Upload
independent
View
1
Download
0
Embed Size (px)
Citation preview
Disputes in Construction Project Prevention, Managing, Resolution
Dedication
Dedicated to the memory of my late father who would have loved to see me graduate in
no other discipline than in law.
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
Abstract
The UK construction industry arguably is the largest industry
attracting an equally large volume of diverse disputes, across a
wide range of values1. It might therefore be thought that
reported causes of construction disputes will not only shed light
on the immediate causes of such disputes, but provide insights
into the industry generally.
The construction industry produces so many varied products
without significant repetition hence a learning curve is
inevitable for every project undertaken. It is further enriched
by the presence of other parties with an interest in the end
result i.e. the funder, the developer, the construction
regulators and the public at large whose built environment is
important to them both economically and aesthetically. Then there1 Gould, 2004
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
is the contractor, sub contractor, supplier and other
professionals who contribute specialist skills and materials to
build the edifice. It is this variety of interests that provides
the catalyst for dispute in the industry.
The dissertation outlines the causes of disputes in the
construction industry as submitted by other researchers. It then
examines the research conducted in the area of Mediation as
Alternative Dispute Resolution for settling construction disputes
in Scotland. The essential features of ADR are then contrasted
with adjudicatory processes such as litigation, arbitration and
adjudication.
The dissertation further emphasizes that the sole reliance on
Adjudicatory processes such as Litigation, Arbitration and
Adjudication for settling construction disputes seems to be
adversarial and therefore limits the scope for preserving
commercial relationship. Focusing on Mediation although is not a
traditional way of resolving construction disputes may well
prove to be the preferred route once the alternatives have been
considered.
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
Key words: Construction Industry, Construction Disputes, ADR, Alternative Dispute
Resolution, Mediation.
Title Page
DISPUTES IN CONSTRUCTION PROJECTPREVENTING, MANAGING, RESOLUTION
A Dissertation submitted in partfulfillment of
LLM in CONSTRUCTION LAW
Kobina Bentum Andoh
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
Glasgow Graduate School of LawA JOINT VENTURE OF THE UNIVERSITIES
October 2010
Declaration of Authenticity or Authors Right
This dissertation is the original of the author’s research. It
has been composed by the author and it has not been previously
submitted for examination which has led to the award of a
degree’.
‘The copyright of this dissertation belongs to the author under
the terms of the United Kingdom copyrights Acts as qualified by
University of Strathclyde Regulation 3.50.’ ‘Due acknowledgement
must always be made of the use of any material contained in, or
derived from, this dissertation’.
Signed: Kobina Bentum Andoh
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
Date: 18th October 2010
Contents Abstract
ii
Title Page
iii
Declaration of Authenticity or Authors Right
iv
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
List of tables
x
List of figures
xi
Acknowledgements
xii
Abbreviations
xiii
1 Introduction 1
1.1 Aim of Dissertation
1
1.2 Rationale of Aim
2
1.3 Motivation for the Dissertation Topic
2
1.4 Research Objectives
4
1.5 Research Methodology
5
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
1.5.1 Data collection
5
1.5.2 Scope of research
5
1.6 Dissertation Structure and Overview
6
2 Disputes in the Construction Industry
8
2.1 Introduction
8
2.2 Nature of the Industry
8
2.3 Construction Disputes – An Overview
12
2.4 Dispute – The Definition
14
2.5 The Fundamental Difference of Dispute Prevention,
Dispute Management and Dispute Resolution
17
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
2.6 Conclusion
19
3 The Causes of Construction Disputes
20
3.1 Introduction
20
3.2 Disputes – Causation Agents 20
3.3 The contract Conditions
27
3.4 The design deficiency
27
3.5 The construction process
28
3.6 Conclusion
29
4 The Structure of a construction Project
30
4.1 Introduction
30
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
4.2 The Project
30
4.3 The Dispute Period
31
4.4 The Material Fact
32
4.5 Decision
33
4.5.1Unilateral mistake 34
4.5.2 Authority 34
4.6 The Analysis So Far 34
4.7 Conclusion
34
5 Applicability of Mediation as ADR in Scotland
36
5.1 Introduction
36
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
5.2 Background
36
5.3 Level of Use and Knowledge of use of ADR. 36
5.3.1 UK Research
36
5.3.2 Other Research
39
5.3.3 Scotland Research 40
5.3.3.1 Satisfaction with Different Element of Settling Dispute
42
5.3.3.2 Attitudes to Mediation
43
5.4 The Impact of ADR on Mediation
45
5.5 Conclusion
48
6 Review of Mediation as ADR in Scotland 49
6.1 Introduction
49
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
6.2 Encouraging the use of ADR
49
6.3 Judicial Attitudes
50
6.4 Legal Profession
50
6.5 Client’s Awareness
52
6.6 Scottish Government
53
6.7 Conclusion
53
7 How Mediation as ADR Works In Practice 54
7.1 Introduction 54
7.2 ADR Defined
55
7.3 Mediation in Practice 55
7.4 Differences between Mediation and Adjudication Processes 56
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
7.4.1 Non Binding Voluntary Nature of Mediation
56
7.4.2 Role of Mediator
57
7.4.3 Informality of ADR Processes
57
7.4.4 Nature of outcome
58
7.4.5 Confidentiality
58
7.5 Advantages of ADR – Mediation in Commercial Disputes
59
7.5.1 Cost
59
7.5.2 Speed
60
7.5.3 Preservation of Commercial Relationship
61
7.5.4 Creative Outcomes – Increasing Settlement Options
61
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
7.6 Conclusion 62
8 – Conclusion 64
8.1 Introduction 64
8.2 Competitive tendering
64
8.3 Changes in Contracts
65
8.4 Partnering
65
8.5 Dispute - The way forward
66
9 Bibliography 67
9.1 Books 67
9.2 Articles 71
9.3 Reports 72
9.4 Others 72
9.5 Websites 73
9.6 Cases 74
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
10 Appendices 75List of Figures1. Parties in Disputes
75
2. Source of Construction Disputes in the Scottish Construction
Industry 76
3 The Disputes Pyramid
77
4. Causes of Disputes in the Scottish Construction Industry
78
4. Payment and Budget Causes of Dispute in the Scottish
Construction Industry 79
5. Quality Issues resulting into disputes in the Scottish
Construction Industry 80
6. Administrative Causes of Dispute in the Construction Industry
81
7. Contractual Relationships in a Construction Project
82
8. Trained Mediators Professional Designation
82
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
9. Respondents’ Training in Mediation
83
List of Tables
1. Respondents decision to refuse a proposal for mediation from the opposing party in dispute 84
2. Response of Element of Mediation Process
84
3. Respondents Attitudes to Mediation 85
Acknowledgement
There are so many personalities who have helped me over the years
in the development of my career to date, that it would be
invidious, if not impossible to single out a few to mention, so I
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
am most grateful to them collectively. Those who have been
closest to me know who they are, and I thank them most sincerely.
There are a number of other special people who have helped me,
either directly or indirectly, in writing this dissertation, and
I shall mention them by name.
My supervisor, Dr. Bryan Clark, for his valuable advice and
suggestions on review of mediation as ADR in Scotland. He has
also helped me in a more direct way with the dissertation as a
whole.
I am most grateful to my course mates George Mandepo, Muhammad
Zin -Zawawi and Abdullah Almedellah. They have all assisted in
diverse ways both by their comments and contributions and that
have served as a sound board for ideas.
I take this opportunity to express my deepest appreciation to my
sister –in- law Naomi Essandoh and the Essandoh family who stood
by me while I have been away in the UK studying and have educated
my children, Tima, Abeiku and Obaa –Yaa. I shall forever remain
indebted. It is not possible to thank everybody within the
compass of this dissertation, but I wish to place on record my
deepest appreciation to Mr. Nicholas Asman for his support both
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
morally and physically. Nicholas I say Bravo and urge you to lift
high the spirit of brotherhood and fraternity. Then most
important of all, there is my dear wife Antwiwaa and my children
Ebow and Ekow who are here with me in the UK. I cannot say enough
to thank them at least for denying them the needed attention when
it was desirable, all for the sake of my studies.
Finally, this acknowledgement will be like the map of the
continent of Africa without Madagascar, if the Jehovah God who
has matched me with His hours is not recognized. The Omnipotent
God I thank you for everything.
Abbreviations
ADR – Alternative Dispute Resolution
CEDR – Centre for Effective Dispute Resolution
CMI – Construction Management Instruction
CPR – Civil Procedure Rules
DAB – Dispute Adjudication Board
DRA – Dispute Resolution Adviser
DRB – Dispute Review Board
EU – European Union
ICE – Institution of Civil Engineers
Kobina Andoh 200984350
Disputes in Construction Project Prevention, Managing, Resolution
ISA – Interim Statement of Accounts
JCT – Joint Contract Tribunal
KBA&S – Kobina Bentum Andoh & Sons
RSE – Royal Society of Edinburgh
SBCC – Standard Building Contract for use in Scotland
SEC – Scottish Executive Commission
TCC – Technology and Construction Court
UK – United Kingdom
USA – United States of America
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION 1 Introduction
1.1 Aim of DissertationThis dissertation aims to investigate a better method of
resolving construction disputes within the context of the factual
cause and technical arena rather than in the courts of law. This
is because when disputes are taken to the courts of law the
criteria used for their progress and resolution are those of the
law and the lawyers rather than the parties to the dispute.
However, not only are the courts of law the wrong place to debate
simple factual differences but they are also poorly placed to
resolve technical problems. The courts of law apply the law to
the facts as they are presented and arrive at a judgement. That
being said, this necessarily imply that the problems in putting a
wide range of technical matters before a (legal) judge may be
just as frightening whether the sum involved is in hundreds of
pounds or whether it is in millions of pounds. The parties to a
construction project want to be proactive in how their dispute is
resolved and to have the opportunity to bring about a more
creative and flexible outcome than a court of law can deliver.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONSo, should it be Adjudicative Dispute Resolution where a decision
is imposed on the parties or Consensual Dispute Resolution where
the parties resolve the dispute by agreement? The dissertation
should answer that question definitively.
Construction disputes are caused by project uncertainties,
problems in the process, or people issues2. So long as the nature
of the construction industry and process is what it is, there
will always be disputes. And those disputes, whatever their kind
must be resolved in an adequate, as quickly as possible, as
cheaply, and as satisfactory manner as possible.
1.2 Rationale of Aim
The Construction Industry all over the world experienced
sweeping changes after the Second World War.3 Notable among
these dramatic changes have been the sharp increase in the
incidence of serious disputes4 between parties to construction2 Gould,N. et al 19993-Whitfield, J. 19944 - Whitfield, J. 1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONcontracts. This may be attributable to the fact that contracting
parties have become more commercially aware especially in the
current economic climate5 and increasingly employed Quantity
Surveyors and Construction Lawyers to safeguard the contractual
rights of the said parties. Besides, new contract conditions
have proliferated. This renders even experienced practitioners
uncertain of the terms embodied in the standard form of
contracts. Disputes in construction projects exert enormous
financial strain on the parties involved, even forcing some into
liquidation. In spite of resolution procedures being expensive
they are considered as being generally ruinous to the national
economy6. The construction industry account for 10% of the UK’s
Gross Domestic Product and employs about 1.5million people7 and
any dispute in the industry if not properly handled contribute
towards the diminished efficiency of the construction industry8
and having an impact on the economy.
1.3 Motivation for the Dissertation Topic
The motivation for the research is of two fold:5 Course Note – Dispute Resolution6 Lord-Smith, P.J. 19947 Corporate Watch,20088 Latham,1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONa) The authors interest when comparing a good dispute management
team within a construction project with the alternative, and,
b) The benefit to be derived from Negotiation and Mediation
during a lecture on Mediation by Gordon Hollerin of Semple
Fraser LLP and reading the Latham report particularly on
contractual issues and methods of dispute resolution. An area
which drew the author’s attention and of specific interest
was early recognition of areas which are problematic and
potential dispute within a construction project and finding
quick and efficient means of resolving such disputes before
they escalate.
As human beings, we sometimes forget the real issue in the heat
of battle and the disputes generate into an emotive personality.
In such situations it is quite natural for one party to score
points against the other by going the extra mile. In this
damaging, and often escalating type of dispute nobody really
wins. If so, then the prevention, managing and resolution of
construction dispute are absolutely essential to avoid any
unpleasant experience.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe construction industry as a body needs to be creative in
resolving disputes and move away from the lose/lose9 situations
of the past and even win/lose10 scenario prevalent in the
industry. In so doing we can then identify and pursue the
win/win11 result that would be so advantageous for the industry.
Some sceptics may argue that there can never be two winners and
that one side may always be the loser or at least give something
up in order to reach a compromise. This seems to be an undisputed
fact but it is not always the case. Inventive and forward looking
Negotiators have often increased the size of the cake, making it
possible for both parties to receive a fair share12. This type of
invention exists only in a situation when there is no ‘them and
us’ environment and this is only possible when there is a good
dispute management team. But it is sometimes assumed that it is
too costly to have a good dispute management team who are well
trained and enjoy interpersonal skills within a construction
project. In all probability it is cheap when compared with a
dispute of any proportion because as has been emphasised already9 Ury, W. 200810 Ury,W. & Fisher,R. 199911 Ury,W. 200812 Whitfield, J.1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONputting a wide range of technical matters before a (legal) judge
may be just as frightening whether the sum involved is in
hundreds of pounds or whether it is in millions . The cost of
training such a team will be compensated against any litigation
or arbitration that would arise if it had been prevented, managed
or resolved13. This will eventually translate into cooperation
and the principle that co-operation is a more efficient method
of working14 than the approach resulting from traditional
contracting in which each party is driven toward looking after
their own independent objectives.
It can not be over emphasised that the downside of disputes
generally exceeds the perceived benefit. This suggests that
disputes must be addressed properly and a critical approach
adopted to the causes that are likely to result into disputes
prevalent in the construction industry.
1.4 Research Objectives
The construction industry is very large and accounts for about
10% of UK’s Gross Domestic Product and employs 1.5 million13 Baden Hellard, R. 198814 Whitfield, J. 1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONpeople. Being such a large industry there are contracts signed
every day. Some projects are very simple, others complex, some
may involve just two organisations; others may involve hundreds
of suppliers, sub-contractors and consultants. Irrespective of
the size of a project, be it simple or complex project, it can
still go wrong. These developments make it imperative to identify
the differing meanings of disputes within the construction
industry and understand the causes of each defined meaning. By
this process we will be able to consider a dispute resolution
mechanism which can bring about a satisfactory result.
In summary in order to realize the aim of this research, the
following objectives were formulated:
Identify disputes in construction projects
Analyse Mediation as Alternative Dispute Resolution process and how it works in
practice and contrast the essential features of the process on the one hand with
adjudicatory processes such as litigation, arbitration and adjudication on the
other.
