Upload
independent
View
0
Download
0
Embed Size (px)
Citation preview
Multi-criteria selection of wind farms locations using AHP method
Igor Provči, HEP Croatian transmission system operator company, [email protected]
Prof. Marinko Stojkov, Faculty of Mechanical Engineering, Josip Juraj Strossmayer University of Osijek, Croatia [email protected]
Prof. Damir Šljivac, Faculty of Electrical Engineering, Josip Juraj Strossmayer University of Osijek, Croatia [email protected]
SUMMARY
Production of electricity from wind energy is a technology with the highest annual growth rate of nearly 20 percent compared to other „classic“ technologies used in producing of electricity. The paper presented the possibility of applying multi-criteria analysis in selecting the location of wind farms. Multi-criteria analysis has been made using AHP method (Analytical Hierarchy Process). AHP is one of the methods of multicriteria analysis, and in general is one of the most useful mathematical methods for decision support. The complexity of decision making is reduced to a set of comparison criteria and alternatives, and the synthesis of the final result. Criteria such as wind potential, access to the power system, the impact on the environment, significantly influence on the priorities of the alternatives, and ultimately to the goal, and that is the best location for wind farm. AHP method is implemented in program tool Expert Choice, in versions for individual and group decision making. The Expert Choice (EC) software package wich apply AHP method for decision making is one of the most commonly used program tool. Expert Choice allows structuring of problem in different ways and comparing the alternatives and criteria in pairs in many ways. Additionally, it has ability to conduct sensitivity analysis and visualization based on a simple interactive mode that change the weight of criteria and alternatives. After determining the criteria and definition of alternatives, setting up all the necessary weight sensitivity analysis will be presented in several graphs.
Key words - AHP (Analytical Hierarchy Process), multi-criteria analysis, site selection, wind farms
1. INTRODUCTION
Galloping climate change, dwindling fossil fuel reserves as well as negative effects of
fossil fuels on the environment is reflected in higher prices of fossil fuels. Energy crisis is raising the
question of operation of power systems and security of supply , further more energy growing
needs suggest the necessity of energy conservation measures and the implementation of energy
efficiency. About this a set of EC Directive and policy objectives for renewable energy sources and
energy efficiency are clearly indicates and formulated as "20-20-20 by 2020" (20% share
of renewable energy, 20% reduction in consumption and 20% reduction in CO2 emissions by 2020).
All above has forced many countries, particularly developing countries, to begin
using renewable energy sources. From many renewable energy technology wind energy is the fastest
growing technology . The real expansion of wind power worldwide has resulted, that only in Europe
in last two years has been installed more wind power than any other source of electricity (11).
According to this, production of electricity from wind energy is increasing its capacity by 19 to
20 percent annually, which can be compared with areas that are characterized by strong growth,
such as Internet or mobile communications.
Benefits of electricity production from wind energy are numerous: wind is free source which
ensures energy independence, diversify the production of electricity and reduces dependence on
fossil fuels, wind is not expendable, and there is no harmful gaseous emission and environmental
pollution, opening of new workplaces.
From shortfalls it is necessary to mention the stochastic nature of wind as an energy source,
necessary energy for the secondary control of power system and possible impacts on human and
animal health that careful planning can minimize (quiver, noise, visual effect, threat to birds and
bats). All these issues are solved by selecting wind farm with good location.
Ideal wind farm for commercial exploitation of wind energy would be built on a site with
favorable wind regime, with good road access, close to the electricity networks, with good
capabilities of power evacuation, without conflict with allocation of land and under conditions of
environmental protection. But, ideal locations are rare, and selection of locations is always looking
for a comprehensive multidisciplinary approach with consideration of larger number of relevant
parameters, which includes various kinds of activities and a variety of professions.
The first step in the development of wind farm project is to find appropriate location taking
into consideration many criteria with respect to conditions. Finding a favorable location to build a
wind farm is a long and iterative process that involves many different factors and criteria. Precisely
for this reason we use the AHP method as a multi-criterion method for making a decision.
2. Criteria for selection of wind farm location
In selecting locations for construction of wind farm undoubtedly the most important criteria
is the wind potential of location. Another important criterion is the possibility for connecting wind
farm to the electrical infrastructure which is, as well as wind potential, on most potential locations
unknown, and without systematic analysis is not possible to evaluate their impact on the project.
