
14
Amelia VisagieFrom: MulaloSU <[email protected]>Sent: Friday, February 3, 2017 5:27 PMTo: Amelia VisagieCc: RennyM; IzakVDM; ShumaniD; Diane Erasmus; Wendy MlotshwaSubject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: Comments on the notice of EIA for the proposed Botswana -South Africa Transmission Interconnected Project.pdfCategories: Yellow Category
Good Day Ms Amelia Visagie Kindly receive attached comments on the notification of Environmental Impact Assessment for the proposed Botswana –South Africa (BOSA) Regards Ms Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Cell: 0760216115 Tel: 012 309 5865 E-mail: [email protected] [email protected] From: Amelia Visagie [mailto:[email protected]] Sent: 10 January 2017 03:19 PM To: MulaloSU Cc: RennyM; IzakVDM; ShumaniD; Diane Erasmus; Wendy Mlotshwa Subject: RE: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Thank you Mr Sundani I Acknowledge receipt of your mail and will ensure to update the BOSA database accordingly. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER
15
From: MulaloSU [mailto:[email protected]] Sent: Tuesday, January 10, 2017 12:42 PM To: Amelia Visagie <[email protected]> Cc: RennyM <[email protected]>; IzakVDM <[email protected]>; ShumaniD <[email protected]> Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Good Day Ms Amelia Visagie The Department of Agriculture , Forestry and Fisheries is hereby acknowledge the receipt of the above-mentioned Notification of the Environmental Impacts Assessment Report for the proposed Botswana –South Africa Transmission Interconnection Project. For more information on the matter, kindly contact Ms Mulalo Sundani at [email protected] : (012) 309 5865 , Ms Shumani Dzivhani at [email protected] : (012) 3095765 or Mr Izak van der Merwe at [email protected]: (012) 309 5771 Regards Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Tel: 012 309 5865 E-mail: [email protected] [email protected]
16
Amelia VisagieFrom: Diane ErasmusSent: Monday, February 6, 2017 2:38 PMTo: Sebenzile VilakaziCc: Wendy Mlotshwa; Amelia VisagieSubject: RE: BOSA project - Stakeholder Engagement PlanCategories: Yellow Category
Thanks Sebenzile. We will update the timelines. Kind regards Diane Diane Erasmus EAP, MSc Nature Conservation Associate, Aurecon T +27 44 8055428 F +27 44 8055454 [email protected] DISCLAIMER From: Sebenzile Vilakazi [mailto:[email protected]] Sent: Monday, February 06, 2017 1:30 PM To: Diane Erasmus <[email protected]> Cc: Wendy Mlotshwa <[email protected]>; Amelia Visagie <[email protected]> Subject: RE: BOSA project - Stakeholder Engagement Plan Hi Diane The plan seems fine except that the map in it needs to change as well as the timelines to accommodate the new substation study area. Sebenzile Vilakazi Senior Environmental Advisor ERE: Land Development Group Capital Megawatt Park D1Z42 PO Box 1091 Johannesburg 2000 T +27 (0)11 800 4902 M +27 (0)82 885 8114 F +27 (0)11 800 3917 E-mail [email protected]
From: Diane Erasmus [mailto:[email protected]] Sent: 31 January 2017 03:19 PM To: Sebenzile Vilakazi Cc: Wendy Mlotshwa; Amelia Visagie Subject: BOSA project - Stakeholder Engagement Plan
17
Hi Sebenzile It was good to see you again today. Please could you confirm, as discussed, that you are happy with the Stakeholder Engagement Plan for the project and we can take it forward to the greater project team for sign off. Thank you. Kind regards Diane Diane Erasmus EAP, MSc Nature Conservation Associate, Aurecon T +27 44 8055428 F +27 44 8055454 [email protected] Suite 201, 2nd Floor, Bloemhof Building, 65 York Street, George South Africa 6529 PO Box 509, George 6530 South Africa aurecongroup.com
DISCLAIMER NB: This Email and its contents are subject to the Eskom Holdings SOC Limited EMAIL LEGAL NOTICE which can be viewed at http://www.eskom.co.za/Pages/Email_Legal_Spam_Disclaimer.aspx
18
Amelia VisagieFrom: Willie Gunther | Avenatus <[email protected]>Sent: Tuesday, April 11, 2017 10:29 AMTo: Amelia VisagieSubject: RE: Feedback after meetingCategories: Yellow Category
Thanks for your feedback Amelia regards WILLIE GUNTHER SEL/CEL 0829245514
From: Amelia Visagie [mailto:[email protected]] Sent: Tuesday, 11 April 2017 10:17 AM To: 'Pat Loots' Cc: Diane Erasmus; Nigel Waters; Deon Vrey; Noeleen Greyling; Wendy Mlotshwa; Willie Gunther | Avenatus Subject: Feedback after meeting Good day Pat, Thank you for taking time to visit us last week. It was interesting to hear about your expansion ideas and how the BOSA project may impact your planning process. Thank you for sharing your perspective on the potential constraints on your land and the surrounding area. As indicated in our meeting, we are currently in the feasibility phase of the project, so we are still a minimum of twelve months away from a decision as to whether to construct the line or not. This decision will be taken by SAPP CC, as the client, as well as the two Sponsor utilities. As the appointed Transaction Advisor, Aurecon is actively engaging with affected stakeholders and considering potential impacts on the proposed line route. At this early stage of the project, the first step in this instance is to review the line route in light of the specific constraints that you have brought to our attention. The outcome of this review will be communicated to you in due course for your further consideration and interaction. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER
19
DISCLAIMER
Right-click here to download pictures. To help protect your privacy, Outlook prevented auto matic downlo ad o f this picture from the Internet.
Virus-free. www.avast.com
20
Amelia VisagieFrom: Pat Loots <[email protected]>Sent: Tuesday, April 11, 2017 1:56 PMTo: Amelia VisagieCc: Diane Erasmus; Nigel Waters; Deon Vrey; Noeleen Greyling; Wendy Mlotshwa; 'Willie Gunther | Avenatus'Subject: RE: Feedback after meetingCategories: Yellow Category
Gaad Day Amelia, Thanks for your time and input , hope my farm will be a farm with a future in Nwes. Stay well. Kind regards. Pat Loots Cell: +27 (0) 82 494 0989 Email: [email protected]
From: Amelia Visagie [mailto:[email protected]] Sent: 11 April 2017 10:17 AM To: 'Pat Loots' Cc: Diane Erasmus; Nigel Waters; Deon Vrey; Noeleen Greyling; Wendy Mlotshwa; Willie Gunther | Avenatus Subject: Feedback after meeting Good day Pat, Thank you for taking time to visit us last week. It was interesting to hear about your expansion ideas and how the BOSA project may impact your planning process. Thank you for sharing your perspective on the potential constraints on your land and the surrounding area. As indicated in our meeting, we are currently in the feasibility phase of the project, so we are still a minimum of twelve months away from a decision as to whether to construct the line or not. This decision will be taken by SAPP CC, as the client, as well as the two Sponsor utilities. As the appointed Transaction Advisor, Aurecon is actively engaging with affected stakeholders and considering potential impacts on the proposed line route. At this early stage of the project, the first step in this instance is to review the line route in light of the specific constraints that you have brought to our attention. The outcome of this review will be communicated to you in due course for your further consideration and interaction. Kind regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER
21
DISCLAIMER
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.Avast logo
This email has been checked for viruses by Avast antivirus software. www.avast.com
1
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
1
Amelia VisagieFrom: Amelia VisagieSent: Tuesday, August 1, 2017 4:56 PMTo: Wendy Mlotshwa; Diane ErasmusSubject: FW: Comments on the draft Scoping Report for the proposed BOS Transmission Interconnected ProjectAttachments: COMMENTS ON THE DRAFT SCOPING REPORT FOR THE PROPOSED BOSA TRANSMISSION INTERCONNECTED PROJECT.pdf
Good day everyone, Please receive the feedback from DAFF for your attention. Kind regards Amelia Visagie Senior Consultant, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: MulaloSU [mailto:[email protected]] Sent: Tuesday, August 1, 2017 1:43 PM To: Amelia Visagie <[email protected]>; PPP Aurecongroup <[email protected]> Cc: ShumaniD <[email protected]> Subject: Comments on the draft Scoping Report for the proposed BOS Transmission Interconnected Project Good Day Mrs Visagie Kindly receive attached comments on the draft Scoping Report for the proposed BOS Transmission Interconnected Project Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Cell: 0760216115 Tel: 012 309 5865 E-mail: [email protected] [email protected]
1
Amelia VisagieFrom: Amelia VisagieSent: Wednesday, July 12, 2017 2:35 PMTo: '[email protected]'Cc: Wendy Mlotshwa; Roshantha Nanoolal; Diane ErasmusSubject: NOTICE OF SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT PROCESS (ESIA) FOR THE BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Good day Mr Ackerman Thank you for your email. The Botswana –South Africa Transmission Interconnection Project will undertake the relevant authorisation in term of the National Water Act (Act 36 of 1998). A pre application meeting was held with the Mahikeng DWS Regional office on the 28 February 2017 with Clement Makwela. Water uses that are identified for authorisation includes the following: Section 21 (c and i) water uses for construction of pylon within the 500m buffer of wetland or within the