1.5 RESEARCH METHODOLOGY
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe research methodology adopted was non-experimental, as no
intervention was involved, but the situation as it existed is
being investigated. As the research was only making observations
on the state of affairs and did not become part of the observed
phenomenon, it employed qualitative research methodologies, and
is presented in the following general structure:
Data collection
Scope of research
1.5.1 Data collection
The data collection as a research methodology to be adopted for
this topic will be based on a comprehensive literature review
drawn from databases of the following sources:
Academic and practitioner literature that has previously
been written in the field of disputes in the construction
industry.
The internet, Westlaw and Lexis Library websites.
Technical and academic Journals and text books.
Reports from government and other bodies.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION Building Industry Journal.
Course Notes: Dispute Resolution ( Glasgow Graduate School
of Law, 2010)
1.5.2 Scope of research
The research as a whole will be focused on the Scottish
construction industry. Although the research is limited to the
Scottish construction industry, there is considerable evidence to
suggest that the case history is peculiar to other parts of the
UK and as such comparisons will also be drawn from relevant
scenarios in the UK, the United States of America and other parts
of the world.
1.6 Dissertation Structure and Overview
Following the Introduction chapter, in Chapter 2 an attempt is
made to explain the nature of the construction industry, define
what a dispute is in relation to the construction industry.
Clearly, in many instances, dispute can and should be eliminated.
In the construction industry, a great many destructive disputes
have arisen which could have been prevented. Of course, with so
many imponderables, and human nature being less than perfect,
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONsome degree of dispute is inevitable and our ability to prevent,
manage and resolve a dispute successfully will depend largely
upon our recognition of the real causes which this chapter sets
out to do.
Chapter 3. The real causes of dispute within the construction
industry are wide ranging and varied and those are discussed and
the more common ones are highlighted in this chapter.
In chapter 4 the focus is on a structure of a construction
project. Chapters 2 and 3 have been considered in a theoretical
way and we are now going to examine it in the context of a
construction project. The analysis is based on a fictional
project which has progressed to adjudication and then unto
litigation.
Chapter 5 Sets out to review a research of the use of Mediation
as an ADR in UK and other common law jurisdictions by other
Researchers and discusses the impact of ADR on litigation.
Chapter 6 – Provides a framework for the ADR concept and examines
a number of reasons put forward as barriers which have existed to
date to the growth of Mediation in Scotland.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONChapter 7 Explains how Mediation as ADR works in practice and the
benefits to be derived in using such a method for settling
commercial disputes.
Chapter 8 Finally in the concluding chapter, an attempt will be
made to answer the searchable question: Is there a real hope in
the future for a general reduction in construction dispute in
Scotland? If the answer is yes, then this will be as a result of
preventing, managing and resolving dispute in a fashionable way
hitherto undreamt of in Scotland.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
2 Disputes in the Construction Industry
2.1 Introduction
This chapter outlines several areas within the construction
industry that could lead to dispute. The chapter raises awareness
between the main parties involved in the building contract, the
risks that lay in wait during the course of the project and what
steps can be taken in an attempt to prevent those risks. Some,
risks however, will always be present and are part of the
commercial environment. In these cases the duty is to be aware of
those risks in advance and manage them so that they are contained
and do not damage the commercial viability of the project.
2.2 Nature of the Industry
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe Construction Industry is made up of role players like the
employer, the contractor and consultants who endeavour to create
long – term, unique and complex building projects and
infrastructures15 . A diverse arrays of stakeholders i.e. the
client who may be either individual or local authority, the
consultant, the main contractor, sub-contractors, suppliers,
financial institutions, legal representatives and others all
contribute to a building project from planning through design,
construction and occupancy. These role players sometimes bring
varying and sometimes conflicting expectations to a project. They
operate in an environment in which their influences over a
project swing as the project progresses. They demand to deliver
projects in less time and at lower cost. It is a lamentable fact
that many clients, especially those with no experience of
building, imagine that it is possible to construct a quality
building at breakneck speed for a knock-down price.
The construction industry is a project- based industry with each
project being unique16 hence noted for high levels of disputes
15 Levy, 200716 Chin, 2003
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONand conflicts. A failure on the part of one party involved in a
project can spread to other participants within the project
culminating to the rise of a dispute. The complex dispute found
in construction projects stems from the fact that construction
projects are increasingly complex17. The industry has often been
described as one of the most adversarial and a problem prone
industry, where claims and disputes on construction projects are
frequently considered as the rule rather than the exception18.
Cost overruns and schedule delays can be the subject of expensive
and protracted claims and litigation. This particularly poses
serious risks for all parties to a construction project. The
Scottish construction industry covers a diverse range of
activities making it complex with comprehensive field of
activities. It entails many operative skills and conditions with
every project being a prototype. The uniqueness of every project
is a prolific source of dispute and it erupts at any point in
time during the construction process. Arguably, a project may be
filled with individuals with differing beliefs who are happy to
promote their belief or opinions loudly. This will of course lead17 Harmon, 200318 Steen, 2002
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONto dispute where those beliefs do not concur with the beliefs of
others.
According to Kennedy, Conlin and Langford19 the stakeholders in
the Scottish construction industry consists of Local
Authority/Planning, Sub-Contractors, Civil/Structural Engineers,
Quantity Surveyors, Client, Architects, Suppliers, Others and
those carrying extra contractual duties. Appendix 2 illustrates
each stakeholder’s contribution to dispute in the industry.
Kennedy and Milligan20 present useful diagram21 comparing the
various parties in dispute in the construction industry for a
specific period.
The construction industry has been besieged with sweeping changes
in the form of dispute after the Second World War, it can be
considered to be less adversarial in the early 1960’s compared to
the present22. In 1960 some 250 writs were issued in the whole of
UK relating to construction disputes, yet within 30 years this
number increased ten-fold23 or even more. During this period the19 1996, Appendix 220 200721 Appendix 122 McGuin, 198923 Whitfield, 1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdesign and construction environment was such that friendly and
pleasant relationships generally existed between all of the
parties involved in a project. To put it mildly, construction
project and processes were not complex and complicated compared
to the present where construction projects are increasingly
complex….. often resulting in complex disputes24. The
construction players were few and developed long-term
relationships. Clients admitted the fact that undertaking
construction projects embodied inherent risks and, therefore
accepted a certain amount of errors. Claims were not prevalent
and, surprisingly, design consultants and construction firms
worked together to maximise project performance25. The focus of
the construction industry was team work centred for the overall
success of the project.
One may ask what happened during those intervening years to bring
about such a transformation. Perhaps this may be attributable to
the fact that during this period construction companies became
more commercially aware and employed a number of Quantity
24 Harmon, 200325 McGuin, 1989
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONSurveyors and Construction Lawyers to safeguard the contractual
rights of contractors, sub-contractors and even suppliers26.
Again during the late 1960’s and early 1970’s claims consultants
emerged, purposely to promote the claims advanced by both sides
of the industry27.
The construction industry today is different28. In the 1980’s
upwards, somewhat piously the writer submits that there was a
shift from significant public financing of construction by
central and local government, and so the industry became reliant
upon profit-oriented speculative development. The strong
relationships and trust between clients, contractors and sub-
contractors has been replaced with growing distrust and conflict
as noted by Sakal29. Sakal is also of the view that, the
construction industry has continually fragmented into narrow
specialty areas that have resulted in an ever-growing number of
potential participants. This phenomenon is difficult for the
contractors and sub-contractors cum the client’s expectation of
26 Whitfield, 199427 Whitfield 199428 Sakal,200429 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONperfection in the contractor’s performance culminating in
contract disputes and claims being common30.
The infinite complexities of delivering a building or
infrastructure project, the multiplicity of organisations and
individuals involved and the quantum of money at risk, it is
perhaps not surprising that the construction industry has been
characterised by an adversarial operating environment that
generates disputes and claims31. Stipanowich32 was of the view
that disputes are estimated to arise in 10% to 30% of all
construction projects and that one in four construction projects
end up in a claim leading to a dispute.
All the above factors point toward the industry’s fragmentation
resulting in conflicts and disputes plaguing the industry like
chronic disease. The fragmentation ranges from work undertaken
(building or civil engineering), technologies employed, clients
(public and private), and the firms/companies (professional and
contracting) involved. The fragmentation has resulted in non
coordination and integration between different disciplines at30 Sakal, 200431 Stipanowich,199832 1998
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONvarious stages of the project procurement process and the
construction process33. And as a result, failure on the part of a
party involve in a project to fulfil a contractual obligation
results in a claims, counter claims and disputes which has
characterised the industry. Sometimes it may not be the
fulfilment of contractual obligation which results in dispute.
The dispute may be based on the law of delict34.
In summary, all of these factors, arguably have impacted on the
relationship between main contractors and sub contractors’,
clients and main contractors etc and increased the incidence e of
dispute35.
2.3 Construction Disputes – An Overview
The last four decades have witnessed the construction projects
continually becoming much more dynamic in nature36. The
construction projects are accomplished today in an environment
33 Love et al, 199834 BT V James Thompson & son Ltd, [1999]35 Appendix 1
36 Sakal, 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONwhich is completely complex, uncertain projects within tight
budget and time constraints. The dynamics of the construction
industry by virtue of it continual fragmentation37 contributes
specifically to it complexities - more parts, more interfaces.
The dynamic environment of the industry forces client to attempt
to reduce cost and time while at the same time demanding high
quality finished products. But the grim reality is that quality
and speed do not always sit easily together. Clients also include
bespoke clauses in an attempt to offload risk to contractors.
This subsequently leads to the main contractor passing the risk
onto the sub-contractors. In an attempt by project participants
to safeguard their contractual rights backfires resulting in
adversarial relationships and expensive litigation. The plethora
of these factors unsurprisingly negatively affects project
performance resulting in dispute arising between parties involved
in construction projects. The result of these conflict is heated
disputes and ultimately litigation claims that are detrimental to
project participants economically. But irrespective of the nature
of dispute, one thing is certain for all, the efficiency and
37 McGuin, 1989
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONproject performance is impaired38 due to mistrust between project
participant and decline in teamwork in an attempt of the major
players trying to offload risk.
Construction disputes however are as old as the recorded history
of man’s building structures and other projects. In the UK as a
whole and Scotland in particular, construction disputes have
increased dramatically in number, complexity in cost as project
become imponderable with ever increasing competing interest
involved in execution of project39.
In an ideal environment construction projects would be team led
where the effectiveness of each participant is utilised to the
realisation of the project performance. This is the reverse
expectation since most parties enter into construction contract
with ulterior motives. The adversarial situation stems from the
fact that a good framework for developing good relations between
the parties are missing. The contract is written to include a
bespoke clause to favour the drafter of the contract. The
mistrust of one another cause the increased antagonistic
38 Latham,1994, Sakal, 200439 Canterbury Jnr, 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONrelations between the client and contractor40 that are clearly
not in the best interest of the project41.
Arguably, construction projects are amongst the most complicated
of human enterprises and as such, not free from problems such as
disputes and that, so long as human nature is what it is,
disputes will always prevail and those disputes whatever their
nature must be prevented, managed and resolved as early as
practicable42. Prevention, managing and resolving of disputes43 is
considered as a sound business practice and a very important
management process which enables project objectives in terms of
cost, time and quality to be achieved. Nystrom44, noted that
disputes prevention encompasses a shared, cooperative effort
between potential disputants in pursuit of a common goal namely;
success of the project so that potential disputes could be
prevented as early as possible before they start. Therefore the
prevention, managing and resolving of disputes are considered as
the most important areas for the future of the construction
40 Appendix 141 Steen,199442 Motsa, 200643 Nystrom, 199544 1995
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONindustry to curb the problems of disputes. It is no longer
acceptable for professionals in the construction industry to sit
back and tinker with contracts and commercial arrangements,
hoping that the resulting decline in dispute will be as rapid as
was the growth. Intensive action is needed now to manage the
disputes which seem to arise inevitably from every construction
project.
2.4 Dispute – The Definition
The terms ‘conflict’, ‘claim’ and ‘dispute’ are used
interchangeably. They are sometimes used separately or in pairs
and frequently without clear indication of the precise meaning of
each. There is often a lack of clarity as to whether the research
is about claim, conflict or dispute. To fully unearth the sources
of construction disputes, these three terms need to be properly
explained because under section 108 of the HGCRA 1996, it is only
a ‘dispute that can be referred to adjudication’.
Gardiner & Simmons45 defines conflict as any divergence of
interest, objectives or priorities between individuals, groups or
45 1992
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONorganisations. Powell-Smith & Stephenson46 also defines claim as
an assertion of a right to money, property or a remedy and can be
made under the contract itself for breach of the contract, for
breach of a duty in common law; or a on a quasi-contractual basis
while Brown & Marriot47 also defines dispute as a class or kind
of conflict, which manifest itself in distinct justifiable
issues. It involves disagreement over issues capable of
resolution by negotiation, mediation or third party adjudication
while the oxford advanced learners dictionary of current English
also defines dispute as a heated contention, a disagreement in
which opposing views are strongly held. The ICE arbitration
procedure states that: a dispute can be said to exist when a
claim or assertion made by one party is rejected by the other
party and that rejection is not accepted48. Fenn et al49 advise
that stake holders involved in a project should understand the
essential difference between the terms ‘conflict’ and ‘dispute’.
They assert that conflict is manageable and impact positively on
construction while dispute impacts negatively on projects.46 198947 199348 Kumaraswarmy & Yogeswaran, [1997]49 1997
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAccording to Ellenberg50 dispute ranges in levels, the lowest
being disagreement followed by argument and the third level being
dispute. The distinction between conflict and dispute is not
substantiated by Eilenberg51 but consideration of the suggestion
made by Fenn et al52 implies that conflict could be the lowest
level of dispute in any construction contract. Thus in this
context, it is fair to conclude that if there is no action taken
to manage the conflict in the first place, it could possibly
generate to dispute.
It is generally assumed that every dispute in the construction
industry leads to litigation or arbitration but Gould53 suggests
only very few dispute result in litigation or arbitration.
According to Sarat54 greater number of claims and grievances
emerge but are not pursued. He therefore demonstrates the stages
of a disputes manifestation and escalation visually as a
pyramid55. The “dispute pyramid” represents the stages in the
disputing process. A reference to the dispute pyramid was made by50 200351 200352 199753 200454 198555 Appendix 3
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONGallanter56 and stated that the lower layers relate to
construction of dispute while the upper layers refer to the
lawyers and the courts.
Despite the simple meaning of the word ‘dispute’ there has been
much litigation over the years as to whether or not dispute
existed in particular situations. This litigation has not
generated any hard-edged legal rules as to what is or is not a
dispute. However, the accumulated contractual wisdom of
generations (case laws) has produced helpful guidance. A number
of general comments can be made about the courts approach to what
constitutes dispute. The tenor of the courts approach to dispute
has depended on two schools of thoughts in determining whether a
dispute has arisen i.e. the narrow approach and the wider
approach.
