72
... .. ... .. .. .. .. - - .. ... .. - .. .. - .. - - .. .. -. VIL-N 002 Fal se ARYCOfI3Y RECONNAI SSANCE STUDY OF ENERGY REQU I REMENTS AND ALTERNATIVES PROPERTY OF: aska Power Authority 334 W. 5th Ave. FOR A chorage, 99501 PASS ANIAK ATKA MEKORYUK CHEFORNAK NEWTOK CHIGNIK LAKE NIGHTMUTE COLD BAY NIKOLSKI FALSE PASS ST. GEORGE HOOPER BAY ST. MARYS IVANOF BAY ST. PAUL KOTLIK TOKSOOK BAY LOWER AND TUNUNAK UPPER KALSKAG PREPARED BY NORTHERN TECHN ICAl SERVICES a VAN GUllK AND ASSOCIATES ANCHORAGE, ALASKA ___ ALASKA POWER AUTHORITY __

~. VIL-N ~. .. Fal se ARYCOfI3Yakenergyinventory.org/hyd/SSH-1982-0012.pdf · hooper bay st. marys ivanof bay st. paul kotlik toksook bay lower and tununak upper kalskag prepared

  • Upload
    hakhue

  • View
    217

  • Download
    2

Embed Size (px)

Citation preview

~.

~".

... ~111 .. ... .. ..

..

.. --.. ...

.. -.. .. -.. --.. .. -.

VIL-N 002

Fal se ARYCOfI3Y RECONNAI SSANCE STUDY

OF ENERGY REQU I REMENTS

AND ALTERNATIVES

PROPERTY OF: aska Power Authority

334 W. 5th Ave.

FOR

A chorage, Alask~ 99501 '--44------~--~LSE PASS

ANIAK ATKA MEKORYUK

CHEFORNAK NEWTOK

CHIGNIK LAKE NIGHTMUTE

COLD BAY NIKOLSKI

FALSE PASS ST. GEORGE

HOOPER BAY ST. MARYS

IVANOF BAY ST. PAUL

KOTLIK TOKSOOK BAY

LOWER AND TUNUNAK UPPER KALSKAG

PREPARED BY

NORTHERN TECHN ICAl SERVICES

a VAN GUllK AND ASSOCIATES

ANCHORAGE, ALASKA

___ ALASKA POWER AUTHORITY __ ~

FALSE PASS ,

RECONNAISSANCE STUDY OF ENERGY REQUIREMENTS AND ALTERNATIVES

A Report

by

Northern Technical Services

Van Gulik and Associates

Anchorage, Alaska

July, 1982

,.,.

TABLE OF CONTENTS

1.0 Summary and Recommendations

2.0 Background

3.0 Village Meeting

4.0 Existing Heating and Electrical Power Generating Facilities 4.1 Bulk Fuel Storage and Heating Appliances 4.2 Electrical Generation Facilities 4.3 Fuel Oil Usage 4.4 Electrical Energy Distribution

5.0 Energy Balance

1.1

2. 1

3. 1

4. 1 4. 1 4.1 4. 1 4.2

5.1

6.0 Energy Forecasts 6.1 6.1 Population Projection 6.1 6.2 Capital Projects 6.1 6.3 Thermal Energy Projection 6.2 6.4 Electrical Energy and Peak Demand Projection 6.3

7.0 Energy Resource Assessment

8.0 Energy Plans 8.1 Base Case 8.2 Alternate plan A 8.3 Alternate Plan B

9.0 Analysis of Alternatives and Recommendations

Appendix

Review letters and replies

i

7.1

8.1 8.1 8.6 8.12

9.1

LIST OF TABLES

Table 5.1 Energy Balance for 1982

Table 8.1 Itemized Present Worth Analysis of the Base Case

Table 8.2 Estimated Heat Recovery Costs

Table 8.3 Itemized Present Worth Analysis of Alternate Plan A

Table 8.4 Itemized Estimated Cost to Install a Hydroelectric System

Table 8.5 Itemized Present Worth Analysis of Alternate Plan B

Table 9.1 Summary of the Present Worth Analysis and Any Non-electric Benefits for Each Energy Plan

Table 9.2 Direct Power Generation Costs for Each Energy Plan

Table 9.3 Preference Ranking of Village Energy Plans and Associated Recommended Actions

II

5.2

8.3

8.7

8.9

8.13

8.15

9.1

9.2

9.3

• • • -• • • • • .. .. • • • • • -• .. • • • • .. .. • • --• • • --

LIST OF FIGURES

Figure 2.1 Location Map

Figure 2.2 Climatic Background

Figure 4.1 Bulk Fuel Storage Capacities and Types of Heating Appliances

Figure 4.2 Electrical Generation Facilities

Figure 4.3 Fuel Oil Usage

Figure 4.4 Electrical Generation Sector Energy Distribution

Figure 5.1 Energy Flow Diagram

Figure 5.2 Distribution of Total Useable Energy

Figure 6.1 Population Projection

Figure 6.2 Thermal Energy Projection

Figure 6.3 Peak Demand and Electrical Energy Projection

Figure 7.1 Appropriate Technology Ranking Diagram

iii

2.2

2.4

4.3

4.4

4.5

4.6

5.3

5.4

6.4

6.4

6.5

7.5

1.0 SUMMARY OF FINDINGS AND RECOMMENDATIONS

The production of electricity is the focus of the Energy

Reconnaissance Program. This study has focused on seeking

potential alternatives to diesel powered electrical generators.

However, wherl' there were opportunities to reduce the cost of

electrical ge leration, these were detailed. False Pass is one

of a few vill,:ges ~hich does not have a central electrical

generation facility. ]n order to establish a basis for

comparison between energy plans a central generation system was

designed and used as the base case.

There is potential for a hydro electric generation station at

False Pass and a plan to develop this resource was compared to

the central generation base case and the base case scenario

complemented by waste heat capture.

Summary Statements

Only those technologies that could be readily assimilated

into False Pass were considered.

1. Fuel oil was found to be the major source of energy

used in the village. Additional energy was supplied

by wood and gasoline.

2. Significant amounts of energy are lost in the village

due to: (1) ineffici~nt combustion; (2) poor

insulation and excessjve air infiltration; and (3)

wasted heat from diesel electric generation.

3. Forecasts show an inevitable increase in energy

consumption in the village due to population growth.

1.1

4. Energy resource baseline data is generally weak in the

village. This weakens the accuracy of technological

or economic predictions. However, the estimates

relative to waste heat availability appear reasonably

reliable.

• • • • • • • • •

5. T~e feasibility of various technologies for electrical _

6.

7.

and thermal energy production were evaluated. Wind,

coal, peat, geothermal, wood and solar were considered

as potential energy resources but are not viable

alternatives to fuel oil generated electricity. Waste

heat capture from the anticipated central power plant

and hydropower were the basis of the alternative

energy plans.

The Base Case Plan was formulated based on the

anticipated use of centrally generated electric

power.

A present worth analysis of each alternative plan was

performed.

General Recommendations

1. The supporting energy and resource data base should be

strengthened.

2. New technologies, and advances in old technologies,

need demonstration projects to determine their

feasibility in rural Alaska.

3. Significant energy savings could be realized by a

village-wide energy conservation and weatherization

program.

1.2

• • • • • .. • .. • .. • .. • .. • • •

• • • • • • .. • •

vi llage :~peci f ic Recommendat ions

1. The installation of the central diesel electric power

station is recommended. This will provide a source of

economical, reliable electric power for the village.

2. Waste heat recovery from the anticipated central power

plant, utilized for space heating in the village is

marginally economically feasible. Further detailed

analysis of feasibility should be done once the

central power plant is operational.

3. Hydroelectric power generation was considered but

found to be economically unattractive.

4. The following steps should be taken:

a. Initiate design of a central power plant.

b. Initiate feasibility study of waste heat

recovery.

1.3

2.0 BACKGROUND

Introduction

False Pass was established in 1918 by P. E. Harris Co. as a

salmon fishing and processing site. The community has

always been directly involved in the fishing industry. The

P.E. Harris Cannery was purchased by Bristol Bay Native

·Corporation in 1975 and renamed Peter Pan Seafoods. The

complex w~s sold after the processing plant burned in 1981.

There is no indication from the present owners as to

whether it will be rebuilt.

False Pass receives barge service from three shipping

companies, Western Pioneer Lines, Alaska Marine Shipping,

and the Alaska Standard. Because of the weather, air

travel is unpredictable year round. Charter flights are

available from Peninsula Airways.

The village consists of 16 wood frame houses. There is an

average of 3.5 person per household. The ground is quite

marshy so most homes are built on pilings. The older

houses have little or no insulation. The cannery

bunkhouse, mess hall, hotel, clinic and laundry now receive

only intermittent use. The school, owned by the State, and

the community building are the only public facilities. The

school, serving 15 students, is a member of the Aleutian

Region School District.

Location

The unincorporated village of False Pass lies on the east­

ern side of Unimak Island overlooking the Isanotski Strait

which connects the Gulf of Alaska and the Bering Sea (Figure

2.1). False Pass is 635 miles southwest of Anchorage and

2.1

KEY

1 KOTLIK 2 SAINT MARYS

:3 KALSKAG

4 ANIAK

5 LOWER KALSKAG

6 NEWTOK

7 NIGHTMUTE

8 CHEFORNAK

9 MEKORYUK 10 TOKSOOK BAY

II TUNUNAK

12 HOOPER BAY

1:3 CHIGNIK LAGOON 14 CHIGNIK

15 IVANOF BAY

16 FALSE PASS 17 COLD BAY

I\.) 18 [IIIKOLSKI

I\.) 19 ATKA

20 ST. PAUL

21 ST. GEORGE

. , I • • • I. I I '1 •

- ~

I I / ,

I

"/

. . , " :12 HOOPER

j i i

Ii

s •

r ' .... ~'......, ,

.~---_~ __ ,_' - .. ~." ., ~-.'

