Upload
others
View
19
Download
3
Embed Size (px)
Citation preview
Introduction
Sand Control Core
Learning Objectives
This section will cover the following learning objectives:
Identify the need for sand control
Recognize the causes of sand movement
Define what consolidated sand is, and what it is not
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
1
COPYRIGHT
Oilfield Sand Production is a Worldwide Problem
Why does sand production create such a problem?
Examples of Potential Sand Control Problems
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
2
COPYRIGHT
Examples of Potential Sand Control Problems
Examples of Potential Sand Control Problems
Apply API 14E standards to limit
allowable produced gas well rates to effectively minimize erosive
conditions
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
3
COPYRIGHT
Examples of Potential Sand Control Problems
Production Rate
Examples of Potential Sand Control Problems
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
4
COPYRIGHT
Examples of Potential Sand Control Problems
$
Sand Control Practices
Completion and operations engineers carefully monitorformations prone to sand production
Decisions are made early in a field development or re-development project regarding the need for sand controlpractices
These practices include:• Doing nothing and tolerating an expected very small or insignificant
sand volume production• Imposing rate restrictions to limit sand production potential• Using complex gravel pack and frac pack mechanical well
completions• Using other well completion methods such as slotted or pre-
perorated liners, screen mesh designs, expandable sand screens,resin consolidation techniques, proprietary mechanical sand controlcompletions, and other approaches
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
5
COPYRIGHT
Sand Control – A Safety Issue
Before being a productivity issue, it is a safety issue
Thk: 2.9 mm
Thk: 1.9 mm
Thk: 1.6 mm
Thk: 1.9 mm
Flow Direction
* Note the degree of erosion / wall thickness thinning due to sand production.
Thk = Wall thickness
Tubing Blast Joint Failure from Sand Erosion
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
6
COPYRIGHT
Causes of Sand Production
The formation components move when:• The forces induced by the flow or other factors are stronger than
the forces that hold the grain in place• This can result from:
– Compaction squeeze– Radial differential pressure
• Fluid inertia
• Fluid drag
– Relative permeability effects
– Reduction of bonding strength
– Change in choke setting– Other
AcidizingAcidizing
WaterfloodingWaterfloodingChange in choke settingChange in choke setting
Changes Due to:
Spike Sand Production
Sand Production Spike: Temporary – likely a reaction to a change in well operations
# o
f sa
nd
per
bb
l
Time or Volume Flowed
– Flowrate
– Drawdown
– Slight ∆saturation
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
7
COPYRIGHT
Catastrophic Failure
# o
f sa
nd
per
bb
l
Time or Volume Flowed
• Large scale ∆saturation• Depletion
Sand Production Failure: Major event which fills the wellbore and possibly surface facilities; requires a well workover
Temporary Condition
Catastrophic Failure
Sand production causes damage to facilities and resultant curtailment or production shut-down
Surface separator filled with produced sand, requiring cleanout
Consequences of Sand Production
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
8
COPYRIGHT
• Highly consolidated sandstone
• Consolidated sandstones
• Weakly consolidated sandstones
• Very weakly consolidated sandstones
• Very, very weakly consolidated sandstones
• Unconsolidated sand
Which Reservoirs Produce Sand?
Normally no sand control problemsNormally no sand control problems
Many ways of classifying sandstone strengths
One method:
Will produce sand at some
point
Will produce sand at some
point
Sand Classification
Zero strengthDry sand
Strength fromCapillary forcesDamp sand
Source: Schlumberger
Varying sand strengths and their classifications from very, very weak, to very weak, to weak, to
degrees of consolidation involve capillary pressure, cementing, sand compressive strength and related compaction for each sand sampled
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
9
COPYRIGHT
Potential Causes of Sand Movement
Fluid saturation changes
Surfactants in drilling fluids, completion fluids, etc.
Acid stimulation treatments
Solvents
Reservoir fluid flowrate / velocity changes and increased drag forces
Changes in the overburden stress, increased as fluids are withdrawn
Additional phases causing relative permeability problems
Shut-in and start-up changes which alter the sand packing arrangement near perforations
Other
Why?
Late Eocene sandstone is much shallower and would have a greater chance of being more unconsolidated.
Exercise – Sand Production
Two formations are under evaluation by a major production company. One is a Late Eocene sandstone
(about 60 million years old) and the other a Permian sandstone (about 350 million years old).
Two formations are under evaluation by a major production company. One is a Late Eocene sandstone
(about 60 million years old) and the other a Permian sandstone (about 350 million years old).