Therefore, in this paper will be, based on network elements as well as the actual load on the network
but without a detailed calculation, perform evaluation of connection opportunities and power
acceptance from wind farms. In addition to these two criteria there is whole range of environmental
and other criteria for the construction of wind farm. These criteria, we will be reduced to a one
common criteria - the impact on the environment.
Wind farms are usually built in areas for which we found that possess a appropriate wind
potential. These are usually rounded hilltops that are open to air flow from all directions, ridges of
the hill, plateau and open spaces which are usually away from urban areas thinly populated with
poor infrastructure resources. Wind farms usually occupy about 1% of the land on which are found
and their work does not represent an obstacle to perform other activities which is up to construction
of wind farm in a region dominated, such as livestock.
Construction of wind farm is usually precede the measurement of wind parameters which are
indicative indicator of available wind potential and a key factor in deciding the viability of
investments in wind farm. Furthermore, on the basis of the available wind potential at the selected
location is calculate potential production of electrical energy.
2.1 Wind-potential
Winds farms are usually built in areas for which determine that possess an appropriate wind
potential. Wind potential is initially tested in the wind atlas or data from weather stations around the
locations. This method of testing can be used only for orientation while for the proper assessment of
wind potential it is necessary at least one year of wind measurements at the site. One year
measurement covers all four seasons and avoids the effect of seasonality. But this measure is not
enough for the study of wind. It is possible that the year in which it measure is above or below
average year in terms of wind potential. This means that is necessary to put one year data in the
context of several years measurement. It is necessary to make long-term correlation of measurement
data measured for many years (ten or more years) with data from measurement station (usually
weather station) near the location. Such long term correlated data is used for the study of wind and
mapping of the energy potential of sites. Also, this data is used to calculate expected production of
electricity from wind power.
Measurement of wind potential is mostly performed on measuring towers with the
anemometer and signposts of minimum two different heights. According to international
recommendations, the height of measurement tower should be at least two thirds expected hub
height of wind turbine. For example, for wind turbines with a height of 90 feet, measuring tower
should be at least 60 feet tall. Although measurements using measurement tower is still most
common methods for measuring wind potential but there are also newer measurement techniques
that use sound (SODAR) and light (LIDAR) to measure wind potential(4). In general, rule for
measuring wind potential is „more measurement data is better" because it gets a better description
of the actual location. Measurements using different techniques are also recommended, in order to
avoid potential problems as a result of using only one technique.
2.2 Connection to electric power system
For construction wind farms it is necessary to build access roads, adequate transportation
infrastructure, and often new transmission lines to the appropriate connection points to transmission
and distribution system. Communication with the transmission or distribution system operator in the
early stages of the project is very important, so that operator can be inform in advance about the
project, but also to obtain initial feedback on the possible points and the method of connection.
Location of potential wind power should be close to the transmission or distribution network, and
substations. It is necessary to take in account the regulations, concerning the method of connection
(on transmission line or SS), the voltage level of connection (depending on the desired power of the
wind farm), and consult with the transmission or distribution system operator on the possibilities and
conditions for connecting wind farms. Wind farm connection to the grid is a significant problem
considering that wind farms can have a significant impact on system stability and power quality in
the grid. Connection criteria are defined in the form of Wind grid codes.
2.3 Impacts on the environment
While the most of the protected areas are specified in physical plans, it is necessary to additionally
verify the potential negative impacts on the environment at the location. This particularly refers to
protected species of birds (raptors, migratory species) and other animals, plants, protected species,
water protected areas, etc. Also, it is necessary to take into account the nearby villages (noise and
shadowing), roads and infrastructure, protected cultural property and other impacts that
preparation, construction or operation of wind turbines could have on the environment. Most of
these effects are investigated within the formal procedures assessment of the impact on the
environment. But with preliminary examination of locations and consultation with experts, it is
possible prior to making the environmental impact study to determine whether the location in the
area where it is likely that construction will have a significant impact on the environment. The
European Union has a directive related to the current assessment of the impact on the environment
(3), and special rules relating for a Bird Protection (4) and habitat (5).
In Republic of Croatia for a wind power above 20 MW it is obliged to make environmental impact
assessments (EIA) while for the wind power installed capacity greater than 10 MW Ministry of
Environmental Protection, Physical Planning and Construction (MEPPPC) perform evaluation of the
need for environmental impact assessment (Official Gazette No. 67/2009). Within the procedure of
environmental impact assessment, in most cases it is necessary to make the impact assessment for
the National Ecological Network (Official Gazette No. 118/2009).