1:100 year flood line of the water course or within a wetland/watercourse. Section 21 (a) for abstraction of water form a water resource for construction The application has not yet been submitted to DWS Mahikeng office and currently being compiled by Aurecon. Please let me know if you need any additional information. Kind regards Amelia Visagie Senior Consultant, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Ackerman Pieter [mailto:[email protected]] Sent: Monday, July 10, 2017 8:08 AM To: Amelia Visagie <[email protected]> Subject: RE: NOTICE OF SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT PROCESS (ESIA) FOR THE BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Hi Is any water use authorisation required? Regards Pieter Ackerman (PrLArch) Chief Landscape Architect Department of Water and Sanitation (DWS), South Africa Sub Directorate Instream Water Use Tel: 012 336 8217 Cell: 082 807 3512 Fax: 012 336 6608
2
From: Amelia Visagie [mailto:[email protected]] Sent: 28 June 2017 04:53 PM To: [email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN); Makwela Clement (MMB); Ackerman Pieter; Roets Wietsche; [email protected]; [email protected]; [email protected]; Shumani Dzivhani; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Cc: Diane Erasmus; Wendy Mlotshwa; [email protected] Subject: NOTICE OF SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT PROCESS (ESIA) FOR THE BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear stakeholder, This mail serves to inform you about the next phase of the Environmental and Social Impact assessment Process (ESIA) for the proposed Botswana-South Africa (BOSA) Transmission Interconnection Project. The attached Executive summary and letter provides background information on the project. The Draft Scoping Report is available for review and comment, as detailed in the attachment. Details of meetings to be held in the week of the 17 July 2017 are also provided. Please send any updates related to the database information, as well as concerns or queries to:
The Public Participation Office Aurecon South Africa (Pty) Ltd Attention: Ms Amelia Visagie Fax: +27 86 538 6115 Tel: +27 12 427 3149 Email: [email protected]
Please also inform any other person that might be interested to register on the project and attend meetings. We look forward to your participation in the project Kind regards, Amelia Visagie Project Manager, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER
DISCLAIMER DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use,
3
alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e-mail, nor for any consequence of its use or storage.
1
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
2
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
3
Amelia VisagieFrom: Microsoft OutlookTo: Diane ErasmusSent: Wednesday, December 14, 2016 4:05 PMSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Your message has been delivered to the following recipients: Diane Erasmus ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
4
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
5
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
6
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
7
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
8
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
9
Amelia VisagieFrom: Microsoft OutlookTo: [email protected]: Wednesday, December 14, 2016 4:04 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Delivery to these recipients or groups is complete, but no delivery notification was sent by the destination server: [email protected] ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
10
Amelia VisagieFrom: Microsoft OutlookTo: Diane ErasmusSent: Wednesday, December 14, 2016 4:04 PMSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
Your message has been delivered to the following recipients: Diane Erasmus ([email protected]) Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
11
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 4:05 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mail1.nwpg.gov.za. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system <[email protected]>: delivery via 0.mx.nwpg.gov.za.internal[10.145.142.11]:25:
250 Ok
12
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 4:29 PMTo: Amelia VisagieSubject: Read report : NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Green Category
Recipient: [email protected] Time of reading : 2016/12/14 04:28 PM Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Proje
13
Amelia VisagieFrom: Natasha Higgitt <[email protected]>Sent: Wednesday, December 14, 2016 4:25 PMTo: Amelia VisagieSubject: Re: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: image001.png; image002.png; image003.png; image004.png; image005.png; image006.png; image007.pngCategories: Purple Category
Good afternoon, Thank you for notifying SAHRA of the proposed development. Please note that SAHRA does not accept posted, emailed, hardcopy or website links as official submissions. Please create a case on the South African Heritage Resources Information System (SAHRIS). Please see step-by-step tutorial videos on the SAHRIS home page (http://sahra.org.za/sahris/). Please inform me when this has been completed and reference the Case ID number. Kind Regards, Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502 | F: +27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town www.sahra.org.za Please note that SAHRA will be closed for the Festive Season from the 26th to the 30th December 2016. Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502| C:+27 82 507 0378| F:+27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town | 8001 www.sahra.org.za
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.SAHRA Logo
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.SAHRA Values
From: "Amelia Visagie" To: "tiro seleka" , [email protected], "gaoruiwe matlawe" , [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], [email protected], "mosenki lemme" , [email protected], "Pieter Swart" , [email protected], [email protected], "Biance Schoeman" , [email protected], [email protected], "alpheus matseke" , "Litha Mnqojana" , "nietverdiend sc" , [email protected] Sent: Wednesday, 14 December, 2016 4:11:50 PM
14
Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission Project. The attached Background Information Document (BID) and notification letter will give you some background information about the project. Please send the relevant contact person’s information through to:
The Public Participation Office Aurecon South Africa (Pty) Ltd Attention: Ms Amelia Visagie Fax: +27 86 538 6115 Tel: +27 12 427 3149 Email: [email protected]
Please inform any other person that might be interested to register on the project. Kind regards, Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER This electronic communication and its content(s) are subject to a disclaimer which can be accessed here: http://mail.sahra.org.za/disclaimer.html
Right-click here to download pictures. To help protect your privacy, Outlo ok prevented auto matic download of this pictu re from the In ternet.Break The Corruption Chain
15
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 4:36 PMSubject: Undeliverable: Change of email address.
This is the mail system at host relay.mailchannels.net. I'm sorry to have to inform you that your message could not be delivered to one or more recipients. It's attached below. For further assistance, please send mail to postmaster. If you do so, please include this problem report. You can delete your own text from the attached returned message. The mail system <[email protected]>: host fw2a.nwpb.org.za[196.220.62.2] said: 550 23.83.214.25 is not allowed to send mail from aurecongroup.com. Please see http://www.openspf.net/Why?scope=mfrom;[email protected];ip=23.83.214.25 (in reply to end of DATA command)
16
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 6:04 PMTo: Amelia VisagieSubject: Read report : NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTCategories: Green Category
Recipient: [email protected] Time of reading : 14/12/2016 06:04 pm Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT Dear Stakeholder, You have been identified as a potential key stakeholder for the above-mentioned application for environmental authorisation of a proposed Botswana-South Africa (BOSA) Transmission P
17
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Wednesday, December 14, 2016 7:21 PMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mx1.wmi2.net. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system
<[email protected]>: delivery via dovelmtp: delivered via dovelmtp service
18
Amelia VisagieFrom: [email protected]: Wednesday, December 14, 2016 7:19 PMTo: Amelia VisagieSubject: Delivered: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: ATT00001Categories: Green Category
Your message was delivered to the recipient. Sent via my BlackBerry from Vodacom - let your email find you!
