Dear Neighbour,
0 EWR AllianceConnecting People
EWRAlliance 2nd Floor
Phoenix House
Elder Gate
Milton Keynes
MK91AW
As part of our continuing works ahead of the construction of the Bletchley High Level Station
and Bletchley Flyover, we need to relocate the compound and weighbridge near the Brunel
roundabout. We also need to carry out some road improvement works near the roundabout.
Please be aware, that we will be working the following hours on weeknights and Sundays:
• Monday 15th November to Friday 20th November 9:00 PM to 5:00 AM
• Sunday 29th November 7:30 AM to 4:00 PM
• Sunday 5th December 7:00 AM to 4:00 PM
In addition, we will be carrying out temporary sheet piling activities near the West Coast Main
Line.
The activity is part of the rebuild phase of the Bletchley Flyover. The sheet piling will be installed
around several of the remaining flyover piers near to Buckingham Road. The piled sheets will
provide ground support for the pier foundations in order to carry out re-strengthening works to
the existing piers which will support the new Bletchley Flyover.
Due to their proximity to the operational railway, these works are only permitted to be
undertaken during rail possessions when the West Coast Main line is closed.
As such, please be aware that this activity will take place on the following nights:
• Saturday 28th November 11 :00 PM to Sunday 29th November 11 :00 AM• Saturday 5th December 11 :00 PM to Sunday 5th December 11 :00 AM• Saturday 12th December 11 :00 PM to Sunday 13th December 11 :00 AM• Saturday 19th December 11 :00 PM to Sunday 20th December 11 :00 AM
Our working hours are dictated by the times we are granted possession of the railway, and this
can vary from week-to-week.
We appreciate that these works are disruptive to the local area, and we are doing what we can
to minimise the noise by using noise reducing equipment.
We would like to apologise in advance for any disturbance these essential works may cause.