Upload
jalynn-merrifield
View
215
Download
1
Tags:
Embed Size (px)
Citation preview
111
Changes to the PS RF system
04 April 2014
H. Damerau
Many thanks for discussions and input toL. Arnaudon, D. Cotte, S. Hancock, R. Maillet, M. Morvillo, M. Paoluzzi, D. Perrelet, S. Rains, C.
Rossi, S. Totos
BE/OP Shutdown Courses 2014
2Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
3Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
4Introduction
® Beams from single bunch to 72 bunches, flexible longitudinal pattern
® Intensity range from about 109 to 3 · 1013 particles per cycle
® Major bunch shortening along the cycle, from 180 ns to 4 ns (45 times!)
® After LS1: BCS, BCMS, PBC, etc.
What has changed for the RF systems after LS1?
What to do with the modified RF systems? Steven’s lecture
PSProtons
from PSB• Protons and ions
to SPS (and LHC)
• Protons to AD and nTOF target
Pb54+ (future: Ar11+, Xe39+) from LEIR
Protons to fixed target experiments
5RF Systems to perform manipulations
to SPS
PS
24 (+1) cavities from 2.8 to 200 MHz
Acceleration
2.8 – 10 MHz
200 MHzLongitudinal blow-up and 200 MHz structure for SPS 13/20 MHz
80 MHz
40 MHz
RF Manipulations
RF Manipulations
6Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
7
• Bunches from PSB must be placed into the correct buckets
• Batch compression works only for even number of bunches
® Bucket number control during both transfers PSB PS
1 turn
Injection bucket selectionPA.DCNBINJ
8
DDS
h128
Inj. Bucket selectio
n
MHS
DDS
MHS h = 1
… …
RF
dir
ectl
y to
cavit
ies
(
on
e D
DS
per
cavi
ty)
f rev, c
lose
d
loop
Tagged clock
fRF, inj. = 9 ·
436.568 MHz
MHS hPL = 9
1. Sync. on h = 1,
fix bucket #
2. Lock f- loop on
inj. synth.
Shifted trains to
PSB, 1st inj.
Bucket number control
Synchronizing PSB and PS – 1st injection
Generate synchronous h1, h4 and h8 for PSB, while locking f-loop on h9
R.
Garo
by,
Mu
lti-
harm
on
ic R
F
Sou
rce f
or
the A
nti
-pro
ton
P
rod
ucti
on
Beam
of
AD
, C
ER
N
PS
/RF
/Note
97
-10
Df (phase loop)
Df (injection synchro.)
4 ms/div
1. 2. Inj.
9
DDS
h128
Inj. Bucket selectio
n
MHS
DDS
MHS h = 1
… …
f rev, c
lose
d
loop
Tagged clock
MHS hPL = 9
1.Sync. on h =
1, fix bucket
#Shifted
trains to PSB, 2nd inj.
Generate synchronous h1, h4 and h8 for PSB, while locking f-loop on h9
Bucket number control R
F d
irectl
y to
cavit
ies
(
on
e D
DS
per
cavi
ty)
Synchronizing PSB and PS – 2nd injection
R.
Garo
by,
Mu
lti-
harm
on
ic R
F
Sou
rce f
or
the A
nti
-pro
ton
P
rod
ucti
on
Beam
of
AD
, C
ER
N
PS
/RF
/Note
97
-10
10Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
11Major renovation of LLRF controls
• Profit from global controls renovation (ACCOR) to move front-ends for PS beam controls to central building
Before The plan…
12Major renovation of LLRF controls
During… Back on…
® Close collaboration between BE/CO and BE/RF
• Profit from global controls renovation (ACCOR) to move front-ends for PS beam controls to central building
E. S
aid
and
inst
alla
tion
team
13Migration of controls devices
Devices Obsolete GM class
New class
Timings PTIM-V LTIM
Functions GFAS CVORB
Digital bit controls
DIGIO CGDIO_B (bit)
Digital selectors DIGIO CGDIO_E (enum)
Digital controls DIGCTL CGDIO_C (cont.)
Pentek synthesizer
DIGCTL V346
10 MHz matrix RFMAT MATRF
‘Tra
nsp
are
nt’
m
igra
tion
® 67 CVORB function channels® ~220 physical timing channels, ~1240 timings in total
(multi-pulses)® ~35 Further devices: digital controls, RF synthesizer,
etc.® Kontron PC front-end for MIL1553 loops (all cavities)
on/off/reset® About 10 kilometers of new cables, but in about 250
smaller pieces
14
® Should be sufficient for the future® Should be sufficient for the near future?
