NASSER P. SALIK, IBsCEngICPEng®IM.ASCE®I Contact Numbers : +639950029996 (Mobile-1) : +639284851575 (Mobile-2) Email Address : [email protected] : [email protected] PROFILE Dedicated and passionate Senior Civil / Structural Engineer with over 25 years of comprehensive large-scale management and engineering experienced in diversified projects, i.e., Oil & Gas, Petrochemical Plant Facilities, Cement Plant Facilities, Airport Facilities, Industrial Buildings, Medium to High-rise Structures Development, Residential Housing Facilities, Corporate Fit-outs, and related Infrastructure projects. Extensive overseas experienced, including the Kingdom Saudi Arabia and State of Kuwait. Strong background in construction development in high standard quality assurance coupled with HSE requirements. Outstanding history of managing projects from initial inception, through development / implementation to completion. Proficient record of bringing mission-critical projects on schedule and within budget constraint. Excellent communication talents with proven ability to work with own initiative and as part of the team to convey complex concepts in understandable terms. Those experienced gained from both on consultancy /client representative roles and contractor’s side had given me an in depth understanding into various domain of construction industry and the implementation of international codes and standards, i.e., ACI 318, ASCE, AISC, ASTM, AASHTO, BSi, CRSI, IBC, & UBC. Saudi Aramco Standards, i.e., SAES, SAEP, SAER, SATIP & SAMSS. Familiar with FEED / Detailing and FIDIC contract interpretation in coordination with the local authority policies in both ways perspectives governing to the general construction practices. EDUCATION Bachelor of Science in Civil Engineering, (BsCEng) Technological Institute of the Philippines ABET (Accreditation Board for Engineering and Technology), globally recognized and certified institution. PROFESSIONAL MEMBERSHIP / AFFILIATION Saudi Council of Engineers ------------------------------------- SCE (www.saudieng.com.sa) Saudi Engineering Group International ---------------------- SEGI (www.segi-sa.com) Kuwait Society of Engineers ------------------------------------ KSE (www.kse.org.kw) Gulf Engineering Council ---------------------------------------- GEC ( www.gulfengineeringcouncil.org) Project Management Institute Arabian Gulf Chapter------ PMI-AGC (www.pmiagc.com.sa) Assn. of the Advancement of Cost Engineering ----------- AACE-AGS (www.aace-ags.org) American Concrete Institute ------------------------------------ ACI (www.concrete.org) American Society of Civil Engineers -------------------------- ASCE (www.asce.org) Philippine Project Managers Association -------------------- PPMA (www.philpma.org) Philippine Safety Practitioners League ----------------------- PSPL (www.pspl-ksa.org) Philippine Institute of Civil Engineers ------------------------- PICE (www.pice.org.ph) Philippine Council of Engineers & Architects --------------- PCEA (www.pcea-ksa.org) Alpha Phi Omega -------------------------------------------------- APO (www.apo.org.ph)

NASSER P. SALIK, IBsCEngICPEng®IM.ASCE®I - SETS Intl

Embed Size (px)

Citation preview

NASSER P. SALIK, IBsCEngICPEng®IM.ASCE®I

Contact Numbers : +639950029996 (Mobile-1)

: +639284851575 (Mobile-2)

Email Address : [email protected]

: [email protected]

PROFILE

Dedicated and passionate Senior Civil / Structural Engineer with over 25 years of comprehensive

large-scale management and engineering experienced in diversified projects, i.e., Oil & Gas,

Petrochemical Plant Facilities, Cement Plant Facilities, Airport Facilities, Industrial Buildings,

Medium to High-rise Structures Development, Residential Housing Facilities, Corporate Fit-outs,

and related Infrastructure projects. Extensive overseas experienced, including the Kingdom Saudi

Arabia and State of Kuwait. Strong background in construction development in high standard

quality assurance coupled with HSE requirements. Outstanding history of managing projects from

initial inception, through development / implementation to completion. Proficient record of bringing

mission-critical projects on schedule and within budget constraint. Excellent communication talents

with proven ability to work with own initiative and as part of the team to convey complex concepts

in understandable terms. Those experienced gained from both on consultancy /client

representative roles and contractor’s side had given me an in depth understanding into various

domain of construction industry and the implementation of international codes and standards, i.e.,

ACI 318, ASCE, AISC, ASTM, AASHTO, BSi, CRSI, IBC, & UBC. Saudi Aramco Standards, i.e.,

SAES, SAEP, SAER, SATIP & SAMSS. Familiar with FEED / Detailing and FIDIC contract

interpretation in coordination with the local authority policies in both ways perspectives governing

to the general construction practices.

EDUCATION

Bachelor of Science in Civil Engineering, (BsCEng) – Technological Institute of the Philippines ABET (Accreditation Board for Engineering and Technology), globally recognized and certified institution.

PROFESSIONAL MEMBERSHIP / AFFILIATION Saudi Council of Engineers ------------------------------------- SCE (www.saudieng.com.sa) Saudi Engineering Group International ---------------------- SEGI (www.segi-sa.com) Kuwait Society of Engineers ------------------------------------ KSE (www.kse.org.kw) Gulf Engineering Council ---------------------------------------- GEC ( www.gulfengineeringcouncil.org) Project Management Institute Arabian Gulf Chapter------ PMI-AGC (www.pmiagc.com.sa) Assn. of the Advancement of Cost Engineering ----------- AACE-AGS (www.aace-ags.org) American Concrete Institute ------------------------------------ ACI (www.concrete.org) American Society of Civil Engineers -------------------------- ASCE (www.asce.org) Philippine Project Managers Association -------------------- PPMA (www.philpma.org) Philippine Safety Practitioners League ----------------------- PSPL (www.pspl-ksa.org) Philippine Institute of Civil Engineers ------------------------- PICE (www.pice.org.ph) Philippine Council of Engineers & Architects --------------- PCEA (www.pcea-ksa.org) Alpha Phi Omega -------------------------------------------------- APO (www.apo.org.ph)