In using the narrow approach to determine whether a dispute has
arisen in the case of Fastrack Contractors Ltd v Morrison
Construction Ltd57 and Edmund Nuttal Ltd v RG Carter Ltd58, it was
held that for a dispute to have arise, it is necessary for a56 1983, Gould, N. 200457 [2002] B.L.R. 168; 75 Con. L.R. 3358 [2002] EHWC 400 (TCC)
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONclaim to have been made and for the responding party to have “had
an opportunity of considering and admitting, modifying or
rejecting the claim or assertion”. In contrast to that, in the
case of Cowlin Construction Ltd v CFW Architects59 the court in
adopting the wider approach intimated that “there is a dispute
once money is claimed unless and until the defendants admit that
the sum is due and payable”.
In light of the definitions given above, it is the submission of
the author to entreat project managers involved in a construction
project to actively focus on ways of preventing, managing and
resolving conflicts from escalating into claims and resolving
claims to prevent them from becoming disputes60 resulting in
arbitration or litigation61. Moreover, Singh62 is of the view that
the paramount task or obligation of any construction industry
practitioner is to prevent dispute from arising in the first
place and given their potential adverse ramification on a
particular construction project.
59 [2003] B.L.R. 24160 Ng,H.S. et al 200761 Gould, N. 200462 2003
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONIn sharp contrast to the above, Gerber63 indicated that there has
been lack of focus on prevention of dispute. Gerber is on record
of saying that: “To date, our efforts have been largely reactive
rather than proactive. We have focused on resolving disputes as
quickly and efficiently as possible rather than systems to
prevent disputes in the first place. To the extent that we have
been proactive it has been in the project delivery vehicle arena
(partnering, alliancing etc) rather than in early intervention
conflict resolution”.
The inference from the above definitions seem a simple enough
concepts to appreciate and the author submits that the word
‘dispute’, as it occurs in many arbitration clauses and also in
section 108 of the HGCRA64 should be given its normal meaning. It
would be for all practical purposes and the purpose of this
research to adopt the definition as contained in the narrow
approach65 and it is therefore assumed that the genesis of claim,
conflict and dispute are synonymous.63 200064 199665 Fastrack Contractors Ltd v Morrison Construction Ltd and Edmund Nuttal Ltd v RG Carter Ltd i.e. a dispute to have arise, it is necessary for a claim to have been made and for the responding party to have ‘had an opportunity of considering and admitting, modifying or rejecting the claim or assertion’
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe alternatives to resolve disputes in the industry are becoming
imponderably expensive in terms of time, finances, personnel and
opportunity costs. The visible expenses (solicitors/advocates,
expert witnesses etc) speak for itself. The less visible costs
(e.g. company resources assigned to the dispute, lost business
opportunities) and the intangible cost (e.g. damage to business
relationships, potential value lost due to inefficient dispute
resolution) are also considerable, although difficult or
impossible to quantify66.
2.5 The Fundamental Difference of Dispute Prevention, Dispute
Management and Dispute Resolution
Having defined dispute and the meaning understood, it is
important to differentiate between dispute prevention, dispute
management and dispute resolution. It is also important to
recognise the purpose and objective of each method by
establishing its identity and creating a conducive environment in
which it can operate.
66 Michael,1999, Penamona et al, 2003
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONGenerally, the mechanisms of dispute resolution can be
categorised into two main methods67, namely Adjudicative Dispute
Resolution - a decision is imposed on the parties in dispute and
Consensual Dispute Resolution – the parties resolve the dispute
by agreement. Dispute resolution will only come into existence if
there is a dispute and is being referred to it, which it has to
study the claims submitted by both parties and to appreciate the
underlying cause of the dispute, which is usually complex in
nature. This neatly fits into the concept of Adjudicative Dispute
Resolution where the dispute referred to a third party imposes a
decision on the parties. Under this type of dispute resolution
mechanism, we have arbitration, litigation and adjudication and
the decision is binding on the parties.
On the other hand an objective evaluation of dispute prevention
suggests that it is to handle and resolve conflict as early as
possible before it escalates into the third level of disagreement
otherwise known as dispute, an indication that the system is
already in operation even before any dispute rear it ugly head.
The fact that it is already in place consequently enables them to67 Glasgow Graduate School of Law 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONhandle and detect dispute as soon as possible68 and to resolve
the dispute with less difficulty should it occur. As observed by
Gerber69 in this regard, it may appear in the form of several
identities and distinct approaches, namely the DRB, DAB and DRA.
Furthermore, according to Chan et al70 the dispute prevention
can be categorised under the theme of ‘structured facilitation’,
or ‘willingness to compromise’, ‘rough and ready’, or ‘binding
but not final’ and ‘hybrid system’ or ‘advisory’.
Again Brewer71 opines that dispute management is a subset of
dispute prevention. Also, Brewer is of the view that dispute
management aims to reduce risk through proper project planning
and selection of appropriate procurement route during the
inception stage of a project. In a nutshell, dispute management
aims to prevent disputes from cropping up, which may unwittingly
require reference to some sort of dispute resolution process. In
view of this dispute management could also be termed
interchangeably as dispute prevention. That said, dispute
68 Harmon 200369 200170 200571 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONmanagement can be termed as a non-binding process while dispute
resolution can be grouped under binding and non-binding
processes. However, dispute management may arguably also include
a binding process as an enhancement to the procedure; such
examples are by way of agreement between the parties and through
the third party’s decision as may be provided in the contract.
2.6 Conclusion
The chapter indicated that mechanism for preventing construction
dispute needs to be in place to save the industry from enormous
amount of money. Again, following the invaluable lesson learned
in the construction of the ‘tower of the Babel72’, it is appropriate to
identify the generating sources or the potential triggers of
construction disputes, especially from the view point of the
stakeholders73 (i.e. the client, consultants, contractor and sub-
contractors) to a construction project. In this way, it will help
resolve dispute as early as possible, reduce or manage inevitable
disputes occurring and above all, prevent disputes escalating
into formal and informal costly resolution procedures.
72 Genesis chapter 11 v 1-873 Appendices 1 & 2
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Chapter 3- The Causes of Construction Disputes
3.1 Introduction
This chapter is to review the causes of disputes on construction
projects as indicated by other researchers.
When a dispute has been defined adequately and the causes for it
occurrence is known within the industry, a meaningful way
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONacceptable to all those involved in the project will be sought
for managing the dispute.
3.2 Disputes – Causation Agents
Inevitably, disputes are a reality on every construction
project74. They may arise on a construction project for a number
of reasons and can be grouped into 3 main categories75
Organisational – Increased project complexity has resulted in
varying forms of contract76, each with varying interfaces where
misunderstandings occur giving rise to dispute.
Contractual – This area covers the majority of construction
disputes, i.e. extension of time, liquidated damages,
variations, loss and expense, payment, late deliverables,
adverse weather etc.
Technical – Poor/Incomplete design, workmanship, material
selection etc.
Notwithstanding the categorisation of disputes, it still arises
on projects with best intentions. Even when every possibility of
74 Steen, 200275 Scwczuk, B. 1996, Carmichael, 2002, Steen, 2002, Kennedy, Conlin and Langford,199676 Steen, 2002, Kennedy, Conlin, Langford, 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdisagreement has been potentially eliminated, problems can still
occur. Consequently, understanding how disputes arise on project
site can be very helpful for anticipating situations that may be
turbulent. While it may seem, at times, that anything can start a
conflict and when not eliminated can result into a dispute,
especially in the present economic climate construction disputes
will typically revolve around defects and payment77.
Arguably, many construction disputes have their origin in the
seeds sown by or in, the client’s error78. This often happens
when the client expects something unrealistic to be done such as
the buildability of a complex design or the client taken
possession of his building within a very short time not taking
into consideration unexpected delays and unforeseen setbacks. As
indicated by Hellard79, there are four sets of contractual
relationships which are common in the construction programme and
thus when any of this relationship get strained, minor issues can
fester and grow into disputes with crippling consequences for the
projects participants. These relations can be summarised thus:
77 Glasgow Graduate school of Law, 78 Hellard, 198779 1987
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONa) The relationship of the client to the designer
b) The relationship of the designer to another designer
specialist(s)
c) The relationship of the client to the prime contractor;
and
d) The relationship of the prime contractor to suppliers
These four basic relationships have been studied over the years
by interested individuals as well as professional committees of
varied membership from all corners of the industry, along with
private and public attorneys. The result of these studies have
been the publication and wide usage of standard form contract
documents which are published in different construction
industries all over the world. Appendix 1 illustrates parties in
disputes collated by the Adjudicator Nominating Bodies for the
period 2000 to 2004.
In a study by Levy80, it was shown that, the principal reasons
for misunderstandings leading to disputes on construction
projects in the United States of America were the following:
80 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONI. Plans and specifications containing errors, omissions and
ambiguities or which lack proper degree of coordination
II. Incomplete or inaccurate responses or non responses to
questions or resolutions of problems presented by one party
in the contract to another party in the contract.
III. The inadequate administration of responsibilities by the
client, consultants, contractor, subcontractors or
suppliers.
IV. An unwillingness or inability to comply with the intent of
the contract or to adhere to industry standards in the
performance of work.
V. Site conditions which differ considerably from that
contained in the contract data.
VI. Unforeseen subsurface conditions.
VII. The uncovering of existing building conditions which differ
materially from those indicated in the contract drawings
situations that occur primarily during rehabilitation or
refurbishment work.
VIII. Extra work or change order work.
IX. Breaches of contract by either party in the contract.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONX. Disruptions, delays or acceleration to the work that creates
any deviation from the initial baseline schedule, and
XI. Inadequate financial strength on the part of the client,
contractor or subcontractor.
However, giving a comparative analysis of construction disputes
in the UK generally and Scotland in particular, Kennedy, Conlin
and Langford81 survey found that the cause of disputes is due to
the following:
Administrative
Managerial/Material/Workmanship/Quality
Negligence
Schedule
Performance
Payment and Budget
The above mentioned causes of dispute are illustrated
diagrammatically in Appendix 4 indicating the proportion each
contributes to dispute in the industry. The construction industry
as described by Kennedy, Conlin and Langford may not be still the
81 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONsame, but no research has been conducted since then so we will
assume the situation is as depicted by Kenny and Milligan82
In the survey conducted by Kennedy, Conlin and Langford83 to
ascertain the causes of dispute in the UK construction industry,
it was indicated that Payment and Budget contribute significantly
to dispute in the industry. The integral parts of payment and
budget causes contained in the survey are as follows:
a) Additional work
b) Over budget
c) Basis of fee
d) Additional fees
e) Non return of retention money
f) Liquidated damages claimed by client
g) Extension of time costs and expenses claimed by contractor
h) Non payment of balance of contract sum to subcontractor
82 2007, Appendix 183 1996, Appendix 5
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION i) Non payment of interim payment to subcontractor
j) Non payment of interim payment to contractor
k) Variation claim by contractor
In a study conducted on the US construction industry by Osborn,
the following were found to be the ten most contentious sources
of construction disputes.
i. The lack of focus up front, failure to choose the most
appropriate delivery method
ii. Inability to assemble the right project team
iii. Inability to coordinate the project team and scope of works
iv. Failure to understand local conditions
v. Inaccurate or too elaborate schedules
vi. No periodic job meeting minutes or failure to keep minutes
vii. No vision on dispute resolution; and
viii. The failure to recognise that quality wins
The failure to recognise that Quality wins was also a separate
survey conducted by Kennedy, Conlin and Langford84 and it was
84 1996, Appendix 6
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONfound that the below summarised issues constitute quality issues
and contribute significantly to the cause of dispute in the
Scottish construction industry.
a) Restrictions placed on contractors working method
b) Differing site conditions
c) Poor construction coordination
d) Poor coordination of subcontractors
e) Design information not timeous
f) Poor design coordination between consultants/subcontractors
g) Poor design coordination between consultants
h) Clients perception of construction design
i) Clients perception of specialists sub contractors design
j) Clients design team perception of contractors quality of
workmanship
k) Defective material.
From the above, the survey concluded that Poor construction
coordination was the major cause of dispute slightly followed by
defective materials85.
85 Appendix 6
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONA similar investigation in the Hong Kong construction industry,
Yates revealed that contractual incompleteness and consequent
‘post-contract’ adjustments, asset specificity in terms of
client’s investments in respect of purchase of land for the
project and opportunistic behaviour in particular on the part of
the contractor are the root causes of conflicts, claims, and
disputes.
The two causes of construction disputes that drive into
litigation process in the construction industry in the UK
according to Nystrom86 are uncertainty and imperfect contracts.
Furthermore, a research conducted by Hall87 during his practice
as a lawyer in the UK also found out that, the common cause of
construction dispute is ineffective communication. This is due
to the failure for someone to communicate effectively with
another concerning design issues, compensation and payment
issues. This was confirmed earlier by Kennedy, Conlin and
Langford88 in their research on the causes of dispute in the
Scottish construction industry and rather called it
86 200387 200288 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONadministrative issues89. Other issues which also result in legal
dispute include scope of changes or variations and in the
Scottish construction industry; arguably it is the major source
of disputes90.
The findings of Silver & Furlong91 on the main causes of
construction disputes were attributable to the complex set of
dependencies and interrelationships and delays and payment
schedule problems. Also indicated in his article ‘avoiding
construction disputes’, Walton92 was of the view that most
disputes have their root causes in one of the following:
A clash of expectations, usually entrenched during the
tender process, and not assisted by one party being overly
opportunistic in contract negotiations, with the other party
being overly aggressive or perhaps optimistic in pricing.
Poor allocation of risk.
Poor communication and contract administration.
89 Appendix 490 Appendix 591 200492 2005
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION Failure on the part of the parties to deal properly with
issues as they crop in.
In other common law jurisdictions such as Sri Lanka, Weddikara &
Abeynake93 revealed that disputes in the construction industry
are normally those that arise under contracts for the procurement
of supplies and services and the installation of equipment,
breaches of contract by any party to the contract, inadequate
administration of responsibilities by either the client,
contractor or sub-contractors, plans and specifications that
contains errors, omissions and ambiguities and sudden tax and
cost increases due to either inflation or sudden economic
changes.
As evidenced from examination of factors leading to disputes in
construction as outlined by Levy and Campbell among other
researchers, it is possible to fairly comprehensively tune that
the factors put together very much stick and carrot.
In a study conducted by Hellard94 into the sources of
construction disputes, his findings collaborated with factors of93 200794 1987
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONother research reports as contained in their various studies and
papers and it is as follows:
3.3 The contract Conditions
This is made up of:
Imperfection in the contract document
Inability to quantify cost
Interpersonal relationships of people involved in construction
i.e. sociological issues, psychological issues and
physiological issues.
3.4 The design deficiency
This consists of:
o The underground or subsurface problem, changed, and differing
conditions
o Poor and unfair allocation of risks
o Defective plans
o Construction methods and specification performance
As indicated by Hellard95 and supported by other researchers the
ground or subsurface problem, changed and differing conditions
95 1987
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONare a subset of design deficiency but the author is of the view
that it should be a cause on its own. The writer offers no
opinion in this but set it forth as a discussion point since
these conditions are almost unforeseen when the documents are
prepared and do not just occur.