Controls upgrade from TG8 to CTRV:® Each function with restarts now 16 instead of 8 restart
timings
Twice more complicated RF manipulations possible:® Sequence of 16 phase loop harmonics® Sequence of 20-25 RF harmonics® RF manipulations twice as complicated as before LS1
(2 BCMS)
Ready for new RF manipulations
15Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
16
AVC
1TFB
h h200
Final Amplifier, 10 MHz
Cavity, Fast Wideband FB
DAC
ADC
DAC
Gap ReturnDrive
H
- Fast wide-band feedback around amplifier (internal) Gain limited by delay
- 1-turn delay feedback High gain at n frev
- Slow voltage control loop (AVC) Gain control at fRF
Vprog (digital)
PS 10 MHz feedback overview
D. Perrelet
17Voltage control (AVC) loop
• Pre-LS1 hardware required analog voltage program• Regulation characteristics not optimum for fast voltage
jumps
RF
fro
m
beam
con
trol
Vp
rog
(an
alo
g)
Analog voltage control:1. AVC loop
functionality2. Interlocks
Loop filter
® Upgrade to fully digital implementation of AVC loop® Migrate interlock part to separate surveillance hardware
P. M
aese
n, P
S/R
F/N
ote
94-2
5
Pre-LS1
18Digital voltage control (AVC) loop
® Harmonic number functions PA.GSHA/B/C required for all beams
RF
fro
m
beam
con
trol
Vp
rog
(dig
ital)
Digital PID
Non-I/Q detector
• Digital voltage control loops integrated into 1-turn delay feedback HW
• Separate surveillance module to assure hardware safety
M. H
aase
D. P
erre
let
Veto
h (digital)
19Principle of the 1-turn delay feedback
® Comb filter for high gain at frev harmonics® Delay circuit to correct total feedback delay to a full
turn® Additional notch filter to cancel feedback gain at fRF
• Classical feedback limited by unavoidable delay• BUT: Impedance reduction of cavities only needed at frev
harmonics
D. Boussard, G. Lambert, PAC83, pp. 2239-2241
20
• No need for:• Multiple clocks, avoiding double sampling at 4 fRF and 80
frev
• Wide-range clock phase locked loops
• External delay cables
• Increased resolution of signal processing from 10 to 14 bits
• Ready for proton beams at any harmonic number• No need to start from h = 8 (limitation in old
system)• Compatible with all LHC-type beams
• Integrated electronic delay generation
• Possibility to raise feedback gain by firmware improvements
• Include a digital AVC in the firmware to replace analog hardware
New 1-turn delay feedback
21Flexible feedback board development
D. P
erre
let
• Versatile board:• 4 ADC/DAC channels with powerful FPGA• Delay line chains to complete delay of 1-turn• CVORB and fast serial ports for connections• Further/future applications: PS transverse feedback,
coupled-bunch feedback, 1-turn delay feedback for 20/40/80 MHz systems and transverse dampers of PSB, AD, LEIR
22
• Four new VME crates installed in building 359 (one per tuning group)
• Example for tuning group B (cavities C56, C66, C76 and C81):
Installation
All 10 MHz cavities equipped:
AVC loop commissioning ongoing, then 1-turn delay feedback
D. P
erre
let
23Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
24
• 10 MHz require a tuning current of up to 3000 A to cover 2.8…10 MHz
• Multiple cavities in series to reduce tuning power supplies:® 3+1 tuning power supplies since 1984® Two groups of 2 cavities and one big group (2 + 2 +
6)® For RF manipulations voltage limited to 40 kV per
group• Change tuning group
configuration to 3 + 3 + 4® Adapt to present needs® 60 kV per group
® Rewire 3 kA cables!
Change of tuning group configuration
Below PS ring (inside)
25
To C66
Connections to C56
Rewiring 3 kA cables: before
To C66
To C51
To C51
Connection box below C10-56
V. D
esq
uie
ns
26
To C66
Connections to C56
Rewiring 3 kA cables: after
To C66
To C51
To C51
Connection box below C10-56
V. D
esq
uie
ns
27
hA: 36, 46
hB: 51, 56, 66, 76, 81, 91
hC: 86, 96
Tuning-Groups:
Group 4: 11, test cavity
→ All cavities of group tuned to same frequency
→ Hard-wired structure of tuning groups
→ 40 kV in three groups
Frequency: Fixed tuning circuits (1984-2013)
28
hA: 36, 46, 51hB: 56, 66,
76, 81
hC: 86, 91, 96
Tuning-Groups:
Group 4: 11, test cavity
Frequency: Fixed tuning circuits (2013-)
→ All cavities of group tuned to same frequency
→ Hard-wired structure of tuning groups
→ 60 kV in three groups
29Tuning group change: status and consequences
Behavior of tuning groups verified before and after the change
First six cavities in the ring now pulsing
• But:
• All cavities in voltage program group should be in same tuning group
® Now violated for almost all cycles® Need to adapt timing trees ( Steven’s presentation)® Need to rebuilt each cycle before it can be executed!