CV of Engr. Nasser Salik 2 of 12

CAREER PROGRESSION

FLOUR DANIEL, INC. (PHILIPPINES) – EPCM Contract Asian Building, 2402-2404 Asian Drive, Filinvest Corporate City, Alabang, Muntinlupa City, Philippines 1781 Site Manager September 18, 2020 – October 31, 2021

Project Highlights: Flour is providing engineering, procurement and Construction Management (EPCM) supports for Petron Bataan Refinery Expansion in response to increasing demand for refined petroleum products. Work scope includes civil & structural works, new boundary fencing, new pipe bridge and pipe racks, catch basin & sumps, pump station, cooling tower basin, and mechanical, electrical, instrumentation structural supports, and among other relevant facilities.

Duties and Responsibilities: ➢ Execute and monitor field construction activities in conformance with IFC drawings, specifications, schedules, method statements & procedures, quality requirements, and safety regulations.

➢ Control approved construction schedule and cost through the efficient use of all construction resources, including materials, manpower, tools, and equipment.

➢ Monitor productivity and implements appropriate action to maintain maximum labor productivity, and cost effectiveness.

➢ Active in the development of safety culture in the project, and adopt safety a natural part of all activities performed. ➢ Keep informed the client and stakeholders of current trend, site issues, and progress schedule update.

➢ Proactively identify construction constraint and carry out necessary measures to prevent schedule delay. ➢ Preside weekly progress meeting, quality meeting, safety meeting in order to assess work performance, trends,

and other relevant issues onsite.

JGC JV TECNIMONT CONSORTIUM – EPC Contract Madrigal Business Park Prime Street, Ayala Alabang, Muntinlupa City, Philippines 1780 Project Construction Manager July 20, 2019 – August 31, 2020

Project Highlights:

JGC Philippines Incorporated in JV with Tecnimont Philippines awarded an EPC Lump Sum contract by JG Summit Petrochemical Corporation (JGSPC), for the implementation of a new High Density Polyethylene unit (HDPE) and the upgrading of an existing Polypropylene unit (PP). Once the project is completed, the new HDPE plant will have a capacity of 250,000 tons per year of HDPE based on Chevron Phillips Chemical’s MarTECH™ technology, while the existing PP plant will expand to 300,000 tons per year of PP based on Grace’s UNIPOL® PP technology. JG Summit Holdings Group, is the largest manufacturer of polyolefins in the Philippines.

Duties and Responsibilities: ➢ Prepare schedule of activities in logical steps and budget time required to meet deadlines.

➢ Consolidate, review, analyzes and monitors work methodology, project budget and contract management.

➢ Regular checking and inspection of works in progress with reference to the required availability of logistics, quality of workmanships, and completion parameters.

➢ Reports to the higher management of pertinent issues, instructions order or policies requires to implement and updates on construction progress schedule.

➢ Obtain all necessary permits and licenses and supervise on-site construction execution.

➢ Review and coordinates with the designers / consultants for site work clarification issues.

➢ Validates compliance to contract specifications / budget as stipulated in the contract agreement.

➢ Enforce safety measures and company regulations, obtain required permits, and other relevant documents.

➢ Proactive to deal with the results of work delays, bad weather, or emergencies at construction site.

➢ Attend regular weekly progress meeting with the client representative, stakeholders, and designated members of the construction team.

CV of Engr. Nasser Salik 3 of 12

AECOM (PHILIPPINES) – PMC Contract 14th Floor Bonifacio Stopover Corporate Centre, 2nd Avenue corner 31st Street, Bonifacio Global City, Taguig City, Philippines Civil Section Construction Manager May 21, 2018 – June 30, 2019

Project Highlights: Upgrading the capacity of republic cement plants to 10 million tons per day. The cost of the first phase is part of the USD300 million capacity expansion program over the next five years both in the provinces of Bulacan, Tanay, Batangas & Iligan.

Duties and Responsibilities: ➢ Monitor site progress and project cost through on-site observation and maintenance of daily records of site activities

to ensure project is constructed in accordance with the design, budget and milestone schedule.

➢ Develop schedules for reaching objectives and make sure activities comply with accordingly.

➢ Established & evaluate deviations to contract technical specifications & regulatory requirements to ensure that such deviation shall be process in accordance with project’s procedure & properly documented.

➢ Enforce safety measures and company regulations and obtain required permits and other relevant documents.

➢ Authorize / approve project personnel transactions, purchase requisitions, change requests in considering the relative costs and potential actions to choose the most appropriate one.

➢ Regular present on site to ensure that work is carried out safely and efficiently (take time off in lieu to compensate for unsocial hours).

➢ Keep client and project director of current trend on site issues that may potentially affect the project milestone schedule.

➢ Monitor schedule of daily activities including manpower, equipment and materials availability onsite.

➢ Ensure that quantities of completed work items are agreed with the concerned prime Contractor.

➢ Identify construction constraints and carry out measures to prevent construction schedule delay.

➢ Provide routine daily, monthly reports and/or special reports required by the company procedures, operating mgt.

➢ Update and inform the client, project director, design consultants of the status of deliverables, milestone schedule and among others issues concern.

➢ Attend in weekly progress meeting in order to assess work performance, schedule update, trends and other relevant issues.