Which formation would likely have a greater chance of having sand production problems?
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
10
COPYRIGHT
Summary
It is mandatory that an asset team tasked with field development and operations consider a formation’s lithological properties to assess the potential to both:
a) Produce formation sandb) To plan accordingly to design the most effective approach to
managing sand production problems
This module addresses:• The conditions surrounding sand production• The approaches taken to choose the most effective remedial
techniques applicable for a wide variety of cases• The API 14E standard addressing erosional velocity limits • The engineering procedures to design a modern gravel pack
completion • The various empirical design steps for understanding effective sand
control techniques
Learning Objectives
This section has covered the following learning objectives:
Identify the need for sand control
Recognize the causes of sand movement
Define what consolidated sand is, and what it is not
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
11
COPYRIGHT
Sand Control Completion Options and Design
Sand Control Core
Learning Objectives
Identify both non-mechanical and mechanical methods of sandcontrol
Recognize that rate restriction is a valid practice to managesand production
Recognize that minor sand volume produced may be tolerated
This section will cover the following learning objectives:
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
12
COPYRIGHT
Sand Control Methods – Various Options
No Direct Mechanical Control
Mechanical Methods
Sand Control Methods – Various Options
No Direct Mechanical Control
• Living with / dealing with limited sand production
• Surface sand separation
• Rate reduction
• Cavity formation, wormhole formation
• Selective completion practices
• High-density and/or phase-oriented perforating
• Wellbore trajectory designs – horizontal, laterals, etc.
Small volume of sand
Small volume of sand
Safe operation with no threats to
erosion
Safe operation with no threats to
erosion
Difficult to sell to management
Difficult to sell to management
Avoid areas that produce high sand volumes
Avoid areas that produce high sand volumes
Access only sections free
of sand problems
Wellstream desandersWellstream desanders
Wellhead desandersWellhead desanders
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
13
COPYRIGHT
Sand Control – Live With It
SANDPRODUCTION
DRAWDOWN
FIELD PROVEN LIMIT
RESER
VOIR PRESSU
RE SAND
FREE+
‐
+
150 psi (134 kPa) drawdown may induce sand production on unconsolidated turbiditic sandstones
No Control / Cavity Formation / Rate Restriction
Will sand stop moving, after cavity formation, when velocity drops below threshold necessary to tear sand loose from formation?
Will sand move continuously? Is it tolerable?
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
14
COPYRIGHT
No Sand Control
• Wellbore fill accumulation• Sand disposal• Subsidence• Casing collapse or damage• Surface erosion or blockages• High well maintenance• High facilities maintenance including shut down
“Do nothing” and let sand be produced
Risks
• Not unrealistic as an approach
Cavity Formation
Enlarging the wellbore, whether by perforating (tunnel extension),underreaming, wormhole formation or cavity creation, increasesthe area of contact with the formation and decreases the flowingfluid velocity at any set flowrate
Original hole Becomes
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
15
COPYRIGHT
No Sand Control
May require no more than:• Periodically removing a
small amount ofproduced sand fromsurface facilities andbailing the well; and,
• Regularly pigging surfaceflowlines
The overall cost of doingnothing may be small
Minimal sand productionmay have little negative effectupon operations
In this case, note minimal sand in
separator
No Sand Control – But, Limit Velocity
Larger / more perforations
Larger wellbore
Reduce the rate
Underream
Cavity completion
Slow down fluid movement rate at the sand face
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
16
COPYRIGHT
Sand Production Strategy
Provide Clean Perforations
First… Reduce the Frictional Forces (Flow Rate per Unit Area)
1
Open Increased Section2
Create a Conductive Path into Formation3
• Increase the number and/or size of the perforations• Consider horizontal well completion
• Gravel pack the well• Frac pack the well
Mechanical Methods of Sand Control
Chemical Consolidation
Resin-Coated Sand
Slotted Liners or Screens without a gravel pack• Open Hole or Cased Hole (not recommended)
Slotted Liners or Screens with a gravel pack• Open Hole or Cased Hole
Frac packing or Fracturing
Expandable Screens
Vent Screens
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
17
COPYRIGHT
Perforating May De-Stabilize the Formation
Perforating Creates Perforation Tunnel Damage
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
18
COPYRIGHT
Perforating Creates Perforation Tunnel Damage
Two well completion perforating designs are under evaluation bya major production company. Both are weakly consolidatedsands.