3. AHP for the selection of Wind farm location
AHP is a popular method used in finding a solution to the problem of multi-criteria decision choice
(MCDM). One of the reasons for the popularity of AHP as an applicable method is the fact that it
takes into consideration not just tangible but also intangible criteria. For instance, determining the
best location for a Wind farm is a problem that involves both many numerical and non-numerical
criteria. Therefore, AHP method seems to be an easily applicable method in finding a solution to the
problem of where exactly to build a Wind farm. AHP approach categorizes a decision problem into
several levels and thus uses a hierarchic structure in order to define this problem. The first and the
most important step to be taken as far as a decision-making process through AHP approach is
concerned is to determine goal, alternatives a criteria with a view to forming a hierarchic structure
regarding the decision-making problem. In this approach, each element existing in the hierarchy is
assumed to be independent of one another (10). The goal that forms the first level of the hierarchic
structure is the goal to solve the problem. The ultimate goal in our case is to determine the most
suitable location for a possible Wind farm based on the other levels of hierarchy. In the second level
of hierarchy are present main criteria. In setting up the, three alternative locations are considered as
probable choices. The layout of these locations is shown in Fig. 1
Figure 1. Layout of the three alternatives locations.
AHP is a process that starts with the establishment of the hierarchy shown in Fig. 2 and ends with the
determination of importance values as to the alternatives by making pairwise comparisons. The
hierarchy model of the decision problem is developed in such a way that the goal is positioned at the
top, with criteria and subcriteria on lower levels and finally alternatives at the bottom of the model.
Figure 2. AHP hierarchy model of the decision structure
Lokacija 3 Lokacija 2
Lokacija 1
Judgement scales
The pair-wise comparisons on each hierarchy structure level should be done by comparing all
possible pairs of the elements of this level, starting with the top of the hierarchy and working this
way to the lowest level. A pair-wise comparison in Expert Choice is the process of comparing the
relative importance, preference or likelihood of two elements with respect to another element (the
goal) in the level above.
Pair-wise comparisons are based on the Saaty scale of relative importance that assumes values
between 1 and 9. Saaty scale is ratio scale which has nine intensity of importance and each of one
corresponds to the value judgments about how many times one criterion is more important than
another. The same scale is also used when comparing two alternatives, but in this case, the scale
values are interpreted as an evaluation of how many times one alternative is more preferred than
another(9).This scale can be applied with ease to criteria that can be defined numerically as well as to
those cannot be defined numerically.
The fundamental Saaty scale (1).
Intensity of
importance
Definition Explanation
1 Equal importance Two activities contribute equally to the objective
2 Weak Between equal and moderate
3 Moderate importance Experience and judgment slightly favor one activity over
another
4 Moderate plus Between moderate and strong
5 Strong importance Experience and judgment strongly favor one activity over
another
6 Strong plus Between strong and very strong
7 Very strong or demonstrated
importance
An activity is favored very strongly over another; its
dominance demonstrated in practice
8 Very, very strong Between very strong and extreme
9 Extreme importance The evidence favoring one activity over another is of the
highest possible order of affirmation
One of AHP’s strengths is the possibility to evaluate quantitative as well as qualitative criteria and
alternatives on the same preference scale of nine levels. These can be numerical (figure 3), verbal
(figure 4) or graphical (figure 5).
Figure 3. Numerical scale
Figure 4. Verbal scale
Figure 5. Graphical scale
Analyses were made through Expert Choice packet programme following the completion of pair-wise
comparisons. The first of analyses is to check the consistency of judgments. In particular, the decision
maker may inadvertently misevaluate comparisons of large-scale decision-making problems.
Therefore, the consistency of matrixes in a pair-wise comparison should be ensured. If the matrix is
inconsistent, reassessment should be made until a consistency is achieved between the judgments
given by the decision maker. Expert Choice programme provides the ratio of inconsistency for each
pair-wise comparison matrix. ‘‘Inconsistency Ratio’’ can also be used in determining whether
pairwise comparisons are consistent with one another. For a pairwise comparison matrix, to be
accepted as consistent, inconsistency ratio should be smaller than 0.10.