I 21 '_::0:::... ST P~UL 20

I

I ST. GEORGE ::::::: •. , " I -~ .. I

I I

I

... l. f U I

--

"

... 2..-==::JI_-==O_-=== •• O_-=~1;;20;..-=~';;80;..-==~2;4;;.O _0::==';,00 "II. .. £S

Figure 2, I

LOCATION MAP

I I • • I • • • I I I • • •

" I .-'. I

ri l '-

\" " ~ - .'

. ,. , "

I • , . r I I •

35 miles west of Cold Bay. Unimak iE: the largest and first

island of the Aleutian Chain.

Climate

The island topography includes mountains rising to 10,000

feet, broad glacial valleys, low swampy areas, meandering

streams and several active volcanoes, all within 25 miles

of False Pass. The village is located on a flat beach and

outwash plain of an unnamed stream wtich drains a broad

glacial valley.

Climatic data is not recorded routinely at False Pass, but

records from neighboring Cold Bay are considered

representative of the area (Figure 2.2). The maritime

climate of False Pass is characterized by mild winters and

cool summers.

The mean summer temperature is 55°F and the mean winter

temperature is 12°F. The temperature extremes are a

maximum of 78° and a minimum of minus 13°F. Annual

precipitation is approximately 33 inches. There are

approximately 9,865 heating degree days at False Pass.

Strong winds are common at False Pass. There may be

considerable differences between wind speeds and direction

at the village site and those at Cold Bay because of

differences in topography. Local topography suggests the

winds would be extremely gusty and turbulent, precluding

their use for wind generated electricity.

2.3

Source:

Climatic Background

I I I I ' I I ' I ' I I J':'~, I FI t:! ,MAti I API! I MAY JUN: JUL AUG: S£P' OCT; NOV: DEC

.. ' Li ht Condltio"'n"s:....-__ ------() ,t • ~ " .. I l

: j. ,~t"~ 111j ~ t..) -i j,nrludel ,.v,1 r .... '.,Qht'

I 1 Ii·'

oL-__ L-~ __ -L __ L-~~~~~~~~ __ ~ __ ~~

30rVV~in~d~s~-r _ _rM~.~.~n~W~,~"~d~'~P.:c.~d~/~P~,.~.~.~,~',~n~._d~i,r.~'~.'~o~n~~

::0 20 :-S5ei s5' l-sSEt-Nw f 5'_):5'.) =5SEj 5Et

551-! wSW I S5E ; NNW

§.o ~=t=t=~--=j--r~I-- ~+.-~--+----j

100~-~~~~~--~-.-_.-~-~-_r-_r----~ '- \''''~d-''', k.no,'_' _1. ~~, \ __

, ,GO rH-"e:..;a-'t.;.;.in'""---'D:..;e::..;g"-r.;:.ee"--'D::;.=.ay!....s=--__ ..,..... ___ -r __ ...,...._~----~

-' \ r(.r;

-~---- j I

-I ,:,1('

250

'-1AR' APR! MAV: JUN ! )Ul ; AUG: Sf" ocr: NOV DEC

Department of Community and Regional Affairs, Community Profile Series.

Figure 2.2

• • .. -• • • -• • • • • -• • .. -• • • .. .. • .. • • -• • • • .. • till

• • •

Population

The population of False Pass has been related to the

salmon can,lery which is the economic mainstay of the

village. 'rhere were 170 seasonal employees in 1981. The

growth ratf~ is expected to decrease if the cannery is not

rebuil t.

r------

Census Year 1920 1939 1950 1960 1970 1980

Population 59 88 42 41 62 65

Number of douses 16

Economy

The village economy has always been based on the salmon

industry and subsistence hunting and fishing. The village

is located wholly within the Aleutian National Wildlife

Refuge and wildlife is diverse and abundant.

Several residents own commercial boats which are moored

either at False Pass or King Cove. A few residents are

engaged in the crabbing industry. The school employs two

teachers. The post office and cannery store are combined to

provide a permanent position for the store employees. The

cannery also requires a year round caretaker.

The 1978 census estimated the per capita income as $11,420.

False Pass is associated with the Aleut Regional

Corporation. The local profit making organization is the

False Pass Corporation.

2.5

3.0 VILLAGE VISIT

Poor weather condition delayed many attempts to reach the

village of False Pass from Cold Bay. Weat:ler conditions

were favorable on December 1st and the field team was able

to reach the village. Many attempts at radio and telephone

communication prior to the visit were unsuccessful.

The majority of the villagers were out hun:ing because of

the improved weather. At a meetings with :he villagers the

Energy Reconnaissance Program was explainej and discussions

soon focused on the recent fire at the cannery (March 8,

1981). The villagers were concerned that there were no

known plans to rebuild the cannery.

At present there is no central electrical generation

facility at False Pass. The villagers were hoping that

such a facility would be installed in the near future.

The majority of the villagers work at the canneries in

Chignik, Kodiak and Bristol Bay; however many w,:>uld prefer

to work in the village.

Although the Corps of Engineers has determined that

hydropower is not feasible at False Pass. it appeared that

there might be opportunities for a more restricted

development just to supply the villagers' needs.

Wind power is a source of interest in all villages althouqh

there are severe doubts about its reliability, especially

in light of all the widely reported problems at Nelson

Lagoon.

3.1

Several residents expressed interest in the State

assistance programs for weatherization. Because of

rapidly climbing costs of fuel oil for residential

weatherization was seen as a necessary first step.

3.2

heating

• • • • • .. • • • • • • • • .. .. • -• .. • ... • .. • • • -• .. • .. • • • • • •

4.0 EXISTING HEATING AND ELECTRICAL POWER GENERATING FACILITIES

4.1 Bulk Fuel Storage and Heating Appliances

Bulk fuel storage capacity within the village is

listed, segregated by sector, in Figure 4.1. These

capacities are based on actual tank sizes and on

estimates where reliable data could not be obtained.

The storage capacity of domestic fuel tanks and 55

gallon drums is not included in the bulk storage

capacities.

Also listed in Figure 4.1 are the types of heating and

cooking appliances, segregated by sector, being used

in the village.

4.2 Electrical Generation Facilities

The existing generating equipment installed in the

village is listed in Figure 4.2. Comments on the

operation of the generators are included.

The anticipated generation equipment for a central

power plant is also listed on Figure 4.2. Once the

central power plant becomes operational the individual

generators now used would be disconnected or used for

back up.

4.3 Fuel Oil Usage

Figure 4.3 illustrates the use of fuel oil in the

village. Consumption of fuel oil by sector for space

heating is listed as a percentage of the total oil

consumption. Similarly, the percentage of oil used

for electrical power generation is shown.

4.1

The oil used for space heating is broken down to show

the portion that actually heats building space, and

that which is lost to waste. The electrical

generation fuel oil is also separated into electrical

energy and waste heat segments.

Fuel oil consumption in the village was based on

records, where avilable, and calculated estimates

where no reliable records existed. Please refer to

the main report for an explanation of the estimating

process.

The fuel oil consumption for electrical power

generation was based on an anticipated central

electrical power plant, with the generating equipment

listed in Figure 4.2.

4.4 Electrical Energy Distribution

The energy flow through the electrical generation

sector is depicted graphically on Figure 4.4. The

"pie-chart" represents the total energy dedicated to

the geneLation of electrical power. Each sector in

the village consumes a slice of the pie, as shown.

4.2

• • • • • • • .. • -• .. • • • -• -• • •

• • • .. •

• .. • • • • • ...

FALSE PASS/1982

BULK FUEL STORAGE CAPACITIES AND TYPES OF HEATING APPLIANCES

SECTOR

RESIDENTIAL COMMERCIAL SCHOOLS PUBLIC ELECTRICAL GENERAT ION

** * FUEL OIL w <.!),...

275000 <tCf) 20000 a: J 0<

GASOLINE t-e U)

45000

TYPE OF HEATING APPLIANCE 1,4 1,3 1,3 3 w

LEGEND: TYPE OF HEATING APPLIANCE

OIL - FIRED FORCED AIR FURNACE

2 OIL - FIRED BOILER WITH WATER/GLYCOL DISTRIBUTION

3 DR:r - TYPE OIL STOVE/FUh;~t,C;E

4 WOOD STOVE

5 PROPANE COOKING STOVES

6 WASTE HEAT FROM GENERATORS

*DAY TANKS AND FUEL DRUMS ARE NOT INCLUDED.

** Anticipated central generation storage

Figure 4.1

NO. OF OWNER UNITS

School 1

Village Residents 10 Est.

Proposed Central 2 Electrici ty Generation Facility 1

, . , . " , . , .

ElECTR ICAl GENERAT ION FACILITIES

GENERATOR OUTPUT RAT ING

20 KW

3-7 KW

50 KW

30 KW

, I I •

Fl\LSE PASS

TYPE OF TYPE OF ENGINE GENERATOR

Kato

Various Various

, , Figure 4.2 ,. ,. ..

ELECTRICAL DISTRIBUTION

l20/240V

l20/240V

7200V

f, , .

COMMENTS ON OPERATION

Engine is in poor condi tion. Scheol may get pov.:er f rO!T. t:le Peter Pann Cannery in .. the no:! r future.