3.5 The construction process
A major cause of construction dispute arises as a result of
the construction process according to Hellard96 and this view
is supported by other researchers. Although Hohns97 supports
Hellards view on construction process as a major cause of
construction dispute, he is of the view that it is difficult
to differentiate between design error and the consequence of
the process.
It is thought that provided the contractor carries out the
work strictly in accordance with the contract documents, he is
not responsible if the works prove to be unsuitable for the
purpose which the employer or architect has in mind. On the
other hand, it is probably the contractors implied duty to
96 198797 1979
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONbring any obvious errors in the architect’s design of which
the contractor had actual knowledge to the architect’s
attention.
Research into disputes during the construction process
according to Kennedy, Conlin and Langford98 and classified as
administrative causes is as follows:
Poor feed back from contractors
Contractor’s non adherence to administrative procedure
Lack of information from design team/client
Lack of Working information from design team
Design teams non adherence to administrative procedure
Sub contractor’s non adherence to administrative procedure
Extra contractual third party coordination
Certainly, the above list is not exhaustive but by standard
professional ethics, the items thereon is an indication of
failure on the part of someone to do that which was required by
the contract and having an impact on the project in question and
resulting into dispute.
Conclusion 98 1996, Appendix 7
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe chapter spelt out many causes of construction disputes from
different researchers which all suggest that there is the need to
ascertain time and time again whether the causes as outlined by
different researchers are improving or getting worse and thus
design a strategy to prevent them from occurring.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
4. The Structure of a construction Project
4.1 Introduction
In the earlier chapters we have examined in some detail the
component parts of a construction industry dispute. It is now
apparent that there are many aspects to contention between
parties on a construction project. Each area identified has been
examined in an almost theoretical and we now have to examine the
dispute in a context of a construction project. In reality, do
any or all of these issues arise in a typical construction
project? This chapter should partly answer that question.
The construction industry is marked by disputes, many of which
lead to litigation99. It might therefore be thought that
reported construction cases will not only shed light on the
immediate causes of such disputes, but provide insights into the
industry generally and the debates surrounding it. In this
chapter we have chosen to base the analysis on a real project
which has now progressed to litigation. All procedural issues are
99 Latham 1994, Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdefined and a hearing is set. There are many reasons for choosing
this particular project, but of particular importance is realism
and variety and to test this hypothesis. Whilst those familiar
with the case may recognize some of the incidents, the account
given below is a fictionalized version to protect the anonymity
of the project and those involved.
4.2 The Project
The client K. Bentum Andoh & Sons Ltd also known as KBA&S Ltd a
multinational company wants to develop a new West African
headquarters in the City of Abuja. This major project, on a
difficult and confined site, consisted of the erection of two
large buildings and the refurbishment of some existing buildings.
Ankoben Ltd was engaged as construction manager for the project.
Its role was to coordinate the work of the trade contractors and
to carry out administrative work in relation to the contracts.
Ankoben Ltd was represented onsite by Ms.Obaa-Yaa . The
contractual relationships between the various parties involved in
the project are shown in Appendix 8
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe project involved several trade contractors. Abeiku Ltd was
to undertake toilet fit-out works. The contract between KBA&S
Ltd - Abeiku Ltd was negotiated specifying Ankoben Ltd as the
construction manager. It was not possible for Abeiku Ltd to
price all the fit-out works at this stage, as not all of KBA&S
Ltd toilet facility requirements had yet been sufficiently
designed or specified. Abeiku Ltd was to carry out its works for
a specified period. Despite this timescale, the contract was not
signed immediately, by which point Abeiku Ltd had been on site
for months. Abeiku Ltd appointed Ms. Tima as its project
manager. Ms. Tima was based onsite.
Under the KBA&S Ltd - Abeiku Ltd contract, Ankoben Ltd was
entitled to issue formal (“CMIs”) to Abeiku Ltd. Many of the
CMIs issued by Ankoben Ltd did not affect the contract price;
some, however, instructed considerable additional works. Of
these, CMI 0100 is the most significant: It specified very
extensive additional works which Abeiku Ltd could not have priced
at the original negotiation stage. Under CMI 0100, Abeiku Ltd
contract period was extended but could not complete its works
within this extended period due to it not receiving possession of
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONall work areas timeously. It eventually completed its works by
having been late for several months.
4.3 The Dispute Period
Abeiku Ltd submitted its “Final Account” in the sum of nearly
¢6.5 million100 to KBA&S Ltd through Ankoben Ltd. This figure
included claims for loss and disruption, the latter being in the
sum of ¢2.5million. Abeiku Ltd justified this claim on the
basis that its works had been delayed or disrupted as a result of
the late completion of preceding works. It claimed that the late
completion of these works was due to Ankoben’s Ltd failure to
manage other contractors. Ankoben Ltd immediately rejected this
statement, stating that was bound by a document signed on its
behalf by Ms. Tima, which specified a figure in full and final
settlement of all its claims outstanding to that date. If
Ankoben Ltd could successfully maintain its position, the value
of Abeiku Ltd disruption claim would be greatly reduced. The
case was referred to adjudication of which Abeiku Ltd lost; it
100 Appendix 14
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONthen applied to the courts for a declaration that the document
referred to did not have the effect contended for by Ankoben Ltd.
4.4 The Material Fact
The court had to consider various terms of the contract and
evidence of the parties’ claims. Clause 20 of the contract dealt
with variations to the trade contract works. In terms of clause
20.3, Abeiku Ltd was required not to execute any variations
instructed by Ankoben Ltd unless it provided Ankoben Ltd with an
assessment of (i) the value of the variations (i.e. the cost of
labour, plant and materials), (ii) the impact of the variations
on time and (iii) any “direct disruption costs to which Abeiku
Ltd might be entitled101”. Clause 23 set out the payment
mechanisms for works carried out under the contract. Clause
23.6.4 regulated monthly ‘ISAs’. Generally, Ankoben Ltd was
required to issue Abeiku Ltd with ISAs in a standard form
detailing all CMIs issued to Abeiku Ltd which would entitle
Abeiku Ltd to an adjustment in the trade contract sum; Abeiku was101 This clause is similar to clause 61.2 under NEC 3 whereby the contractor isinvited to provide a quotation for a compensation event that is under contemplation. This reflects the real world where an Employer may decide to instigate a change but only if it is not going to have horrendous repercussions.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONto value each ISA, taking account of the value of variations, and
return it to Ankoben Ltd. Once Ankoben Ltd had agreed with
Abeiku Ltd valuation, Abeiku would sign the ISA, thus accepting
the total valuation as “the full and final value of our contract
works at the date of this statement.” As Abeiku Ltd project
manager, it was Ms. Tima that valued the CMIs listed in each ISA
and signed it ISA on Abeiku Ltd behalf.
The terms of the referred document differed significantly to the
standard ISA’s. It was headed “Final Statement of Account, Stage
1” and declared that Abeiku Ltd agreed that the final payment
specified in the document “will be accepted by Abeiku in full and
final settlement of all its claims… arising out of or in
connection with the Trade Contract Works which have accrued up to
and including the date of this statement. The origin of this
document was a critical issue for the court.
The court was unable to substantiate the exact background to
this document. Indeed, the court commented that “at the start of
the exercise it does not appear to have registered with Ms. Tima
that he was embarking upon an accounting exercise of a markedly
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdifferent kind to the consideration he had to give each month to
the value of the CMIs in order to complete the ISA Form.” Abeiku
Ltd in reviewing the evidence of meetings and contact between
Ms. Obaa-Yaa and Ms. Tima in a certain period of the project
currency, the court found that these were concerned only with the
valuation of CMIs; they did not touch upon the general issue of
contractual claims. After agreeing on a valuation for a specified
period, Ms. Obaa-Yaa then provided Ms. Tima with the referred
document. Ms. Tima signed the referred document without reading
it properly. The court found that he had not been alerted by Ms.
Obaa-Yaa to the changes that differentiated it from the standard
ISA. The court said that;
When Ms.Tima prepared her "Final Account" and met with Ms. Obaa-
Yaa and signed the referred document, she did not understand that
she was being requested to deal generally with the issue of
contractual claims and to allow for them, and there was no reason
why she should have thought that she was…. She did not appreciate
that, by the terms included on the last page, Ankoben Ltd was
inviting Abeiku Ltd to forego any and all as yet unrecognised
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONcontractual claims for additional costs that it might have. These
terms had been included, without any prior hint that they were to
be there and they were, unfortunately, overlooked by Ms. Tima.
4.5 Decision
Abeiku Ltd succeeded before the court on two alternative grounds.
4.5.1Unilateral mistake Ms. Tima had been mistaken as to the
nature of the referred document, the terms were considered contra
preferentum (i.e. favoured KBA’S Ltd and prejudiced Abeiku Ltd).
As Ms. Obaa-Yaa was found to have actual or constructive
knowledge of Ms. Tima’s mistake, Abeiku Ltd was entitled to a
remedy under the equitable doctrine of unilateral mistake.
Accordingly the court granted Abeiku Ltd rectification of the
referred document. The effect of such rectification would be
that the document would record agreed values for the last CMI,
with reference to general contractual claims being struck out.
4.5.2 Authority Ms. Tima’s authority only extended to matters
specified under the trade contract. The contract did not specify
any such document as a Final Statement of Account, Stage 1. In
view of this the, referred document could only bind Abeiku Ltd if
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONit was a valid variation of the contract. Thus, even if there
could be no finding of unilateral mistake, Ms. Tima did not have
the authority to vary the contract. Accordingly, Abeiku Ltd was
not bound by the referred document.
4.6 The Analysis So Far
To allow clear analysis the major issues that beset construction
projects i.e. measurement, variations and late payment was not
the source of dispute but rather what is explored below:
Time – The project is being rushed leading to mistakes being
made and those errors costly to rectify.
Honesty – The client is deliberately withholding information
which the contractor needs in order to price the works properly.
An increase in suspicion and mistrust, and an ignorance of the
facts, provides fertile ground for parties to dispute.
Fairness – The Management contractor has altered the contract
terms to increase the Package contractors risk and the Package
contractor, not being aware of the cleverly worded contract which
removes any remedy he may have, is not in a position to identify
that risk.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION4.7 Conclusion
The chapter has shown the ways in which dispute, in all its
forms, can arise in a normal constructional project. The client
failed to be honest in dealing with the contractor and allowed
dispute to grow rather than deal with them. It cannot be repeated
often enough that record keeping is the single most effective
method of preventing a conflict from turning into dispute. If
facts can be established early, the disputes will be more
manageable.
From appendix 1 it would be seem that dispute between Management
contractor and Package contractor is not prevalent. This is not
to suggest that Management contracting as a Procurement Method is
less adversarial and does limit dispute102. In Scotland we see it
but not often. Some colleagues down south think it is being used
more but that is not a universal view.
102 Copthorne Hotel (New Castle) Ltd – v- Arup Associates and Others
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
5 Applicability of Mediation as ADR
5.1 Introduction
Some disputes are quite unavoidable as seen in the previous
chapters. Proper management of the dispute will ease the impact
it has on a construction project, but resolution must follow
quickly. How then do we set about resolving disputes? It is
either formally or informally. This chapter will focus on the
informal process of dispute resolution. Informal resolution has
two major avenues down which disputant may pursue. They are
Negotiation and Mediation but Mediation as an Alternative Dispute
Resolution mechanism would be examined and the research conducted
in this area analysed.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION5.2 Background
The term ADR has generated a lot of debate in legal and quasi-
legal field since mid 1980s103. An enormous growth of ADR debate
was witnessed in the 1990’s when academics, lawyers and
consultants expressed interest and joined in the debate. Although
the concept of ADR is not new, the recent more formalised
technique as an alternative settlement procedure to the court has
it roots from the USA104. This was due to a variety of reasons;
notable among them was the workload of the court system and the
resultant inability of parties to a contract or any other
commercial transaction to have their dispute resolved in a timely
and cost effective manner105.
5.3 Level of Use and Knowledge of ADR.
5.3.1 UK Research
The commencement of the use of ADR in the UK can be traced to its
launch in November 1990106 by a non profit making body known as
CEDR supported by CBI to promote knowledge and use of ADR to
resolve commercial disputes in the UK.103 Gould, N. 2004104 Phen,L.S. 1996, Gould,N. 2004105 Uff, J. 2005106 Third mediation audit report of November 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAccording to CEDR107, the growth of the use of ADR has been steady
with a particularly rapid increase in the last five years or so
in the period of just under 20 years of its launch.
The report further states that cases with a total claim value of
over £4 billion are now mediated each year in England and Wales
and that the cumulative value of mediated cases since November
1990 was £23.5 billion. These cases have been referred from a
wide range of industry sectors, with the construction industry
one of the largest users being responsible for 6% of the total
mediation cases.
ADR has now found wide-spread use and is encouraged by the formal
court systems the world over, with some now requiring that before
a case is placed before the court, the case should have been put
through some form of ADR procedure108.
The Civil Procedure Rule109 proposed by Lord Wolf, empower judges
in England to stay proceeding for one month either with the
consent of both parties or on their own initiative to allow a
period of time for an ADR process to be conducted.
107 Third mediation audit report of November 2007108 TCC Pre Action Protocol109 April 1999
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION In the UK, Gould110 pioneered a major research into dispute
resolution in the construction industry in 1994. The research
indicated that less than 30% of the respondents had actually
being involved in an ADR process. The research further indicated
that the UK construction industry lacked an understanding of the
principle of ADR. Another research in this area conducted by
‘Brooker and Laver111 in construction disputes concluded by
accusing contractors of running away from mediation112.
From this survey, Brooker and Laver113 could be justified in
concluding that ADR is seen as being in its infant stage in the
UK. The Turner Kenneth Brown Report114 indicated that 75% of the
respondents considered ADR developments as a positive step with
6% considering it negative when executives responsible for
company legal services were interviewed. A comparative analysis
of construction arbitration and mediation in Australia and the UK
suggests that mediation is the preferred route115.
110 1994, Gould, N. 2004111 2000112 Gould, N. 2004113 2000114 1993, Gould, N. 2004115 Watts, V. and Scrievener, J. 1994, Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONA recent research by Gould et al116 into the use of mediation in
UK construction disputes focussed on parties at TCC in London,
Birmingham and Bristol. The respondents were interviewed on how
they settled their disputes as well as their experiences with
mediation during litigation. The results of the survey indicated
that 35% of the cases that settled after commencing litigation in
the TCC used mediation. The survey concluded that cost savings
attributable to successful mediations were enormous and
successful mediation were undertaken within the stipulated
litigation timetable.
In another research undertaken by Brooker and Laver117 with
respect to processes, perceptions, and predictions of dispute
resolution indicated that the use of adjudication would make the
most significant increase in the UK construction industry over
ADR processes such as mediation or expert determination.