• Major effort of reprogramming all RF functions
Please do not just put pre-LS1 cycles in the super-cycle!
Absolutely ‘non-transparent’
30Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
3131Voltage program generation: hardware matrix
Pre-LS1
® Dangerous single point of failure
Fu
ncti
on
s an
d
tim
ing
s p
er
gro
up
Fu
ncti
on
s an
d
tim
ing
s p
er
cavi
ty
• Hardware matrix has served from the mid 1990’s until LS1
• Complicated hardware with embedded micro-processor
6 analog functions + 12 timings in 11 analog function + 22 timings out
• Few spare boards in unknown state left
32
Global program
Modifier grp. 1
Modifier grp. 2
Modifier grp. 3
Modifier grp. 4
Modifier grp. 5
Modifier grp. 6
×
×
×
×
×
×0…100%
0…200 kV
C1 1
C3 6
C4 6
C5 1
C5 6
C6 6
C7 6
C8 1
C8 6
C9 1
C9 6Voltage programs to
cavities:
Global red. ×0…100%
Mapping from groups to cavities
• voltage programs• gap relay timings
Voltage program generation
3333New software based 10 MHz matrix
New implementation guidelines:• Distribution of digital voltage program data to each
cavity® CVORB function generator channel and CTRV timings per
cavity • No specific central hardware as single point of failure
® Only simple electronics to distribute serial data streams• Move relevant parts of matrix to software virtual
matrix
1. Combine functions and restart timings to so-called real-time function per voltage program group
2. Copy real time functions per group to functions per cavity
® Major implementation effort by P. Pera Mira and G. Kruk
H.
D.,
S.
Han
cock,
CE
RN
-AT
S-N
ote
-20
13
-02
1 T
EC
H
34Real-time function generation
• Voltage program modifier functions per group (with restarts) difficult to map
1. Calculate real-time functions PA.GS…RT, based on functions and timings
2. Copy only real-time (RT) functions to the functions per cavity
Function with
restarts
Real-time function• Functions per group drive
no hardware anymore® Possibility to virtualize
later
( )
35
Global program
Modifier grp. 1
Modifier grp. 2
Modifier grp. 3
Modifier grp. 4
Modifier grp. 5
Modifier grp. 6
×
×
×
×
×
×
0…100%
0…200 kV
C1 1
C3 6
C4 6
C5 1
C5 6
C6 6
C7 6
C8 1
C8 6
C9 1
C9 6Voltage programs to
cavities:
Global red. ×0…100%
Modifier grp. 7
Modifier grp. 8
×
×
Mapping from groups to cavities
• voltage programs• gap relay timings
• Hardware switching of functions and timings migrated to software
• InCA MakeRules to copy settings from groups to cavities
• Integrated spare cavity selection mechanism for C11
® Virtual matrix
Voltage program generation
36
• More flexibility thanks to renovated generation of voltage programs: so-called ‘matrix’
• New hardware to generate digital voltage program data for each cavity
® 8 logical groups of cavities® Matrix functionality implemented in software® Commissioned and essentially ready for start-up
Upgraded distribution of voltage programs
37Application program
• New application (D. Cotte, R. Maillet)
® Finally little changes from the operations point of view® Integrated spare cavity selection, also based on InCA
MakeRules
38Spare cavity selection
• Spare cavity C11 replaces any other 10 MHz cavity, needs:• Voltage program like any other cavity• Harmonic number and relative phase special
• Previous implementation: hardware multiplexers for GFAS functions
• MakeRules now copy relevant functions and timings on all LSA cycles
PA.GSHART
PA.GSHBRT
PA.GSHCRT
PA.GSHDRTA, B or C
PA.GSRPART
PA.GSRPBRT
PA.GSRPCRT
PA.GSRPDRTA, B or C
Tuning group of cavity to be replaced by C11
® No dedicated hardware involved anymore® Flexible, could even drive C11 with its own functions and
timings
Harmonic Relative phase
39Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
40Glue logic for the control: linked timing
→ Timing tree structure assures coherence between harmonic number (tuning group) and voltage programs (matrix)
• Old timing trees (LKTIM) incompatible with LTIM/CTRV timings
• Migration of X-motif application to Java needed
→ New trees again with node and parent lists (Mbno device ID)