19
Amelia VisagieFrom: Mail Delivery System <[email protected]>To: [email protected]: Thursday, December 15, 2016 3:38 AMSubject: Relayed: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT
This is the mail system at host mx2.wmi2.net. Your message was successfully delivered to the destination(s) listed below. If the message was delivered to mailbox you will receive no further notifications. Otherwise you may still receive notifications of mail delivery errors from other systems. The mail system
<[email protected]>: delivery via dovelmtp: delivered via dovelmtp service
1
Wendy Mlotshwa
From: Wendy MlotshwaSent: Monday, September 11, 2017 9:32 AMTo: Diane Erasmus; Amelia VisagieSubject: FW: Delivery details: Dept. of Rural Environmental & Agriculture, Mmabatho
Proof of Delivery. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Consultant, Environment and Planning, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected]
DISCLAIMER
From: Terence Cornelius Sent: Monday, September 11, 2017 9:29 AM To: Wendy Mlotshwa <[email protected]> Subject: Delivery details: Dept. of Rural Environmental & Agriculture, Mmabatho
Good morning Wendy Hope you are well? Please find below delivery details and person who signed for the Urgent Documents to: Dept. of Rural Environmental & Agriculture, Mmabatho
Thank you
2
Regards Terence Cornelius Business Support: F&P Facilitator, Aurecon T +27 12 4272004 F +27 12 4272010 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
1
Wendy Mlotshwa
From: Amelia VisagieSent: Friday, September 08, 2017 10:06 AMTo: '[email protected]'Cc: Wendy Mlotshwa; Diane ErasmusSubject: Comments on the draft Scoping Report for the proposed BOSA Transmission Interconnected Project
Good day Natasha; Thank you once again for your feedback on the proposed BOSA Transmission Interconnected project. Please see below the feedback on your comments: The comment is noted and an HIA has been commissioned in compliance with section 38(3) of the NHRA. The visual impacts of the proposed development on heritage resources and the comments from the public regarding heritage resources will be taken into consideration in the HIA. The compiled HIA will be submitted to SAHRA as the commenting authority during the public comment period as per the NEMA EIA 2014 Regulations (as amended). Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
1
Wendy Mlotshwa
From: PPP AurecongroupSent: Tuesday, September 05, 2017 1:34 PMTo: Wendy MlotshwaCc: Diane ErasmusSubject: FW: 112581 - Botswana-South Africa transmission interconnection project
Good day Wendy I have just received this mail. Will you please give feedback to Obitseng? I can’t see where the person is from – looks according to the email like North West Provincial Government. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
From: Obitseng Moholo [mailto:[email protected]] Sent: Monday, September 4, 2017 4:12 PM To: PPP Aurecongroup <[email protected]> Subject: 112581 ‐ Botswana‐South Africa transmission interconnection project
Good afternoon. The Department would like to know if the file is still open because since we received the notice for EIA process on 12 January 2017 we haven't received anything report until now. Please let us know if the file is still active or not. Kind Regards Obitseng
Disclaimer
"This e-mail and any files transmitted with it may contain information which is confidential, private or privilege in nature and it is for the sole use of the recipient to whom it is addressed. If you are not the intended recipient, you must
immediately notify the sender via electronic mail and further refrain from reading, disseminating, distributing, copying or using this message or any of its transmitted files. Any views of this message and its transmitted files are those of the
sender unless the sender specifically states such views to be those of the North-West Provincial Government. Though this message and its transmitted files have been swept for the presence of computer viruses, the North-West Provincial
Government accepts no liability whatsoever for any loss, damage or expenses resulting directly or indirectly from the use or access of this message or any of its transmitted files."
Interim CommentIn terms of Section 38(3) of the National Heritage Resources Act (Act 25 of 1999)
Attention: Mr David TunnicliffEskom Holdings SOC Ltd
Proposed 400kV transmission power line, stretching between the Mahikeng area (North WestProvince) in South Africa and Gaborone in Botswana. The line will connect the existing Isangsubstation in Botswana to the proposed Watershed B substation in South Africa.
Aurecon South Africa (Pty) has been appointed by the Southern African Power Pool (SAPP) to conduct anEnvironmental Impact Assessment (EIA) process for the proposed Botswana-South Africa (BOSA)Transmission Interconnection Project, North West Province. A draft Scoping Report has been submitted interms of the National Environmental Management Act, Act No 107 of 1998 (NEMA) and the NEMA EIA 2014Regulations. It must be noted that this project crosses the border of South Africa to Botswana. The commentsissued by SAHRA apply only to the section of the project within the borders of South Africa.
The proposed development will include the construction of approximately 560 km 400kV transmission lineconnecting the Isang 400kV substation in Botswana to a proposed new Watershed B 400/132 kV substation inthe North West Province, South Africa and further connecting the proposed Watershed B substation to theMookoodi and Pluto 400kV substations in the North West Province, South Africa. A total of five (5) alternativeroutes are being considered. Option C is the preferred route. Three routes are being considered for theWatershed B-Isang Route, Option 2 is the preferred option. Three alternative locations are being consideredfor Watershed B Substation, Option C is the least preferred option.
G & A Heritage: Heritage Management Consultants were appointed to conduct the Heritage Pre-ScopingReport.
Gaigher, S. 2016. Heritage Pre-Scoping Report for the First Phase of Investigation into the Heritage Sensitivityof the proposed BOSA Power Line Alignment.
Several types of heritage resources have been identified to be located within and around the proposedpowerline routes. These include Palaeo-Anthropological sites, Stone Age and Iron Age sites, Rock Art sites,battlefields, cemeteries, historic farmlands, historic rural towns, historic institutions, and scenic routes.
Recommendations provided include that the final alignment of the Watershed B to BOSA connecting lines be
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Thursday August 10, 2017
Tel: 021 462 4502
Email: [email protected]
Page No: 1
CaseID: 11363
subjected to a Heritage Walk-down to ensure that it will not impact on historic battle sites associated with theSiege of Mafikeng. It is also recommended that a Heritage Impact Assessment (HIA) be conducted that willinclude desktop data collection, field surveys, oral interviews and public consultation.
Interim Comment
The SAHRA Archaeology, Palaeontology and Meteorites (APM) Unit requests that an HIA must be conductedfor the section of the proposed development located in South Africa. The HIA must assess all heritageresources as defined in section 3(3) of the National Heritage Resources Act, Act 25 of 1999 (NHRA) and theHIA must comply with section 38(3) of the NHRA. The Visual Impact of the proposed development on heritageresources and any comments provided by the public regarding heritage resources must be taken into accountduring the HIA. The HIA must be submitted to SAHRA during the Public Review period as per the NEMA EIA2014 Regulations.
Should you have any further queries, please contact the designated official using the case number quotedabove in the case header.
Yours faithfully
________________________________________ Natasha HiggittHeritage OfficerSouth African Heritage Resources Agency
________________________________________ John GribbleManager: Maritime and Underwater Cultural Heritage Unit / Acting Manager: Archaeology, Palaeontology andMeteorites UnitSouth African Heritage Resources Agency
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Thursday August 10, 2017
Tel: 021 462 4502
Email: [email protected]
Page No: 2
CaseID: 11363
ADMIN:Direct URL to case: http://www.sahra.org.za/node/405813(DEA, Ref: )
.
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Thursday August 10, 2017
Tel: 021 462 4502
Email: [email protected]
Page No: 3
CaseID: 11363
Powered by TCPDF (www.tcpdf.org)
1
Wendy Mlotshwa
From: Natasha Higgitt <[email protected]>Sent: Friday, September 08, 2017 10:10 AMTo: Amelia VisagieCc: Wendy Mlotshwa; Diane ErasmusSubject: Re: Comments on the draft Scoping Report for the proposed BOSA Transmission Interconnected
ProjectAttachments: image001.png; image002.png; image003.png; image004.png; image005.png; image006.png;
image007.png
Good morning, Thank you for the response. SAHRA awaits the HIA. Kind Regards, Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502 | F: +27 21 462 4509 | C: +27 82 507 0378 E: [email protected] | 111 Harrington Street | Cape Town www.sahra.org.za Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502| C:+27 82 507 0378| F:+27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town | 8001 www.sahra.org.za
From: "Amelia Visagie" <[email protected]> To: [email protected] Cc: "Wendy Mlotshwa" <[email protected]>, "Diane Erasmus"
2
<[email protected]> Sent: Friday, 8 September, 2017 10:06:37 AM Subject: Comments on the draft Scoping Report for the proposed BOSA Transmission Interconnected Project Good day Natasha; Thank you once again for your feedback on the proposed BOSA Transmission Interconnected project. Please see below the feedback on your comments: The comment is noted and an HIA has been commissioned in compliance with section 38(3) of the NHRA. The visual impacts of the proposed development on heritage resources and the comments from the public regarding heritage resources will be taken into consideration in the HIA. The compiled HIA will be submitted to SAHRA as the commenting authority during the public comment period as per the NEMA EIA 2014 Regulations (as amended). Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER This electronic communication and its content(s) are subject to a disclaimer which can be accessed here: http://mail.sahra.org.za/disclaimer.html
1
Amelia Visagie
From: Amelia VisagieSent: Thursday, September 21, 2017 7:39 PMTo: '[email protected]'Cc: Roshantha Nanoolal; Diane Erasmus; Wendy MlotshwaSubject: RE: FINAL SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT
REPORT FOR BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT, BETWEEN MAHIKENG (SOUTH AFRICA) AND GABARONE
Dear Mr Ackerman Thank you for you input into the water use authorisation process. Our concern is that access road might influence the GA. Does a risk assessment matrix need to be completed by a relevant specialist to ensure that the access roads are of low risk in order to register the entire activity as a GA . If it is not a low risk, does Eskom still qualify for the GA based on Appendix D2 of GN 509 of 2016? Looking forward to your feedback. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
From: Ackerman Pieter [mailto:[email protected]] Sent: Thursday, September 21, 2017 10:46 AM To: Amelia Visagie <[email protected]>; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN) <[email protected]>; Makwela Clement (GAU) <[email protected]>; Roets Wietsche <[email protected]>; [email protected]; [email protected]; [email protected]; Shumani Dzivhani <[email protected]>; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Cc: Diane Erasmus <[email protected]>; Wendy Mlotshwa <[email protected]>; Marianna Taljaard <[email protected]>; Erika Du Plessis <[email protected]>; Roets Wietsche <[email protected]>; Meulenbeld Paul <[email protected]>; Hadebe Xolani <[email protected]>; Kuse Lumka <[email protected]>; Mulaudzi Nkhumbudzeni <[email protected]>; Khosa Tsunduka <[email protected]> Subject: RE: FINAL SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT REPORT FOR BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT, BETWEEN MAHIKENG (SOUTH AFRICA) AND GABARONE Hi Amelia
2
This activity falls within the ambit of a General Authorisation (Appendix D2) The project must be registered as a GA at the DWS Regional Office. Regards Pieter Ackerman (PrLArch) Chief Landscape Architect Department of Water and Sanitation (DWS), South Africa Sub Directorate Instream Water Use Tel: 012 336 8217 Cell: 082 807 3512 Fax: 012 336 6608
From: Amelia Visagie [mailto:[email protected]] Sent: 21 September 2017 08:06 AM To: [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN); Makwela Clement (GAU); Ackerman Pieter; Roets Wietsche; [email protected]; [email protected]; [email protected]; Shumani Dzivhani; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Cc: Diane Erasmus; Wendy Mlotshwa; Marianna Taljaard; Erika Du Plessis Subject: FINAL SCOPING AND ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT REPORT FOR BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECT, BETWEEN MAHIKENG (SOUTH AFRICA) AND GABARONE Good afternoon all stakeholders, We would like to inform you, as a registered Interested and Affected Party (I&AP), that the Final Scoping Report was submitted to DEA in South Africa last week. The Scoping Report will be submitted to DEA in Botswana shortly. Please see the link to the documents for your information: http://www.aurecongroup.com/en/public-participation/projects/bosa.aspx. You will need to register to review the reports. If you need any addition information please contact: Mrs Amelia Visagie Aurecon South Africa (Pty) Ltd, PO Box 74381, Lynnwood Ridge, 0040 Fax: +27 (0) 86 538 6115, Tel: +27(12) 427 3149, Email: [email protected]
Kind regards
3
Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use, alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e-mail, nor for any consequence of its use or storage.