Which completion would likely have a greater chance of havingsand production problems?
Why?
• One is beingcompleted using 4shots per foot(13 shots per meter) of zone thickness
• The other at 12shots per foot(39 shots per meter)
Careful additional study is necessary to size diameter and determine pressure drop through each perforation. Well
drawdown would need to be carefully managed to restrict rate to constrain tendency of sand to flow.
Exercise – Sand Production
InchesEntrance Hole Dia. 0.91CFE 0.73
4.483.36
TTPTCPECP 2.47 (62.7 mm)
(85.3 mm)
(113.8 mm)
(18.5 mm)
(23.1 mm)
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
19
COPYRIGHT
Resin Consolidation
Creates stronger matrix by cementing grains together withsynthetic plastics / chemicals
• Leaves wellbore open• Hard to evenly apply• Length of effective life questioning
Industry results with resins have been mixed and the jobs maybe short-lived
Many new products available
The gravel is placed in the perforations and also fills thewellbore
Gravel is pre-coated with resin
Also used for other purposes, such as screenless frac packs
After allowing the resin to set, drill out the wellbore, leavingthe perforations filled with the consolidated gravel
Resin-Coated Gravel
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
20
COPYRIGHT
Mechanical Sand Control Methods
Basic Problem• Control sand without reducing productivity
Design Parameters• Optimum gravel-sand size ratio• Optimum slot width to retain gravel or sand• Effective placement technique
Screen Alone – or – Screen with Gravel
Learning Objectives
Identify both non-mechanical and mechanical methods of sandcontrol
Recognize that rate restriction is a valid practice to manage sandproduction
Recognize that minor sand volume produced may be tolerated
This section has covered the following learning objectives:
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
21
COPYRIGHT
Non-Gravel Pack Completions, Options, and Design Alternatives
Sand Control Core
Learning Objectives
This section will cover the following learning objectives:
Identify various screen types for sand control
Outline aspects of pre-packed screens for sand control
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
22
COPYRIGHT
Wire-Wrapped Screen
Consists of base pipe with drilledholes and wire-wrapped screenjacket
Jacket is welded or mechanicallyattached to base pipe
Rod-based screen without innerpipe is also available
The gauge of the screens issized based on the formationsand size distribution
Views of Sand Screen and Mesh
Construction
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
23
COPYRIGHT
Ported base pipeMesh
Support screen
Woven Wrap Mesh
Premium Screen
Base Pipe
Bakerweld Inner Jacket
Vector WeaveMembrane
Vector Shroud
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
24
COPYRIGHT
Note resin-coated sand between outer and inner wraps
This type of screen offers improved abrasion control
This type of screen plugs easily
Pre-Packed Screen
Pre-Packed Screen
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
25
COPYRIGHT
Examples
Slotted liners and screens in a non-gravel pack are
Except For Expandable Screens
Non-Gravel Pack Horizontal Well Completions
Open Hole With Slotted Liner
FILTRATION DEVICES
Open Hole With
Screen or Prepacked Screen
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
26
COPYRIGHT
Learning Objectives
Identify various screen types for sand control
Outline aspects of pre-packed screens for sand control
This section has covered the following learning objectives:
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
27
COPYRIGHT
Gravel Pack Completions, Options, and Design Alternatives
Sand Control Core
Learning Objectives
This section will cover the following learning objectives:
Describe the principles of sand control screen and gravelcompletions
Identify the three steps comprising a gravel pack completiondesign
Describe various fluid options for pumping gravel slurry into agravel pack completion
Outline the function of a gravel pack “crossover tool”
Outline the function of a gravel pack “shunt tube”
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
28
COPYRIGHT
Consolidation:Resin
Sand Control Principles: 3 Ways
Filtration:Stand-Alone
Screen
Bridging:Gravel Pack
Sand Control Principles
Screen
Gravel Pack
Perforation
Formation Sand
PerforationTunnelCement
Casing
Internal gravel pack
recommended thickness of pack
or pre-pack is 0.75 in. to 1.25 in.