The above snippets make it particularly noteworthy to delve into
Kennedy’s research118 into adjudication over the past 20 years.
The work of Adjudication Reporting Centre at Glasgow Caledonian
116 2009, Agapoui and Clark, 2010117 2000118 Kennedy, 2005
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONUniversity119 appears to represent best practice for collecting
data on the adjudication process and produced periodic reports on
the progress of adjudication in the UK. The centre has being
issuing regular reports from 2000 with information obtained from
Adjudicator Nominating Bodies .The data covered includes:
Number and skill base (discipline) of adjudicators
Trends in adjudications (growth, decline, fluctuations)
Performance of adjudication (complaints)
Best practices, major sources, causes and effects of
disputes in the construction industry
Such approach has been adopted by others within a number of other
jurisdictions, such as Hong Kong120, Egypt121 and Malaysia122. The
Kennedy and Milligan123 report concluded that there seems to be
some drift in terms of the original mission to replace litigation
and arbitration. The Latham report of 2004, commissioned to
review the successes of the Construction Act 1996 of the types of
disputes being referred to adjudications i.e. simple payment
119 Kennedy, 2005120 Cheung et al, 1999, 121 El- Aldaway et al, 2007122 Zulhabri et al, 2006123 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdisputes as against complex disputes’ involving highly technical
matters and legal issues and recommend any necessary amendments
was consistent with Kennedy and Milligan report.
5.3.2 Other Research
A similar research aimed at establishing the perceptions,
attitudes and experiences of industry participants towards
arbitration and mediation as ADR mechanisms has been conducted in
the construction industry in other parts of the world. Notable
among them include, New Zealand, England, South Africa, Hong Kong
Malaysia and Australia. The importance of ADR in justice delivery
is acknowledged in Ghana, and the Ghanaian judiciary had
integrated it into the country’s justice system. As a result of
that ADR has been advocated as the most appropriate mechanism for
the peaceful resolution of disputes in the country’s oil
industry124.
Some empirical investigations which exist suggests that
Stipanowich125 found that construction disputes in the USA
represents one of the first attempts to explore non binding
124 www. Modernghana.com, 2010 125 1992
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONdispute resolution in the context of construction126 and this
research has documented the rise of mediation127. From the survey,
Stipanowich concluded that, the Army Corp of Engineers pioneered
the process in order to reduce the high costs of litigation128.
In South Africa, Povey’s survey129 of mediation practice in the
construction industry was a notable addition to the empirical
evidence and suggests that there is a plethora of research and
literature on mediation as it is used by mediators and litigators
world wide and in various fields of dispute resolution. Barth130
investigating the suitability of arbitration in the South African
construction industry found that mediation was considered a more
suitable dispute settling mechanism than arbitration or
litigation by the industry participants (including attorneys).
Schindler’s131 research into the role of mediation and arbitration
as dispute resolution mechanism in the South African construction
industry focused on the awareness, experience, attitudes and
perceptions of architects, engineers and contractors and126 Agapoui and Clark, 2010127 Gould, N. 2004128 Gould, N. 2004129 Povey, 2005, Agapoui and Clark, 2010130 1991131 1989
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONconcluded that these participants did not have much experience in
mediation and as such have negative attitudes and perceptions
about the process.
5.3.3 Scotland Research
However, the vast majority of the mediations which take place in
the UK take place in England and Wales. In terms of related
research in Mediation, few authors have been identified in
Scotland. Agapoui and Clark132, May and Clark133, Clark and
Dawson134 dealt with Mediation as ADR as a continuum and
therefore provided valuable input into the corresponding part of
research in this area of the dissertation.
Agapoui and Clark135 dealt with Mediation practice in Scotland
which yielded useful attitudinal information. The research was
very informative in that, it provided useful insights to the
knowledge and level of use of ADR to resolve disputes in Scotland
by investigating into commercial litigator’s attitude and
experience of ADR generally and commercial specifically. Since
132 2010133 1996134 2006135 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONthis is the major research on ADR in Scotland and did not address
the construction industry, it can be said that research and
literature on the mediation of disputes in the Scottish
construction industry is limited and generally found to be of an
advisory or anecdotal in character.
A report by the Scottish Consumer Council136 entitled “Consensus
without court” noted that: While there are considerable numbers
of trained Mediators in Scotland there remains little demand for
their services in commercial and consumer disputes. The Scottish
Consumer Council Report echo those from Agapoui and Clark137, and
it would be comforting to keep one’s finger on the pulse and
observe if and to what extent Mediation as ADR is able to deliver
on these expectations. Agapoui and Clark 2010 presents useful
diagrams and tables illustrating breakdown of trained mediators,
their professional designation, element of the Mediation process
etc. and put these into continuum to illustrate their
applicability to a dispute and is contained in the Appendices.
136 August 2001137 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONA recent survey conducted by Agapoui and Clark138 on trained
mediators found that 82% of the respondents had receive some form
of training in mediatory techniques while 26% have attended
external courses on mediation and 14% attended in-house training
sessions. Figure 8 indicates the breakdown of respondents’
training in mediation.
The RSE139 noted in a report called “Encouraging Resolution”-
Mediating Patient/Health Services Disputes in Scotland and
concluded:
“In Scotland…. the use of ADR process such as Mediation is
negligible”.
The picture demonstrated in the RSE140 report may not be
different today but at least Table 1 suggests some changes,
although could not be compared to England and other common law
jurisdictions. Agapoui and Clark141 recent research on the
knowledge and level of ADR indicates 90% of the respondents were
able to provide an explanation of the process with confidence in
terms of knowledge of Mediation. 138 2010139 January 2002140 January 2002141 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONIn the RSE report, it was outlined that approximately 500 medical
negligence claims were pursued each year in Scotland. The report
further indicated that 70% of the total claims were dropped at
some stage prior to going to court. Those pursued in court were
settled before hearing and that amounted to 25%. The report
stated that only 5% went to a court hearing. It was also noted in
the report that the time taken to settle a claim from the date
when a formal claim was made was on average in the range of 31/2
and 41/2 years.
From the above, it could be concluded that a better method of
resolving disputes could be appreciated by the parties.
5.3.3.1 Satisfaction with Different Elements of Settling Disputes
According to Lord Coulsfield report142 aimed at finding out
satisfaction with elements of settling disputes noted that the
disputes decided by the courts, less than 50% thought the result
was fair – interesting as you would always expect to satisfy at
142 November, 2005
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONleast 50% but a result which probably explained by the costs
which even the winner of a court action has to incur143.
In a comparative analysis, 80% of those who had reached a
settlement extra-judicially thought they had in part or
completely achieve their objective compared to 43% of those who
had gone to court and received a hearing. The report found that a
high number of respondents – 43%, had never heard of Mediation.
However, of those involved in a dispute 50% of respondents said
they would have preferred their case to have gone to mediation
rather than to court. Among those who were surveyed and had gone
through Mediation expressed general satisfaction with the
process.
The Lord Coulsfield report further discussed the processes
available for solving civil justice problems and suggested that
there should be ‘a menu of choices’ available for parties in
dispute ranging from Negotiation and Mediation at the ‘least
intervention’ end of the scale to arbitration and litigation at
the ‘most intervention’ end.
143 Multiplex v Cleveland Bridge- the cost of photocopying amounted to £1million. Then guess the cost of legal fees.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAgapoui and Clark144 investigating the satisfaction with different
elements of the Mediation process found that around 33.3% of the
cases which go to formal Mediation were always satisfied and
43.3% with the speed of the process. Between 27% and 43% of
respondents were either always satisfied or often satisfied with
the cost of mediation respectively. From the survey, Agapoui and
Clark145 concluded that, overall, it would seem that a large
proportion of the respondents who had experience of mediation in
particular were satisfied with the process since almost 50% of
the respondents expressed satisfaction with the mediator and
63.3% satisfied with the outcome of mediation.
5.3.3.2 Attitudes to Mediation
The SEC report entitled ‘Modern Laws for a Modern Scotland146 –
opined that: “there is a need for an in-depth look at the
structure and procedures of the civil courts with a remit to
produce recommendations for changes to achieve a system which
deals with cases partly within a reasonable cost by incorporating
144 2010145 2010146 Report on Civil Justice in Scotland, February 2007.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONMediation into the civil justice system in the not too distant
future”.
Agapoui and Clark147 investigation into respondent’s perception of
dispute resolution, ADR as Mediation found out that about 80% of
the respondents considered Arbitration unsuited to the needs and
practices within construction. Arbitration which until recently
has been a favoured method of resolving such disputes, is under
attack in the UK because of its “perceived complexity, slowness
and expense”148. Similar criticisms149 have been levelled in the US
where arbitration for many years have been well entrenched as the
preferred method of construction dispute resolution.
Interestingly, the survey found out that 84% of the respondents
strongly and somewhat agreed that Adjudication was generally well
adapted to the construction context. Agapoui and Clark150 research
conforms to international trends and show that ADR was not always
understood or agreed by respondents and that although the system
has taken off so far, the knowledge base needed to be expanded.
147 2010 148 Latham, supra. Note 1 p.90149 Thompson. Supra. Note 3 p.140150 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONIn expanding the knowledge base as suggested above, the Lord
Gills Review151 specifically dealt with the reform of civil
procedure emphasising on the role of Mediation and other methods
of dispute resolution and further described the growth of
interest in methods of dispute resolution other than formal
adjudication by the courts as one of the most notable
developments in civil justice over the past decade or even more.
Perhaps even more relevant research work cited by others like
Agapoui and Clark152 suggest that this line of reasoning will be
welcomed in the construction industry as a large proportion of
the respondents, 62% strongly and somewhat agreed that contracts
should have a Mediation clause, such as Adjudication clause
provided by the SBCC/JCT standard forms of contract. Agapoui and
Clark153 present useful table comparing breakdown of frequency and
percentage response of respondents’ attitude to mediation and is
illustrated in Table3 in the Appendix.
5.4 The Impact of ADR on Litigation
151 A chapter of consultation paper issued in November 2007152 2010153 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThere has been great encouragement of the use of ADR from the
judiciary in England and Wales in cases resulting in a highly
significant decision in the English courts regarding cost order
against successful litigants on the grounds that those litigants
failed to seriously consider Mediation. The first of these154 was
Susan Dunnet v Railtrack Plc 155 in the court of Appeal.
In this case, there was appeal and counter appeal, from the first
instance decision, and because of it highly flexibility, the Lord
Justice suggested Mediation or a similar process for it
resolution. Regardless of the court suggestion, Railtrack failed
to engage in Mediation. Railtrack effectively won the appeal, but
the court of appeal found that as Railtrack has failed to mediate
then a costs order should not be made against the unsuccessful
claimant. In concluding one of the appeal court judges said that
“a skilled Mediation could achieve results far beyond the courts,
and a party who dismiss the opportunity for mediation without
proper thought suffer the uncomfortable consequences”.
154 Gould, N. 2004155 22 February 2002, Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONIn a survey conducted on factors leading to mediate in Scotland156
it was found that these include reduction in client legal costs,
achieving a speedier settlement and the possibility of achieving
a creative settlement to dispute. The findings concluded that
other factors associated with the decision to recommend Mediation
such as gaining information on the other side’s case etc seem
much less relevant and critical in respect of a decision to
mediate. These findings may not be in consonant with
circumstances of Susan Dunnet v Railtrack Plc but serves as
encouragement for the use of ADR in Scotland.
This ability in the English Rules to encourage the use of ADR has
been backed up by comment and orders from judges in a series of
cases since Susan Dunnet v Railtrack culminating in the decision of
the court of Appeal in Hasley v Milton Keynes NHS Trust157. Of particular
concern to the court of Appeal in this case was the question of
when a costs sanction would or would not be imposed on a
successful party who had unreasonably refused to enter into ADR.
156 Agapoui and Clark, 2010157 [2004]ECWA Civ 576
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONIn determining that issue the court said that the following six
factors were to be considered:
The nature of the dispute
The merits of the case (on the basis that a successful party
who reasonably believed it had a watertight case could be
justified in refusing to mediate)
The extent to which other settlement attempts had been made
Whether the cost of ADR would have been disproportionately
high
Whether delay in setting up ADR would have been prejudicial
Whether ADR had a reasonable prospect of success.
The facts and circumstances in Hasley v Milton Keynes NHS Trust suggest
that it is not in every situation that ADR has reasonable
success.
In finding out whether ADR always has reasonable success, a
survey conducted on the decision to refuse proposal for mediation
from the opposing party in the dispute in Scotland158, it was
found that 31% of the respondents always considered the clients
wishes not to use mediation as relevant while one – fifth of the158 Agapoui and Clark, 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONrespondent was of the view that the opposing party would not take
part in good faith as always relevant. More details of the
research are presented in Table 1 and are contained in the
Appendices.
In another case, The Wethered Estate Lt v Michael Davis and Others159, the
court was of the view that for the fact that mediation has taken
place will not prevent a party from claiming that a delay in
going to mediation was unreasonable. On the facts of this case,
the defendants had not shown that the claimant was unreasonable
in refusing to agree to mediation commencing proceedings. The
judge in this case was sympathetic to the claimants’ belief that
mediation would have had greater prospects of success in
formulating the issues considering the case having disputed
facts. At the mediation itself, the court was required by the
defendant to scrutinise the claimants’ behaviour. A mediation
being entirely without prejudice was confirmed by the court and
this privilege must be maintained unless there is clear
unequivocal waiver consent to a mutual waiver.
159 2005
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe determining factor in making a cost award by the judge based
on the conduct of the parties resulting in the failure of the
mediation settlement is demonstrated in the case Earl of Malmesbury
v Strutt & Paraker160. In this case the judge was able to pry into the
parties conduct because of the waiver of the confidentiality of
the mediation process. Commenting on the conduct of the
mediation, the judge said:
“I consider that the claimants’ position at the mediation was
plainly unrealistic and unreasonable. Had they made an offer
which better reflected their true position, the mediation might
have succeeded”.
In the opinion of the author, for a party who agrees to mediation
but then causes the mediation to fail by his reason of his
unreasonable position in the mediation is in a similar situation
as a party who unreasonably refuses to mediate. The conduct of
such party is tantamount to an unreasonable refusal to engage in
mediation.
There will be times when a party to a dispute will be insincere
in his intentions to settle. Some will cynically use ADR to defer
160 2008
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONsettlement of a dispute. In these instances formal dispute
resolution will be necessary utilising adjudication, arbitration
or litigation.
These cases express the position in England regarding mediation.
It is a testimony that the English courts will not excuse
unreasonable refusal to mediate where the parties have express a
desire to mediate or the courts is of the opinion that a
settlement outcome could be achieved.
5.5 Conclusion
As a result of CPR changes and the conduct of the judiciary, it
can be concluded that the position in England relating to the use
of ADR processes and mediation has taken off beginning from the
introduction of the CPR. On the other hand as evident from Gill
Report and research conducted by Agapoui and Clark161, Scotland
has of date not followed the trend as seen in some other
jurisdictions, where mediation as ADR is on the ascendancy.