.

Cen tral power system would repl ace individual generators. Those listed above would serve as indi-vidual emergency backup. cyp ical operation would be a single 50 KI'i unit, with the 30 KW unit used at night.

,

, ,

I • • • I. • • , . I "

100

90

80

70

60

c: Q)

u 50 .... Q)

n.

40

30

20

10

o

R

C

P

S

E

FUEL OIL USAGE

FALSE PASS / 1982

SECTOR END USE

Space Heat

39%

R

------

Waste Heat

P 26%

S

Generator Waste Heat

E 28%

-------Electrici ty

7%

Residential 50

Commercial 0

Publ i c 5

School 10

Electrical Power 35 Generation

%

%

%

"/0

%

ESTn.1ATED FUEL OIL USE = 37200 GAL = 5020xl06

BTU

Figure 4.3

4.5

~ LEC TR I CAL GENERAT ION SECTOR

ENERGY DISTRIBUTION

FALSE PASS

p

G

H

R Residential 12 %

C Commercial o %

P Public 2 0/0

S School 3 0/0

H Waste Heat 81 0/0

G Generation Losses 2 %

TOTAL ENERGY 1740 x 10 BTU/YEAR

TOTAL ELECTRIC POWER 351 MWH / YEAR

Figure 4.4

4.6

• .. • • • • • .. • .. • • .. • • • -• .. • -• .. •

• .. • • • • .. .. • .. • ..

5.0 ENERGY BALANCE

The estimated energy consumption in False Pass during 1982

is listed in Table 5.1. Estimates of the different types

of energy consumed by the various sectors are based upon

the 1980-81 fuel purchase records kept by the cannery

store and the school. Estimates based on the population,

square footage of residences and other buildings, and

calculated energy usage factors, were used where data were

incomplete. Wood use ~as estimated using the observations

and discussions with wood users that occurred during the

village visit.

The flow of energy through the village is illustrated in

Figure 5.1. In 1982 it is estimated that 7,774 MMBTU of

fuel will enter False Pass in the form of gasoline, wood

and fuel oil. This fuel will be distributed to the various

sectors and used for transportation, cooking, heating and

electricity generation. The conversion of the fuel to its

end use will result in 53% or 4,103 MMBTU of energy lost as

heat. 53% of this waste heat could be recovered using

conservation and waste heat recovery practices. The actual

amount of energy used by each sector is listed in the last

column of the diagram.

The 1982 projected distribution of useable energy, if a

central generation system is installed in the village, is

shown in Figure 5.2. The distribution represents the

quantity of energy that will be required by each sector

(excluding transportation) for electric lights and

appliances, water heating, space heating and cooking, and

generation station service. Percentages listed in the

figure can be multiplied by the useable energy of 12922 X

10 6 Btus to determine the projected energy requirements

for a 9articular end use in a given sector. These

projected energy requirements do not include energy

conversion losses and therefore represent the actual

quantity of energy required for each end use.

5.1

VILLl,GF: FALSE l'ASS/1982 ENERGY BALANCE

FUEL Oil GASOLINE PROPANE WOOD '//i-.S 1E TOTAL HE?;T E;JERG f

TC'T4L ELECTRICITY TCTt.L t-- E Sc..'"/-BTU BTU BTU

BTU E.Rt...2LE BTIJ 0/ SECTOR BTU BTU GAL • 10" LBS,

• 10" CORDS • 10· E::T I) A 106 ,.:)

GAL K !~ 6 0/0 MWH X 10" 0/0 x I 0 ~

'I 1815

RESIDENTIAL 18500 ,'" n (1 50 G-:t 216 62 :07 2000 2400 1200 23H 63

COMMERCIAL 0 0 0 0 0 0 0

PUBLIC 2000 270 5 12 41 12 108 54 203 6

lT1

SCHOOLS 3800 514 10 17 59 16 205 20 368 10

ElECTR ICAl 12900 GENERATION 1740 35 10 35 10 1390 903 35 1

TRANSPORTAT ION 6000 750 750 20

TOTAL 37200 5024 100 102 351 100 6000 750 107 2000 4103 2177 3672 100

*station service or distribution losses

Table 5.1

, I , , , . , . • I , . , , , I , I • • • I , , , , , . • • II , . , . • •

" _ . .0

1 C ..... til

r--I

FUEL AMOUN. ay SECFR l ________________ -L _________ _

PROPANE

FUEL OIL

(::' 0 24)

TOTAL INPUT

ENERGY

(7774)

TRANSPOR1.~ 1 ;ON

RESIDENTI.c.L

(2500;

COMMERCIAL

-lJ-

POWER GENERt.TION

(1740)

SCHOOL{S)

(514 )

PUBL I C

POP: 60 HOUSEHOLDS· 16

9,865 HTG. DEGREE DAYS

EI~ERGY

CONVERSION

TRA/';SPORTATION

COOK ING

(750)

~·----------~-----(G-C-:O--)----·-

HEATUJG <:>:<: (1400)

HEATINGI COOKING

HEAT ING

ELECTRICAL GENERATORS

HEATING/ COOKING

HEATING

(1500)

(350)

(309)

(162)

. : :.~( :: TOTAL

WASTE HEAT

:::

':::::::::::,:, 2ill::

(4103) .. ::::::::::::: .;:::;:::::::::::::::,:::::: ..

:::;::;:::::::::::::{::: .

WASTE HEAT NON - RECOVERABLE

(1926)

TRAtlSPOR rl;T IO~J

~ _____________ +-____ L~-~"~~j~ _______ _

RESIDENTIAL

(216)

COMMERCIAL

I (35 )

POWER GEN.

( 59)

(41)

RECOVERABLE WASTE HEAT

(2177)

NOTE :'

SCHOOL(S)

PUBLIC

• NUMBERS IN BRACKETS ARE

I I I

(:2 31 C)

-0-

( 35)

( 368)

(203)

TOTAL USABLE ENERGY

( 5849)

106 BTU'S.

-I I I

rrJ Z rn ::0 G)

-<

CJ

1> G)

::0 1> S

DISTRIBUTION OF

TOTAL USABLE ENERGY*

FALSE PASS WI CENTRAL GENERATION INSTALLED

-UJ (!J

« f­Z UJ o a: UJ n.

1

P W R G E N --

00

90

80

70

60

50

40

30

20

10

0

------

SECTOR

i-

r-..A

< -I-r- z

w a -

'-tI)

w a:

r-

-

-

-SCHOOL

--

PUBLIC

END USE

BY SECTOR

E(7.4%) - -- - - - - --

WH(6.2 .. ) - -- - - - ---

H/C(6S.6cr.)

--------= -'= = = = = = :-:

H/C(9.7%)

r- -=-=-= - - --:: H/C(S.Scr.)

V I---

~

,.-

P(1.2cr.)

£-:(2.0cr.)

WH(O.Scr.)

E(1.4%)

END USE SUMMARY

E LIGHTS, REFRIGERATOR/FREEZERS, 10.8 % VIDEO, AND OTHER ELECTRICAL USES

WH WATER HEATING 7.1 %

H/C SPACE HEATING, COOKING AND MISC. 80.8%

P GENERATOR STATION SERVICE/ 1.2% TRANSMISSION LOSSES

-"OTAL USABLE ENERGY = 12922 x 10 6 BTU

* DOES NOT INCLUDE ENERGY USED FOR TRANSPORTATION AND RECOVERABLE WASTE HEAT

-•

• .. • -• -•

-• • •

• .. • .. • ..

• • • .. • ..

6.0 ENERGY FORECASTS

6.1 Population Projection

The population of False Pass was forecast for the

twenty year planning period based upon historical

population trends, expected changes resulting from

planned capital projects, and the villagers'

projections of the growth of their community.

Historical data from 1950 to 1980 approximates an

average annual growth rate of 2%. Capital projects

that would increase the current rate of growth are not

planned at this time, therefore, a 2% growth rate was

used in the projection.

Historical and projected populations are listed below.

Figure 6.1 illustrates the population projection over

the 20 year planning period.

Historical

1950 1960 1970 1980

42 41 62 65

6.2 Capital Projects Forecast

Projected

1990 2000 2010

75 8d 102

~s far as can be determined, no major capital

projects are imminent at False Pass. No details could

be obtained over the future of the cannery site.

Although the villagers would prefer to see the

facility rebuilt, the owners are undecided.

The State Department of Transportation proposes to

repair the runway but this will not have an effect on

6.1

the electrical or thermal energy requirements of the

community.

Some potential capital projects mentioned during the

village visit are as follows:

Airport

Schools

Cannery

The State Department of Transportation

plans to repair the runway to its full

3900 length.

The school plans to buy electrical power

from the Peter Pan Cannery as soon as

the cannery installs an additional

generator. The school will then operate

its current generator as backup.

Some of the cannery buildings burned in

March 1981. Plans are indefinite as to

whether or not these will be rebuilt and

operated in the future. Current cannery

plans are to install a 75 KW generator

to service remaining cannery building

needs and provide power for the school.

6.3 Thermal Energy Projection

Figure 6.2 presents the anticipated thermal energy

consumption of False Pass during the forecast period.

The thermal energy is provided by the combustion of

fuel oil and wood.

The proje~tions were based on fuel usage records, and

fuel use estimates, of the facilities in False Pass.

Details of the estimation methods and calculations are

6.2

• • .. • .. • .. .,

• .. .. • • • • .. •

.. -.. •

.. --.. .. .. -•

• -•

inc luded in the Jl1ain report.