(19 mm to 31.8 mm)
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
29
COPYRIGHT
Gravel Pack Design Principles
• Establish a highlypermeablepathway betweenformation andwellbore thatformation sandcannot penetrate
• Gravel retainsthe formationsand in place
• Screen holds thegravel in place
Gra
vel
Pac
k D
esig
n
Pri
nci
ple
#2
Gra
vel
Pac
k D
esig
n
Pri
nci
ple
#2
Gra
vel
Pac
k D
esig
n
Pri
nci
ple
#1
Gra
vel
Pac
k D
esig
n
Pri
nci
ple
#1
• Gravel is placed between the screen and the formation
Open Hole2
• Gravel is placed between screen and casing, andinside perforations
Cased Hole1
Cased Hole vs. Open Hole Gravel Packs
The trend is toward more open hole gravel packs beingplaced in horizontal wells
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
30
COPYRIGHT
Gravel Pack Design Principles
Gravel Pack Completion Sand Control
Works as a two-part retainer:
Step 1: Gravel is sized to retain formation sand
Step 2: Screen sized to retain gravel in place
“Bridging” occurs at this interface
Importance of Good Bridging in a Gravel Pack Design
Gravel Pack Design Principles
GOOD BRIDGING
Formation Sand is Restrained By Gravel Pack Gravel in a Good Design
POOR BRIDGING
Formation Sand Invades Gravel Pack
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
31
COPYRIGHT
Gravel Pack Design Principles – 3 Steps
Obtain a good description of the formation sand grainsize distribution1
Select gravel size based on the formation sandgrain size distribution2
Select screen based on smallest gravel range3
• 50% cumulative grain size x 6 for gravel pack• 50% cumulative grain size x 8 for frac pack
• 50% to 75% of smallest gravel range size
Formation Sampling for Sieve Analysis
Conventional Cores
Sidewall Cores
Produced Samples
• Avoid Composite Samples, whenever possible
Bailed Samples
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
32
COPYRIGHT
Conducting a Sieve Analysis in the Lab
Core sample is frozenand then thawed
During thaw, it breaks upinto smaller components
Sample is placed on thetop tray
Screens of different sizesfilter sand formationsample into a range ofdifferent sizes
Conducting a Sieve Analysis in the Lab
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
33
COPYRIGHT
Conducting a Sieve Analysis in the Lab
Conducting a Sieve Analysis in the Lab
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
34
COPYRIGHT
Conducting a Sieve Analysis in the Lab
Sieve analysis resultsmeasure weight percentsample retained on eachsieve size screen opening
The following series of slides illustrate gravel
pack design
1. Determine Gravel Size for Gravel Pack
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
35
COPYRIGHT
2. Determine Range of Gravel Size Using Median
mesh inch mm microns18 0.0394 1 100020 0.0331 0.84 84025 0.0278 0.71 71030 0.0234 0.59 59035 0.0197 0.5 50040 0.0165 0.42 42045 0.0139 0.35 35050 0.0117 0.3 30060 0.0098 0.25 25070 0.0083 0.21 21080 0.007 0.177 177
100 0.0059 0.149 149120 0.0049 0.125 125140 0.0041 0.105 105170 0.0035 0.088 88200 0.0029 0.074 74
Gravel PackChoose 20/40
Frac Pack
Choose 16/30
32
mesh inch mm microns18 0.0394 1 100020 0.0331 0.84 84025 0.0278 0.71 71030 0.0234 0.59 59035 0.0197 0.5 50040 0.0165 0.42 42045 0.0139 0.35 35050 0.0117 0.3 30060 0.0098 0.25 25070 0.0083 0.21 21080 0.007 0.177 177
100 0.0059 0.149 149120 0.0049 0.125 125140 0.0041 0.105 105170 0.0035 0.088 88200 0.0029 0.074 74
2. Max/Min Mesh Size For Gravel Pack Example: 20/40
Median gravel size for gravel pack example: 570 microns
Median gravel size for gravel pack example: 570 microns
(0.57 mm)Gravel Packchoose 20/40based upon Uniformity Coefficient
Median Gravel size for gravel pack example: 570 microns (0.57 mm)
[95 x 6]
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
36
COPYRIGHT
Blend gravel size range as follows:• Gravel sizing specifications are per ASTM E-11 and API RP 58• Gravel size distribution is a bell shaped curve by weight• A 20/40 distribution mean % retained on sieves is approximately
• Also, < 2% undersized gravel is allowed(i.e., gravel may not be smaller than 40 mesh for 20/40 gravel)
Max / Min Range
Gravel sizing is a function of the
Uniformity Coefficient of the
grain size distribution plot
2. Determine Range of Gravel Size Using Median
Sieve Size %
20 mesh 0.4
25 mesh 14.1
30 mesh 29.3
35 mesh 47.3
40 mesh 8.1
45 mesh 0.8
3. Determine Screen Slot Cut Spec as 75% of Min Gravel Size