→ Rules for timing and status calculation moved to InCA
… … … …
`
Pre-LS1
41Glue logic for the control: linked timing
• New application (D. Cotte, G. Kruk for the InCA part):
® Little changes from the operations point of view® Comfortable handling of large timing trees, commissioning
ongoing
42Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
43Status of 20, 40, 80 and 200 MHz cavities
• 20 MHz cavities As before LS1
• 40 MHz C40-78 repaired, being commissioned
Pre-driver amplifiers water-cooled Otherwise as before LS1
• 80 MHz cavities Pre-driver amplifiers water-cooled
Otherwise as before LS1
• 200 MHz cavities Cavities as before LS1 Renovation of C201/206 amplifiers
All high frequency cavities will be available for the start-up
44Automatic tuning for 40 and 80 MHz systems
• Keep cavities at fixed frequency® Microprocessor-based system
after LS1
L. A
rnau
don,
S. T
otos
® Will also pilot switching of 80 MHz cavities for protons and ions
® Commissioning during/after start-up
PX.SSC-C200
Start SuperCycle
0V
24V
2µs
0µs
Motor DriverDigital Microstep Driver
DMD5056
R
Control Panel
Lim OutLim Out
Lim InLim In
RUNRUN
LCD 2*16 or7-segLED
CMD INCMD IN CMD OUTCMD OUT
AUTO
MANUAL
AUTO
MANUAL
I2C
AUTOTUNING
CONTROL
FESA
ETHERNET
RFSHUT OFF
&TIMING
VETO 2
AVCCTRLLOOP
DAC
ADC
AVC VETO
TEST PERTURBATION
CONTROLMOTORCONTROL
RF 0degAmplifiers
CAVITYPHASE DISCRIMINATOR
RABBITRCM4010
SERVOTUNER
AY04Pulse
Repeater
RESOLVERDECODER
M
45Renovation of 200 MHz amplifiers (C201/206)
Before
New amplifiers in BA3 (SPS)
Old amplifiers
• High power chain C202/C203/ C204/C205 completely renovated during the 2006/2007 shutdown
® C201/206 followed during LS1
S. R
ains
, Ch.
Ren
aud
New amplifiers
46Renovation of 200 MHz amplifiers (C201/206)
New amplifiers ready in building 151 (C201) • Amplifiers
® Special old types irradicated
® Interchangeable with SPS
• Interlock system® More evolved
then for C202-C205
• Power supplies® Reliability
® C201/206 renovated for the start-up all systems almost identical
® Strategy for operation after LS1:1. Run with four 200 MHz RF systems, including C201
and C2062. Keep two cavities as hot spares
New amplifiers
47Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
48New cavity (#25) in the PS ring
M. P
aolu
zzi
• Wide-band (0.4 – 5.5 MHz, VRF = 5 kV) cavity based on Finemet material
• No acceleration, but damping of coupled-bunch oscillations SS026-cell cavity unit
Accelerating gap
Power amplifiers (solid state)
B E A M
F I N E M E T
G A P
• Cavity installed in SS02, start with amplifiers on 2 gaps® First installation of transistor power amplifiers close to
beam in PS
49Coupled-bunch oscillation damping• Bunches oscillate with different phases (and
amplitudes)Example of an n = 12 mode (Df ≈ 206)
• Mode number n defined by phase advance from bunch-to-bunch:
® Coupled-bunch oscillations show up as side-bands of nfrev or (h-n)frev
Df = 2p n/h
® Frequency range of new Finemet cavity allows to damp all modes
® Commissioning after start-up
frf
Kick
MeasureKicker
basebandPreferred detection
50Overview
• Introduction• RF systems for manipulations
• Global beam control system modifications• Injection bucket control• RF controls renovation
• 10 MHz RF system• Voltage control and 1-turn delay feedback loops• Tuning group restructuring• 10 MHz matrix control, spare cavity selection and
linked timing
• High-frequency and wide-band RF systems• 20, 40, 80 MHz and 200 MHz• Wideband cavity for longitudinal damper
• Summary
51Summary
• Extensive modifications to the PS RF systems during LS1
® Most of them expected to be ‘transparent’, though the underlying design changes are significant
® Tuning group change not transparent: ® Rebuilt almost all cycles® Existing cycles must not be played without prior
modifications!
• Re-commissioning of RF systems progressing• Initial commissioning of new equipment, e.g.,
longitudinal damper will continue after start-up
® Steven’s lecture on 10/04/2014
What to do will all this (new) stuff? ® Smooth start-
up?® Smooth start-
up!
52
Thank you very much for your attention!