6.4 Ele~trical Energy and Peak Demand Projection

Fig~re 6.3 presents the anticipated electrical

enecgy consumption of False Pass, by sector, during

the forecast period. The projections were based on

the existing electrical loads, consumption records,

and estimates where accurate data were not available.

Det~ils of the estimation methods and calculations are

included in the main report.

6.3

A

:J I-m 'Z L: '-'

>-C) 0::: w z W

-1 < :z r::r w I I-

z a

POPULATION PROJECTION FALSE PASS

10~.------------------------------------------------,

g"

H 8(3 I-< -l :J Q 7~ a Q

60

seL-~·-L~--~-L~--~~~--~~--L~--~~~--~~~

1982 1984 1986 1988 199~ 1992 1994 1996 1998 20~~

YEAR

Figure 6.1

TH~RMAL ENERGY PROJECTION FALSE PASS

4~3Jr------------------------------------------------,

3Sp.e

3ee~

2S~~

2~~~~~~~--~~~--~~~--~~~~--~~~--~~-J

1932 1~o4 198~ 1982 1992 19~2 1994 1996 199~ 2~~~

':' =:,.A,R

Figure 6.2

6.4

• -• .. • .. • • • .' •

• -• -.. • . ' .. • -• -•

• -• • • -• -• •

,.... =-~ '-'

Cl Z -< :::E L.1.J Cl

~ -< L.1.J D...

-1 c::: <0 Ur­....... U c::: w r-Ui U w>­-.Jrn W

PEAK DEMAND PROJECTION FALSE PASS

7(3

63

S0

4(1

313 1982 1984 1986 1988 lSOla 1992 1994 19a6 199a 222B

YEAR

ELECTRICAL ENERGY PROJECTION FALSE PASS

175~----------------------------------------------~

153

125

t Hl0

75 ~--~~~--~--~--~~~--~~~~~~~~

125~----------------------------------------------~

75 . . .

52

. . . . . . . . . ...

. . . . . . . . . . . .

...

25 __________ Sp~ __ _ -------- - ~

r C-· .. -... -... -.... -. " .-. '.' . 'G~' .•

1932 199~ 1925 1989 19~:m 1992 199~ 1995 1998 2CC2

YEAR G = Electrical Generation Sector C = Commercial P = Public S = Schools R = Residential

Figure 6.3

6.5

7.0 ENERGY RESOURCE ASSESSMENT

Wind

False Pass is protected on the east and west sides by steep

mountain ranges. It is suspected that these mountains

cause turbulent, unsteady winds much of the year. Long

term wind data must be gathered before the feasilibity of

wind power in False Pass could be judged.

Wood

There are no trees at False Pass, but a small amount of

driftwood is gathered by village residents for home

heating. The use of driftwood for fuel in a central power

station would require high gathering cost and would not be

viable for power generation.

Coal

No coal deposits have been identified near False Pass.

Transportation charges to bring in coal from Anchorage are

high.

Peat

The Island of Unimak has large reserves of low quality

peat. The peat is not considered fuel quality due to the

high content of volcanic ash.

7.1

Geothermal

A small warm spring is located 1 mile west of the village.

The great distance from the hot springs and the

unpredictable changes in a volcanic area make development

of geothermal energy not feasible.

Solar

The sky has an average of 9/10 cloud cover every day of the

year. The low occurrence of cloud free days and low

intensity of radiation make even passive solar heating

unfeasible.

Hydropower

Although precipitation sustains a number of small streams

throughout the year, none of the streams have reasonable

potential for adequate hydroelectric generation.

A Corps of Engineers study completed in 1981 identified

potential hydroelectric power sites in the vicinity of

False Pass.

Alternate Plan B investigates the potential for hydro power

on the stream that is 3 miles west of the village.

7.2

.,

.,

., • • ., .,

-• -., -., ., .. .. • .. • -• -• • ., .. .,

-., -., -.,

.. ..

Conservation Measures

Waste Heat Capture

The majority of the energy in the fuel oil burned in a

diesel generator is lost as waste heat through the engine

cooling water, exhaust gases, and radiant heat from the

engine. Much of the waste heat can be reclaimed from the

engine cooling water and exhaust gas by transferring the

heat in heat exchangers to a secondary fluid, usually an

antifreeze solution. This is then pumped to buildings and

used in heaters for space heating.

Alternate Plan A, detailed in Section 8.2 of this report,

investigates the feasibility of waste heat recovery at

False Pass.

Weatherization

Homes and buildings built on the Alaska Peninsula in the

past have in general been poorly insulated and weatherized.

Heat loss from such buildings is high, in the forms of heat

Joss directly through the walls, floor, and ceiling, and by

the cold air that enters around leaky doors and windows.

Insulating and weatherizing a home can often cut the

heating fuel requirement in half or more, and make the

building more comfortable and liveable at the same time.

The materials required are inexpensive, and the skills

necessary for installation low. This work is perhaps the

most effective way of reducing village energy usage.

7.3

Technology Ranking

Figure 7.1 presents a ranking of the technologi?s that

could be applied to the village. Each technology was

examined on the basis of state-of-the-art quality of the

technology, cost, n~liability, resource, labor, and

environmental impact. Please refer to the main report for

the ranking methodology.

7.4

• • • .. • • • • • • • • • • • • .. -• • • • • • • • • .. .. .. • • • • • • • •

.....,J

Ul

T",chnology State-of-the-Art

h"eatherization* 5

Diesel Power 5

h"aste Heat Recovery* 5

Hydroelectric Power 5

Wind Energy Conversion 3 Systems

Geothermal Energy 3

Steam Power from local N!A fuel,wood,coal,ect ...

Gasification of wood,coal N/A or peat

Generation via synchronous IndlJe"t- i on* 4

Electrical Load Management* 5

* Energy Conservation Measures

Note: 0 = worst case, 5 = best case

Village of Fals0 Pass

Relia- I Re,ou,ce i i Environ- Rar.kinq

Cost bility Labor mental Factor Impact

5 5 ~-- 5 5 1. OC

I 4 4 4 I

4 I 4 0.87 I

4 4 4 4 4 0.87

1 4 3 4 4 0.75

3 2 3 2 5 : 0.60

1 1 1 2 3 0.38

N/A N/A 0 N/A N/A 0.00

N!A N/A 0 N/A N/A 0.00

3 2 2 1 4 0.57

2 2 3 1 4 0.68

N/A Not Applicable

Figure 7.1

8.0 ENERGY PLAN

8.1 Base Case

8.1.1 General Description

The base case plan for False Pass is to install a

central electrical generation plant.

A reconnaissance level study of the village indicated

that the centralized power system should include the

following components:

1. Two 50 KW diesel generators that would be used to

meet the major power demands.

2. A 30 KW diesel generator to be used for night and

summer time lower demands and as hackup.

3. A central power distribution systE~m operating at

7200 volts, single phase. This higher voltage

would minimize distribution loses and voltage drop

in the system through the use of step-up and step­

down transformers. Single phase power of 120/240

volts would be provided to village residents.

4. Wntt meters at the service entrance of all power

users in order to provide equitable billing for all

consumers.

5. A 12' X 20' building that would house the

generators and electrical equipment.

8.1

8.1.2 Base Case Cost Analysis

The installation cost of the anticipated central

electric power plant was estimated to be $364,000.

The cost is itemized below:

Generators and Equipment

Fuel Storage

Generator Building

Shipping

Labor

Equipment Rental

Subtotal

Engineering

Project Management

Test

Contingency

Total Estimated Cost

64,600

3,500

120,000

7,400

18,400

50,000

263,20fJ

25,200

12,600

12,600

50, 40(~

$364,000

The plant value was amortized over a 20 year period.

Additional generation capacity was added, in

increments of 50 kw, as required by the growing peak

demand. The cost of additional generation capacity

was estimated to be $1650/kw.

The cost of fuel oil was set at $9.6~/MMBTU, ba3ed on

a fuel cost of $1.30/gallon. Operatcon and

maintenance expenses were estimated dt 8~/kwh.

Table 8.1 presents the i temized pres.~nt value a r1alysis

of the base case for the 20 year study period. The

discounted 20 year present value was $1,012,400.

8.2

• .. • .. • ....

l1li' .. III'

• • .. • • • .. • • • .. • .. .. •

• .. • • • .. • • • .. • ..

co . w

DIESEL - ELECTRIC INTEREST AND AMORTIZATION FUEL OPERATION AND MAINTENANCE TOTAL

TOTAL YEARLY PLAN COST

DI~CUUNTEO ~LAN CU~T

DIESEL - ELECTRIC INTEREST AND AMORTIZATION FUEL OPERATION AND MAINTENANCE TOTAL

TOTAL YEARLY PLAN COST

DISCOUNTED PLAN COST

TOTAL YEARLY PLAN COST TOTAL DISCOUNTED PLAN COST TOTAL PLAN COST

1982 24.4 17.9 8.5

50.8

50.8

50.8

1992 29.9 29.6 10.9 70.4

70.4

52.4

1983 24.4 18.9 8.7

52.0

52.0

50.5

1993 29.9 31.0 11.1 72.1

72 .1

52.1

1982-2034 4360.0 2076.6 2076.6

1984 24.4 19.9 9.0

53.2

53.2

50.2

1994 29.9 32.6 11.4 73.9

73.9

51.8

FALSE PASS PLAN 1

BASE CASE

1985 24.4 20.9 9.2

54.5

54.5

49.9

1995 29.9 34.1 11.6 .] 5.7

75.7

51.5

Table 8.1

1986 24.4 22.0 9.4

55.9

55.9

49.6

1996 29.9 35.8 11.9 77 .6

77 .6

51. 3

1987 24.4 23.2 9.7

57.2

57.2

49.4

1997 29.9 37.5 12.1 79.6

79.6

51.1

1988 24.4 24.4 9.9

58.7

58.7

49.1

1998 29.9 39.3 12.4 81.6

81.6

50.9

1989 24.4 25.6 10.1 60.1

60.1

48.9

1999 29.9 41.2 12.6 83.8

83.8

50.7

1990 24.4 26.9 10.4 61.7

61.7

48.7

2000 29.9 43.1 12.9 86.0

86.0

50.5

1991 29.9 28.2 10.6 68.8

68.8

52.7

2001 29.9 45.2 13.2 88.3

88.3

50.4

NOTE: *** ALL VALUES IN $lOOO'e

TOTAL 549.0 597.3 2l5.5

1361.8

1361.8

1012.4

8.1.3 Social and Environmental Evaluation

Base Case Plan Summary: Operation of anticipated

central diesel generation

1) Community Preference: At the time of the village

visit there was no central generation system. The

villagers are requesting that central generation

be installed to reduce their cost of electricity

and increase its availability and reliability.