mesh inch mm microns18 0.0394 1 100020 0.0331 0.84 84025 0.0278 0.71 71030 0.0234 0.59 59035 0.0197 0.5 50040 0.0165 0.42 42045 0.0139 0.35 35050 0.0117 0.3 30060 0.0098 0.25 25070 0.0083 0.21 21080 0.007 0.177 177
100 0.0059 0.149 149120 0.0049 0.125 125140 0.0041 0.105 105170 0.0035 0.088 88200 0.0029 0.074 74
Median Gravel size for gravel pack example: 570 microns
(0.57 mm)Gravel Packchoose 20/40
Frac Pack
choose 16/30
Therefore: screen slot spec is 75% x 0.0165 in. (0.42 mm) = 0.0124 in. (0.32 mm)
Illustratessize conversion
Minimum Gravel Size Range (D98)
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
37
COPYRIGHT
Sieve Analysis Indicates Whether Formation has Uniform or Non-Uniform Grain Size Distribution
Non-uniformNon-uniform
UniformUniform
Poorly Sorted Sand
Well Sorted Sand
(2.54 mm) (.254 mm) (.0254 mm) (.00254 mm)
Selecting Gravel Based Upon Sand Grain Size
Lower case “d“ designates formation sand median diameter
Upper case “D” is the selected gravel median diameter
Definitions to Assist Sand Control Design (SPE 37437)
Uniformity Coefficient40
90
d=
dCu
Sorting Coefficient10
95
d=
dC s
Saucier50
50
Gravel
Formation sand
D=
d6
1
2
3
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
38
COPYRIGHT
15© 2010 PetroSkills, LLC. All rights reserved. 15
Uniformity Coefficient
Cu = Uniformity Coefficient
d40 = Grain Diameter at 40% Cumulative Weight
d90 = Grain Diameter at 90% Cumulative Weight
Cu = d40 / d90
if Cu < 3
if 3 < Cu < 7
if Cu > 7
Sorting Coefficient is defined as Cs = d10 / d95
Uniform Sand Distribution=
Non-Uniform Sand Distribution=
Highly Non-Uniform Sand Dist.=
16
Various Grain Size Distribution Design Points
Design Point = d40
Design Point = d90
Design Point = d70
Design Point = d50
Design Point = d10
x 6
(2.54 mm) (0.254 mm) (0.0254 mm) (0.00254 mm)
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
39
COPYRIGHT
1717
Design Point Selection for Gravel Pack
Coberly and Wagner – D10 10(d10)
Saucier – D50 6(d50)
Stein – D85 4(d15)
Schwartz – D10 6(d10) for Cu < 5
D40 6(d40) for 5 < Cu < 10
D70 6(d70) for Cu > 10
Lower case “d“ designates formation sand median diameter
Upper case “D” is the selected gravel median diameter
Saucier Method:The most common gravel pack design
method
Saucier Method:The most common gravel pack design
method
Gravel to Sand Size Ratio (Saucier Method)
Gravel‐pack perm
eab
ility ratio
(Eff. vs Initial)
Gravel‐pack perm
eab
ility ratio
(Eff. vs Initial)
Gravel‐sand size ratio
(D50 Gravel vs D50 Formation)
Gravel‐sand size ratio
(D50 Gravel vs D50 Formation)
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
40
COPYRIGHT
Another Example: Grain Size Distribution Sieve Analysis
Sieve Size Opening – inches (mm)
U.S. Sieve Number
.08(2.54) (2.03) (1.52) (1.02) (0.51) (0.25) (0.203) (0.152) (0.102) (0.051) (0.025)
U.S. Sieve Number
Other Examples: Grain Size Distribution Sieve Analyses
Bailed Sample
Core Barrel Sample
Produced Sample
(2.54 mm) (0.254 mm) (0.0254 mm)
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
41
COPYRIGHT
Grain Size Comparison Analyses at Various Depths –Same Well
Grain Diameter (mm)
Grain Diameter US Mesh Size
Obtain a good description of the formation sand grain sizedistribution
Select gravel size based on the formation sand grain sizedistribution
Select screen based on smallest gravel range
Summary Review: Gravel Pack Design – 3 Steps
• 50% cumulative grain size x 6 for gravel pack• 50% cumulative grain size x 8 for frac pack
• Design screen opening as:− 75% of the diameter of the smallest gravel range size
− This size retains gravel in place behind screen
1
2
3
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
42
COPYRIGHT
Gravel Pack Rules of Thumb
Gravel to Sand Size Ratio• Use a gravel size as large as possible; the sand must be retained
at the outer edge of the pack• The size of the gravel is usually 6 times the size of the formation
sand at D50 or D40 (many other sizing techniques have beenreported in the literature)
• For frac packs, multiply the median by 8 instead of 6• Pay more attention to smaller sand grain sizes with:
– Non-uniform sands
– Higher flow velocity– Fluctuating flow rates
– High gas oil ratios
Again – Sorting Coefficient Defined as
Cs = d10 / d95
24© 2010 PetroSkills, LLC. All rights reserved. 24
Other Relevant Reservoir Criteria
How Does Degree of Sorting Affect Gravel Sizing?