161 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
6 Review of Mediation as ADR in Scotland
6.1 Introduction
The question now is, is there any reason to appreciate that the
standing barriers which have existed to date and have prevented
significant growth in the use of ADR in Scotland have a turning
point?
In the authors view that is the case and it is useful for the
moment to get a framework of this concept and examine a number of
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONreasons put forward as barriers which have existed to date to the
growth of mediation in Scotland, many of which are as strong now
as they have been to date.
6.2 Encouraging the use of ADR
The opportunity to introduce procedures for mandatory mediation
in appropriate cases or for cost sanction for unreasonable
refusal to engage in mediation on the model of the English CPR
has not been adopted in Scotland. The Gill Report162 which was
expected to accelerate the growth of ADR also rejects the idea
that parties should have taken averments in their pleadings about
the steps, if any; they have taken to resolve their dispute by
alternative means.
However, the Reports recommendation was to increase measures to
increase some awareness of mediation such as information on the
Scottish Court Service website, leaflets and a helpline in
addition to the introduction of a mediation service for small
claims.
It is unlikely; therefore, that anything in Gill Review will lead
to a rapid growth in the use of mediation for resolution of
162 October 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONcommercial disputes in Scotland as was seen when the Woolf
Reforms was introduced in England and Wales.
In the author’s view a major reason which may influence changes
especially in the construction industry is the growing
disenchantment with statutory adjudication both because of its
perceived unpredictability and also because of the increasing
role that appeal to the courts appear to be paying in the
adjudication process.
6.3 Judicial Attitudes
It is difficult to trace similar judicial enthusiasm in Scotland
either from the Gill Review or prior to that. So far Scotland has
no mandatory rule encouraging the use of ADR either in the Court
of Sessions rule or the Sheriff Court rules. The court of Session
Commercial Action rules provide at chapter 47.11(2) that “both
parties may wish to consider whether all or some of the dispute
may be amenable to some form of ADR. The Sheriff Court Commercial
Action rules provide that at case management conference the
sheriff is to seek to secure the expeditious resolution of the
action”. Rule 40.12(3) m provides that one of the orders the
Sheriff may make in order to achieve that expeditious resolution
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONis any order which the sheriff thinks will result in the speedy
resolution of the action – including the use of ADR. The power
to make an order for ADR to take place already exists in the
Sheriff Court commercial cause rules. It is anticipated that this
power will begin to be used in appropriate cases. There is also
realisation that commercial judges in the Court of Session are
favouring the use of ADR and are prepared to support it use.
In spite of the introduction of above measures there is no
indication or little evidence of the use of ADR being encouraged
to resolve commercial disputes either by the Court of Session
judges or by Sheriffs in the Sheriff Courts.
6.4 Legal Profession
According to Clark and Dawson163 only 1/3 of respondents had any
experience of representing clients in ADR processes. This figure
notwithstanding over 2/3 had recommended participation in ADR to
clients, the survey added.
Taking cognisance of this fact, it would be for all practical
purpose point out that there is the ‘unknown quantity’ element of
ADR. As is evident in a recent survey by Agapoui and Clark164,163 2006164 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONmany lawyers in charge of the conduct of litigation in Scotland
have little knowledge of what ADR is and how it operates, far
less any experience of the operation of ADR in practice. Many
have had no training either at the University or subsequently and
accordingly are subject to, on the one hand, the fear of the
unknown as opposed to on the other hand an adversarial process
which for all its imperfection they understand inside out.
That latter reference confirms that lawyers in Scotland are by
and large inherently conservative in their approach to the
conduct of disputes brought to them by clients. They tend to play
the game according to familiar rules. When instructed initially,
there may be steps taken to reach a negotiated settlement with
the other party’s advisers if that is what the client instructs
but for the most part a lawyer instructed in a commercial dispute
will tend to quite quickly enter into the tried and tested
process he knows best. Agapoui and Clark165 found in their recent
survey that 52% of respondents considered mediation to an
opponent were a sign of weakness. This reaffirms earlier
research by Gould166 where a section of the respondents argued165 2010166 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONthat to suggest ADR or mediation demonstrates a weakness in the
case. This leads to the ‘door of the court settlements’ which are
such a common feature in Scottish litigation. The litigious
nature of Scottish dispute in general was brought to light in
Lord Cullen’s review of Court of Session business. The report
stated that, 94.3% of the 300 sample actions he considered
settled but of those which settled 30% did so within one week of
a proof. From the above supported by Agapoui and Clark167
research it can be concluded that there has been a drift in terms
of the original mission to replace litigation and arbitration
with ADR.
Then, there is the argument to threat of income. Arguably,
certainly not all but some litigation lawyers in Scotland are of
the view that ADR is a threat to fee income than an opportunity
to expand their dispute resolution business by offering
commercial clients a process more attuned to the needs of their
business. This perception has been contrasted by Agapoui and
Clark168 recent research where 78% of the respondents strongly
disagree that the growth of mediation would be detrimental to167 2010168 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONfuture earnings. Indeed, a large majority, about 88%, strongly
and somewhat agreed that mediation would provide an opportunity
to offer further services to their clients.
In economic parlance as the demand grows more of the items will
be supplied169. In the same vein, as client demand grows lawyers
will have to become acquainted with the use of ADR or risk
endangering their client relationship. With increased awareness
from lawyers will result, in the author’s opinion, an awareness
that ADR is to be embraced rather than suspect it as threat to
fee income. Once lawyers embrace it and involve in the resolution
of disputes to the satisfaction of clients, there is the
possibility of expanding their dispute resolution businesses.
Cynically, it has been suspected that as young lawyers come
through the profession who are aware of and have an understanding
of ADR through their University training the fear of the unknown
factor will vanish.
6.5 Client Awareness
169 Stanlake 1994
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThis may neatly roll up the’ chicken and egg’ factor, that
because ADR is little used in Scotland and lawyers are by and
large reluctant to promote its use, there is a lack of awareness
amongst commercial clients both of the existence of ADR and of
its benefits to them in many cases.
Agapoui and Clark170 research into decision to recommend Mediation
to client suggests that recommending mediation to client was
inversely proportional to representing a client in mediation.
This stems from the fact that experience and track record in
mediation would seem to be critical factors for legal counsel in
respect to their recommendations to clients171.
It would be understandable to conclude that the lack of demand
from Scottish clients for ADR to be used to resolve their
disputes may be attributable to lack of awareness. The growth of
the use of ADR in England, the USA, Hong Kong and other parts of
the world and the satisfaction which users normally express
regarding the process suggest that clients who have used ADR
processes want to use it again than to use litigation172. Equally
170 2010 171 Agapoui and Clark, 2010172 Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONit is reasonable to believe that since many of the large
commercial disputes in Scotland involve UK or international
companies, as the use of ADR grows in other jurisdictions the
demand for ADR to be used to resolve disputes in Scotland will
also grow.
6.6 Scottish Government - The Civil Justice Review being
announced in Scotland is an indication that the Scottish is ready
to support the use of ADR in appropriate cases notwithstanding,
the results of the review been a disappointment for supporters of
ADR.
6.7 Conclusion
Reports from other common law jurisdictions seem that ADR has
attained a de facto finality in its use, and though it has
challenges, it is believed that through regular reviews173,
performance reporting174, and the expansion of its knowledge base
through workshop and the like175, its position in the Scottish
Construction Industry dispute resolution can get stronger.
173 Latham, 2004174 Kennedy, P. 2007175 Van Langelaar, 2001
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
7 How Mediation as ADR Works In Practice
7.1 Introduction
It would be useful at this stage to define ADR and explain how it
works in practice.
Available literature indicates that ADR is a widely discussed
discipline within the jurisprudence of construction disputes. An
anecdotal review of the subject matter has been provided by many
academics. Few writers are careful and dare go beyond the
normative to describe ADR definitely, some also suggest that this
term only refers to Mediation. Others have also revealed their
attitude towards the subject by labelling it one of the
following:
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAlternative Dispute Resolution
Amicable Dispute Resolution
Assisted Dispute Resolution
Appropriate Dispute Resolution
Another Disappointing Result
Another Drink Required
Another Dammed Rip-off
Alternative Dispute Resolution is the most widely used phrase.
ADR involves a change of mind set to some extent and is generally
viewed as being consensual and conducted outside formal court
system176. It involves getting away from looking exclusively at
how lawyers and judges operate and adopting a more sociological
approach. For example in the formal dispute resolution, there is
a ‘winner’ and ‘loser’, whereas ADR should be attempting to make
both parties feel like ‘winners’. In a nutshell ADR is any
process whereby disputes are resolved through negotiation between
the parties with the assistance of a neutral party.
7.2 ADR Defined
176 Uff,2005
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe definition of ADR as given by Brown & Marriot177 is a range of
procedures that serve as alternatives to litigation through the
courts for the resolution of disputes, generally involving the
intercession and assistance of a neutral and impartial third
party. The authors go on to state that most definitions would
exclude not only litigation, but all other forms of adjudication
or third party determination. In other words the process is one
of assisted negotiation rather than third party decision-making.
7.3 Mediation in Practice
The most widely used ADR process is Mediation. The origins of
Mediation and conciliation can be traced to China some 3,000
years ago. China has used these techniques as a primary dispute
resolution process in order to maintain harmony in the
community178. In the UK, Mediation under the banner of ADR was
first used for settling family disputes and the ICE in 1988
incorporated this process in its standard form of contract179. The
courts in UK have recently piloted a court-based mediation
177 1993178 Gould, N. 2004179 Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONscheme180. According to Gould181, research by Stipanowich has
documented the rise of Mediation in US construction industry.
In Mediation, the mediator through a combination of open sessions
with both parties and private or ‘caucus’ sessions, assists the
parties to reach a negotiated agreement. Mediation is therefore a
process of facilitation. The parties to the dispute use the
assistance of an impartial third party to help them to arrive at
an agreed resolution of the dispute, but the mediator has no
power to make any decisions that are binding on the parties.
This assisted negotiation technique is intended to reconcile the
parties in dispute by using the good offices of independent and
impartial professionals who are skilled in the techniques and
experienced in construction. The mediator has, as his main aim,
the resolution of the dispute by the parties to achieve a
practical and commercial remedy. The distinction between
mediation and formal adjudication is the lack of legal procedure.
This is an advantage in encouraging the parties to come to
mediation, because the hearings are usually without prejudice.
180 Butter, N. 1997, Gould, N. 2004181 Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThis is not to say that it does not have disadvantages. Perhaps
the most difficult of these disadvantages is the lack of a
legally binding result.
7.4 Differences between Mediation and Adjudication Processes
According to Gould182 there are five main areas of distinction and
it will be explored below.
7.4.1 Non-Binding Voluntary Nature of Mediation
The first important distinction is that while Adjudication
methods are binding and mandatory once commenced, Mediation is a
non-binding voluntary process. What this highlight is either
party’s ability to ‘walk away’ from the Mediation at any time.
That ability is in fact an important factor in bringing about
resolution of the dispute. This suggests that so far as the
parties remain engaged in the process, the parties impliedly
accept that they retain a desire to arrive, with the assistance
of the mediator, at a solution to the dispute.
182 Gould, N. 2004
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAccording to CEDR183 statistics, the success rate of ADR in
achieving settlement is very high, and is between 75-80%.
However, even if no settlement is reached, the original
commitment to the process will, at the very least, get the
parties to meet round the table in a shared, though initially
unsuccessful, desire to resolve the dispute. That alone may well
help to break down barriers and clarify the issues in dispute and
will often commence a dialogue which will later lead to
resolution.
7.4.2 Role of Mediator
In ADR, the parties resolve the dispute by agreement whereas in
litigation and sometimes arbitration, a decision is imposed on
the parties. Arbitration which used to be the preferred method of
resolving such disputes is unsatisfactory because of frequent
delays and the “constant spectre of appeal”184. The Mediator helps
the parties to reach an agreement and not to make any decision on
183 2007
184 King, V. W. 1999
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONeither the facts or the laws. The essential aspects of being a
Mediator as suggested by Brown and Marriot185 is as follows:
The first consist of the basic elements which are
theoretical understanding, practical skills, ethical
awareness and emotional sensitivity.
The next element is that the mediator must bring sound
judgement, personal empathy and substantive knowledge of
legal, technical or practical aspects of matters which are
relevant to the dispute.
The third is that the mediator must be creative and
flexible.
Finally the mediator must have balance - he must
demonstrate impartiality and an even handed approach to the
issues and the parties involved.
7.4.3 Informality of ADR Processes
In ADR how the process works is up to the parties and the neutral
to decide. This results in the third important distinction,
namely the respective formalities of the procedures. In Mediation
the parties agree the procedure. They do that having regard to
185 1993
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONthe nature of the dispute they wish to resolve. They are at all
times in control of the timetable, the agenda and essentially the
outcome.
Notwithstanding the informal nature of ADR, the parties can give
them a structure which is akin to the formal processes, in order
to formalise them. This suggests that the procedure is under the
parties’ control.
Contrast that with adjudicatory methods such as litigation and
arbitration. How often has one heard the criticism that, once
lawyers get involved in a dispute it develops a life of its own
with complicated and difficult rules of pleadings and evidence,
disclosure of documents and the like. More and more that approach
to dispute resolution is not acceptable to commercial clients.
They want to be proactive in how their dispute is resolved and to
have the opportunity to bring about a more creative and flexible
outcome than a court can deliver.
7.4.4 Nature of outcome
Another principal distinction relates to the outcome achieved.
The whole thrust of ADR is the voluntary, consensual nature of
the process. The parties enter the process and remain in it
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONbecause they want to reach settlement. They choose the Mediator
and the procedure is under their control. Again, it is the
parties who arrive at the settlement. If the outcome achieve is
not acceptable to both sides, then the parties can walk away and
if they choose, go back to court or Arbitration. If an agreement
is reached, it will reflect their respective business interests.
In contrast to adjudicatory methods, if they proceed to a
conclusion it will produce a decision of fact and law based on
principle which will be imposed on the parties whether they like
it or not. In some cases, that is exactly what the parties’ want,
in which case adjudication methods are appropriate. In the vast
majority of cases however, the dispute settles prior to the
decision being given.
7.4.5 Confidentiality
ADR is, like arbitration but unlike litigation, an entirely
private and confidential process and that will be explicitly
agreed by the parties and the Mediator in the agreement to
mediate. No publicity is given to the fact that the parties are
engaged neither in ADR nor to the outcome or conduct of the
mediation unless with the consent of both parties. There is a
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONgeneral confidentiality attached to the whole process and also
where the mediator meets a party in a private session, he will
have agreed not to disclose anything said to him during that
session without express authority.
The parties will also agree in the mediation agreement that the
process is privileged and without prejudice so that anything
disclosed during the process cannot be referred to in any
subsequent court or arbitration proceedings.