CH2M Hill – (EPCM Contract) PO Box 8772 – Riyadh 11492, Saudi Arabia Senior Project Engineer November 12, 2016 – March 08, 2018

Project Highlights: Saudi ARAMCO awarded CH2M the execution of two turnkey contracts for the Fadhili Gas Plant. CH2M scope covers EPCM of Package 1 Fadhili Gas Inlet & Treatment Facilities and Package 02 – Fadhili Process Utilities & Interconnecting Systems. The Fadhili Gas Plant (FGP) consist of five processing trains. Four of these trains will process Hasbah offshore gas, consisting of inlet gas handling, gas sweetening, dehydration, and one train will process Khursaniyah onshore gas, consisting of inlet gas handling, and gas sweetening to produce fuel for the cogeneration facilities.

Duties and Responsibilities: ➢ Provide technical knowledge and recommendations in resolving any unforeseen conflicts in the plan and specification.

➢ Participate in inter-discipline planning and simultaneous operation (SIMOPS).

➢ Ensure all staff and workers have attended safety induction prior to mobilization onsite.

➢ Identify construction constraints and carry out measures to prevent construction schedule delay.

➢ Prepare project safety plan including HIP (hazard identification plan), risk analysis and risk mitigation for approval of Dhahran Safety Department and Loss Prevention Department.

➢ Monitor schedule of daily activities including manpower, equipment and materials availability onsite.

➢ Oversee excavation and backfilling of underground pipelines, power cables and related utilities.

➢ Supervise the construction/erection of structural steel shelters and above ground pipe racks.

➢ Monitor the fabrication and installation of pipe sleepers and various types of pipe supports.

➢ Supervise the construction of facilities i.e. offices, industrial building paving of process areas and roads.

CV of Engr. Nasser Salik 4 of 12

➢ Ensure availability of resources and materials at all times and compliance to project specifications.

➢ Participate in weekly progress meeting in order to assess work performance, schedule update, trends and other technical / site relevant issues.

BRUCE SHAW INTERNATIONAL LIMITED Engineering and Project Management (E&PM) PO Box 6326, Jeddah-21442 Kingdom of Saudi Arabia Lead Project Engineer March 05, 2015 – October 31, 2016

Project Highlights: The new expansion of King Abdul Aziz International Airport (KAIA) in Jeddah, Saudi Arabia will increase the airport’s annual capacity to 30 million passengers in the first phase and 80 million in the final phase. The 27 billion Saudi riyals (USD7, 200,000,000) project is designed to make KAIA one of the largest hubs in the world. The airport will have two new terminals for both domestic and international passengers respectively. Apart from the construction of two terminals, the project includes passenger lounges, a new concourse building with 25 additional passenger bridges and connector buildings linking the terminals, Air Bridges and Movable Gates. Extension and overall renovation of the existing South Terminal, Apron and Taxiway modifications and extensions, Electro / Mechanical System, and Car Park.

Duties and Responsibilities:

➢ Develop project objectives by reviewing project proposals and plans, and conferring them to the higher management.

➢ Conducted pre-mobilization meetings with approved contactor/s to validate contract terms and conditions, workforce composition, materials specifications, equipment, and HSE regulations.

➢ Manage project budget and review change orders, monthly payment to contractor/s per actual progress measurements.

➢ Review design drawings with field verification to ensure contractor is meeting design requirements.

➢ Review of proposals and deliverables, construction milestone schedule, shop drawings, project quality plan (PQP), method statements and HSE requirements.

➢ Directed and monitored progress during project execution to ensure project deliverables conform to design specifications and quality standards.

➢ Monitoring of accurate project’s implementation and to ensure compliance with the IFC drawings, specification and relevant contract documents.

➢ Monitor EPC contractor’s manpower, materials and equipment resources to ensure availability on site and effectively utilized in accordance to the contract requirements.

➢ Establish & monitor Key Performance Indicators (KPI) to measures quality performance in different areas of work development and various project phases.

➢ Maintain logs & records of site activities, prepare progress highlights report in daily, weekly and monthly basis.

➢ Attend weekly progress meetings held onsite as required to assess work progress, resolved pending issues and deliverables.

YANBU ARAMCO SINOPEC REFINING COMPANY (YASREF) Yanbu Export Refinery Project Solids Handling and Hydrogen Generation Division Yanbu Industrial City, Saudi Arabia Lead Project Engineer May 31, 2013 – December 31, 2014

Project Highlights: Yanbu Aramco Sinopec Refining Company (YASREF) is a large and complex joint venture project between Saudi

Aramco & SINOPEC of China, designed to utilize the world class full conversion of a new “grassroots” refinery using

400,000 barrels per day (bpd) of Arabian Heavy crude oil to ultra clean transportation fuels for international and

domestic markets. In addition of high-value refined products of 90,000 (bpd) gasoline, 263,000 bpd of ultra-low-sulfur

diesel, 6,300 metric tons per day (mtd) of coke and 1,200 mtd of sulfur located mainly at Yanbu red sea cost.

Duties and Responsibilities: ➢ Worked with Project Management Team to support and accelerate the construction phase project in supervising

and monitoring of EPC contractor/s daily work performance.

CV of Engr. Nasser Salik 5 of 12

➢ Review of EPC contractor’s submittals i.e. Shop Drawings, Materials Approval Request (MAR), Red lines / As-Built Drawings, Method Statements, Material Samples including Inspection Test Plan (ITP) to ensure in compliance with the design drawings, specifications and project quality mgt. & Information system (PQMIS).