May Require Smaller Gravel Size if Highly Non-Uniform
Fines % of particles smaller than 44 μm (0.00173 in.)
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
43
COPYRIGHT
Gravel Placement Fluid
Gravel can be placed with brines or polymer fluids
Super-clean fluid essential (especially for brines)• No solids• Most open hole pack failures result from surface solids (dirty fluid /
brine / polymer tanks)
Properly hydrate the polymer fluid• Shear properly; permit no “fisheyes”
Problems• Viscosity and fluid loss control• Density
Key is achieving a tight pack
How is the gravel actually placed in the well?How is the gravel actually placed in the well?
Polymers as Carrying Fluid
Three different polymer concentrations providing a wide range ofviscosities
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
44
COPYRIGHT
Polymer (HEC) Mixing Procedure (per bbl fluid)
Use fresh water or 2-5% KCl or NH4Cl in water
Lower the pH to 3-5 with citric acid [0.25 - 0.33 lbs (0.11 - 0.15 kg)]
Disperse 1.5 - 2.0 lbs (0.68 - 0.91 kg) polymer in agitated tank
Raise pH to 6-8 with caustic or soda ash
Mix at high shear rate, but avoid over-shearing• Monitor viscosity with Brookfield viscometer• And run sand suspension test• Monitor filterability – 1 quart (946 cm3) in 1-2 minutes
Filter to remove any unhydrated solids
Pre-hydrated polymers are also available
Well Site Gravel Pack Pre-Job Preparation
Onsite Gravel Pack Operations
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
45
COPYRIGHT
Polymer (HEC) Carrier Fluid Being Mixed at the Well Site
Prior to Job
Gravel Pack Pumping Equipment
Baker Hughes Sand Control Skid Mounted Frac Pack and Gravel Pack
Pumping Equipment Package
Large volume operations
Horizontal well applications
Modular for offshore or onshore jobs
Superior Energy Services Sand Control Barge Mounted Gravel Pack Pumping
Equipment Package
Rated for inland waters
Pumps: 2 x 2000 hydraulic HP / 1 x 600 HP
Sand storage / mixing tanks / sand screw feeder
Wet chemical storage / delivery
Related sand control support equipment systems
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
46
COPYRIGHT
Stimulation Vessel
Equipment SchematicCrew’s
Quarters and Wheelhouse
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Downhole Pumps –High Pressure
Proportioning Blender
Observation Deck and
Control Room
Platform Rig Up
Offshore Stimulation
Vessel
High-Pressure Discharge Line to Platform
High-Pressure Discharge Line to Offshore Vessel
Hydraulic Quick
Disconnect
High-Pressure Discharge Line to Tubing Rig
Pump
Check Valve
Radioactive Densometer
Flow Meter
Electronic Pressure
Transducers
Rig manifold to casing
Blender bypass
High-Pressure Regulating Pop-Off Valve
High-Pressure Discharge Line to annulus High-Pressure
Regulating Pop-Off ValveHalliburton
Lo TorcValve
Gel feed line from below dock storage
Gel feed line from below dock storage
Sand Tank
3 ½ in IF tubing with full-opening TTW valve
Dow
nhol
e P
ump
Suc
tion
and
Dis
char
ge M
anifo
ldin
g
The layout of the stimulation equipment on vessels and platforms for offshore frac pack and gravel-pack treatments is critical.
On vessels especially,horizontal and vertical weightdistribution affects the centerof gravity.
Equipment placement onplatforms is crucial forpersonnel safety and efficientworking conditions.
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
47
COPYRIGHT
Gravel Packing Position
.
.
