Lammey + Giorgio Architects 215 Highland Avenue, # B Haddon Twp, NJ 08108 lgarch.com ADDENDUM NO. 1 Project: Additions & Alterations – Oaklyn Senior Citizens Center 20 West Clinton Avenue Oaklyn, NJ Date: June 11, 2021 L+G: 21555 Bidder must acknowledge receipt of this Addendum on the bid form in the space provided therefor. This Addendum is issued for the purpose of amending certain requirements of the original Contract Documents, as noted hereinafter, and is hereby made part of and incorporated in full force as part of the Contract Documents. Unless specifically noted or specified hereinafter, all work shall comply with the applicable provisions of the Contract Documents. GENERAL AND ANSWERS TO QUESTIONS ASKED AT THE MANDATORY PREBID MEETING Q1. How will the bids be selected if there is not a consistent insurance requirement? A1. Delete reference to insurance coverage in specifications section 008100, Paragraph 11.1.1. Bidders to provide the following minimum insurance coverages: A. Commercial General Liability a. Each Occurrence = $1,000,000. b. Damage to Rented Premises (Ea. Occurrence) = $100,000. c. Medical Expenses (Any one person) = $15,000. d. Personal and ADV Injury = $1,000,000. e. General Aggregate = $3,000,000. f. Products – Comp/OP Aggregate = $2,000,000. g. Pollution = $1,000,000. B. Automobile Liability a. Combined Single Limit (Ea. Accident) = $1,000,000. C. Umbrella Liability a. Each Occurrence = $5,000,000. b. Aggregate = $5,000,000. D. Workers Compensation and Employers’ Liability per Statute a. E.L. Each Accident = $1,000,000. b. E.L. Disease – Each Employee = $1,000,000. c. E.L. Disease – Policy Limit = $1,000,000. E. Property Section a. Property = $77,250. F. Equipment a. Equipment = $70,000. Bidders shall include an allowance of $10,000 in their base bid for costs

lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

Lammey + Giorgio Architects 215 Highland Avenue, # B Haddon Twp, NJ 08108

lgarch.com

ADDENDUM NO. 1

Project: Additions & Alterations – Oaklyn Senior Citizens Center 20 West Clinton Avenue Oaklyn, NJ

Date: June 11, 2021 L+G: 21555 Bidder must acknowledge receipt of this Addendum on the bid form in the space provided therefor. This Addendum is issued for the purpose of amending certain requirements of the original Contract Documents, as noted hereinafter, and is hereby made part of and incorporated in full force as part of the Contract Documents. Unless specifically noted or specified hereinafter, all work shall comply with the applicable provisions of the Contract Documents. GENERAL AND ANSWERS TO QUESTIONS ASKED AT THE MANDATORY PREBID MEETING

Q1. How will the bids be selected if there is not a consistent insurance requirement? A1. Delete reference to insurance coverage in specifications section 008100, Paragraph 11.1.1. Bidders to provide the following minimum insurance coverages:

A. Commercial General Liability a. Each Occurrence = $1,000,000. b. Damage to Rented Premises (Ea. Occurrence) =

$100,000. c. Medical Expenses (Any one person) = $15,000. d. Personal and ADV Injury = $1,000,000. e. General Aggregate = $3,000,000. f. Products – Comp/OP Aggregate = $2,000,000. g. Pollution = $1,000,000.

B. Automobile Liability a. Combined Single Limit (Ea. Accident) = $1,000,000.

C. Umbrella Liability a. Each Occurrence = $5,000,000. b. Aggregate = $5,000,000.

D. Workers Compensation and Employers’ Liability per Statute a. E.L. Each Accident = $1,000,000. b. E.L. Disease – Each Employee = $1,000,000. c. E.L. Disease – Policy Limit = $1,000,000.

E. Property Section a. Property = $77,250.

F. Equipment a. Equipment = $70,000.

Bidders shall include an allowance of $10,000 in their base bid for costs

Page 2: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

2

lgarch.com

Page

for any additional insurance coverages requested by the owner. Q2. Required insurance amounts are not proportional with the scale of the project. Can these be reduced to align with the project scale? A2. Refer to answer 1. Q3. The bid documents state that the subcontractors need to carry the same insurance coverage and amount as the contractor, is this correct? A3. No, the subcontractor is bound to carry the insurance coverage to the extent of the work to be performed by the subcontractor per the General Conditions of the Contract for Construction. Q4. Difficult to bid a job without clear direction on the insurance requirements for all of the bidders. Will this be resolved before bids are due? A4. Refer to answer 1. Q5. Who is responsible for removing all the furniture and records from the building? A5. All furniture and records will be removed by the Owner.

Q6. Structural drawings indicate lintels on the roof level. Is that correct or are there only lintel opening on the lower level and second floor level? A6. No lintel openings are at the roof level. Lintel openings are at the lower level and second floor level.