➢ Oversee the construction of Transport Conveyor Structures (7.3km), Jetty (31m x 300m), Ship Loader Structures, Mechanical / E&I’s Support Structures, Sulfur Storage Building (1,200 mtd storage capacity), Coke Storage Building,

(6,300 mtd storage capacity), Operation & Maintenance Building, Substation /Transformer Building, Pelletizer Building, RMCC’s Pad Foundations, Skid Mounted Rotating Equipment’s Foundation, Security & Supports Building, A/G & U/G Piping Support Structures.

➢ Familiarity with pipeline construction i.e. trenching, bedding, shoring/supports, benching/sloping, pipe stringing, pipe laying, testing and lateral tie-ins to existing facility lines interfaced.

➢ Good knowledge with Permit to Work system (PTW – Hot & Cold Works), Job Safety Analysis (JSA).

➢ Prepare project status reports by collecting, analyzing, summarizing information trends accordingly.

➢ Assessed EPC contractor’s request for information (RFI’s) and recommend corrective resolution.

➢ Ensure the construction interfaces scoping activities with interconnecting packages were managed efficiently, facilitating the prompt resolution of any technical queries onsite.

➢ Work interfaced among other trade disciplines of various teams and departments on issues relevant to the work packages.

➢ Proactively, identify & bring to the attention of senior project engineer of any potential problems which could trigger the delay & cost deviations and have adverse effect on baseline schedule.

➢ Maintain logs & records of site activities, prepare progress highlights report in daily, weekly and monthly basis.

➢ Establish & monitor Key Performance Indicators (KPI) to measures quality performance in different areas of work development and various project phases.

➢ Monitor EPC contractor’s manpower, materials and equipment resources to ensure availability on site and effectively utilized in accordance to the contract requirements.

➢ Participate in weekly Progress Meeting, QA/QC meeting, Safety Meeting and Coordination / Interface Meeting.

➢ Manage MCC walkthroughs throughout the project prior to pre-commissioning schedule and handover processes.

SAUDI ARAMCO NGL PROGRAM SNGLPD / EW&ID RIC Expansion Project Sabkha-113, Rub Al Khali, Shaybah, Saudi Arabia Senior Civil Engineer April 15, 2011 – May 18, 2013

Project Highlights: The project scope encompasses of Saudi Aramco’s mega project @ Shaybah NGL Recovery Program located in the remote desert area of Rub Al Khali, (SHAYBAH) 800km from Dhahran Saudi Arabia. Major works include the construction of NGL Recovery Facilities (BI-10-00167), NGL Pipeline (BI-10-00168), Increase Gas Handling Capacity (BI-10-00905), Residential Industrial Complex (RIC) Expansion Project (BI-10-00774) and Site Preparation for NGL Recovery Facilities (BI-10-0076). Residential Facilities expansion composed of Three New Residential Buildings (11,664m2). Construction of utility facilities i.e. New Substation Building (576m2), New Room for 13.8kV, 3,000KW Emergency Generator (100m2), New Pump house / Chiller Yard (400m2) and expansion of the existing Sewage Treatment Plant (STP) system along with upgrade of conventional aeration system to MBR technology. Expansion of existing Potable / Fire Water System Network (New Fire / Potable Water Tank & 10km. U/G RTR Pipeline.

Duties and Responsibilities: ➢ Worked with Saudi Aramco in assisting the project’s management team for work packages execution phases.

➢ Perform proactively by conducting field surveillance works, observing and analyzing the contractor’s work

progress, material handling / storage and preservations to ensure all works are compliance with project’s specifications, quality requirements and effective implementation of Quality Mgt. Information System (QMIS).

➢ Manage the construction site activities that will deliver the project in accordance with the agreed define target milestone schedule, safety, quality and follow up procurement issues to avoid any delays to the project.

➢ Review contractor’s submittals, i.e. shop drawings, materials samples, work method statements and respond totechnical site queries (TSQ) for both civil, structural and architectural discipline.

➢ Review and process contractor’s change orders (C.O.), contractor’s daily activities report and Saudization reports

for Saudi employees.

➢ Establish & monitor Key Performance Indicators (KPI) to measure quality performance in different areas of work development and various project phases.

Attend to the mandatory Saudi Aramco sponsored self-development e-learning courses.

CV of Engr. Nasser Salik 6 of 12

➢ Monitor contractor’s manpower, materials and equipment resources to ensure availability on site and effectively

utilized in accordance to the contract requirements.

➢ Oversee the ongoing activities based on the applicable Saudi Aramco prevailing standards, i.e. Saudi Aramco

Engineering Standard (SAES), Saudi Aramco Engineering Procedures (SAEP), Saudi Aramco Materials System Specification (SAMSS), Saudi Aramco Testing & Inspection Plan (SATIP), IFC drawings and other relevant standards.

➢ Prepare weekly report highlights, i.e. work percentage accomplishments, progress photos, proactive notifications,

focus assessment, and lessons learned.

➢ Attend to the weekly progress meeting, quality meeting, safety meeting and communication meeting.

➢ Utilize quality management information system (QMIS), an e-log SAP module to verify RFI’s, record inspection

findings and test results, in compliance with Saudi Aramco requirements

➢ Oversee the construction of perimeter fencing / gates, installation of CCTV cameras in all perimeters and access points to be monitored 24/7 by CCTV. These cameras have Pan/Tilt/Zoom (PTZ) capabilities, and are strategically placed throughout the projects.

➢ Monitored the installation of exterior lighting strategically placed throughout the utility / facilities area to highlights the perimeters, gate and guard post access points, entry points into buildings, and areas of interest.

➢ Installation of Electronic Access Control System (EACS), which has been installed throughout the projects and facilities.

➢ Installation of Intrusion alarms serve two important functions; to provide 24/7 monitoring in remote locations where staff is not always present and in all CIP-designated spaces. These Intrusion alarm systems are monitored 24/7.