7.5 Advantages of ADR- Mediation in Commercial Disputes
An objective evaluation, after a depth study and analysis of the
many factors of ADR, the writer opine that there are four
principal advantages:
7.5.1Cost
The first and perhaps most obvious advantage of ADR is cost –
both in relation to legal and other fees to be paid, and also in
relation to the hidden cost of loss of management time.
In formal dispute resolution mechanism, i.e. litigation and
arbitration, parties are faced with lawyers’ fees often for
Solicitors and Counsel, and in more complex litigation, often
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONalso with fees for experts witness. In Arbitration, the costs
also include fees for the Arbiter and his clerk and the cost of
hire of the arbitration avenue.
In both litigation and arbitration, the rules on taxation of fees
mean that even the winner can usually recover no more than
approximately 60% of those fees from the unsuccessful party186.
The costs in both litigation and arbitration are high because the
emphasis in preparing the case for hearing is on the factual
detail. It is on the exploration of every relevant fact and
production of every document to substantiate your own side’s case
and to repudiate the evidence of opponent. There is a tremendous
additional cost of management time both in preparing the case
prior to hearings and in relation to attendance at hearings.
For ADR to work properly, it is essential that parties or their
lawyers prepare the case properly. Often lawyers will play an
important role in the preparation and presentation of their
client’s case at Mediations. So in ADR parties will very often
have legal cost to incur. Putting these elements together very
186 Glasgow Graduate School of Law 2010 Course work
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONmuch stick and carrot and however produces total costs which are
a small fraction of costs than in long-running litigation or
arbitration processes – even where those processes produce a
settlement before a hearing takes place.
7.5.2 Speed
Closely linked to the cost advantage is the speed with which ADR
brings settlement about. The system in both litigation and
arbitration tends to be slow in focusing the real issues in
dispute. There is a tendency for case management practices to be
such that preparation for a hearing takes place late in the day.
Lawyers and their clients will often be reluctant to propose
settlement early on in the process in case that should be
interpreted as a tacit acknowledgement that their case is weak.
All of these reasons lead to “door-of-the court” settlements
induced more by fear than anything else, particularly by fear of
the cost of proceeding with the hearing. Because the settlements
are often last-minute, they tend to be on the basis of a
compromise position between success for the respective parties
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONrather than truly creative solutions on the basis of the genuine
business interests of the parties.
Once the parties have agreed to try to mediate, they will agree
on the appointment of a Mediator. They may have an initial
meeting with the Mediator to agree on procedure. They will then
usually be allowed a relatively short period to prepare brief
written statements to the Mediator, backed up by a supporting
document where appropriate. A full day, or sometimes more, will
then be set aside for the Mediation. If the process produces a
settlement a binding agreement will be arrived at there and then.
In the UK the success rate187 is over 75%.
Above all the whole process will in most cases have taken a
matter of weeks, compared with the several years which litigation
or arbitration can often take to produce a negotiated settlement
or a binding decision.
7.5.3 Preservation of Commercial Relationships
The third important advantage in the writer’s opinion arises from
voluntary nature of the process. Litigation and Arbitration are187 CEDR 2007 statistics
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONadversarial processes. Parties adopt position where they seek to
justify their highest possible claim and to destroy the other
side’s case. Aggressive positions are adopted, trenches are dug
from which parties and their lawyers find it difficult to get
out. All that leads to a breakdown of commercial relationships
between the parties, which may often be permanent, between
parties who in many cases are only in this position because
previously they were happy to contract together for their mutual
benefit, for example a main contractor and a subcontractor in a
building contract or a client and his professional adviser.
When the parties get together in ADR, they do so not out of a
desire to defeat the other, but out of a shared desire to reach
agreement. They come to that process voluntarily and they only
remain in it as long as they want to. If a settlement is reached
it is the parties’ settlement – not the lawyers’ settlement and
not a third party imposing a ruling on the parties. The nature of
the process therefore enables parties who are in dispute to
resolve it in a way which will enable them to preserve their
relationship and so give them a much better chance to work again
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONin the future. This is particularly relevant to parties to
construction and engineering disputes where the concept of
partnering has become so important.
7.5.4 Creative Outcome – Increasing Settlement Options
To some extent, the writer is of the view that the most
important and telling advantage which ADR has is the opportunity
which it gives the parties, assisted by a Mediator, to be
creative in finding a solution to their dispute.
It enables them to move beyond the parameters of the ‘win – lose’
outcome based on strict interpretation of past events, and arrive
at a solution on the basis of their own business interest and
future commercial options.
Litigation and Arbitration cases proceed on the basis that, if
the matter goes to its conclusion, one side will win and the
other side will lose and a sum of money is awarded by the judge
or arbiter to the winning party. The ‘win – lose’ may not be the
solution which is most appropriate for the parties’ commercial
needs. Think of the building contract situation, if say a main
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONcontractor has a claim against his sub-contractor and is
successful, the judge or arbiter will award the main contractor a
sum of money. The sub-contractor may not be able to pay. He may
go into insolvency with the result that the main contractor gets
nothing except a large legal bill, the loss of management time
over 2 to 3 years. It may be that in that situation a better
solution for both parties could have been found in negotiating
terms for future contracts whereby, for example, the sub-
contractor could have carried out work for a period for the main
contractor on discounted terms. Does that not have the potential
to be a better outcome for both sides? The commercial
relationship is preserved, legal fees and management time are
minimised, and the settlement is a creative outcome for both
sides. That is the kind of settlement which ADR can offer but
which litigation and arbitration by their nature cannot.
7.6 Conclusion
The aim of ADR is to bring the parties together to find a joint
solution which is mutually acceptable. The ADR refers to another
way of settling disputes beyond litigation and arbitration. The
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONkey to this method of resolving disputes is always to ask the
question “what is it that will help the parties resolve the
dispute”. This provides an agenda for the resolution process that
excludes laying the blame, digging up old arguments and
criticising the behaviour of others. The ADR process can be
either reactive or proactive. It can be in place preventing and
managing disputes from arising as early as it can be and for
resolving those that have arisen.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
8 Conclusion
8.1 Introduction
In the previous chapters we have sought to set out the symptoms,
causes and effect of disputes in the construction industry. The
behaviours and techniques which need to be developed to prevent,
manage and resolve disputes in order to preserve commercial
relationship has been addressed. Whilst all of this has been
necessary and worthwhile, perhaps the greatest emphasis should be
placed on the prevention of disputes rather than managing and
resolution.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe conclusion chapter will therefore place emphasis on the
concept and ideas which can be addressed to alleviate the
pressure on the construction industry to disputation. That being
fulfilled, the harmonisation of construction and its related
industries will come as a result of examining all possibilities
and finding useful contributions from each of them and then
answering the searchable question for this dissertation.
Is there real hope in the future for a general reduction in construction disputes?
8.2 Competitive tendering
The letting of contracts by competitive tendering has been much
criticised188. It is contended that it encourages contractors to
bid low to secure work in the hope of securing additional
payments through variations and claims. The system might also
lead to “motivational problems”, once contractors are locked into
executing work at a very low price189. An associated problem is
that the system of competitive tendering selects contractors by
price and might not ensure value for money, competency or
efficiency.
188 Egan 1998189 Winch 2002 p. 101
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe pattern of delay and the inefficient and defective execution
of works in the construction industry can, to some extent at
least, clearly be linked to the disadvantages of competitive
tendering.
8.3 Changes in Contracts
In construction and engineering, not only in the UK but the
world all over, contracts have been designed to be fair and well-
balanced, and a great deal of effort has been exerted to achieve
this. Perhaps now is the time to make them less adversarial and
more investigative.
We need to be innovative in the field of preparing contract
documentation to ensure that dispute is prevented wherever
possible. Furthermore, contracts can be simplified to avoid
misunderstanding, and certainly can be improved in terms of
cooperation.
8.4 Partnering
Pursuant to laws governing competition in trade and fair trade in
the EU, partnering may be a way forward towards more harmony on
construction projects. Some large clients, such as supermarkets
have now developed links with contractors and subcontractors on
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONwhom they can rely. The ongoing relationship created by this
partnering has two significant benefits when it comes to reducing
disputes.
An interest in an ongoing relationship, so that small disputes
are put into a proper perspective.
The relationship is based upon mutual trust and cooperation
This is not to say that, Partnering will exclude the dispute in
totality, but it will certainly encourage the parties to minimize
the impact which the dispute has upon the project and upon the
future relationship.
A widely accepted definition of partnering is: “A management
approach used by two or more organisations to achieve specific
business objectives by maximising the effectiveness of each
participant’s resources. The approach is based on mutual
objectives, an agreed method of problem resolution and an active
search for continuous measurable improvements”190. Egan argued
for partnering, defined in this way, to be implemented throughout
the supply chain; this would allow benefits to accrue to the
190 NAO 2001, quoting Bennett and Jayes’ Trusting the Team at the Reading Construction Forum 1998
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONclient through rigorous implementation of lean production
techniques. Many bodies have subscribed to the Egan agenda.
8.5 Dispute - The way forward
The dissertation as a whole has examined, with some optimism, at
the future how current trends can assist in preventing, managing
and resolving construction disputes. Having identified dispute
in construction projects, a more nuanced approach be adopted in
order to promote changes in culture which are adversarial in
nature. By this procedure, a step forward would have been taken
to answer the searchable question “Is there real hope in the future for a
general reduction in construction disputes”?
The End
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
9 BIBLIOGRAPH Y
9.1 Books
AAA, 1996 American Arbitration Association, Building Success forthe 21st Century – A Guide to Partnering in the Construction IndustryAgapoui, A. and Clark, B. (2010) unpublished, on file with theauthor).
Allen, R. K. 1993, Dispute Avoidance and Resolution forConsulting Engineers, American Society of Civil Engineers, New York
Bachner, J. 1995 Alternative Dispute Resolution: Successful newapproaches ancient problems, A Message to Client from Associationof Soil and Foundation Engineers, Silver Spring, Md
Baden Hellard, R. 1988. Managing Construction Conflict
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONBattele, A.E. 1995. The growing impact of ADR on the Constructionindustry; ‘Real Time’ Dispute Processing on the Boston CentralArtery/Tunnel Project. Construction Law Journal, November 13
Brennan, F. P.E. 2006 ‘the ABC of ADRs’ Cause and Effects: Newsfrom CPMI Spring
Brown Arthur, H. J. and Marriott, L. ADR principles and practice2nd ed. London: Sweet & Maxwell 1999Butter, N. (1997) Mediation and the Courts: first official pilotmediation; The Expert, September
Campbell, P. 1997, Construction Dispute Avoidance and Resolution(Latheronwheel: Whittles Publishing)
Canterbury (Jnr), J. F. 2007, Construction Dispute Avoidancepresented to American Institute of Contractors, April 20
Carmichael, D.G. 2002, Disputes and International projects.Liase: A.A. Baklava PublishersChan et al., “Pattern in the use of dispute resolution methods inthe international construction industry” (2005) 16 AustralasianDispute Resolution Journal 65.The ADR Practice Guide – Commercial
Cheung et al. 1999 – “Factors affecting clients” Project DisputeResolution Satisfaction in Hong Kong: Construction Management andEconomics; 281, 282.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONCheeks, J.R. 1996, Settlements of shadow foundations onuncontrolled mine spoil fill, J. Perform. Constr.Facil. 10(4),143-151
Chin S.L. 2003 Procurement method as Conflict and DisputeReduction mechanism for the construction industry in Malaysia,Faculty of Civil Engineering, Universti Technologi Malasia, MSc.Construction Management report, unpublishedDering, C. “Dispute Boards: It's Time to Move On” (2004) 21 TheInternational Construction Law Review 438.
Eilenberg, I.M. Dispute Resolution in Construction Management (Sydney:University of New South Wales Press Ltd, 2003).
El –Adaway, I.H.and A.S.Ezeldin, (2007) “Dispute Review Boards:Expected Application on Egyptian large – scale constructionproject”
Fenn, P. Lowe D. and Speck C., “Conflict and dispute inconstruction” (1997) 15 Construction Management and Economics 513.
Fenn, Lowe and Speck, “Conflict and dispute inconstruction” (1997) 15 Construction Management and Economics 513,514.
Gallanter, M. (1983) “Reading the landscape of disputes; what weknow and what we don’t know (and think we know about ourallegedly contentious and litigious society” UCLA Law Review 31
Gerber, P. “Dispute avoidance procedures (‘DAPs’)” (2001) 18International Construction Law Review 122.
Gerber, P. “The changing face of construction dispute resolutionin the international arena: where to from here?” (2000)Australian Construction Law Newsletter 5.
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONGould,N. et al 1999, Dispute Resolution in the Construction
Industry
Gould,N. Capper, P. Dixon, G. Cohen, M. (1999) Dispute
Resolution in the Construction Industry
Gould, N. Capper, P. Dixon, G. Cohen, M. (1999) “DisputeResolution in the Construction Industry” Thomas Telford, London
Harmon, K.M.J (2003), Resolution of Construction Disputes: AReview of Current Methodologies. Leadership ManagementEngineering, Vol. 3 Issue 4. (American Society of Engineers)
Hazel G. and Paterson A. 2001, Paths to justice Scotland : whatpeople in Scotland do and think about going to law OfficialReport on Scottish Parliament Debate on Alternative DisputeResolution –November 2007
Hellard, B. R. 1997, Preventing and solving construction contractdispute: Litton Educational Publishing Company
Irvine, C. (2010) The sound of one hand clapping: the GillReview’s faint praise for Mediation; Edinburgh Law Review 85-92
Karl J. Mackie, David Miles; William Marsh Tottel, 2007,Commercial dispute resolution: an ADR practice guide (3rd
edition)
King,V.W. (1999) Constructing the team, A US perspective
Kumaraswarmy, M.M.,Yogeswaran,K. (1997), Encouraging Conflicts,Discouraging Disputes and Managing claims, NIMCAR Journal ofConstruction Management, XII, 15-30
Levy, S.M. 2007 Project Management in Construction 5th edition,
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONLord-Smith, P.J. A voiding Claims in Construction, 1994
Mays, R. and Clark, B. (1996) Alternative Dispute Resolution in
Scotland (the Robert Gordon University)
McGuin, J.F.(1989) Use and Abuse of risk allocation in theconstruction industry, “Allocating Risk in today’s Construction:A Search For Fairness And Solution; The Fifth Annual Meeting OfThe American Bar Association Forum On The Construction Industry,New Orleans, LA
Michel, H.L.1999, The next 25 years; “The Future of theConstruction Industry” Journal of Management in Engineering,ASCE; Vol.18
Motsa,C.D. (2006) Managing Construction Disputes; Faculty ofCivil Engineering, University Technologi Malaysia Unpublished
Ng,H.S. F. Pena-Mora and T. Tamaki, “Dynamic conflictmanagement in large-scale design and constructionprojects” (2007) 23 Journal of Management in Engineering 52.