Multi-Function Gravel Pack Packer
Crossover Tool
Packer shifted to crossoverposition
Carrier fluid and gravel arepumped down tubing andthrough tool to be placed inthe screen / perforatedcasing annulus atperforations
By job end, packer is shiftedback to producing position
Gravel Pack Equipment – Packer
Crossover open
Crossover open
Wire wrapped screen
Wire wrapped screen
GravelGravel
Port Collar, Open
Wash Pipe(Tail Pipe)
Cased Hole
Note that gravel also fills perfs
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
48
COPYRIGHT
Horizontal Well Gravel Pack Completions
Horizontal well pack gravel pack completions are quite common
Certain mechanical methods should be used for an extendedlength horizontal gravel pack
Horizontal wells allow significantly more reservoir accesscompared to vertical wells
More access results in significantly higher well productivity
Sand production is normally decreased because of lower fluidflux rates
However, sand control if often required in horizontal wells
Horizontal Well Gravel Packing
Long horizontal wells can be successfully gravel packed using:• Brine carrier fluids• Gel carrier fluids (with alternate path technology)• In cased hole mode• In open hole mode
Frac packs can also be successfully placed
Expandable Sand Screens (ESS) have been used to controlsand production
Stand-Alone Screens (SAS) can be used (no gravel pack) butonly in uniform sands
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
49
COPYRIGHT
Can completion and tight packing of the whole section be achieved in long extended length holes?
With proper design and equipment, the answer is… Yes.
Gravel Placement in Horizontal Wells with Brine
gk14.ppt
Shunt Tube Tool• Alternate slurry path• Ports every 3 ft (0.9 m)
Alternate Path Shunt Tube Configuration
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
50
COPYRIGHT
Halliburton “PetroGuard” Shunt Tube System
Use of a shunt tube in a gravel pack completion is referred to as alternate path technology to mitigate incomplete annulus gravel packing
Two transport shunt tubes deliver slurry along the well and shunttube path
Two packing shunt tubes are separately connected from tubingjoint to tubing joint
Along the shunt tubes are exit ports for fluid slurry to leave theshunt tubes
Gravel Exit Port
Packing Shunt Tubes Transport Shunt Tubes
Horizontal Well and Multi-Zone Gravel Pack
Alternate path technologies allow gravelpacking of horizontal wells using gelcarrier fluids
Zonal packing is also aided by shunt tubes
from: Schlumberger
Gravel Pack Equipment Tool String
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
51
COPYRIGHT
Sources of Gravel Packing Problems
Formation sand mixed withshale layers
Damage from drilling fluidinvasion
Dirty gravel placement fluids
Improper gravel size
(1) Case Study: An engineer’s first gravel pack with complete responsibility for the job resulted in a total failure requiring pulling all G.P. equipment out of the hole, a cleaning out of the well, and the re-running of the entire completion. The failure was due to dirty tanks (even though a rigorous Clean Tanks spec was included in the gravel pack completion program) which picked up huge amounts of trash. The rig tried to pump it all downhole. This has not happened to the engineer ever since. All tanks are inspected!!
Insufficiently packed perforationsplugged by formation particles
Gravel crushed or mixed with formationsand
Dirty brine(1)
Solids InvasionSolids Invasion
Filtrate invasionFiltrate invasion
Improper perforation packing
Improper perforation packing
Crushed zoneCrushed zone
Importance of Clean Tubulars and GP Equipment
Clean tubing before setting packer (pickle tubing)
Apply pipe dope moderately on pin only
Check that equipment is free of rust, mill scale, acidizingand cementing materials
Check that gravel pack completion equipment is not painted
Check that fluids storage containment is thoroughly cleanedbefore mixing completion fluids
• Acid• Solvent
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
52
COPYRIGHT
API RP 58 Gravel Quality Specifications
Sieve analysis• Less than 0.1% oversized and less than 2% undersized
Sphericity and Roundness• Average sphericity and roundness of 0.6
Acid solubility• Less than 1% soluble in 12/3 HCl-HF mud acid
Silt and Clay Content• Turbidity NTU reading lower than 250
Crush resistance• Less than 2% fines created by 2,000 psi (13,790 kPa) confining stress
Gravel Pack Quality Control
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
53
COPYRIGHT
Learning Objectives
This section has covered the following learning objectives:
Describe the principles of sand control screen and gravelcompletions
Identify the three steps comprising a gravel pack completiondesign
Describe various fluid options for pumping gravel slurry into agravel pack completion
Outline the function of a gravel pack “crossover tool”
Outline the function of a gravel pack “shunt tube”
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
54
COPYRIGHT
Frac Pack for Sand Control
Sand Control Core
Learning Objectives
This section will cover the following learning objectives:
Describe the function of a frac pack completion
Outline the frac pack completion well performance results
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
55
COPYRIGHT
Frac Pack Completions
Gravel pack screencompletion equipment inplace
Gravel / proppant pumpedto fill fracture created
Completion properties are:• Enhanced rate and sand
protection control
Fracture completion andgravel pack completioncombined
Highest end completionthat can be designedallowing for both fractureproductivity and protectionagainst sand production asa gravel pack
Frac Pack – Sand Control with Well Stimulation
Conventional cased hole gravel packs often result in low well productivity, i.e., a high skin.