➢ Review the EPC Contractors progress and productivity measurement reports and advising the senior project engineer on trends or occurrences that might potentially on negative impact.

KUWAIT OIL COMPANY (K.S.C.) PO Box 9758, Ahmadi 61008 State of Kuwait Senior Project Engineer October 22, 2009 – March 18, 2011 Senior Project Engineer

Project Highlights: Facilities upgrade and flowlines replacement project estimated $848 million, 30-month engineering, procurement and construction (EPC) contract. Scope of work covers the replacement of existing underground crude oil and gas flowlines in the south and southeast and the rehabilitation of 17 gathering centers (GCs) and three gas booster stations. Expansion of gathering center were due in by the revised deadline for the EPC contract to revamp and expand by 40,000 barrels a day (b/d).

Duties and Responsibilities: ➢ Monitor and manage project schedule, and utilize CPM schedule as a tool in project implementation. ➢ Obtain all necessary permits and licenses and supervise on-site construction execution. ➢ Led the supervision and control of contractor/s in accordance with the approved construction documents. ➢ Oversee all aspects of job layout, surveying, concrete piling works for foundation of Tanks, Culverts/Bridges, Pipe Racks,

Buildings / Substations, Vessels, and among other equipment. ➢ Review and commented job hazard analysis (JSA), work method statement, and other related documents. ➢ Share knowledge in construction methodology to guide / assist contractor/s during construction execution phase. ➢ Familiarity with pipeline construction i.e. trenching, bedding, shoring/supports, benching/sloping, pipe stringing, pipe

laying, testing and lateral tie-ins to existing facility lines interfaced. ➢ Regular coordination and communication with the concerned parties, and other team members regarding the update

status of the project. ➢ Assist in the interface issues in construction activities, and participate in the discussion of field engineering, quality, and

safety. ➢ Review the Contractor/s progress and productivity measurement reports and advising the project manager on trend or

occurrences that might potentially on negative impact. ➢ Close monitoring of site construction activities, and ensure personnel compliance with all safety regulations and guidelines. ➢ Prepare and submit daily report, and contribute to monthly progress report to the Project Manager. ➢ Monitor contractor’s manpower, materials and equipment resources to ensure available on site in compliance

with the contract requirements. ➢ Participate to the weekly progress meeting, quality meeting, safety meeting and communication meeting.

KEO INTERNATIONAL CONSULTANTS PO Box3679, Safat – 13037 State of Kuwait (PM/CM Division) Resident Engineer September 05, 2006 – September 11, 2009

CV of Engr. Nasser Salik 7 of 12

Projects Highlights:

AL BABTAIN Mixed-use Tower Complex

The development & construction of multi-storey mixed-use tower consists of forty (46) six floors, five (5)

level podium complex and basement levels (B3) Car Park of four hundred fifty (450) cars capacity.

Project located @ Jaber Al Mubarak street opposite side of Amiri Hospital in Al Sharq District, Kuwait.

City. The project’s original budgetary cost of KD28,420,000.00) equivalent to USD98,000,000.

SAIFC – Marketing Suite Building (Phase-1) project composed of Pre-Engineered Structures, Sandwich Composite Panels, Aluminum Glazed Curtain Wall & Spider System with the total built-up area of 6,000 sq.m. The project located in Kuwait City proper particularly at Sharq adjacent to Kuwait’s Courtyard Marriot. The said project completed within six months from March to Sept. 2008 on lump sum contract of KD171, 000.00 (Kuwaiti Dinars One Hundred Seventy One Thousand Only) equivalent to USD589,950.00.

THE SULTAN CENTER COMMERCIAL COMPLEX Four (4) storey commercial complex having 16,803 sq.m. footage area design for Retail Shops, Supermarket, Electronics Stations and Sports Facilities. The project’s lump sum contract value of Kuwaiti Dinars Six Million Eight Hundred Thousand (KD6,800,000.00) equivalent to USD23,460,000.00.

Duties and Responsibilities: ➢ Review and update technical standards, construction techniques, and use of proper materials to ensure that

specifications and schemes prepared by the division reflect best practices with continuous improvement.

➢ Provide a high level of technical sufficiency within the team , including the identification and promotion of innovative and practical design solutions.

➢ Assist the construction manager in dealing with the team relevant to civil/structural inspections assessments, implement of contract documents and effective site supervision.

➢ Represent and action matters in the absence of the Construction Manager as required including the dealing of resources and monitoring cost in achieving target objectives.

➢ Perform pre-pour inspection and post-concrete surveillance to ensure all construction requirements in particular to “hot-weather concreting” are being followed on site.

➢ Provide professional advice to the team in the event of emergency incidents affecting the structural integrity of the

structures, which may involve working outside normal hours.

➢ Administering and prompt exchange of correspondence, inform the construction manager on matters related to valuation / variations on bill of quantities (BOQ), payments, liability and claim submittals.

➢ Review the contractor’s quality plan and have comments / recommendations as if necessary, including regular checking of health, safety & environment (HSE) requirements on site.

➢ Review main contractor’s monthly payment certificates based on work progress achievements and advice the construction manager accordingly.

ILF CONSULTING ENGINEERS PO Box 132548, Jeddah – 21382, KSA

Senior Project Engineer August 27, 2004 – September 01, 2006

Project Highlights: Construction of a Sanitary Sewer Mainlines System in Jeddah, Saudi Arabia. The said project was executed by way of both the conventional open trench method, tunneling and micro-tunneling. Overall length of pipeline designed as 250 kilometers composed of (Vitrified Clay Pipe (VCP) ranging from Ǿ400mm - Ǿ600mm and Glass Fiber Reinforced Plastic Pipe (GFRPP) ranging from Ǿ700mm – Ǿ2, 500mm respectively. Sewage Treatment Plant included in the contract with the design capacity of150,000 m3.