Q7. Is there any known asbestos in the building? A7. According to the owner there is no known asbestos, we will advise if lead is present.

Q8. Has or will there be an asbestos report provided? A8. Will be requested from owner and included in the next addendum.

Q9. How are permit approvals and release being addressed? A.9 The contractor is only responsible for securing permits, scheduling inspections, and receiving approvals for the work being completed as part of the contract.

Q10. Who covers the cost of the permit? A10. No cost for the permit. The Borough will cover permit cost. Q11. Will an area on the site be allocated for a dumpster to be located? A11. Yes, there will be an area on-site for a dumpster. This will be coordinated with the Borough.

Page 3: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

3

lgarch.com

Page

Q12. Will parking be allowed in the Borough parking lot? A12. No, all parking will be on the street. Q13. Is the sawing cutting of the existing lower-level slab solely for the plumbing rough-in and not for an under-slab drainage system? A13. Yes. Q14. Are the areas of the lower-level slab that have been removed for plumbing rough-in required to have concrete poured to close the slab? A14. No, backfill with 6” of clean stone up to bottom of slab elevation. Q15. What is the depth of the elevator pit? A15. The elevator pit depth is 14” below the existing lower-level slab. Refer to A600. Q16. Is a fire alarm system required as part of the base bid? A16. No. Q17. Is a sump pump or drain required in the elevator pit? A17. A sump pump will be used to drain pit. Refer to detail #3 on E-500. Q18. Will a copy of the sign-in sheet and agenda be provided to the bidders? A18. Yes, see attached.

OTHER ITEMS DISCUSSED AT MANDATORY PRE-BID MEETING 1. It was determined that the building would be made available for an

additional site visit on Wednesday June 16, 2021, between 9:00AM and 12:00PM.

2. Pre-Bid sign-in sheet has been attached for the bidder’s reference. Pre-Bid Agenda has been attached for the bidder’s reference. Pre-Bid meeting minutes has been attached for the bidder’s reference.

Reminder that bids are due and will be opened and read out loud on Thursday July 8, by 2:00PM at 500 White Horse Pike, Oaklyn 08107, NJ 08075. The Bidders are responsible to ensure that their bids are delivered on time. The Owner takes no responsibility for bids that are delivered late.

Page 4: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

4

lgarch.com

Page

QUESTIONS FROM BIDDERS AND ANSWERS

Questions from Eagle Construction Services

Q1. What is the last date for questions on this bid? A1. The last date for questions will be June 18 at 4:00 PM. Q2. I see no reference to liquidated damages in the

specifications, are there any and if so, how much? A2. Please refer to spec section 008100-B-8.3.3.1 for liquidated

damages requirements. Q3. I see no reference to a maintenance bond in the

specifications, if a maintenance bond is required, kindly advise the percentage and duration?

A3. There are no requirements for a maintenance bond. Q4. As stated: Rough-in sanitary waste and vent (to a height of

4ft. above the floor) “for future fixtures.” Please confirm there will be no domestic water to be installed at this time?

A4. Correct.

Questions from Levy Construction. Q1. Who will be responsible to hire third party testing agency? A1. The Contractor is responsible for third party testing

agencies per spec section 014000-1.7. Q2. Will there be any permit/review fees and who will be

responsible? A2. The Borough will be responsible for any permit/review fees. Q3. Do you know the radius? A3. The radius for the glazing above door #108 is 3’-0”. Q4. Existing sure looks like an unequal pair (picture) Are you

enlarging the opening? A4. The existing ground floor door and opening are to remain.

The opening for door #108 is for a pair of 3’-0” doors that are part of the new vestibule.

Q5. Hardware set on page 12 of alum frame entr-says closers is

that a mistake? A5. There will be no closers at door #108. Q6. Concealed holder/stop may interfere with auto operator? A6. Addendum No. 2 will address holder/stop with auto

Page 5: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

5

lgarch.com

Page

operator.

Q7. There are some big-ticket insurance requirements on this project. For a project that is so small, this is going to increase the cost. Can you please confirm that the insurance required is a Crime Policy, Pollution Policy, & a Cyber Policy?