Nystrom, L. (1995), Settling Construction Disputes, Virginia Tech
Spectrum2 March
Penamora, Sosa, F.CE. and Mccone, D.S. (2003), Introduction to
Construction Dispute Resolution
Phen,L.S. 1996, Gould, N. (2004) The influence of ChinesePhilosophies on Mediation and Conciliation in the Far East,Arbitration.Povey, A. ( 2005) An Investigation Into The Mediation OfDisputes In The South African Construction Industry: Journal OfThe South African Institute Of Civil Engineering, Vol. 47 No. I
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Richbell, D, 2005, Mediation of Construction Disputes,
Sakal, M.W. (2004); Constructing Projects In A DynamicEnvironment; A Focus On Relational Contracting, Master OfEngineering Report, University Of California, Berkeley,Unpublished.
Sarat, A. (1985) The litigation Explosion, Access to Justice andcourt Reform: Examining the critical issues 37” Reutledgers Lawreview 299
Silver, R. and Furlong, G. (2004) Complex construction disputescan be hammered out. The Lawyers weekly, March26,
Singh, H. Engineering and Construction Contracts Management: Post-Commencement Administration (Singapore: LexisNexis, 2003).
Stanlake, G.F. (1994) Introduction to Economics 4th Edition
Steen, R.H. (2002) Alternative Dispute Resolution in the
Construction Industry
Stipanowich, T.J. 1998, Reconstructing Construction Law: Reality
and reform in a transactional system
Stipanovich, T.J. (1996) Beyond Arbitration: Innovation andEvolution in the US Construction Industry, 31 Wake Forest LawReview, 65
Turner Kenneth Brown (1993) Alternatives to Litigation in the UK.
Kenneth Turner Brown Library, London
Uff, J. (2005) Construction Law. 9th Edition. Sweet & Maxwell
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONUry, W. & Fisher. 1999, Getting to Yes: Negotiating an Agreement
without giving in; 2nd edition
Ury, W. (2008) Getting Past No, Negotiating with difficultpeople,
Walton, J. (2005) Avoiding construction disputes just a matter
of price?
Watts, V. Scrievener, J. (1994) Building Dispute settled byLitigation, Comparison of Australia and UK Industry” 31 WakeForest Law Review 65
Weddikara, C and Abeyance, M. (2007) Resolving ConstructionDisputes, the Nation on Sunday
Winch G.M. (2002) Managing Construction Projects: Oxford;Blackwell
Whitfield, J. Conflicts in Construction – Avoiding, Managing,Resolving, 1994
Zulhabril, I. Jamalunlaili and Rosli, M.Z. (2008) Findings ofAlternative Dispute Resolution (ADR) Application and Obstaclestowards Active Development of ADR in the Malaysian ConstructionIndustry” 3rd Conference on Law and Technology 2008
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
9.2 Articles
Clark, B. and Dawson, C. 2006 – Scottish Commercial Litigators,Published in the Journal of the Law Society of Scotland inSeptember 2006
Gould, N. (2004) Dispute Resolution in the Construction Industry:
An Overview
Fenn, P and Gould, N. (1994) Dispute Resolution in the UKconstruction Industry, DART Conference, Lexington, Kentucky, USA,16 – 19 0ctober
Kennedy. P, and Milligan, J. (2005). Adjudication ReportingCentre – Research Analysis of the Progress of Adjudication basedon Adjudicator Nominating Bodies (ANB’s) returned questionnaires:Report No.7, August 2005
Langford, D. Kennedy, P. and Conlin,J. (1996) The Sources,causes and effects of conflicts in the construction industry;Engineering and Physical Science Research Council (EPSRC) FinalResearch Report for Grant No.GR/J48603
Latham, M. (1994), Constructing the Team, Final Report of theGovernment/Industry Review of Procurement and ContractualArrangements in the UK, Construction Industry, HMSO, 1994NAO 2001, quoting Bennett and Jades’ Trusting the Team at the Reading
Construction Forum 1998
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONLatham, M. (1994) Constructing the Team, Final Report of theGovernment/Industry Review of Procurement and ContractualArrangements in the UK Construction Industry, HMSO, London
Lavers, A. and Brooker, P. (1997) Contractors Negative Attitudesare hindering the Development of ADR, paper delivered to Arbixclub, Kings College London
Nystrom, L. (2003) Settling Construction Disputes: Virginia Tech
Spectrum March 2
PricewaterhouseCoopers. 2004. Partnering in practice: New
approaches to PPP delivery.
Van Langelaar, (2001) The use of Dispute Board as an ADR onconstruction projects in Southern Africa. Unpublished MScDissertation, University of Cape Town
9.3 Reports
Civil Procedure Rules – Woolf Reforms
CEDR Commercial Mediations: CEDR Statistics, 2007
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONLord Coulsfield report, November, 2005 - The Scottish ConsumerCouncil Justice Advisory Group. – The Civil Justice System inScotland – A Case for Review
Modern Laws for a Modern Scotland- A Report on Civil Justice in
Scotland- February -2009
Modern laws for a modern Scotland: A report on civil justice inScotland, 2007
Official Report on Scottish Parliament Debate on ADR -1 November
2007
Paths to Justice! – Essays Prompted by the Gill Review- Scottish
Legal Action Group 2007
Report of the Scottish Civil Review – October 2009Scottish Civil Courts Review - A Consultation Paper – November2007, and Responses to the Consultation Paper:
TCC Pre Action Protocol (2000) – The Pre –Action Protocol forConstruction and Engineering Disputes
The Civil Justice System Scotland – A case for Review- Finalreport by The Civil Justice System in Scotland – A Case for Review! FinalReports by Scottish Consumer Council Civil Justice Advisory Group– November 2005
Third mediation audit report of November 2007
9.4 Others
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONCourse Note – Dispute Resolution, Glasgow Graduate School of Law,2010
Course Note – Context of Construction Industry, Glasgow GraduateSchool of Law, 2010
Genesis chapter 11 v 1-8 The New International Version of the
Holy Bible
9.5 Websites
www.aci.adr.com
www.brewerconsulting.co.uk
www.cedr.co.uk
www.coremediation.com
www.fernwick-elliot.co.uk
www.leanconstructionjournal.org
www.lib.strath.ac.uk
www.scotscourt.gov.uk/civilcourtsreview
www.scottish.gov.uk
www.scottishlawreports.org.uk
www.scotscourts.gov.uk/civilcourtsreview
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONwww.modernghana.com
www.publications.parliament.co.uk
www.tonybingham.co.uk
www.wlv.ac.uk
9.6 Cases
BT V James Thompson & son Ltd, [1999]
Copthorne Hotel (New Castle) Ltd – v- Arup Associates and Others[1997]CILL1318/2997
58 ConLR 138/1997 85 BLR 22
Cowlin Construction Ltd v CFW Architects [2003] B.L.R. 241
Earl of Malmesbury v Strutt & Paraker, [2008]
Edmund Nuttal Ltd v RG Carter Ltd [2002] EHWC 400 (TCC)
Fastrack Contractors Ltd v Morrison Construction Ltd [2002] B.L.R. 168; 75 Con. L.R. 33
Hasley v Milton Keynes NHS Trust [2004]
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONSusan Dunnet v Railtrack [2002]
Wethered Estate Lt v Michael Davis [2005]
10 Appendices
Appendix 1: (Figure 1)
Parties who have been in dispute with each other over three time periods (provided by the Adjudication Reporting Centre, Glasgow Caledonian University).
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Source: Kennedy, P. and Milligan, J. 2007
Kobina Andoh 200984350
0.0%
10.0%
20.0%
30.0%
40.0%
50.0%
60.0%
70.0%
to Feb 2000 to Oct 2001 to July 2004Parties in dispute
M ain Contractor & Dom esticSub-contractor
Client & M ain Contractor
Client & Nom inated Sub-contractorSub-contractor & Sub sub-contractor
Client & consultant
M ain Contractor & Nom inatedSub-contractor
Consultant & Contractor
Trade Contractor & Em ployer
M anagem ent Contractor &Package Contractor
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
0
Appendix 2 Sources of Construction Disputes in the ScottishConstruction Industry (Figure 2)
Local Authority/Planning4%
Sub Contractor13%Others1%Civil/
Structural Engineer
6%Quantity Surveyor
2%
Client15%
Contractor29%
Extra Contractural
1%
Architect23%
Supplier6%
Sources of Construction Dispute
Source: Langford, Kennedy and Conlin, 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Appendix 3 (Figure 3) The Dispute Pyramid
Litigation
Third Party Alternatives
Lawyers
Success of Claim
Claim Accepted
Compromise
Claim Rejected
Claim
Grievance
Perceived Injurious
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONExperience
All Events /Transaction
Source: Sarat, A. 1985, Gould, N. 2004
Appendix 4 (Figure 4)
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Administrative Managerial/Material/
Workmanship/Quality
Negligence Schedule Performance Payment & Budget0%
5%
10%
15%
20%
25%
30%
35%
40%
28%
34%
3%
14%
5%
16%
Causes of Disputes in the Scottish Construction Industry
Causes of Dispute
Percentages
Source: Langford, Kennedy and Conlin, 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONAppendix 5 (Figure 5)
Payment and Budget Causes of Dispute in the Scottish ConstructionIndustry
Additional Work
Basis of Fees
Non - Return of Retention Money
Extention of Time Cost & Expenses Claimed by
Contractor
Non Payment of balance of interim payment to sub
contractor
Variation Claim by Contractor
0% 5% 10% 15% 20% 25%
5%
10%
4%
6%
14%
5%
8%
5%
14%
9%
20%
Payment & Budget Causes
Payment & Budget Causes
% Causation Agent leading to dispute in the Scottish Construction Industry
Langford, Kennedy and Conlin, 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Appendix 6 (Figure 6)
Breakdown of Quality Issues resulting into disputes in theScottish Construction Industry
0%2%4%6%8%
10%12%14%16%18%20%
4%5%
18%
11%
15%
2%
11%
14%
2%
16%
Quality Issues
Percentage of Quality Issues causing Dispute
Source: Langford, Kennedy and Conlin, 1996
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Appendix 7 (Figure 7)
Administrative Causes of Dispute in the Construction Industry
Extra Contractual third party coordination
15%Sub-contractor non adherence to administrative
procedure8%
Design team's non adherence to administrative
procedure8%
Lack of Working information from
design team2%
Lack of information from design team/client
24%
Contractors non adherence to administrative
procedure25%
Poor feed back from contractors
18%
Administrative Causes
Source: Langford, Kennedy and Conlin, 1996
Kobina Andoh 200984350
The Client(KBA&S Ltd)
‘(Trade Contractor)
(Trade Contractor)
Abeiku Ltd (Trade
Contractor)
Other members of KBAS’s professional team
Ankoben Ltd(Construction Manager)
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Appendix 8 (Figure 8)
Contractual relations in the project
Appendix 9 (Figure 9)
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Solicitors82%
Commercial
Attorney6%
Advocates5%
Solicitors/Advocates4%
QC3%
Trained Mediators Professional Designation
Source: Agapoui and Clark, 2010
Appendix 10 (Figure 10)
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Received Training during
Degree or Diploma
Accredited Mediator
Attended External Training courses
Received Training In- house
No Training0%
5%
10%
15%
20%
25%
30%
Respondents Training in Mediation
Source: Agapoui and Clark 2010
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTION
Appendix 11 (Table 1)
Respondents decision to refuse a proposal for mediation from theopposing party in disputeFactors to consider to refuse a proposal for mediation from the opposing party in dispute
Always Relevant
OftenRelevant
Sometimes Relevant
RarelyRelevant
NeverRelevant
Total0%
Client did not want to use mediation
831%
727%
935%
28%
00%
26100%
Belief in the strength of the clients case
14%
519%
1350%
519%
28%
26100%
Belief that the opposingparty would not take part in good faith
519%
623%
935%
415%
28%
26100%
Case type not appropriate for mediation
312%
831%
935%
415%
28%
26100%
Belief that negotiation was capable of settling the case
28%
623%
1246%
519%
14%
26100%
Belief that recovery of documents was essential before reaching settlement
14%
14%
1039%
1039%
415%
26100%
Source: Agapoui and Clark, 2010
Appendix12 (Table 2) Response of Element of Mediation Process.Element of the mediation process
Always satisfied
Often Satisfied
SometimesSatisfied
Rarely Satisfied
Never Satisfied
Total0%
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONThe speed 10
33.3%1343.3%
723.3%
00%
00%
30100%
The Cost of Mediation 826.6%
1343.3%
620%
310%
00%
30100%
The Mediator 516.6%
1446.6%
1033.3%
13.3%
00%
30100%
Outcome of Mediation 413.3%
1963.3%
723.3%
00%
00%
30100%
Source: Agapoui and Clark, 2010
Appendix 13 (Table 3)Respondents Attitudes to MediationAttitudes Strong
ly Agree
SomewhatAgree
SomewhatAgree
Strongly disagree
Don’tKnow
Total%
If a lawyer participated in mediation his/her status among colleagues would suffer
00%
12%
1122%
3774%
12%
50100%
Mediation is detrimental to the development of law
36%
1938%
1326%
1224%
36%
50100%
Mediation is inappropriate where there is a power imbalance between parties
12%
816%
2754%
1326%
12%
50100%
Judges should refer more cases to mediation
24%
2652%
510%
1224%
510%
50100%
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONMaking a mediation mandatory first step would be a positive development
24%
2040%
714%
1632%
510%
50100%
Legal Practitioners make the best mediators
12%
1632%
2142%
12%
1122%
50100%
Litigation is generally well adaptedto the needs and practices of the construction community
24%
1632%
2346%
918%
00%
50100%
Arbitration is generally well adaptedto the needs and practices of the construction community
12%
816%
2346%
1734%
12%
50100%
Adjudication is generally well adaptedto the needs and practices of the construction community
1224%
3060%
714%
12%
00%
50100%
Default to adjudication in many construction disputes renders mediation obsolete
00%
1734%
1734%
1428%
24%
50100%
Mediation suffers froma lack of coercive power
12%
1224%
2040%
1428%
36%
50100%
Mediation is an opportunity for lawyers to offer further services to their clients
1122%
3366%
24%
24%
24%
50100%
Lawyers will lose money if mediation grows
00%
36%
2346%
1632%
816%
50100%
Suggesting mediation to an opponent is a sign of weakness
00%
12%
2040%
2652%
36%
50100%
Construction contracts 6 25 9 5 5 50
Kobina Andoh 200984350
DISPUTES IN CONSTRUCTION PROJECT PREVENTION, MANAGING,
RESOLUTIONshould contain a mediation clause
12% 50% 18% 10% 10% 100%
A barrier to mediation’s development in Scotland is its negative perception among clients
24%
1734%
1530%
48%
1224%
50100%
A barrier to mediation’s development in Scotland is its negative perception among lawyers
12%
1224%
2652%
510%
612%
50100%
Source: Agapoui and Clark, 2010
Appendix 14
¢2.30 = £1.00GBP Source: Foreign Exchange rate, http://www.Ghanaweb.com/finance/html [01/10/10]
Kobina Andoh 200984350