Further more, on the basis of the pair-wise comparisons, relative significance (weights) of elements
of the hierarchy structure is calculated. The calculation of relative priorities for each decision making
element through a number of numerical calculations are made. Finally, these results are eventually
synthesised into an overall priority list of alternatives. Decision maker is allowed to change
preferences and to test the results if the inconsistency level is considered high. Results are priorities
of the alternatives in the form of priority list of alternatives and hierarchy tree with objectives’
relative significance. As a result of the analysis conducted using AHP method, „Lokacija 1“ seems to
be the best location for a wind farm as it shown in Figure 6.
Alternative PriorityLokacija 1Lokacija 2Lokacija 3
,521,246,233
Figure 6. Synthesis of the final result
Sensitivity analysis
A decision maker might be very interested to know the consequences of varied weights after he gets
the first results from his model. Some influence could have been underestimated or a slight variation
in one criteria weight could lead to a completely different decision. For that reason, almost all
decision analysis tools come with a sensitivity analysis. Sensitivity analysis is used to determine the
sensitivity of the alternatives to changes in the objectives’ priorities. If the ranking does not change,
the results are said to be robust. The sensitivity analysis is best performed with an interactive
graphical interface. Expert Choice allows different sensitivity analyses, where the main difference is
the various graphical representations (figure 7).
Figure 7. An example of four possible graphical sensitivity analyses in Expert Choice
DISCUSSION:
The European Commission adopted a directive 2009/28/EC which sets of ambitious targets for all EU
member states. According this directive till 2020, 20% of EU energy needs should be met from
renewable energy sources. It is assumed that in 2020. 35% of EU electricity needs will be settle from
renewable energy sources. It is expected that wind energy most contribute to this goal , about 35%
of the total energy produced from renewable sources. In Croatia according to the “Decision on the
minimum share of renewable energy (without large hydro plants) in the structure of the electricity
that Energy Service Company shall supply to the customers” it's suggested the amount of 300 MW of
total installed capacity from renewable sources by year 2010. from which the electricity will be
purchased at fixed rates. We can assume that most will be wind farms with respect to their economic
profitability. If they remain at the proposed amount, this would mean a 6-7% share of wind power in
the total installed capacity of Croatian power plants.
It is expected that the installed capacity of wind power plants in Croatia in 2020. will reach amount of
1200 MW. Since Croatia is on the way to EU, these objectives should be a guideline for future use
planning of wind farms in Croatia.
CONCLUSION:
Wind power is certainly represents an interesting energy source, which should be used in the most
efficient possible way. It is evident that wind farms are profitable technology that could soon become
competitive with other electricity generation technologies.
Making the possible models for decision of the future location of wind power plants based on AHP
method certainly should be taken into consideration.
Expert Choice, the user-friendly supporting software, has certainly largely contributed to the success
of the AHP method. It incorporates intuitive graphical user interfaces, automatic calculation of
priorities and inconsistencies and several ways to process a sensitivity analysis.
REFERENCES:
1.Saaty, T. L. (1980). The Analytic Hierarchy Process. New York, NY: McGraw-Hill.
2.Clemen, R. T. (1996). Making Hard Decisions. Belmont, CA: Wadsworth Publishing Company.
3. European Commission. Council Directive 97/11/EC of 3 March 1997 amending Directive
85/337/EEC on the assessment of the effects of certain public and private projects on the
environment. [Online] 1997. http://ec.europa.eu/environment/eia/full-legal-text/9711.htm.
4. —. The Birds Directive. [Online] 2009. http://ec.europa.eu/environment/nature/legislation/birdsdirective/index_en.htm. 5. —. The Habitats Directive. [Online] 2009http://ec.europa.eu/environment/nature/legislation/habitatsdirective/index_en.htm. 6. Wind Measurements. Courtney, Mike (RISO DTU). Pamplona : EAWE Summer School, 2010.
7. European Wind Energy Association. Economics of Wind Energy. [Online] 2009. http://www.ewea.org/fileadmin/ewea_documents/documents/publications/reports/Economics_of_Wind_Main_Report_FINAL-lr.pdf.
8. Hunjak, T: Višekriterijsko odlučivanje – AHP metoda, Materijali s predavanja na kolegiju
Kvantitativne metode u menadžmentu, FOI Varaždin, 2008/09. godina.
9. T. Hunjak, N. Begičević. How to choose the most suitable form of implementing e – learning?. IIS 2005, Varaždin, Croatia,2005.
10. Karsak EE, Sözer S, Alptekin SE. Product planning in quality function deployment using a combined analytic network process and goal programming approach. Computers and Industrial Engineering 2002.
SOFTVER:
Expert Choice (Demo version) http:// www.expertchoice.com