Central generation has been assumed as the base

case.

2) Environmental Considerations:

i) Air Quality: Exhausting combustion gases

releases a small amount of pollutants to the

local environment, but the impact is

minimal.

ii) Noise: The exhaust stacks from the generator

produce a considerable amount of noise. The

installation of more effective mufflers would

reduce the noise level.

iii) Water Quality: No impact.

iv) Fish and Wildlife Impacts: No known impact.

v) Terrestrial Impacts: There is no impact on

vegetation or soils.

vi) Land Use and Ownership Status: All leases

and permits are in place.

8.4

• .. ., • • .. • .. • • •

WI

• .. .. -•

.. • • • • --.. , .. , • • -• ..

8.1.4 Base Case Technical Evaluation

The anticipated operation of the centJ'al diesel

electric power plant in False Pass is expected to

conform as follows:

1. High Reliability. Diesel electric is a well

proven well understood technology with a

successful history in rural Alaska. Backup

generation allows maintenance operations on the

generators to be performed without major power

interruption. Occasional system downtime is

expected for distribution system naintenance.

2. Safety. A small risk is realized by the stora~e

and handling of fuel oil. Normal risks associated

with electrical power are also pr'~sent.

3. Availability. There are no indic~tions that spare

parts will become difficult to obtain in the

future. The availability of fuel to the power

plant depends on the reliability of transportation

to the village.

8.5

8.2 Alternate Plan A

8.2.1 General Description

The Alternate Plan A for False Pass is the

installation of a waste heat recovery system installed

at the anticipated central electric power plant, with

the following features:

1. Jacket water heat recovery equipment installed on

the two 50 KW generators.

2. A distribution system consisting of pumps, piping

and valves to deliver the ethylene glycol heat

transfer fluid to the heated buildings and return

it to the power plant.

3. Heating equipment installed in the school and

community center buildings, to provide space

heating.

4. A control system that automatically regulates the

supply of heat to the buildings, and rejects any

surplus waste heat to the engine radiators.

8.2.2 Alternate A Cost Analysis

Table 8.2 presents the itemized, estimated cost to

install the jacket water heat recovery system.

The installation cost of the heat recovery system was

estimated to be $89,500. The system value was

amortized over a 10 year period.

8.6

• .. • •

.. .. •

• •

-.. ...

• ..

-• • • • •

..

., •

ESTIMATED HEAT RECOVERY COSTS

Project Location

Generators (kw)

Estimated total kwh generated

Generators equipped with heat recovery

equipment

CALCULATED VALUES

Average Generation Rate

Percent of On-Line Capacity

Maximum Jacket water Heat Recovery

Percent Jacket Water Heat Available

Estimated Recovered Heat Available

Estimated Recovered Heat Utilized

MAJOR COST ITEMS

1. Main piping 150 feet x $120/ft.

2. Heat Recovery Equipment

3. Circulating Pumps

4. Heaters and Miscellaneous Hardware

5. Contingencies (30%)

6. Base Cost

7. Project Management (5%)

8. Engineering (10%)

9. ESTIMATED PROJECT COST

10. 0 & M COST

11. Recovery Efficiency

Table 8.2

8.7

False Pass

50,50,30

103,000 kwh/yr

50,50

12 kw

24%

3300 Btu/min

43%

.085X10 6 BtuH

.054Xl0 6 BtuH

18,000

21,700

65,200

13,700

18,000

78,000

3,900

7,800

89,500

2.11/MMBtu

4593 Btu/kwh

The cost of fuel oil normally used for space heating,

which was offset by the captured waste heat, was set

at $9.63/MMBTU, based on a fuel oil cost of

$1.30/gallon. Operation and maintenance costs were

calculated to be $2.11/MMBTU waste heat captured.

Table 8.3 presents the itemized present value

analysis of the plan, for the 20 year study

period. The discounted net benefit of the

system was $32,200.

8.2.3 Social and Environmental Evaluation

Alternate Plan A Summary: waste heat capture from

anticipated central generators for sale to major

consumers.

1) Community Preference: The villagers of False Pass

recognize that the installation of waste heat in

conjunction with a central power plant will

improve the efficiency of fuel use in the

community.

Installation of the waste heat capture system will

require local expertise and should provide a

number of jobs during the construction phase. The

system should operate with minimal maintenance

although one part time person would be required

until the system has been tested and initial minor

problems have been solved.

8.8

• • • -• WI!

• • .. • .. .. .. -.. Ilk

• • • •

• •

• •

• • III ..

DIESEL - ELECTRIC 1982 1983 !~!TEREST AND Ar10~TIZATIO~1 21.4 ?II 11 '- ~-r. I

FUEL 17.9 18.9 OPERATION AND t1AINTENANCE 8.5 8.7 TOTAL 50.8 52.0

TOTAL YEARLY PLAN COST 50.8 52.0

DISCOUNTED PLAN COST 50.8 50.5

co . \.0

NON ELECTRIC BENEFITS 1982 1983 EXTRA COSTS 0.0 0.0 BENEFITS 0.0 0.0 NET BENEFITS 0.0 0.0 DISCOUNTED-NET BENEFITS 0.0 0.0

NOTE:

1984 2~.4 19.9

9.0 53.2

53.2

50.2

1984 11.6 9.6

-2.0 -1.8

FALSE PASS PLAN 2

ALTERNATE A

1985 21.4 20.9

9.2 54.5

54.5

49.9

1985 11.6 10.1 -1.5 -1. 3

1986 1987 2~.1.l 2~.4 22.0 23.2 9.4 9.7

55.9 57.2

55.9 57.2

49.6 49.4

1986 1987 11.6 11.7 10.6 11.1 -1.0 -0.5 -0.9 -0.4

*** ALL VALUES IN $1000'5

Table 8.3

1988 1989 1990 1991 24.4 24.4 24.4 29.9 24.4 25.6 26.9 28.2 9.9 10.1 10.4 10.6

58.7 60.1 61.7 68.8

58.7 60.1 61.7 68.8

49.1 48.9 48.7 52.7

1988 1989 1990 1991 11.7 11.7 11.7 11.8 11.7 12.3 12.9 13.5 0.0 0.5 1.1 1.7 0.0 0.4 0.8 1.3

co

r-o

DIESEL - ELECTRIC INTEREST AND AMORTIZATION FUEL OPERATION AND MAINTENANCE TOTAL

TOTAL YEARLY PLAN COST

DISCOUNTED PLAN COST

o NON ELECTRI C BENEF ITS EXTRA COSTS BENEFITS NET BENEF ITS DISCOUNTED NET BENEFITS

TOTAL YEARLY PLAN COST

1992 29.9 29.6 10.9 70.4

70.4

52.4

1992 11.8 14.1 2.3 1.7

TOTAL DISCOUNTED PLAN COST TOTAL DISCOUNTED NET BENEFITS TOTAL PLAN COST

1993 29.9 31.0 11.1 72 .1

72.1

52.1

1993 11.8 14.8 3.0 2.1

1982-2034

4364.0 2076.6 143.2

1933.4

1994 29.9 32.6 11.4 73.9

73.9

51.8

1994 11.9 15.5 3.6 2.5

FALSE PASS PLAN 2

ALTERNATE A

1995 29.9 34.1 11.6 75.7

75.7

51.5

1995 11.9 16.2 4.3 2.9

1996 29.9 35.8 11.9 77 .6

77 .6

51.3

1996 11.9 17.0 5.0 3.2

Table 8.3 (continued)

1997 29.9 37.5 12.1 79.6

79.6

51.1

1997 12.0 17.8 5.8 3.6

1998 29.9 39.3 12.4 81.6

81.6

50.9

1998 12.0 18.6 6.6 4.0

1999 29.9 41.2 12.6 83.8

83.8

50.7

1999 12.0 19.5

7.4 4.4

2000 29.9 43.1 12.9 86.0

86.0

50.5

2000 12.1 20.4 8.3 4.7

2001 29.9 45.2 13 .2 38.3

38.3

50.4

2001 12.1 21. 3 9.2 5.1

NOTE: *** ALL VALUES IN $1000'5

TOTi\_ 549.C 597.3 215.5

1361.3

1361.3

1012.4

TO-:-AL 212.9 266.3 53.9 32.2

• I" w, •• ., , •• 1.1 II •• ,1.1 ., '. " I, .• ,. ••

2) Environmental Considerations:

i) Air Quality: There will be a' reduction in

fuel consumption in the village resulting in

reduced hydrocarbon, monoxi~es and nitrogen

oxide emissions.

ii) Noise Levels: No impact.

iii) Water Quality: There would be a minor impact

if a major leakage occurred in the coolant

system.

iv) Fish and Wildlife Impacts: None.

v) Terrestrial Impacts: Will be: minimal during

the installation of the distribution system

and will be restricted to the: village site.

vi) Land use and Ownership Status:: It is assumed

that the village will make the necessary . arrangements for the right of: way

requirements for the distribution system.