Duties and Responsibilities: ➢ Develop, implement and administer project engineering procedures, work controlling of technical documents and

standard quality of workmanship.

➢ Established communication with key representatives of the main contractor & eleven (11) nominated subcontractors

to ensure smooth coordination of respective site activities.

➢ Interpret correctly the contract documents, specifications and the client’s requirements in association with the head

office in order to ensure the client and the contractor have the same understanding of the terms and conditions.

CV of Engr. Nasser Salik 8 of 12

➢ Ensure with the team that workmanship, materials and equipment used onsite have been approved, and all test

reports have been reviewed and approved.

➢ Review/check shop drawings, method statement, material samples, and other relevant document submittals.

➢ Respond to contractor/s raised technical site queries (TSQ) of site related issues and recommend for resolution.

➢ Strictly enforced all provisions of the contract documents from conventional excavation, thrust boring, micro-

tunneling, pipe laying, testing, backfilling until reinstatement of disturbed road surfaces.

➢ Monitor contractor’s work progress relative to the construction baseline schedule and advice the project manager

of any issues or potential delays to the project’s milestone schedule.

➢ Establish & monitor Key Performance Indicators (KPI) to measures quality performance in different areas of work

development and various project phases.

➢ Monitor contractor’s manpower, materials and equipment resources to ensure availability on site and effectively

utilized in accordance to the contract requirements.

➢ Manage MCC walkthroughs throughout the project as per Project Pre-Commissioning Schedule and follow up EIL/MCC consolidation, closure and handover processes.

➢ Dealing with Project Close-Out activities including the Post-MCC items and final assets handover.

FLOUR ARABIA COMPANY LIMITED Engineering, Procurement and Construction Management (EPCM) PO Box 3381, Al Khobar – 31952, Saudi Arabia

Project Engineer January 10, 2002 – August 20, 2004

Project Highlights: Saudi Kayan Petrochemical Complex Project Facilities – Port / Berth/ Jetty Area, Saudi Arabia

Duties and Responsibilities: ➢ Controlling and directing contractor/s on schedule, quality, resources and productivity to ensure adherence with the

contract.

➢ Review and approval of project document such as; Inspection & Test Plan (ITP), Project Procedure, Request for Information, Accomplishment Report, Study, Testing, Materials, Shop drawings, and Change Orders.

➢ Respond with appropriate and necessary levels of construction supervision to provide quality assurance in accordance with contract documents.

➢ Coordinate the interface of the construction work with another contractor/s onboard at site. verify that contractor is following his approved drawings, quality assurance, and Health & Safety plan.

➢ Review the contractor's progress at all times. Monitor the material incorporated in the work, the materials stored at the site, and the contractor's manpower and equipment.

➢ Review, anticipate and resolve problem, bottleneck, conflict and any constraints that may affect target completion, delivery of the project and to keep the project on schedule.

➢ Preparation of various project report documents and correspondence, and implement and manage of overall safety at site.

➢ Establish & monitor Key Performance Indicators (KPI) to measures quality performance in different areas of

work development and various project phases.

➢ Coordination with contractor's supervisory personnel regarding schedule, sequence, and method of work.

➢ Strictly enforced all provisions of the contract documents dealing with work method statements, specifications, applicable standard code of practices and high quality of workmanships.

➢ Review contractor’s interim payment requests prior to issuance of payment certificates based on work percentage accomplishments.

➢ Interpret correctly the contract documents, specifications and the client’s requirements in association with the

head office to ensure the client and the contractor have the same understanding of the terms and conditions.

➢ Attend various meetings and contribute technical inputs and contractual actions, identify constraints and recommend corrective measures.

ZUHAIR FAYEZ PARTNERSHIP CONSULTANTS PO Box 9486, Riyadh – 11413, K.S.A. Senior Project Engineer February 16, 1992 – October 31, 2001

Project Highlights: (1) Saudi Officers and Internal Forces Sports Club in Riyadh, Saudi Arabia. Original Contract Value

of SAR267,315,150.00 – (USD70,905,875.00).

CV of Engr. Nasser Salik 9 of 12

(2) Twin Tower (16th floors) of Saudi Basic Industries Corporation (SABIC) Central Headquarters in Riyadh, Saudi Arabia. Original Contract Value of SAR735,475,000.00 – (USD195,086,207.00)

(3) Seven (7th) Floors Saudi Basic Industries Corporation (SABIC) Eastern Province Headquarter Offices in Al Jubail, Saudi Arabia. Contract Value of SAR294,537,877.60 (USD78,126,758.00).

(4) RSAF project in association with WS Atkins Associates in the construction of a New Airbase Facilities (ABF) Project for the Royale Saudi Air force (RSAF), in Al-Jouf Sakaka, northern frontier of Saudi Arabia. The project’s scheme composed of four Aircraft Fighter Jets Shelters, four Ammunition Building, Energy & Control Building, Explosives Preparation and Inspection Building, Fault Signaling Building, Command / Fire and Rescue Building, Station & Aircraft Ground Equipment Building, Runway Supervisory Building, Water Storage & Supply Building, Aircraft Refueling Apron, Last Chance Apron, Washing Apron, Sewage Treatment Plant, External Utilities, Taxi tract and Service Roads Network. 1. Fencing & Gates, 2. Exterior Lighting System, 3. CCTV Cameras [Pan/Tilt/Zoom (PTZ) capabilities], 4. Electronic Access Control System (EACS), 5. Intrusion alarms and among others.