1
Amelia Visagie
From: Amelia VisagieSent: Wednesday, February 28, 2018 2:40 PMTo: '[email protected]'Cc: Diane Erasmus; Wendy Mlotshwa; Noeleen Greyling; Erika Du PlessisSubject: Comments on the BOSA - Botswana -South Africa Environmental and Social Impact
Assessment Report and EMPr
Dear Mulalo Sundani, Thank you for your feedback on the above mentioned project. Please receive the below feedback regarding your suggestions and concerns. A detailed walkdown by an appropriately qualified specialist will be undertaken before the final placement of pylons prior to construction, to avoid affecting protected trees. As the footprint of the pylons is small it is expected that this should be achieved, However, should any Vachellia erioloba, Boscia Albitrunca or Prunus Africana trees be affected, a licence for removal or disturbance of such species will be made at the Northwest Regional office at the time and the implications in terms of numbers will need to be considered. The Northwest Regional Office of the Department of Agriculture, Forestry and Fisheries will be kept involved in the process should any protected trees be affected. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER DISCLAIMER
From: MulaloSU [mailto:[email protected]] Sent: Tuesday, February 27, 2018 3:30 PM To: Amelia Visagie <[email protected]> Cc: ShumaniD <[email protected]>; ItumelengS <[email protected]>; NevhufumbaL <[email protected]>; NonzameG <[email protected]> Subject: Comments on the Botswana -South Africa Environmental and Social Impact Assessment Report and EMPr Good Day Mrs Visagie Kindly receive attached comments on the Botswana -South Africa (BOSA) Environmental and Social Impact Assessment Report and EMPr for your consideration. Regards Mulalo Sundani Directorate: Forestry Regulation and Oversight Designation: Environmental Impact Management Department of Agriculture , Forestry and Fisheries Cell: 0760216115 Tel: 012 309 5865 E-mail: [email protected] [email protected]
1
Amelia Visagie
From: Amelia VisagieSent: Tuesday, February 27, 2018 11:48 AMTo: '[email protected]'Cc: Diane Erasmus; Wendy Mlotshwa; Erika Du PlessisSubject: Botswana, Medupi powerline and access road: BOSA ENVIRONMENTAL AND
SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT
Dear Mr Ackerman, Thank you for your feedback. Please see our response to your questions and concerns below: I see no water use authorisation required. Response: Several aquatic systems were confirmed within the study area, therefore a water use authorisation will be required. The application will be submitted to the relevant provincial authority once the detailed design is complete and precise water crossings are known. Will there be access road watercourse crossings, road drains? Will they adhere to SANRAL drainage manual....Is that sufficient? Will maintenance include erosion/sedimentation issues? Response: The project is still in the early stages of design, road crossings have not yet been identified or designed and tower positions have not yet been confirmed, hence we have not submitted the application with the DWS. We do however we anticipate that some of the access roads and towers might be within 500 m of the watercourses which will trigger section 21 c and I application. Application will be made once authority once the detailed design is complete and precise water crossings are known Will there be Plant Species Plans drawn up as part of rehabilitation? Response: Yes the plant species plan will be incorporated in the rehabilitation plan. Please let me know whether we answered all your questions and that you are happy with the feedback. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
From: Ackerman Pieter [mailto:[email protected]] Sent: Thursday, January 25, 2018 10:26 AM To: Erika Du Plessis <[email protected]> Cc: Amelia Visagie <[email protected]>; Roets Wietsche <[email protected]>; Mulaudzi Nkhumbudzeni <[email protected]>; Kuse Lumka <[email protected]>; Meulenbeld Paul <[email protected]>; Khosa Tsunduka <[email protected]>; Hadebe Xolani <[email protected]>; Ramudzuli Arinao (GAU) <[email protected]> Subject: Botswana, Medupi powerline and access road: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT Hi Erika I see no water use authorisation required. Will there be access road watercourse crossings, road drains. Will they adhere to SANRAL drainage manual....Is that sufficient? Will maintenance include erosion/sedimentation issues Will there be Plant Species Plans drawn up as part of rehabilitation
2
Regards Pieter Ackerman (PrLArch) Chief Landscape Architect Department of Water and Sanitation (DWS), South Africa Sub Directorate Instream Water Use Tel: 012 336 8217 Cell: 082 807 3512 Fax: 012 336 6608
From: Erika Du Plessis [mailto:[email protected]] Sent: 24 January 2018 05:22 PM To: [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN); Makwela Clement (GAU); Ackerman Pieter; Roets Wietsche; [email protected]; [email protected]; [email protected]; Shumani Dzivhani; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Cc: Amelia Visagie Subject: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT Dear Government Official, The Environmental and Social Impact Assessment (ESIA) Report for the abovementioned project will be available for public comment from 26 January 2018 to 26 February 2018. The attached letter provides information regarding access to the report and also details of public meetings that will be held from 13 February to 16 February 2018. Also attached to this mail is a full summary of the ESIA Report as well as a shortened version in Afrikaans and English for ease of reference. It is important to note that a Final ESIA Report will be submitted to the DEA for decision-making only after the comment period and public meetings to ensure that all comments from I&APs have been taken into consideration in the finalisation of the report. Please use the link below to access the documents for comment: http://www.aurecongroup.com/en/public-participation/projects/bosa.aspx. You will need to register as an I&AP to review the reports. If you need any additional information please contact: Mrs. Amelia Visagie, Aurecon South Africa (Pty) Ltd, PO Box 74381, Lynnwood Ridge, 0040, South Africa Fax: +27 (0) 86 538 6115; Tel: +27(12) 427 3149; Email: [email protected] Kind regards
3
Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 aurecongroup.com
DISCLAIMER DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use, alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e-mail, nor for any consequence of its use or storage.