8.2.4 Alternate Plan A Technical Evaluation

Operation of the waste heat recovery system in False

Pass, in conjunction with the central power plant, is

expf'cted to conform to the following ekpectations: ,

1. High Reliability. The system utilizes simple, ,

reliable components that are readi1y available off

the shelf from a variety of source~ • . 2. Safety. A well maintained systeM has a very low

hazard potential.

8.11

3. Availability. All componentf needed are available

immediately. The system is lelatively easy to

implement.

8.3 Alternate B

8.3.1 General Description

The Alternate Plan B for False PiSS is to install a 40

KW hydroelectric power plant on the stream that is 3

miles to the west of the village. This stream,

identified as "Site 2 Low" in the Corps of Engineers

report, has an estimated low flo~ of 4.5 CFS. The

run-of-river project diverts streamflow through a

penstock to a turbine-generator 10wer plant. Major

features of the plan include:

o

o

o

o

o

A 40 KW turbine-generator po~er plant with a net

head of 118 feet~

A diversion structure~

2000 feet of 10 inch penstock;

16000 feet of 3-phase transmission line~

A 3 mile access road.

NOTE: See site no. 2 of the Corps of Engineers and Fish and

Wildlife Service report "Hydroelectric Development Evaluation

at False Pass, Alaska" April 1981.

8.3.2 Alternate B Cost Analysis

Table 8.4 presents the itemized cost of installing a

hydroelectric system in False Pass. The estimated

initial capital cost of the hydro system was estimated

to be $3,045,000 in 1982 dollars.

8.12

• -• • • • • .. • • • --.,

• .. -• •

-• • III -.. .. • •

ESTIMATED HYDRO COSTS*

Project Location

Average Annual Flow (cfs)

Total Head (ft)

Transmission Line Length (miles)

Road Length (miles)

CALCULATED VALUES

Net Head

Generator Unit Rating (kw)

Energy Available @ 30% Plant Factor (kwh/yr)

Penstock Diameter (inches)

MAJOR COST ITEMS

1. Power House

2. Turbines, Generators, Valves, & Switchgear

3. Diversion Structure (Earthfill dam)

4. Penstock (Buried) 2000 ft X $150/f1:

5. 'l'ransmission Line 3 mi X $900000/m:.

6. Access Road 3 mi X $500000/mi

7. Mobilization and Demobilization

8. Base Cost

9. Contingencies (25%)

10. Project Management (5%)

11. Engineering (10%)

12. ESTIMAT~D PROJECT COST

False Pass

4.5 cfs

130 ft

3 mi

3 mi

118 ft

50 kw

131,000 kwh/yr

10 in

150,000

150,000

655,000

300,000

270,000

150,000

500,000

2,175,000

544,000

109,000

217,000

3,045,000

* From Corps of Engineers Report "Hydroelectric Development

Ev~luation at False Pass, Alaska", October 1981.

Table 8.4

8.13

The hydro project is planned for completion in 1984

• • -•

and is expected to have a useful life of 50 years. In -

False Pass diesel generation will be required to

supplement hydro during periods of low flow.

Table 8.5 presents an itemized present worth analysis

of the plan for the 20 and 50 year study periods.

The discounted present worth of the plan is

$2,200,700 and $4,351,000, respectively.

8.3.3 Social and Environmental Evaluation

Alternate Plan Summary

1) Community Preference: Village interest is high

for hydro electric power as the primary

alternative to diesel. The low O&M and

reliability of the system are important

considreations. Also, there is the potential for

excess power production which would be available

for either local commercial developments or

possibly resistance heating.

Installation of a hydro facility would provide

several jobs locally during the construction phase

and a part time position for a person to operate

and maintain the system.

The community is strongly in favor of a

feasibility study to determine an accurate cost

and fully access the potential of the proposed

installation, if the preliminary reconnaissance

level study indicates that there is an economic

basis for proceeding.

8.14

.. -•

.. -.. .' ., -•

.. • • • • • ., .. • • • • •

DIESEL - ELECTRIC 1982 INTEREST AND A~10RTlZATlON 24.4 i vLL 17.9 OPERATION AND rv'AINTENANCE 8.5 TOTAL 50.8

HYDRO - ELECTRIC INTEREST AND A~10RTiZATlON 0.0 OPERATION AND ~~INTENANCE 0.0 TOTAL 0.0

co . /--'

TOTAL YEARLY PLAN COST U'1 50.8

DISCOUNTED PLAN COST 50.8

1983 1984 24.4 24.4 18.9 19.9 8.7 9.0

52.0 53.2

0.0 0.0 0.0 0.0 0.0 0.0

52.0 53.2

50.5 50.2

FAL~tANA1S ALTERNATE B

1985 1986 24.4 24.4 4.6 5.1 2.0 2.2

31.1 31.7

118.3 118.3 5.4 5.4

123.7 123.8

154.8 155.5

141.6 138.2

1987 24.4

:J • I

2.4 32.5

118.3 5.5

123.8

156.3

134.8

NOTE: *** ALL VALUES IN tl000's

Table B. 5

1988 1989 1990 1991 24.4 24.4 24.4 29.9 6.3 1.0 / . 1 8.4 2.6 2.8 3.0 3.2

33.3 34.2 35.1 41.5

118.3 118.3 118.3 118.3 5.5 5.5 5.6 5.6

123.8 123.9 123.9 123.9

157.1 158.0 159.0 165.5

131.6 128.5 125.5 126.8

co . ,.....

'"

DIESEL - ELECTRIC INTEREST AND Ar~ORTIZATION FUEL OPERATION AND MAINTENANCE TOTAL

HYDRO - ELECTRIC HJTEREST AND AMORTIZATION OPERATION AND MAINTENANCE TOTAL

TOTAL YEARLY PLAN COST

DISCOUNTED PLAN COST

TOTAL YEARLY PLAN COST TOTAL DISCOUNTED PLAN COST TOTAL PLAN COST

1992 1993 29.9 29.9 9.2 10.0 3.4 3.6

42.5 43.5

118.3 118.3 5.6 5.6

124.0 124.0

166.5 167.5

123.9 121.0

1982-2034 8869.1 4351. 0 4351. 0

1994 29.9 10.9 3.8

44.6

118.3 5.7

124.0

168.6

118.3

FALSE PASS PLAN 3

ALTERNATE B

1995 1996 29.9 29.9 11.8 12.7

4.0 4.2 45.7 46.9

118.3 118.3 5.7 5.7

124.0 124.1

169.8 171.0

115.6 113.0

1997 29.9 13.8 4.5

48.2

118.3 5.7

124.1

172.3

110.6

1998 1999 2000 2001 29.9 29.9 29.9 29.9 15.0 16.2 17.5 18.8 4.7 5.0 5.2 5.5

49.6 51.1 52.6 54.3

118.3 113.3 118.3 118.3 5.7 5.8 5.8 5.8

124.1 124.1 124.1 124.1

173.7 175.2 176.7 178.4

108.3 106.0 103.8 101. 7

NOTE: *** ALL VALUES IN $1000's

Table 8.5 (continued)

TOTAL 549.0 237.4 88.1

874.5

2011.9 95.6

2107.4

2931. 9

2200.7

II •• 11.1" 11.1'. 'I ,. 'I ,.,",., II II II ,.

2) Environmental Considerations:

i) Air Quality: There will be a slight

improvement in air quality because the

diesels will be relegated to a back up role.

ii) Noise: Levels will be almost eliminated

except when the diesels are run for testing

or when operating in their capacity as a

backup to the hydro.

iii) Water Quality: No impact.

iv) Fish and wildlife: The small diversion dam

will not have an appreciable effect, although

detailed investigation of stream use would

have to be conducted during a possible

feasibility study.

v) Terrestrial Impacts: Will be associated with

the road construction to the diversion dam

site, the diversion dam construction (assumed

to be rock crib type), the penstock route,

powerhouse and transmission line to the

village.

vi) Land Use and Land Ownership Status: The dam

site is on land administered by the Fish and

Wildlife Service. Either the village would

expand its land selections to include the

site and corridor or the necessary permission

would have to be sought from Fish and

Wildlife.

8.17

8.3.4 Alternate Plan B Technical Evaluati0n

A hydro electric power plant operating in False Pass

is expected to conform to the following:

1. Reliable. A possible power shortage could occur

if a dry season causes low flow.

2. Safety. A well maintained systen will present

little hazard to operators or viJlage residents.

3. Availability. Construction wou16 utilize

conventional well established construction

practices. Replacement parts would be

difficult to obtain at the remotE Alaska

site.

8.18

.. . ' -.. • .. .. • .. .. .' .. • .. .. .,

.,

..

.,

.. .. • • .. . ' •

9.0 ANALYSIS OF ALTERNATIVES AND RECOMMENDATIONS

Table 9.1 summarizes the village plans, the associated

present worth analysis, and any non-electric benefits.

Table 9. 1

FALSE PASS Base ternatlve Energy ource Dlese

Present Worth Non-E Tota

FALSE PASS Energy ource

9.1

Direct power generation costs, excluding administrative costs, are

presented in Table 9.2 for each energy plan.

