Contents
• Project Scope
• Origins of the Program
• BESS Introduction
• Engineering Scope & Progress
• Project Timelines
• Challenges Experienced
1
Project Scope
• Installation of 1440MWh distributed battery storage
• Translates to roughly 90 sites of a average 4MW each; sites range from 1MW to 40MW
• BESS, AC LV & MV equipment, P+C, upstream telecoms, M&O
• DERMS … integration into DMS
• APM Tool … end of life management
2
Origins of the Program
KIWANO CSP
100MW CSP (KIWANO)
GROUND-BREAKING STORAGE
GENERATION AND STORAGE:
60%*100MW*24h = 1440MWh per day
TOWER
TROUGHDISH, TROUGH OR TOWER
TECHNOLOGY
3
BESS Introduction
“The battery will kill fossil fuels … it’s only a matter of time” by Mark Chediak, Bloomberg Magazine, March 2018
5
BESS Introduction
The global energy storage market will double six times between 2016 and 2030, rising to a total of 125 gigawatts/305 gigawatt-hours. US$1B will be invested in this time.Bloomberg New Energy Finance, Nov 2017
6
Engineering Scope & Progress
• Sites identification - use case, business case
• Network studies due diligence
• Concept designs per site – layout, 1-line, P+C
• BESS specification
• MV equipment specification
• DERMS and APM specifications
• Bid Documents
• Costing and estimation
• Commissioning 13
Project Timelines
• Schedule subject to internal Eskom approvals and external approvals by DFIs and statutory bodies (DEA, etc)– Ph1 Bid Documents Finalisation 2018 Nov
– Ph1 Enquiry Issued 2019 Q1
– Ph1 Enquiry Closes, Evaluated and Awarded 2019 Q2
– Ph1 Construction 2019 Q3-Q4
– Ph1 Test & Commissioning 2019 Q4
– Ph2 Enquiry Issued 2019 Q3
– Ph2 Enquiry Closes, Evaluated and Awarded 2020 Q1
– Ph2 Construction 2020 Q1-Q2
– Ph2 Test & Commissioning 2020 Q314
Challenges Experienced
• Developing a decent BESS specification
• Knowledge and skills for network studies
• Defining Use Case and Business Case
• Compilation of Bid Documents- Evaluation Criteria
- Schedules
- Internal Change Management (capacity guarantees, O&M, etc)
• Statutory Approvals – EAs and land rights 15