1
Amelia Visagie
From: Amelia VisagieSent: Wednesday, February 28, 2018 2:33 PMTo: '[email protected]'Cc: Diane Erasmus; Noeleen Greyling; Erika Du Plessis; Wendy MlotshwaSubject: BOSA Putfontein portion 3 and 4 as well as Draailaagte portion 1 and Sandbult Attachments: Putfontein deviation_v2_reduced.pdf
Good day Pat, Thank you for taking time out in your busy schedule to visit our offices. We have good news! Your suggestions were taken into consideration and it was given through to our engineers who made the suggested changes. Please see the attached document with the deviation. Will you be so kind to let me know whether you are happy with the changes. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
DISCLAIMER
1
Amelia Visagie
From: Amelia VisagieSent: Thursday, March 8, 2018 8:04 AMTo: '[email protected]'; '[email protected]'Cc: Diane Erasmus; Erika Du PlessisSubject: FW: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT
AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT
Attachments: BOSA ESIA Ful Summary.pdf; BOSA_ESIA_Short_AFR.pdf; BOSA_ESIA_Eienaar_Afr_SA_Jan18.pdf; Map4_reduced.pdf
More Andries Baie dankie dat ons laas week oor die BOSA projek kon praat. Lyk my die vorige e-pos het jou nie bereik nie. So ek gaan nog ‘n keer probeer. Ek is jammer om te hoor dat jy nie die publieke sessie kon bywoon nie. Dit is goed om te hoor dat jy in prinsiep die projek goedkeur en dat jy net ‘n idee wil kry van waar die transmissie lyn oor jou plase gaan. Soos bespreek heg ek die inligting vir jou aan dat jy ‘n beter idee het van waar ons oor jou plase gaan. Groete Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
DISCLAIMER
1
Wendy Mlotshwa
From: Ackerman Pieter <[email protected]>Sent: Friday, March 02, 2018 12:29 PMTo: Amelia VisagieCc: Diane Erasmus; Wendy Mlotshwa; Erika Du Plessis; Hadebe Xolani; Roets Wietsche; Meulenbeld Paul;
Mulaudzi Nkhumbudzeni; Kuse LumkaSubject: RE: Botswana, Medupi powerline and access road: BOSA ENVIRONMENTAL AND SOCIAL IMPACT
ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT
Hi Remember powerlines are GA for Eskom and other institutions......GA 509 Appendix 2 Crossings can be GA if Risk Matrix show low risk or if SANRAL Drainage Manual is adhered to....Appendix 2 Good news about the Plant Species Plan. Thank you. Regards Pieter Ackerman (PrLArch) Chief Landscape Architect Department of Water and Sanitation (DWS), South Africa Sub Directorate Instream Water Use Tel: 012 336 8217 Cell: 082 807 3512 Fax: 012 336 6608
From: Amelia Visagie [mailto:[email protected]] Sent: 27 February 2018 11:48 AM To: Ackerman Pieter Cc: Diane Erasmus; Wendy Mlotshwa; Erika Du Plessis Subject: Botswana, Medupi powerline and access road: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT Dear Mr Ackerman, Thank you for your feedback. Please see our response to your questions and concerns below: I see no water use authorisation required. Response: Several aquatic systems were confirmed within the study area, therefore a water use authorisation will be required. The application will be submitted to the relevant provincial authority once the detailed design is complete and precise water crossings are known. Will there be access road watercourse crossings, road drains? Will they adhere to SANRAL drainage manual....Is that sufficient? Will maintenance include erosion/sedimentation issues?
2
Response: The project is still in the early stages of design, road crossings have not yet been identified or designed and tower positions have not yet been confirmed, hence we have not submitted the application with the DWS. We do however we anticipate that some of the access roads and towers might be within 500 m of the watercourses which will trigger section 21 c and I application. Application will be made once authority once the detailed design is complete and precise water crossings are known Will there be Plant Species Plans drawn up as part of rehabilitation? Response: Yes the plant species plan will be incorporated in the rehabilitation plan. Please let me know whether we answered all your questions and that you are happy with the feedback. Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected]
DISCLAIMER
From: Ackerman Pieter [mailto:[email protected]] Sent: Thursday, January 25, 2018 10:26 AM To: Erika Du Plessis <[email protected]> Cc: Amelia Visagie <[email protected]>; Roets Wietsche <[email protected]>; Mulaudzi Nkhumbudzeni <[email protected]>; Kuse Lumka <[email protected]>; Meulenbeld Paul <[email protected]>; Khosa Tsunduka <[email protected]>; Hadebe Xolani <[email protected]>; Ramudzuli Arinao (GAU) <[email protected]> Subject: Botswana, Medupi powerline and access road: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT Hi Erika I see no water use authorisation required. Will there be access road watercourse crossings, road drains. Will they adhere to SANRAL drainage manual....Is that sufficient? Will maintenance include erosion/sedimentation issues Will there be Plant Species Plans drawn up as part of rehabilitation Regards Pieter Ackerman (PrLArch) Chief Landscape Architect Department of Water and Sanitation (DWS), South Africa Sub Directorate Instream Water Use Tel: 012 336 8217 Cell: 082 807 3512 Fax: 012 336 6608
From: Erika Du Plessis [mailto:[email protected]] Sent: 24 January 2018 05:22 PM To: [email protected]; [email protected]; [email protected];
3
[email protected]; [email protected]; [email protected]; Ntili Tseliso (BFN); Makwela Clement (GAU); Ackerman Pieter; Roets Wietsche; [email protected]; [email protected]; [email protected]; Shumani Dzivhani; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected]; [email protected] Cc: Amelia Visagie Subject: BOSA ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) REPORT AND ENVIRONMENTAL MANAGEMENT PROGRAMME (EMPr) NOW AVAILABLE FOR PUBLIC COMMENT Dear Government Official, The Environmental and Social Impact Assessment (ESIA) Report for the abovementioned project will be available for public comment from 26 January 2018 to 26 February 2018. The attached letter provides information regarding access to the report and also details of public meetings that will be held from 13 February to 16 February 2018. Also attached to this mail is a full summary of the ESIA Report as well as a shortened version in Afrikaans and English for ease of reference.
It is important to note that a Final ESIA Report will be submitted to the DEA for decision‐making only after the
comment period and public meetings to ensure that all comments from I&APs have been taken into consideration in the finalisation of the report. Please use the link below to access the documents for comment:
http://www.aurecongroup.com/en/public‐participation/projects/bosa.aspx.
You will need to register as an I&AP to review the reports. If you need any additional information please contact:
Mrs. Amelia Visagie, Aurecon South Africa (Pty) Ltd, PO Box 74381, Lynnwood Ridge, 0040, South Africa
Fax: +27 (0) 86 538 6115; Tel: +27(12) 427 3149; Email: [email protected]
Kind regards Amelia Visagie Senior Consultant, Communication and Stakeholder Engagement, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 aurecongroup.com
4
DISCLAIMER DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use, alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e‐mail, nor for any consequence of its use or storage. DISCLAIMER: This message and any attachments are confidential and intended solely for the addressee. If you have received this message in error, please notify the system manager/sender. Any unauthorized use, alteration or dissemination is prohibited. The Department of Water and Sanitation further accepts no liability whatsoever for any loss, whether it be direct, indirect or consequential, arising from this e‐mail, nor for any consequence of its use or storage.
1
Wendy Mlotshwa
From: Wendy MlotshwaSent: Monday, March 12, 2018 3:04 PMTo: 'Natasha Higgitt'Cc: Diane ErasmusSubject: RE: SAHRIS Case ID 11363
Good day Natasha, We apologise for the delayed response to your comments on Draft ESIA and HIA Reports. Our Heritage Specialist is currently addressing your comments. We will be sending you feedback as soon as possible. Kind Regards, Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Consultant, Environment and Planning, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected]
DISCLAIMER
From: Natasha Higgitt [mailto:[email protected]] Sent: Tuesday, March 06, 2018 11:24 AM To: Wendy Mlotshwa <[email protected]> Subject: Re: SAHRIS Case ID 11363 Good morning, Please note that an Interim Comment for SAHRIS Case ID 11363 was issued on the 19 February 2018. Please see email attached of proof of communication and link to the case http://sahra.org.za/sahris/cases/botswana-south-africa-bosa-transmission-interconnection-project. Kind Regards, Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502 | F: +27 21 462 4509 | C: +27 82 507 0378 E: [email protected] | 111 Harrington Street | Cape Town www.sahra.org.za
Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502| C:+27 82 507 0378| F:+27 21 462 4509
2
E: [email protected] | 111 Harrington Street | Cape Town | 8001 www.sahra.org.za
Right-click or tap and hold here to download pictu res. To help protect you r privacy, Outlook prevented auto matic downlo ad o f this pictu re from the In ternet.SAHRA Logo
Right-click or tap and hold here to download pictu res. To help protect you r privacy, Outlook prevented auto matic downlo ad o f this pictu re from the In ternet.SAHRA Values
From: "Wendy Mlotshwa" <[email protected]> To: "Natasha Higgitt" <[email protected]> Sent: Tuesday, 6 March, 2018 10:45:04 AM Subject: RE: SAHRIS Case ID 11363
Dear Natasha,
Hope you are well.