Table 9.2

Energy Base Case Alternative A Alternative B Production Plan 1 Cost Plan 2 Cost Plan 3 Cost

Year (kwh/;r:r. ) (¢/kwh) (¢/kwh) (¢/kwh) 1982 106,100 47.88 47.88 47.88 1983 109,100 47.66 47.66 47.66 1984 112,000 47.50 49.29 47.50 1985 115,000 47.39 48.70 134.61 1986 117,900 47.41 48.26 131 .89 1987 120,900 47.31 47.73 129.28 1988 123,800 47.42 47.42 126.90 1989 126,800 47.40 47.00 124.61 1990 129,800 47.53 46.69 122.50 1991 132,800 51 .81 50.53 124.62 1992 135,800 51.84 50.14 122.61 1993 138,800 51.95 49.78 120.68 1994 141,900 52.08 49.54 118.82 1995 145,000 52.21 49.24 117.10 1996 148,200 53.36 48.99 115.38 1997 151,400 52.58 48.75 113.80 1998 154,600 52.78 48.51 112.35 1999 157,900 53.07 48.39 110.96 2000 161,200 53.35 48.20 109.62 2001 164,600 53.65 48.06 108.38

9.2

• • .. .. • .. .. -WI

• • •

.. •

-•

• • • • .. at

.,

• .. • ..

Table 9.3 presents the plans for the village, in rank of

recommended preference. The recommended Ection appropriate

to each alternative is listed as well.

Table 9.3

Energy Plan Alternative Base Case - Operation of Anticipated Central Power Plant Alternative A - Waste Heat Capture

Alternative B - Hydro Electric Power

Additional Recommendatlons Weatherization .building insulation .building envelope infiltration

.improved combustion

9.3

Recommended Actlon

Initiate a feasibility study for waste heat recovery. Estimated cost of feasibilty study $12,000 -$15,000. Th is al te}~nat ive is not considered economically feasible.

No resource assessment or feas ibil i l:y study indicated. immediate action required to bring Energy Audit and/or weatherization program to this community.

Reconnaissance studies are necessarily preliminary in nature,

however, it is apparent that there is great potential for a

waste heat capture system in False Pass. Sale of the waste heat

will realize increased revenues to the utility which will

decrease the cost of production for electricity. Currently

(1981-82) electricity costs are estimated to be 47.88~ per KWH

based on $1.30 a gallon for fuel and assuming that a central

generation and distribution system is installed. The fuel is

supplied by Standard Oil and barged to False Pass from the

distribution center in Seattle. The computer model used in the

reconnaissance study projected that the 1982-83 cost of

production for electricity will be approximately 47.88~ per KWH.

The study suggested that a waste heat capture system would be

installed, and become operational in 1983-84. It was assumed

that the waste heat would replace fuel oil, which costs $1.30

per gallon, used for space heating.

Therefore it is recommended that a waste heat capture system be

installed. The reconnaissance study estimates that the system

has the potential to save up to 4,000 gallons of fuel oil in the

first full year of operation.

9.4

• • • • .. .. •

• • • .' •

• • ... • • .. • .. .. •

• • • • • ..

APPENDIX.

See Section 3.0 (Methodology) of the Main Report:

RECONNAISSANCE STUDY OF ENERGY REQUIREMENTS AND ALTERNATIVES

FOR THE VILLAGES OF

Aniak, Atka, Chefornak, Chignik Lake, Cold Bay, False Pass,

Hooper Bay, Ivanof Bay, Kotlik, Lower and Upper Kalskag,

Mekoryuk, Newtok, Nightmute, Nikolski, St. George, St. Marys,

St. Paul, Toksook Bay, and Tununak.

REPlY TO

ATTENTION OF

NPAEN-PL-R

Mr. Eric YOll1d

DEPARTMENT OF THE ARMY ALASKA DISTRICT. CORPS OF ENGINEERS

po. BOX 7002

ANCHORAGE. ALASKA 99510

APR - 2 1982

334 West 5th Averue Anchorage, Alaskc 99501

Dear Mr. Yould:

3 1 MAR 1982

Thank you for thE opportunity to review your draft energy reconnaissance reports for FY lS82. In general, we found the reports to be comprehensive and potentially he1pful in our planning studies for both hydropower ana boat harbors. We would appreciate copies of the fina1 reports when they are available.

We have limited our comments to the reports that considered the areas we are most fami1iar with; however, some of the ccmments may apply to the other reports as I'lell. The attached pages list specific corranents for various communities.

If we can be of further assistanc~ please feel free to contact Mr. Loran Baxter of my staff at 552-3461.

Sincerely,

1 Incl ~k~--As stated Chief, Engineering Division

.,

Comments

Atka:

Page 7.1 is inconsistant. The lack of wind data is .":I.ted in the first paragraph,.then details of specific average annual wind speed versus height is given in the next paragraph. Then a comment that a site with wind in excess of 12 mph is a good sHe is fo 11 owed by"the statement that wi nd energy is expensive. We suggest that this be reworded for clarifi~ation .

. ' .'

Page 7.3 - 7.4. The write-up under the heading "Assumptions" is contradictory. The statement is made that "Weather on the Aleutian Islands varies greatly from one island to tfie other .•. " but is preceded and followed by statements stating that weather on Amchitka is comparable to that on Shemya, and that Atka's weather is comparable to that on Adak.

Page S.7. Mobilization and Demobilization costs of $50,000 appear low.

Chignik Lake:

Pages 7.1 and S.13. Location of hydropower site ;s inconsistant.

Page 8.14. Average power of 114 kW assumes 100 percent efficiency. "Energy Available" is wrong based on 30 percent plant factor.

Table 8.5. This table shows the hydropower project displacing all the diesel generation until 2000. However, the peak-demand projectioll on page 6.4 ranges between approximately 85 kW in 1982 to about 125 kW in 2000. Based on th~ streamflows sho'.'m on page 7.2 and the data presented on page 3.14, the hydropower system could not produce more than about 80kW in December, 65 kW in January, 60 kW in February, and 50 kW in March. The peak delnanas would likely fall during this period and not during the summer when most of the village moves to Chignik Lagoon.

Page 9.1 . The feasibility cost estimate of $35,000 to $45,000, including streamgaging, appears low.

Cold Bay:

The hydropO\ ... er potential for Cold Bay referenced from the Corps' 1980 reconnaissanc~ study has been found to be overly optimistic; therefore, the data should not be used.

I / •. '.

False Pass:

~e concur with their findings that hydropower does ~ot appear feasible.

Ivanof 3.3.y:

Table B.S. The table shows the hydropower system will displace all diesel. Based upon load and streamflow assumptions, it would not.

Page 8.15. Mobilization and Demobilization costs appear' low. " .. '

Page 9.1. The feasibility study cost estimate of $25,000 to $35,000, including streamgaging, appears low.

Nikolski:

The findings, as reported, agree with the results of the :orps' study. We feel that wind generation is the most promising alternative to diesel generation. The White Alice site may not be the most feasiole location because of its distance from town. Although it is protected from corrosive salt spray because of its elevation, a wind energy conversion system may be affected by the other structures within the installation. The bluff between the runway and Sheep Creek may be a better site.

The report neglected to mention if~the WECS installed on ~he Chaluka Ranch has been repaired and placed in service and if it is performing satisfactorly.

If a diesel enlargement were recommended to cope with substantial expansion of electrical de!lland, a salvaging of White Alice units could be pursued as an option if appropriate government channels can be identified.

St. Paul:

The reconnaissance study did not consider the impact of ttle proposed expansion of the fishing industry being considered by the local coml~unity. This coulll substantially alter the report findings.

Galena:

In a letter dated 9 June 1981 (copy previously furnished to your office), utt Water Engineers stated that they felt that a storage project with a 100 to 300-foot dam may te feasible. The Corps will De taking a seconu lOOK at this site this SUI~;ner to determine if a feasibility study is w"rranted.

2

• • • ..

• .. .. .. •• • • • • • ...

.. • •

.. .. • .' •

..

.,

7·~;'··'

..

•..... .£. . c'· ~ . . - . ,.. .

i Gustavus:

The National Park Service has been directed to coo~erate with the Corps of Engineers to determine the feas'ibility of hydroelect~ic power on Fa11s Creek. An initial field trip and public meeting is tentatiV~'y scheauled for mid-i·1ay. He will be installing a streamgage this surrmtr.

New Chenega:

The study indicates that it would be possible to construct a hydropower system at the site above the San Juan fish hatchery. It is our understanding that San Juan Aquaculture is going to construct a new hydropower system at this site for their personal use. We suggest you call Mr. Mike Hall with R.w. Retherford Associates at 274-6551. He is involved with the proposed deve 1 opment.

3

Reply to Department of the Army, Alaska District, Corps of

Engineers, letter dated 3/31/82.

Atka

p. 7.1 (draft) Statements concerning wind resoures have been

clarified.

p. 7.3-7.4 (draft) Because of the lack of climatic data from the

Aleutian Islands, it is necessary to extrapolate data from the

nearest recording station. However, variability in the local

climate means that all extrapolations are conservative.

p. 8.7 (draft) Cost estimates for mobilization and

demobilization have been adjusted to reflect Anchorage prices

for equipment rather than those quoted from Adak.

Chignik Lake

p. 7.1 - 8.13 (draft) The distance has been corrected.

8.14 (draft) The energy available value has been corrected.