A7. Refer to answer to Prebid meeting question above. Q8. Please advise on who is the fire alarm vendor and who is the

manufacturer of the existing fire alarm panel? A8. There is no existing fire alarm system and none to be

included in the base bid. Questions from MJJ Construction Q1. Pollution - $5,000,000 Cyber Liability - $3,000,000 Crime Coverage including Employee Dishonesty -

$1,000,000 Profession Liability which includes Internet Related

Exposure - $5,000,000. Are the above insurances applicable to this job? These are

very expensive. A1. Refer to answer to Prebid meeting question above. Clarifications

1. Drawing E-500, 3/E-500: Note that there is no sprinkler head required in the hoistway.

Attachments

o Prebid Meeting Sign-In Sheet – 2 pages o Prebid Meeting Agenda – 3 pages o Prebid Meeting Minutes – 3 pages

END OF ADDENDUM NO. 1

Page 6: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue
Page 7: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue
Page 8: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Lammey + Giorgio 215 Highland Avenue, # B Haddon Township, NJ 08108 June 09, 2021

Pre-Bid Meeting Agenda Time 2:00 PM

Project Additions & Alterations to Oaklyn Senior Citizens Center

L+G No 21555

Client Project No xxxxx-xx

• Introduction and Responsibilities: Authorized representatives of the Owner, Architect and their consultants

• Project Description:

____________________________________________________________

____________________________________________________________

____________________________________________________________

• Due Dates: o Bids due on July 8, 2021 at 2:00 PM o Bid location is 500 White Horse Pike, Oaklyn, NJ

• Questions:

o Questions following today’s Q&A are to be sent by email to [email protected]

o Deadline for questions is June 17, 2021 at 4 PM Architect to answer bidder questions in writing

o Architect to issue written Addendum no later than COB on June 24, 2021

• Review Proposal Form: o Base bid Complete all demolition work and install lintels at new masonry

openings.

Construct the new vestibule, including removals, new construction, and electrical work.

Construct the elevator shaft, new second floor framing and install

the new elevator and machine room. Provide new electric panels

Page 9: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Page 2

and extend power to the elevator. Add exhaust fan with reverse-

acting thermostat as scheduled, but with no intake duct, and

exhaust duct extended to adjacent room only (not to brick vent

shown on plans).

Rough-frame new partitions. Assume all new door frames will be

knock-down.

The total work area is approximately 3,620 square feet in area.

o Alternate #1 – Rough-in plumbing Rough-in all sanitary and vent (to a height 4-feet above floor)

piping for lower level plumbing fixtures, including the following: • Saw-cut, remove and dispose of concrete slab,

excavate, layout, and install piping for future plumbing

fixtures.

• Connection of new piping to existing sanitary line.

• Inspections and approvals from local plumbing subcode

official.

• Backfill after plumbing subcode approval with clean

stone up to bottom of slab elevation.

o Alternate #2 - Rough-in electrical and data outlets in walls, and provide temporary lighting as indicated on drawings.

Wall rough framing will be completed by the general

contractor.

Install outlet boxes with conduit to 6-inches above

future ceiling height; blank plate all outlet boxes.

Relocate existing 2’x2’ lighting fixtures on lower level

and mount to existing plaster ceilings, in quantities

shown below. Wire to new electrical panel and provide

surface mounted switches and wiring. Note that new

ceilings are not part of the Base Bid or this Alternate.

• Lower Level:

• Men’s Room – 1 fixture

• Women’s Room – 1 fixture

• Corridor – 3 fixtures

• Lounge – 3 fixtures

• Stair Landing – 1 fixture

• Upper Level:

• Activity – 6 fixtures

• Corridor – 2 fixtures

• Vestibule – 1 fixture

o Alternate #3 – HVAC system for lower level. Include all labor, material and electrical work for a

functioning HVAC system for the lower level of the building.

Page 10: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Page 3

Ductwork shall be installed without connections for branch flexible ductwork. Make openings in rigid ductwork at those locations and install grilles. Provide blanket insulation as specified.

Provide a surface mounted thermostat and wiring to allow control of the equipment.

Note that new ceilings are not part of the Base Bid or this Alternate.

o Alternate #4 – HVAC system for second floor. Include all labor, material and electrical work for a

functioning HVAC system for the second floor of the building.

Ductwork shall be installed without branch flexible ductwork. Make openings in rigid ductwork at those locations and install grilles. Provide blanket insulation as specified.

Provide a surface mounted thermostat and wiring to allow control of the equipment.

Note that new ceilings are not part of the Base Bid or this Alternate.

o Bid Bond, Consent of Surety. Exhibit A and B o Stockholders Statement – Corporation and/or Partnership Holders.

(CCCD Form C-33). Exhibit C. o Non-Collusion Affidavit (CCCD Form NC-1). Exhibit D. o Affirmative Action Plan. Exhibit E. o Copy of Bidder’s Public Works Contractor Registration. o Copy of Bidder’s New Jersey Business Registration. o Proof of DPMC Contractor Classification. o List of Subcontractors. Required to be classified with the State of

New Jersey Division of Property Management & Construction (DPMC) at the time of the bid due date.

• Other Owner General Requirements:

o Spec section 008100 – Modifications to General Conditions

Article 11 – Insurance and Bonds requires adding types of insurance provided by the Borough of Oaklyn’s Insurance Broker.

• Contract Forms: o Contract, AIA Document A101. o Performance / Labor & Material Payment Bond, AIA Document

A312.