We are in the process of finalising the above mentioned project for final submission to the Department of Environmental Affairs. I just wanted to confirm if SAHRA was satisfied with the information submitted as we did not receive any comments on our Heritage and Draft ESIA reports.
Many Thanks,
Wendy Mlotshwa BSc (Hons.) Environmental Science (Pr.Sci.Nat.) Consultant, Environment and Planning, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected]
DISCLAIMER
From: Lynette Herbst Sent: Wednesday, January 24, 2018 4:58 PM To: [email protected] Cc: Natanya Whitehorn <[email protected]>; Wendy Mlotshwa <[email protected]> Subject: RE: SAHRIS Case ID 11363 and 12152
Dear Natasha
Apologies - it is the same project.
3
The EIA report and the latest HIAs have now been added to case 11363 for review.
Kind regards,
Lynette Herbst MSc Environmental Science; Cand.Sci.Nat. Consultant, Environment and Planning, Aurecon T +27 12 4272627 M +27 72 4399382 [email protected]
DISCLAIMER
From: Natasha Higgitt [mailto:[email protected]] Sent: Wednesday, January 24, 2018 8:20 AM To: Natanya Whitehorn <[email protected]> Subject: SAHRIS Case ID 11363 and 12152
Good morning,
I have noticed a new SAHRIS Case pertaining to the BOSA Transmission Project. Please verify if the project referred to in SAHRIS Case ID 11363 and 12152 is the same project. Should they be the same project, please upload the documents on the newest case to Case ID 11363 as we cannot have duplicate cases.
Kind Regards,
Natasha Higgitt Heritage Officer: Archaeology, Palaeontology and Meteorites Unit
South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502 | F: +27 21 462 4509 | C: +27 82 507 0378 E: [email protected] | 111 Harrington Street | Cape Town www.sahra.org.za
Natasha Higgitt
4
Heritage Officer: Archaeology, Palaeontology and Meteorites Unit South African Heritage Resources Agency - A nation united through heritage - T: +27 21 462 4502| C:+27 82 507 0378| F:+27 21 462 4509 E: [email protected] | 111 Harrington Street | Cape Town | 8001 www.sahra.org.za
Right-click or tap and hold here to download pictu res. To help protect you r privacy, Outlook prevented auto matic downlo ad o f this pictu re from the In ternet.SAHRA Logo
Right-click or tap and hold here to download pictu res. To help protect you r privacy, Outlook prevented auto matic downlo ad o f this pictu re from the In ternet.SAHRA Values
This electronic communication and its content(s) are subject to a disclaimer which can be accessed here: http://mail.sahra.org.za/disclaimer.html
Right-click or tap and hold here to download pictu res. To help protect you r privacy, Outlook prevented auto matic downlo ad o f this pictu re from the In ternet.Break The C orruption Chain
Interim CommentIn terms of Section 38(3), 38(8) of the National Heritage Resources Act (Act 25 of 1999)
Attention: Mr David TunnicliffEskom Holdings SOC Ltd
Proposed 400kV transmission power line, stretching between the Mahikeng area (North WestProvince) in South Africa and Gaborone in Botswana. The line will connect the existing Isangsubstation in Botswana to the proposed Watershed B substation in South Africa.
Aurecon South Africa (Pty) has been appointed by the Southern African Power Pool (SAPP) to conduct anEnvironmental Impact Assessment (EIA) process for the proposed Botswana-South Africa (BOSA)Transmission Interconnection Project, North West Province. A draft Scoping Report has been submitted interms of the National Environmental Management Act, Act No 107 of 1998 (NEMA) and the NEMA EIA 2014Regulations. It must be noted that this project crosses the border of South Africa to Botswana. The commentsissued by SAHRA apply only to the section of the project within the borders of South Africa.
The proposed development will include the construction of approximately 560 km 400kV transmission lineconnecting the Isang 400kV substation in Botswana to a proposed new Watershed B 400/132 kV substation inthe North West Province, South Africa and further connecting the proposed Watershed B substation to theMookoodi and Pluto 400kV substations in the North West Province, South Africa. A total of five (5) alternativeroutes are being considered. Option C is the preferred route. Three routes are being considered for theWatershed B-Isang Route, Option 2 is the preferred option. Three alternative locations are being consideredfor Watershed B Substation, Option C is the least preferred option.
G & A Heritage: Heritage Management Consultants were appointed to conduct the Heritage Pre-ScopingReport.
Gaigher, S. 2016. Heritage Pre-Scoping Report for the First Phase of Investigation into the Heritage Sensitivityof the proposed BOSA Power Line Alignment.
Several types of heritage resources have been identified to be located within and around the proposedpowerline routes. These include Palaeo-Anthropological sites, Stone Age and Iron Age sites, Rock Art sites,battlefields, cemeteries, historic farmlands, historic rural towns, historic institutions, and scenic routes.
Recommendations provided include that the final alignment of the Watershed B to BOSA connecting lines be
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Monday February 19, 2018
Tel: 021 462 4502
Email: [email protected]
Page No: 1
CaseID: 11363
subjected to a Heritage Walk-down to ensure that it will not impact on historic battle sites associated with theSiege of Mafikeng. It is also recommended that a Heritage Impact Assessment (HIA) be conducted that willinclude desktop data collection, field surveys, oral interviews and public consultation.
In an Interim Comment issued on 10/08/2017, SAHRA stated that an HIA must be conducted for the section ofthe proposed development located in South Africa. The HIA must assess all heritage resources as defined insection 3(3) of the National Heritage Resources Act, Act 25 of 1999 (NHRA) and the HIA must comply withsection 38(3) of the NHRA. The Visual Impact of the proposed development on heritage resources and anycomments provided by the public regarding heritage resources must be taken into account during the HIA. TheHIA must be submitted to SAHRA during the Public Review period as per the NEMA EIA 2014 Regulations.
Gaigher, S. 2017. Phase 1 Heritage Impact Assessment Report for the Proposed Botswana South Africa(BOSA) Transmission Project.
It is noted that the entire transmission line was not surveyed and service delivery protests made it difficult toaccess the development area.
The proposed line is located in areas of very high to low palaeontological sensitivity. It must be noted that Fig.29 and 30 do not show the proposed line over the palaeontological sensitivity map.
Heritage resources such as Middle Stone Age (MSA) and Later Stone Age (LSA) artefacts were identifiedalong the proposed route. Possible high risk areas for Stone Age sites were noted in Fig. 41 of the HIA.Surface scatters of Iron Age potsherds were identified along the proposed route. The area is known to consistof Early Iron Age sites, as well as Later Iron Age sites (LIA). Through Lidar and aerial photographs, no suchsites could be identified within the proposed corridor. Smaller Early Iron Age sites may be evident within theproposed route, as the Lidar or aerial photographs would not provide clear images of these smaller sites.Possible sensitive areas for Iron Age sites are noted in Fig. 45.
Several heritage resources were identified from historical maps, such as cemeteries, graves and ruins. Allsites identified from the historical maps are located well outside the development footprint. Several villagesand farmsteads were identified within the proposed route. As is the practice, burials can occur within theconfines of these settlements. The documentation of these burial grounds will form part of the social impactassessment.
The impact assessment showed that the impacts to the palaeontological resources, Stone Age sites, Iron Agesites, Built Environment and burial sites will be medium negative pre-mitigation and low negative post
mitigation.
Recommendations provided in the report include the following:
The final pylon placements should be subjected to a walk-down survey to verify that no sites will beaffected;It is recommended that the development designs consider the positive and negative characteristics ofthe existing cultural landscape type and that they endeavor to promote the positive aspects while at thesame time mitigating the negative aspects;A Chance Finds Procedure is recommended.
The Appendix 9: Heritage Management Plan (HMP) of the Environmental Management Programme (EMPr),and the recommendations contained therein are noted.
Interim Comment
*It must be noted that this project crosses the border of South Africa to Botswana. The comments issued bySAHRA apply only to the section of the project within the borders of South Africa.*
A desktop palaeontological must be conducted by a qualified palaeontologist for the proposed project. Thedesktop study must comply with the 2012 Minimum Standards: Palaeontological Component for HeritageImpact Assessments.
A map/s showing the areas surveyed in relation to the proposed powerline must be submitted. SAHRA doesnot accept the statement in 2.5 of the HIA. Additionally, the Lidar data and aerial photographs used to surveythe line must be provided. Photographs of the Iron Age pottery must be supplied
Further comments will be issued upon receipt of the above.
