Runway 1634 Rehabilitation Construction Phasing Presentation September 13 & 14, 2017

Runway 16-34 Rehabilitation Construction Phasing

Embed Size (px)

Citation preview

Runway 16‐34 Rehabilitation Construction Phasing Presentation

September 13 & 14, 2017 

2

• Runway 16-34 and Blast Pad Rehabilitation• Taxiway Connector and Runway 11-29 Rehabilitation• Pavement Grooving and Marking• Runway 16-34 Centerline and TDZ Light System Replacement• Runway 16-34 Threshold/End Light Replacement• Taxiway Connector Edge Light System Replacement• Runway 16 MALSR Threshold Bar Light Adjustment• Runway 16 PAPI Replacement• Runway 34 REIL Replacement• Primary and Supplemental Wind Cone Replacement• Constant Current Regulator Replacement

Project Scope

3

Project Construction Elements

Demolition Paving Lighting Pavement Grooving Pavement Marking

4

Demolition

Runway and taxiway pavement milling Runway centerline light and conduit removal TDZ light and conduit removal Runway threshold/end light removal Taxiway edge light removal Runway 16 PAPI removal Runway 34 REIL removal Runway 16 MALSR threshold bar light fixture removal Primary and supplemental wind cone removal

5

Paving

Pave full length and width of Runway 16-34 Pave both blast pads Pave all connector taxiways to hold bars Pave Runway 16-34/11-29 intersection

6

Lighting

Install new Runway 16-34 centerline and TDZ light systems

Install new Runway 16-34 threshold/end lights Reinstall Runway 16 MALSR threshold bar light fixtures Install new LED taxiway connector edge light systems Install new Runway 16 PAPI Install new Runway 34 REIL Install new primary and supplemental wind cones Replace Runway 16-34 centerline and TDZ regulators

7

Pavement Grooving

Groove all new Runway 16-34 pavement

Pavement Marking Runway pavement markings, including blast pads Taxiway centerlines, including hold positions, signs,

and enhanced centerline markings

8

Construction Phasing

Phase I - Lighting PreparationPhase II - Runway Paving and LightingPhase III - Taxiway Paving and LightingPhase IV - Pavement Grooving and Marking

9

Phase I

Remove runway centerline lights, TDZ lights and conduit

Install new base cans and conduit

Schedule

May 1 – September 3

Monday ‐ Saturday 12:00 AM – 5:30 AM

10

Phase II

Mill and pave Runway 16-34 including blast pads Install runway centerline and TDZ light fixtures Remove and replace Runway 16-34 threshold/end lights Adjust Runway 16 MALSR threshold bar light fixtures to

grade Remove and replace Runway 16 PAPI Remove and replace Runway 34 REIL Remove and replace primary/supplemental wind cones Temporary pavement markings

Schedule

September 4 – November 1

Tuesdays 9:00 AM ‐ Thursdays 6:00 PM

11

Mill and pave taxiway connectors and Runway 11-29

Remove and replace taxiway edge light systems(Taxiway connectors A, C, F, G, K, and L)

Temporary pavement marking

Phase III

Schedule

September 4 – November 1

Friday ‐ Tuesday 12:00 AM – 5:30 AM

Tuesdays 9:00 AM ‐ Thursdays 6:00 PM

12

Runway 16-34 pavement grooving Permanent pavement marking

Phase IV

Schedule

October 16  – November 1

Tuesdays 9:00 AM ‐ Thursdays 6:00 PM

13

Total Duration – Calendar Days

PHASE I 126 Days (5/1 ‐ 9/3)

PHASE II 59 Days (9/4 ‐ 11/1)

PHASE III 59 Days (9/4 ‐ 11/1)

PHASE IV 17 Days (10/16 ‐ 11/1)

TOTAL 185 Days