Table 8.5 (draft) The table presented in the final report

illustrates the use of diesel powered generators when there is a

projected short fall.

p. 9.1 The feasibility study estimates have been addressed

especially in light of the comments from the U. S. Fish and

Wildlife Service which are included above.

Cold Bay

The hydropower data was included as part of the resource

assessment and was the determining factor for our not including

an alternative plan which was based on hydro.

False Pass

No comment necessary.

Ivanof Bay

Table 8.5 The hydropower scenario calls for the construction of

a small dam and creates a reservoir. Without extensive field

work, it has not been possible to show that this would be

inadequate to meet the estimated demand of the village.

p. 8.15 Mobilization costs have been increased.

p. 9.1 Feasibility study figures have been increased especially

in light of the comments and requirements of the U. S. Fish and

Wildlife Service which are included above.

Nikolski

The White Alice site was considered because excellent

foundations exist and the site is removed from the influence of

salt spray. The bluff between the runway and Sheep Creek has

been reconsidered and discussed with representatives of the

village. The result has been the suggestion that the bluff site

is a viable alternative and marginally less costly to develop

because of a shorter transmission distance. However, this is

largely offset by anticipated foundation problems at the bluff

site.

WECS at the Chaluka Ranch was not in operation when the field

team was in the village.

The diesel set from the White Alice site was purchased by the

utility; however, its condition was uncertain and the engine was

being stored outside.

St. Paul

As the role of the National Marine Fisheries in the Pribilofs is

curtailed, the future of the islands' economies is uncertain.

The proposed boat harbor has not been funded, as yet, and no

data was available which would enable predictions to be made as

to its effect on the local economy and power requirements.

Therefore a scenario including the possible development of such

facilities was not included.

• III

• .. • .. .,

• • .. .. .. .. .,

., .. • • .. • .. .. .. .. • .. •

IN REPLY REFER TO:

WAES

United States Department of the Interior

FISH AND WILDLIFE SER VICE Western Alaska Ecological Services

733 W. 4th Avenue, Suite 101 Anchorage, Alaska 99501 B 1;.0 I; lY 1:. D. _

(907) 271-4575 -

APR_ 91982 Mr. Eric P. Yould Executive Director Alaska Power Authority 334 West 5th Avenue Anchorage, Alaska 99501

AtWcA fOWER AIJJ110BlJ! I APR 1982

Dear Mr. Yould:

We have reviewed the Alaska Power Authority's (APA) Draft FY 1982 Energy Reconnaissance Reports. If the conclusions and recommendations stated in the individual reports become those of the APA, and if the APA undertakes feasi­bility studies'in fulfillment of the recommended alternatives, then the U.S. Fish and Wildlife Service (FWS) requests that the information and studies outlined below be made a part of the feasibility studies.

Without current site-specific resource information and a more complete description of the proposed project, it is difficult to assess what impacts, if any, will occur to fish and wildlife resources and associated habitat. Information should be acquired and studies conducted to identify the fish and wildlife resources of the study area, identify adverse project impacts to those resources, assess alternatives to the proposed action and devise a mitigation plan that would prevent a net loss to fish and wildlife resources.

Specific information to be collected and studies to be conducted which the FWS feels are necessary to adequately assess potential impacts include the following:

1. Plans for construction activities and project features to minimize damage to fish, wildlife, and their habitats should be devised, e.g., erosion control, revegetation, transmission line siting, construotion timing, siting the powerhouse, diversion weir, and penstock above salmon spawning habitat, etc.

2. Losses of fish and wildlife habitat should be held to a minimum, and measures to mitigate unavoidable losses and enhance resources should be devised.

3. If there is to be a diversion of water or if sUbstantial water temperature fluctutations are imminent, then these factors should be addressed because of their possible influence on water quality and fish habitat. Aquatic data collection should at leaat include the following:

Page 2

(a) Identification of species composition and distribution of resident and anadromous fish within and downstream of the pro­ject area. Standard sampling methods such as fyke netting and minnow trapping, as well as visual observation of spawning and/or redds, should be used.

(b) Surveying and mapping of fish spawning, rearing, and over­wintering habitat as defined in the FWS Instream Flow Techniques or similar guidelines.

(c) Harvest levels and subsistence use data, .if applicable.

III .. • .. • • • .. • ..

It should be incumbent upon the APA to document animal species within the • project boundary. If it is determined that impacts to terrestrial mammals or .. bird habitat is imminent, the APA should gather habitat and population infor-mation in a manner consistent with the FWS' Habitat Evaluation Procedures. •

Terrestrial data collection should include the following:

(a) Verification of game and non-game species use and occurrence within the project area.

2.

Mammals.

a.

b.

Historical and current harvest levels and subsistence use data.

Site-specific wildlife observations, including wild­life sign, denning sites, feeding sites, migration routes, winter use areas, and calving areas.

Birds. Raptor nesting surveys within the project area.

(b) Description of vegetation, cover typing, and areal extent of each type.

The FWS requests that bald eagle surveys be undertaken. If nest sites are encountered, the APA should notify the FWS. The FWS seeks to maintain a 330-foot protective zone around all active and inactive nests. Compliance with provisions of the Bald Eagle Protecton Act is mandatory.

We request that the following be accomplished during the course of the studies:

1.

2.

During the period of project planning, the APA should consult with federal, state, and local agencies having an interest in the fish and wildlife resources of the project area, including the Fish and Wildlife Service, prior to preparing any environmental reports.

The APA shall investigate and document the possible presence of any endangered or threatened species in the project area. If endangered of threatened species are determined to be present, the FWS should be notified.

.. • .. • III!

• •

• ., • .. .. • ., II'

• •

• •

Page 3

3. The APA shall design and conduct at project cost, as soon as prac­ticable, preparato~ studies in cooperation with the FWS and the Alaska Department of Fish and Game. These studies shall include, but not be limited to, the above aquatic and terrestrial data. The studies shall also identify and evaluate general measures to avoid, offset, and/or reduce adverse project-caused impacts on fish and wildlife resources. Information from these fish and wildlife related studies shall be provided to the concerned state and federal resource agencies.

Future correspondence on this, or other projects proposed by the APA should include a clear map, in sufficient detail to show the exact location of the project. This will enable the FWS to accurately determine whether or not Interior managed lands are involved.

It is the desire of the FWS to work with the APA to resolve any concerns relating to fish, wildlife, and other resources. If it is determined that the project will result in resource impacts, the FWS will assist the APA in attempting to modify the project to alleviate or mitigate any adverse effects.

Please feel free to contact me if you have any questions regarding our suggested feasibility studies.

Sincerely,

~~ Field Supervisor

Reply to J.5. Fish and Wildlife Service letter, undated.

Environmental work to fulfill the information requirements

detailed by FWS is included in the estimates for feasibility

studies.

Alaska Power Authority J44 W. 5th Avenue, Second Floor Anchorage, AK 99501

Dear Ms. Dejong:

False Pass Corporation False Pass, AK 99583 March 29, 1982

In regard to the energy for reconna.issace study performed for False Pass by the

Alaska Power Authority. We have the £ollowing recommendations.

The minimum size diesel generator needed is a 75kw with a 100 kw standpy. To

include the needs of the Peter Pan Seafoods fish camp in the summer and the growing

needs of the village. The present total generating capacity is about 80 kw at Peter

Fan Seafoods.

We also suggest that a 100,000 gallon fuel stor-age tank be put in the Village.

For security reasons, because the fuel storage tanks owned by Peter Pan Seafoods are

very old and not reliable. Also, i£ possible, it would be cheaper to buy the fuel

directly from Standard Oil.

The enclosed signatures are people of the village who approve o£ the above

recommendations.

• •

-• .. •

• .. .. .. • .. • • •

• .. • .. • .. • .. • • • •

Response to False Pass Corporation letter dated March 28, 1982.

"Minimum size diesel generator needed is a 75 kw with a 100 kw

standby. To include the needs of the Peter Pan Seafoods fish

camp - the summer and the growing needs of the village."

The estimated peak demand for the village of False Pass was 40

kw in 1982 rising ~o 63 kw in 2001. During the study Peter Pan

Seafoods were contacted on several occasions and the project

team was told that there were no definite plans to reopen the

fish processing plant. If reopened, the plant would operate on

a seasonal basis and not provide a regular load to the

generators. The project team decided that they would recommend

the installation of a diesel set which would meet the villagers'

present and growing demands. If the electrical load from Peter

Pan is included, then the generators would be running very

inefficiently for the majority of the year. This would

necessitate the installation of oversized generators, shorter

life span of the generators, increased operation and maintenance

costs and an accelerated overhaul schedule.

Therefore, we recommend that the village proceed to accomodate

its own requirements because of the uncertainty over the future

of the seafood processing plant. The recommendation is based on

the "hidden costs" to the village if it does supply the power to

a seasonal customer. which has a high load.

"We also suggest that a 100,000 gallon fuel storage tank be put

in the village."

Based on the total kwh requirements of the village, the village

will need approximately 13,300 gals in 1982. Other fuel

requirements are for residential use 18,500 gallons, public

sector 2,000 gallons, and 3,800 for the school. Total fuel

requirements are approximately 37,600 gallons. Therefore, we

would recommend that 48,000 gallons of storage be installed for the village's requirements. The costs for the tanks have been

included in the energy plans.

A copy of your letter has been forwarded to the Department of

Community Affairs (CRA) and the Department of Energy and Power

Development (DEPD). CRA has responsibility for fuel storage

programs in rural Alaska and DEPD is responsible for fuel use

management and planning.

.. • .. .. • -•

• .. .. .. .. --• .. • • .. • .. ., .. • • • • • • ..