Should you have any further queries, please contact the designated official using the case number quotedabove in the case header.
Yours faithfully
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Monday February 19, 2018
Tel: 021 462 4502
Email: [email protected]
Page No: 3
CaseID: 11363
________________________________________ Natasha HiggittHeritage OfficerSouth African Heritage Resources Agency
________________________________________ Phillip HineActing Manager: Archaeology, Palaeontology and Meteorites UnitSouth African Heritage Resources Agency
ADMIN:Direct URL to case: http://www.sahra.org.za/node/405813(DEA, Ref: )
.
Botswana-South Africa (BOSA) Transmission Interconnection Project
Our Ref:
Enquiries: Natasha Higgitt Date: Monday February 19, 2018
Tel: 021 462 4502
Email: [email protected]
Page No: 4
CaseID: 11363
Powered by TCPDF (www.tcpdf.org)
1
Amelia VisagieFrom: Chris van Rooyen <[email protected]>Sent: Monday, July 24, 2017 3:05 PMTo: Wendy MlotshwaCc: Diane Erasmus; Amelia Visagie; 'Megan Diamond'Subject: RE: BOSA: Landowner Permission for Access
HI Wendy As advised last week, we will be doing the fieldwork from public roads, therefore we will not need landowner permission. Megan Diamond from Feathers Environmental will be doing the field work on behalf of Chris van Rooyen Consulting. She will be in the field from tomorrow until Thursday, possibly Friday this week. Thanks Best regards/vriendelike groete Chris van Rooyen Chris van Rooyen Consulting 30 Roosevelt Street Robindale Randburg 2194 South Africa Tel. International: +27824549570 Tel. Local: 0824549570 Email: [email protected] “Darkness cannot drive out darkness; only light can do that. Hate cannot drive out hate; only love can do that.” Martin Luther King, Jr. From: Wendy Mlotshwa [mailto:[email protected]] Sent: Monday, 24 July 2017 14:13 To: [email protected] Cc: Diane Erasmus <[email protected]>; Amelia Visagie <[email protected]> Subject: BOSA: Landowner Permission for Access Importance: High Good day Chris, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.)
2
Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
3
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:33 PMTo: Stephan GaigherCc: Diane Erasmus; Amelia VisagieSubject: RE: BOSA: Landowner Permission for Access
Thank you. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] DISCLAIMER From: Stephan Gaigher [mailto:[email protected]] Sent: Monday, July 24, 2017 2:21 PM To: Wendy Mlotshwa <[email protected]> Cc: Diane Erasmus <[email protected]>; Amelia Visagie <[email protected]> Subject: Re: BOSA: Landowner Permission for Access Thanks Wendy, Will do. I will ask Wim (who is handling the Botswana section) for the same. Kind regards,
Stephan Gaigher Chief Executive Officer G&A Heritage (Pty) Ltd 38A Vorster Street Louis Trichardt 0920 [email protected] 0737526583 0155161561 www.gaheritage.co.za
On 2017/07/24 2:14 PM, Wendy Mlotshwa wrote:
Good day Stephan,
4
Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm
property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.)
Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
--
5
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:23 PMTo: Elmie WeidemanCc: Diane Erasmus; Amelia VisagieSubject: RE: BOSA: Landowner Permission for Access
Thanks Elmie Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] DISCLAIMER From: Elmie Weideman Sent: Monday, July 24, 2017 2:22 PM To: Wendy Mlotshwa <[email protected]> Cc: Diane Erasmus <[email protected]>; Amelia Visagie <[email protected]> Subject: RE: BOSA: Landowner Permission for Access Dear Wendy, thanks for the e mail. Noeleen did the site visit on my behalf and all the necessary locations were visited. We don’t have enough budget and therefore 4 days spend working on the report vs. 4 days driving around on site makes much more sense. Best Regards Elmie Weideman PrLArch , ML.(Prof), BL(Hons) Professional Landscape Architect, Aurecon T +27 12 4272537 M +27 79 4993227 [email protected] DISCLAIMER From: Wendy Mlotshwa Sent: Monday, July 24, 2017 2:11 PM To: Elmie Weideman <[email protected]> Cc: Diane Erasmus <[email protected]>; Amelia Visagie <[email protected]> Subject: BOSA: Landowner Permission for Access Importance: High Good day Elmie, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.)
6
Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
7
Amelia VisagieFrom: Elmie WeidemanSent: Monday, July 24, 2017 2:22 PMTo: Wendy MlotshwaCc: Diane Erasmus; Amelia VisagieSubject: RE: BOSA: Landowner Permission for Access
Dear Wendy, thanks for the e mail. Noeleen did the site visit on my behalf and all the necessary locations were visited. We don’t have enough budget and therefore 4 days spend working on the report vs. 4 days driving around on site makes much more sense. Best Regards Elmie Weideman PrLArch , ML.(Prof), BL(Hons) Professional Landscape Architect, Aurecon T +27 12 4272537 M +27 79 4993227 [email protected] DISCLAIMER From: Wendy Mlotshwa Sent: Monday, July 24, 2017 2:11 PM To: Elmie Weideman <[email protected]> Cc: Diane Erasmus <[email protected]>; Amelia Visagie <[email protected]> Subject: BOSA: Landowner Permission for Access Importance: High Good day Elmie, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.) Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
9
Amelia VisagieFrom: Stephan Gaigher <[email protected]>Sent: Monday, July 24, 2017 2:21 PMTo: Wendy MlotshwaCc: Diane Erasmus; Amelia VisagieSubject: Re: BOSA: Landowner Permission for Access
Thanks Wendy, Will do. I will ask Wim (who is handling the Botswana section) for the same. Kind regards,
Stephan Gaigher Chief Executive Officer G&A Heritage (Pty) Ltd 38A Vorster Street Louis Trichardt 0920 [email protected] 0737526583 0155161561 www.gaheritage.co.za
On 2017/07/24 2:14 PM, Wendy Mlotshwa wrote:
Good day Stephan, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm
property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.)
Please send me this information as soon as possible, so we can inform the landowners in advance.
10
Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
--
11
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:14 PMTo: [email protected]: Diane Erasmus; Amelia VisagieSubject: BOSA: Landowner Permission for AccessImportance: High
Good day Stephan, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.) Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
12
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:13 PMTo: [email protected]: Diane Erasmus; Amelia VisagieSubject: BOSA: Landowner Permission for AccessImportance: High
Good day Chris, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.) Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
13
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:11 PMTo: Elmie WeidemanCc: Diane Erasmus; Amelia VisagieSubject: BOSA: Landowner Permission for AccessImportance: High
Good day Elmie, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.) Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
14
Amelia VisagieFrom: Wendy MlotshwaSent: Monday, July 24, 2017 2:10 PMTo: [email protected]: Diane Erasmus; Amelia VisagieSubject: BOSA: Landowner Permission for AccessImportance: High
Good day Brian, Hope you are well. Would you kindly provide the following information so we can assist in getting permission from the affected landowners: Areas you’d like to visit during your fieldwork (you can send me a Google earth file or farm property names); If you will be going to communities or villages – please indicate these, as we will need to inform the relevant
chiefs or tribal authorities; Dates when you will be on site; Names of the people that will be doing the field work with you; and What you will be doing on site more or less (i.e taking soil samples etc.) Please send me this information as soon as possible, so we can inform the landowners in advance. Many Thanks. Wendy Mlotshwa BSc (Hons.) Environmental Science (Cand.Sci.Nat.) Environmentalist, Aurecon T +27 12 4272490 M +27 60 5714933 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
1
Wendy Mlotshwa
From: Noeleen GreylingSent: Monday, July 10, 2017 12:23 PMTo: [email protected]: Amelia VisagieSubject: Impact Assessment for BOSA Transmission Interconnection Project - Meeting requestAttachments: BOSA Project Locality2_Reduced.jpg; Bosa A3P Madikwe_Reduced.jpg; BOSA Project Locality
Wards_Reduced.jpg
Good day,
Aurecon has been appointed to undertake an Environmental and Social Impact Assessment (ESIA) study to assess and
address environmental and social impacts associated with Botswana-South Africa (BOSA) Transmission Interconnection
Project. A social assessment of the study area is required to inform the ESIA of the potential impacts posed by the
construction and operational activities of the proposed project.
I would like to organise a meeting with the reserve manager to obtain input and look at how the proposed project will impact
the reserve.
I am in the area next week with the public participation meetings and would like to sit down with him/her on Wednesday 19
July, as we are of the opinion that the reserve is a key stakeholder in this project.