• Follow-Up Visits (if allowed by Client)

• Site Inspection

END OF AGENDA

Page 11: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Lammey + Giorgio 215 Highland Avenue, # B Haddon Township, NJ 08108 June 9, 2021

Meeting Minutes Mtg #1 – Mandatory Pre-Bid Conference Time 2:00 PM

Project Oaklyn Borough Hall

L+G No 21555

Client Project No xxxxxx

Attendees Company Phone Email

Rick Hawco Borough of

Oaklyn 609.685.9069 [email protected]

Jim Williams JH Williams Inc. 856.793.7114 [email protected]

Ted Pirolli Ocean

Construction 609.653.0133 [email protected]

Troy

Naticchione

R. Maxwell

Construction 609.646.6699 [email protected]

Josh Levy Levy

Construction 856.547.0707 [email protected]

Mike Prokapus MJJ

Construction 856.768.9440 [email protected]

Zachary Piro Kavi

Construction 856.767.2491 [email protected]

Lester Danley

Eagle

Construction

Services

609.239.8000 [email protected]

Dennis Straga Straga Brothers

Inc. 856.881.7960 [email protected]

Nick Russo Russo

Construction 856.467.7006 [email protected]

Norm Orourke Park Orourke 610.608.8367 [email protected]

William

Lammey

Lammey +

Giorgio 856.833.0010 [email protected]

Collin Phillips Lammey +

Giorgio 856.614.9578 [email protected]

Next Meeting: June 16, 2021 for a follow up site visit.

Page 12: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Page 2

Distribution: (Via E-mail): All attendees, B. Taft, R. Hawco, T. Wilson The meeting minutes are organized in a table format that lists “Item”, “Discussion”, and “Action By” columns. Each “Item” is cross referenced to meeting number and item reported (i.e. 1-A.3 refers to meeting no. 1, item A.3). The “Action By” column uses the following abbreviations: A/E Architect Lammey + Giorgio

RH Client Borough of Oaklyn

Item Discussion Action By A. Introduction and Responsibilities 1.A.1 William Lammey introduced the A/E team and client

representative.

B. Project Description 1.B.1 A/E gave a description and overview of the project. C. Due Dates 1.C.1 Bids are due on July 8, 2021 at 2:00 PM. 1.C.2 1.C.3

Bids are to be delivered to Oaklyn Borough Hall, 500 White Horse Pike, Oaklyn, NJ. A/E reiterated to the prospective bidders that it their responsibility to ensure that their bids are received on time to the correct location and that the Borough is not responsible for late bids.

D. 1.D.1

Dates for Bidder Questions and Addendum Questions following today’s Q&A are to be sent by email to [email protected].

1.D.2 1.D.3 1.D.4 1.D.5

Deadline for bidder questions to be submitted is June 18, 2021 4:00 PM. A/E to answer bidder questions in writing. A/E to issue final written Addendum no later that COB on June 25, 2021. A/E to issue Addenda #1 on Friday June 11, 2021.

E. Review Proposal Form 1.E.1 A/E reviewed base bid. See Pre-Bid Meeting Agenda. 1.E.2 A/E reviewed Alternate #1 – Rough-In plumbing. See

attached Pre-Bid Meeting Agenda.

1.E.3 A/E reviewed Alternate #2 – Rough-in electrical and data outlets in walls, and provide temporary lighting as indicated on drawings. See attached Pre-Bid Meeting Agenda.

1.E.4 A/E reviewed Alternate #3 – HVAC system for lower level. See attached Pre-Bid Meeting Agenda.

1.E.5 F. 1.F.1 1.F.2

A/E reviewed Alternate #4 – HVAC system for second floor. See attached Pre-Bid Meeting Agenda. Other Owner General Requirements Spec section 008100 – Modifications to General Conditions Article 11 – Insurance and Bonds requires adding types of insurance provided by the Borough of Oaklyn’s insurance broker. Refer to Addendum No. 1.

Page 13: lgarch.com Lammey + Giorgio Architects 215 Highland Avenue

lgarch.com

Page 3

G. 1.G.1

Follow-up site visit June 16, 2021 – Contractors will be able to have their subcontractors visit the site between 9:00 AM – 12:00 PM.

H. 1.H.1

Questions from bidders Refer to Addendum No. 1.

I. Attachments 1.I.1 Pre-Bid meeting Agenda. 1.I.2 Copy of mandatory Pre-Bid Conference sign-in sheet.

END OF MINUTES

I believe this account accurately reflects what transpired during and directly

following the meeting. Additional input from any of those persons present is

appreciated and will be incorporated into addenda of these Minutes if received in

writing within five (5) days after receipt of these Minutes.

Respectfully submitted,

Lammey + Giorgio P.A.

Collin Phillips, R.A.