(5) Saudi Aramco’s General Engineering Services (GES) Design Contract as follows; A. Housing Community in Abqaiq for land used master planning. B. Residential Community Support Buildings in Hawtah Oil field Development Project, (BI-8174). C. Furniture Storage Building (LIP), Udailiyah, (EWO-58994). D. Travelling Crane Support Structures, Utmaniyah, (EWO-58926).

E. Health Care Building converted into Dental Clinic Facilities, Ras Tanura, (BI-3314). F. Materials Storage Yard and Fencing Facilities, Dhahran, (ER-3298).

Duties and Responsibilities: ➢ Review / checked documents submittals and recommend approval i.e. shop drawings, materials samples and test

records, equipment machines and calibration records, method statements and among others.

➢ Coordinate all engineering details aspects with other discipline and keep aware of interface in services.

➢ Review & check contractor’s project quality plan (PQP) and inspection test plan ( ITP) including performing witness

point and hold point inspections of construction and installation activities.

➢ Strictly enforced all provision of the contract documents and specifications.

➢ Regularly conducted site visit to make sure that ongoing activities were properly coordinated in accordance with approved shop drawings and related contract documents.

➢ Respond to contractor’s raised technical site queries (TSQ’s) regarding site related issues and recommend appropriate resolution.

➢ Review and check contractor's monthly invoices prior to the issuance of payment certificate.

➢ Oversee the maintenance record of site activities, number of contractor’s personnel on site, equipment utilization, difficulties encountered on site and violation of safety rules and regulations.

➢ Attend weekly progress meetings with both the presence of client representative and the concerned contractor/s in order to discuss progress of work, potential project’s difficulties, identify apparent lapses in the schedule and recommend necessary resolutions.

➢ Involved in the evaluation and design conceptualization of Saudi Aramco’s General Engineering Services (GES) contract packages on above mentioned respective projects, (A to F).

➢ Review contractor’s interim payment requests prior to issuance of payment certificates based on work percentage accomplishments.

ABV ROCK GROUP (General Contractor) (Civil & Infrastructure Division) PO Box 89426, Riyadh – 11682, K.S.A. Senior Civil Engineer February 10,1990 – January 08,1992

Project Highlights: Asphalt pavement construction of four (4) lanes 50.00 Km length of road which includes pavement structures, earthworks, one(1) Interchange, five (5) wadi bridges, ten (10) box culverts, twenty five (25) RCPC, slope protection works, new jersey barriers (single & double face), pavement markings and traffic road signs.

Duties and Responsibilities: ➢ Review project plan, construction schedule, material resources, equipment and workforce prior to implement

onsite.

CV of Engr. Nasser Salik 10 of 12

➢ Handled full responsibility of weekly and monthly reports, monthly interim payment certificates submission.

➢ Develop, plan, organize, carry out pavement evaluations and investigations, geotechnical reports evaluation for roadway / infrastructure projects.

Performed road alignment design analysis with respect to geometric aspects.

➢ Led the team in the control supervision of the project in accordance with the approved construction documents, ministry of communication (MOC) standards, drawings and specifications.

➢ Checked as-staked survey plans, profiles, cross sections, drainage structural drawings.

➢ Carried out investigation of materials within the project alignment and took samples for laboratory test.

➢ Checked and approves all materials test results and approved proposed alternative based on contract specifications and relevant standards.

➢ Attend weekly progress meetings with both the presence of client representative, consultants and the contactor/s.

MOHAMMAD BINLADIN ORGANIZATION (General Contracting Company) (Special Building Division) PO Box 11789, Jeddah-21463, KSA Site Civil Project Engineer October 17, 1987 – December 23, 1989

Project Highlights:

Construction of eighty-six (86 Units) multi-palatial complexes including main palace for H.R.H King Fahad Bin Abdul Aziz at Mina, Holy City of Makkah. Also in the contract, the construction of Heliport, Mosques and Service Roads Network. Contract lump-sum value of 1.5 Billion Saudi Riyals (US$397,877,984.00).

Duties and Responsibilities: ➢ Implement approved construction drawings and specifications, prepared method statements and supervised

projects’ execution.

➢ Set out detailed works as per contract drawings, establish the level and control points and ensure carried out on a regular basis. Resolve any unexpected technical difficulties and other problems that may arise at any time.

➢ Review and monitor milestone schedule against actual work progress.

➢ to address slippage in schedule and report/update status to the construction manager.

➢ Preparation of estimates, material submittals and take-offs, complete preparation of quantity statements, purchase orders, procurement of materials and self-checking of all required site material deliverables.

➢ Issued work time table requirements with subordinates to ensure project’s momentum.

➢ Supervised day to day work directions as required for the implementation of new or existing facilities i.e. Civil, Structural RCC works, all kinds of architectural finishing works, asphalt and concrete road pavements.

➢ Met frequently with other members of trade disciplines to make sure that all activities at site were properly coordinated. Produce two (2) weeks look ahead schedule, site diaries and allocation sheets.

➢ Attend progress and coordination meetings including participation in technical/special meetings as necessary in the nature course of the events of site relevant issues.

➢ Review and analyzed properly the schedule of activities and make sure that site work implementation adheres with

the contract documents / specifications and within budget constraint.

BRAUN TRANSWORLD CORPORATION (Santa FE Braun of California U.S.A.) PO Box 25161, Safat – 13112, State of Kuwait Civil / Structural Inspector June 18,1986 – August 25,1987

Project Highlights: Construction of Mina Abdullah Refinery Modernization Project under the clientele of Kuwait National Petroleum Corporation (KNPC). Civil / Structural scope comprises of cast-in-situ of inter-connecting Pipe Racks (Trains 1, 2, 3 & 4) foundations, erection of structural steel for above ground pipe racks, cooker drum and cabling instrumentation system. Excavation (Cut & Fill) for both the routing of underground buried pipelines (Tie-in/Points) and high voltage power cables. Asphalt paving into required surfaced covered process areas and access roads network. Cast in placed of heavy machineries foundations i.e. rotating equipment, Gas Turbines, Vessels, Heat Exchangers, Furnaces, Boilers, Reactors, Towers and among others.