A technique was developed to place short, wide fractures A technique was developed to place short, wide fractures in cased holes, followed by a gravel pack in the annular space.
Typical frac wing lengths are from 30 - 150 ft (9 – 46 m).
Typical fracture widths at the wellbore are 2 - 3 in (51-76 mm).
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
56
COPYRIGHT
Well drainage radius
Frac pack half length
Frac Pack for Sand Control
Top view of a well with a frac pack placed through the damaged zone
Wellbore damaged zone
Fracture has proppant with designed conductivity
Frac Pack Results
Typical skin value for fracpacked well: -2 to -3
Frac packs often result in 3 to 5 times more productioncompared to a conventional cased hole gravel pack
Longevity / gravel pack well life often very good
Fines migration is often completely eliminated
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
57
COPYRIGHT
Frac Pack of Horizontal Wells
Many operators are placing frac packs in highly deviatedand horizontal wells
Multiple frac packs may be placed in horizontal wells
Screenless Frac Pack
Wells can also be fracpacked without screens
Usually resin-coated proppant will be used to hold the proppantinside the fracture (to prevent proppant flowback)
Alternatively, resin can be pumped into the proppant at the endof the job
Some early failures have occurred with screenless frac packs,while other operators have had good successes
One major advantage is that the wellbore is left fully open for alarger flowpath
Not as common as standard frac pack completions
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
58
With multiple frac packs, well productivities are very high
COPYRIGHT
Learning Objectives
Describe the function of a frac pack completion
Outline frac pack completion well performance results
This section has covered the following learning objectives:
Sand Control Core═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
59
COPYRIGHT
Expandable Sand Screens
Sand Control Core
Learning Objectives
This section will cover the following learning objectives:
Outline the function of an expandable sand screen completion
Identify the components of an expandable screen and possiblebenefits resulting from the use of expandables
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
60
COPYRIGHT
ESS – Expandable Sand Screens
ESS joint and “roller” typeexpanding tool
An ESS joint consists of:• A slotted steel tube with
overlapping layers of Petroweavefilter membrane attached
• An outer layer of pre-slotted steelplate which holds and shields themembrane
Connections function well afterrecent design improvements
From: Weatherford
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
61
COPYRIGHT
ESS – Expandable Sand Screens
Remedial Sand Controlcapability – reducedworkover costs
Optimized O.D. / I.D. ratios– maximized flow conduit,minimized well costs
Reduced erosion potential
Reduced P – optimizedproductivity
Borehole stabilization
Sand Control for slimhole /slender wells
From: Weatherford
Example shown:6" (15 cm) O.D. Pre-expanded8-½" (21.6 cm) O.D. Post Expansion
Learning Objectives
Outline the function of an expandable sand screen completion
Identify the components of an expandable screen and possiblebenefits resulting from the use of expandables
This section has covered the following learning objectives:
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
62
COPYRIGHT
PetroAcademyTM Production Operations
Production Principles Core Well Performance and Nodal Analysis Fundamentals Onshore Conventional Well Completion Core Onshore Unconventional Well Completion Core Primary and Remedial Cementing Core Perforating Core Rod, PCP, Jet Pump and Plunger Lift Core Reciprocating Rod Pump Fundamentals Gas Lift and ESP Pump Core Gas Lift Fundamentals ESP Fundamentals Formation Damage and Matrix Stimulation Core Formation Damage and Matrix Acidizing Fundamentals Flow Assurance and Production Chemistry Core Sand Control Core Sand Control Fundamentals Hydraulic Fracturing Core Production Problem Diagnosis Core Production Logging Core Production Logging Fundamentals
Sand Control Core ═════════════════════════════════════════════════════════════════════════
© PetroSkills, LLC. All rights reserved._____________________________________________________________________________________________
63
COPYRIGHT