Please see attached maps to give you a better understanding, our Public Participation Officer, Amelia Visagie will also send
you more Background Information regarding the proposed project.
Please reply as soon as possible so that we can finalise the arrangements.
Kind regards,
Noeleen Greyling BA Environmental Management Social Scientist, Aurecon T +27 12 4272071 M +27 72 3304344 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
1
Amelia VisagieFrom: Amelia VisagieSent: Saturday, June 17, 2017 5:10 PMTo: '[email protected]'Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: BOSA BID_12Dec2016_rev4.pdf; BOSA Notification_OoS SA_Final_12Dec2016_rev2.pdf
Good day Mr Pienaar, I have received your email address from Marinana Taljaard from Aurecon who phoned you this morning. Please find attached the initial information regarding the above mentioned project. I am asking your assistance in helping me to get an appropriate venue for our information sharing session that is taking place during the week of the 17th to the 18th of July 2017. The following places have been identified for landowners and community sessions:
TOWN / COMMUNITY Venue where report to be viewed Meeting Date Meeting Time
SOUTH AFRICA
Miga Klippan Boerevereniging 17 July 2017 11h00 Open House 11h30 Public Meeting
15km from Bewley (a settlement near Ramatlabama border control (RSA)Klippan Boerevereniging???
Lehurutshe Lehurutshe Community Library – Peggy Nkom 018 363 4099 / 076 826 9652
17 July 2017 14h00 Open House 14h30 Public Meeting Lehurutshe Civic Centre???
Serake/ Driefontein Driefontein clinic – Modshediso Gonelotse 073 437 0388 / 018 365 9020
18 July 2017 11h00 Open House 11h30 Public Meeting Klippan Boerevereniging???
Supingstad Supingstad clinic – Bokang Motsusi 073 261 4874 / 018 353 0900
18 July 2017 14h00 Open House 14h30 Public Meeting Community Centre ???
Will you please be so kind to let me know whether the above mentioned places are the best to do our public meetings? If not what alternatives do you suggest? Appreciate your willingness to assist. Warm regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
1
Amelia VisagieFrom: Amelia VisagieSent: Thursday, June 15, 2017 4:15 PMTo: '[email protected]'Subject: NOTIFICATION OF ENVIRONMENTAL IMPACT ASSESSMENT PROCESS FOR THE PROPOSED BOTSWANA-SOUTH AFRICA (BOSA) TRANSMISSION INTERCONNECTION PROJECTAttachments: BOSA BID_12Dec2016_rev4.pdf; BOSA Notification_OoS SA_Final_12Dec2016_rev2.pdf
Good day Prof. Legotlo, I have received your email address from Marinana Taljaard from Aurecon who phoned you this morning. Please find attached the initial information regarding the above mentioned project. I am asking your assistance in helping me to get an appropriate venue for our information sharing session that is taking place during the week of the 17th to the 18th of July 2017. The following places have been identified for landowners and community sessions:
TOWN / COMMUNITY Venue where report to be viewed Meeting Date Meeting Time
SOUTH AFRICA
Miga Klippan Boerevereniging 17 July 2017 11h00 Open House 11h30 Public Meeting
15km from Bewley (a settlement near Ramatlabama border control (RSA)Klippan Boerevereniging???
Lehurutshe Lehurutshe Community Library – Peggy Nkom 018 363 4099 / 076 826 9652
17 July 2017 14h00 Open House 14h30 Public Meeting Lehurutshe Civic Centre???
Serake/ Driefontein Driefontein clinic – Modshediso Gonelotse 073 437 0388 / 018 365 9020
18 July 2017 11h00 Open House 11h30 Public Meeting Klippan Boerevereniging???
Supingstad Supingstad clinic – Bokang Motsusi 073 261 4874 / 018 353 0900
18 July 2017 14h00 Open House 14h30 Public Meeting Community Centre ???
Will you please be so kind to let me know whether the above mentioned places are the best to do our public meetings? If not what alternatives do you suggest? Appreciate your willingness to assist. Warm regards Amelia Visagie Project Manager : Socio Economic Development, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
1
Amelia VisagieFrom: Amelia VisagieSent: Friday, July 7, 2017 3:18 PMTo: '[email protected]'; 'Wilfred Legotlo'Cc: Diane Erasmus; Wendy MlotshwaSubject: Botswana South Attachments: 2. Shortened English BID.pdf; 11. BOSA_Exec Sum shortened_Eng_Final.pdf; 4. Executive Summaries.pdf; Tswana_BOSA DSR Exec Sum shortened_vers2.pdf
Good day Mr Legotlo Thank you for talking to me today and assisting in organising the meetings with the Chiefs. We have been invited by Albanias 071 657 6575 and Mr. Molalodi 083 428 1871to address the Tribal Council on the 12th of July 2017 at 10h00 in Driefonteint / Serake. Serake Village Driefontein The Newspaper adverts were placed in the Daily Sun. We will also hand out the attached translated Tswana shortened executive summary so that It can be distributed. Please find attached the information as discussed. Kind regards Amelia Visagie Senior Consultant, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER
1
Amelia VisagieFrom: Amelia VisagieSent: Monday, June 26, 2017 9:24 AMTo: [email protected]: Sizwe Mabadi; Diane ErasmusSubject: RE: BOSA – BOTSWANA-SOUTH AFRICA TRANSMISSION INTERCONNECTION PROJECTAttachments: BOSA Newspaper_English_SA_Jun2017_ver7.docx
Dear Prof Legotla, Thank you very much for taking our call this morning and advising on our mail last week. As discussed we are currently busy with the scoping phase of the environmental and social impact assessment process for the Botswana South Africa Transmission interconnect Project (BOSA). According to legal requirements we need to inform all stakeholders about the proposed BOSA project and the associated Environmental and Social Impact Assessment (ESIA) process. In the process we are legally required to ensure that the project is advertised in newspapers and site notices needs to go out in order to inform the different stakeholders about the project and the meetings. These needs to go out according to the above mentioned legal requirements, this week in order to meet the given time lines. We do not currently know who all the stakeholders are that might be influenced by the process. We therefore would like to organise meetings on the 17th and 18th of July 2017. The purpose of the meetings is to involve all affected and interested stakeholders and explain the process to them. It is also to ensure that they are included on our database so that we can forward all reports and future information to them. Because it is such a large project, with many stakeholder, we would like to as many interested and affected parties on board. The Chiefs are one of the most important stakeholders, therefore we would like to ask the Chiefs for their blessing to organise information sessions in the following venues (last column on the attached advertisement): Bewley / Miga Lehurutshe Serake/ Driefontein Supingstad Please assist us in asking for the blessing from the Chiefs. I will appreciate your feedback by the end of today in order for us to meet the above mentioned legal requirements. Your assistance in this regard is much appreciated. Amelia Visagie Project Manager, Aurecon T +27 12 4273149 F +27 86 5386115 M +27 83 4544317 [email protected] DISCLAIMER From: Sizwe Mabadi Sent: Thursday, June 22, 2017 10:07 AM To: [email protected] Cc: Amelia Visagie <[email protected]> Subject: BOSA – BOTSWANA-SOUTH AFRICA TRANSMISSION INTERCONNECTION PROJECT Good day Prof Legotlo. Thank you for taking my call this morning and thank you for being prepared to assist us in talking with the Chiefs to get their blessing for our meetings which is taking place on the 17th and 18th of July 2017.
2
Unfortunately the dates has been finalised and cannot change due to the tight deadlines. As discussed the following venues can be identified as possible places to inform the stakeholders: Supingstad: Ntlung Morafe Driefontein / Serake: Tribal Office Lehurutshe: Lehurutshe Civic Centre Possible venue as indicated by you can be Kgosi Lentswe – please let me know where on the map the
village is so that we can determine whether we can include it in our planning. Will you be so kind to assist us in arranging the above-mentioned venues with the relevant stakeholders. It will be wonderful if you can arrange a meeting with the Municipality for early (8h00) Monday morning then we can brief the Mayor about the project. We will then still be on time to go to Klippan for the first meeting. Will you also assist us with what the Chiefs will expect from us please? Your feedback is highly appreciated and it will be wonderful to get feedback about the venues and the Chiefs by Friday the 22nd of June so that we can get approval from our client. You also mention accommodation; please be so kind to forward the contact details as well. Kind regards, Sizwe Mabadi Junior Social Scientist, Aurecon T +27 12 4272304 M +27 79 8473808 [email protected] Aurecon Centre, Lynnwood Bridge Office Park,4 Daventry St, Lynnwood Manor, Tshwane South Africa 0081 PO Box 74381 Lynnwood Ridge 0040 South Africa aurecongroup.com
DISCLAIMER