Duties and Responsibilities: ➢ Monitor civil and structural works including but not limited to setting out of misc. items i.e., excavation / backfilling,

concrete / steel structures, sub-station / industrial buildings, road / paving works, drainage system / grading works,

CV of Engr. Nasser Salik 11 of 12

and other associated civil works within the plant process areas.

➢ Review QA/QC submittals and provide inputs, including but not limited to inspection test plans (ITP), method statements, materials review and other relevant document required for the project.

➢ Monitor and inspect for the erection of structural steel for shelters and above ground pipe racks.

➢ Review concrete mix designs submitted by the contractor and validate trial mix reports according to project specifications and requirements. Ensure batching plant compliance and calibration certificates including competency assessment of operators.

➢ Perform pre-pour inspection and post-concrete surveillance to ensure all construction requirements particularly for “hot-weather concreting” are being followed onsite.

➢ Validate source/vendor for general fill materials as submitted by the contractor, including laboratory test reports of various types of backfill materials as per project requirements.

➢ Monitor the construction of asphalt road including but not limited to survey setting out, formation of sub-grade,

sub-base, road base, and laying of asphalt base course and asphalt wearing course.

➢ Obtained required certificates or schedules from contractor/s for review, witnessed and approve all related tests required to be perform and maintain the records accordingly.

➢ Check calibration certificates of laboratory tools and equipment. Random witnessing of actual test procedures for soils, asphalt and concrete samples.

➢ Issue non-conformance report as necessary and determine corrective / preventive measures.

➢ Maintain daily diary of all relevant status of work done onsite particularly civil and structural activities.

DM CONSUNJI ENGINEERS INCORPORATED 1881 President Quirino Avenue Extension, Pandacan, Manila. Philippines

Field / Office Engineer June 28,1984 – May 10,1986

Project Highlights: Construction of Residential Facilities, Sports Complex, Race Track / Outdoor Sports Facilities and other related Infrastructure Projects.

Duties and Responsibilities:

➢ Analyzed bid documents for both government and private sector entities, establish cost assumptions and financial parameters.

➢ Study and review the approved construction drawings and supervised crew members of site work activities.

➢ Provide materials estimate for civil, structural & architectural and prepare take-off (MTO) per approved construction drawings and specifications.

➢ Collecting, evaluating and interpret all construction documents (specification and manuals) including conduct site surveys and inspection to gather field data.

➢ Assist in the preparation of work schedule, materials, equipment and manpower distribution.

➢ Review and analyzed properly the schedule of activities and make sure that site work implementation adheres with the contract documents / specifications and within budget constraint.

➢ Coordinate activities in materials handling, receipt and inspection to ensure that those items comply with specified specifications. Implement material control, monitoring and inventory updating.

SEMINARS / CONFERENCE ATTENDED

1. Role of Joints in the Durability of Reinforced Concrete Structures Held on the 29th April 2007, Kuwait Society of Engineer Offices

2. ACI-KC Second International Conference Theme of the conference: “Design & Sustainability of Structural Concrete in the Middle East with Emphasis on High-Rise Buildings”. Held on the 12-14 March 2007, Radisson SAS Hotel, Kuwait

3. Post Tensioning for Building Applications VSL Middle East ( www.vsl-intrafor.com), held on the 22nd January 2007

4. Durability of Concrete – Factors and Fundamentals Sponsored by ACI-KC / Al Ghanim Group, held on the 06th December 2006

5. PROLOG Software Seminar (Ultimate Solutions for Project Mgt. & Control)

SPECIAL COURSES / TRAINING 1. Successfully completed 35 hour’s courses on Project Management Body of Knowledge (PMBOK). 2. OSHA-3095 Electrical Low Voltage (Federal Standards), Held in Shaybah on the 17th Sept. 2012.

CV of Engr. Nasser Salik 12 of 12

3. Defensive Driving Course (On & Off-Road Desert Driving) Practical Assessment Training. Held in Shaybah on the 15th June 2012. Conducted by Saudi Aramco Job Skill Training Department. 4. Safety Orientation for “Emergency Response Plan” 5. Saudi Aramco Safety Training & Application i.e. H2S Hydrogen Sulfide Awareness, Confined Space Entry and Hazard Identifications. Held in Shaybah on the 20th July 2011. Conducted by Saudi Aramco Safety Dept.

6. Certified Training on ISO 9000 Quality Awareness & Writing Effectively (QAWE). 7. Claims & Disputes Resolutions under FIDIC of Contract – 2007 8. Effective negotiation skills & Time Management

PERSONAL

Nationality ------------------------ Filipino Passport --------------------------- P1706700A (Issued: 21/01/2017 – Expires: 20/01/2022) Driver’s License --------------- (PHILIPPINES – N02-91-174714), (SAUDI ARABIA – 2304822485), (KUWAIT – 262090803615). Permanent Address --------- Blk126 Lot15 Phase-8 Sitio Imelda, Upper Bicutan, Taguig City, PHILIPPINES Computer Hands-On -------- MS Office Package (Word, Excel, Access, PowerPoint, VISIO), and Internet Application. Engineering Software ------- Primavera (P6), MS Project, X Steel, AutoCAD, Mathcad.

Nasser Salik