PowerPoint Presentation

tools to manage Scope, Time and cost in aN EPC contractMimoune [email protected]://www.plannertuts.com/author/minoune-djouallah/

The PurposeThe purpose of this presentation is the description of the process for Project Controls (covering engineering, procurement and construction) for the execution small size projects The tools are developed as database systems, with a clear separation between datasets and reports.Excel was used for simplicity, but for more data integrity it is advisable to use RDMS ( Like MS Access )

The ApproachThe approach used in this presentation : There is no real time integration or one system to manage the different process. instead every process is managed using a separate tool, the integration is done using well defined interface.The data generated from different process is integrated in one place to generate Reports, curves, and dashboards. All the stakeholder must agree before the start of the project on the interfaces and the level of the details and integration between the different process.

The interfacesWBS : Work Breakdown structure. CBS : Cost Breakdown structure. AREA : a geographic division of the plant. Workpackage is a group of deliverables. - Construction: Group of items ( building, piperack). - Engineering : Group of drawing. - Procurement : Group of equipment, material etc. Task_Code is a standard activity with efficiency and physical quantity SCOPE_ID is the business rule primary key It is a concatenation of Area, Task_Code and WorkpackageSteps is further detail of Task_code to basic activitiesWBS

Level 1 & 2L1 : the project.L2 : Phase (General, Engineering, Procurement, Construction, Precommissioning, Commissioning, Start-up, Handover.

Level 3 : General L4 : Milestones, ManagementL5 : - Milestones are split between contractual Milestones and Project Milestones. - Management is split between the different Department output for the project. Level 3 : EngineeringL4 : Disciplines L5 : Work Packages Level 3 : ProcurementL4 : Subcontract, Long lead items, Disciplines ( auxiliary, Civil ) and Bulk Materials.L5 : Work Packages ( group of equipment)Level 3: ConstructionL4 : Zone L5 : AreaL6 : Work PackagesLevel 3: Precom, CommissioningL4 : systems ToolsSCOPE: provide The whole scope of work(EPC), including manhours and quantitiesSchedule: Time Management ( Planning software) PRT : Progress reporting and tracking, excel tool to managed update progress and reportingTime_Sheet: The manhours spent in Construction.Job Card : detailed Progress report at level 5DPR : Document Progress Register.PSR : Procurement status report.Cost : Cost Control is managed by Separate tool.

Task_CodeTask_CodeDesciplineTask ClassUnique identifierLevelL1L2L3XXXXXXXXXXXXExampleCV1020CV1020CivilConcrete WorksFoundation Civil WorksCV1060CV1060CivilConcrete WorksPipe support Civil WorksTask_Code : is a unique six digit Code.It is the concatenation of Discipline, Task Class and a unique identifier The efficiency per Task_Code is a based on a historical data of the company.

SCOPESCOPE is a live List incorporating all new update to the scope of works (EPC).The integration between the planning software and SCOPE is using SCOPE_ID.When there is a significant change in Scope of Work, the Planning software is update from SCOPE

SCOPE Flow ChartSCOPE_IDSCOPE ( Budget manhours, Quantities, weightage to the client as by the contract revenue)Construction ITEM ListDocument Progress RegisterProcurement Status ReportSCOPE_IDSCOPE_IDConstruction Productivity databaseMaster Schedule Level 4SCOPE_IDContract Value15PRTThe data in the PRT is mapped at the activity level in The Planning software, basically it is the same schedule but handled in a separate spreadsheet.It is easier to record period performance in excel then in a planning software.Anyone with basic Excel skills, can update the progress and produce reports without the need to operate a Planning software.

PRT ( Progress Reporting and Tracking) Flow ChartPRT (Progress Reporting and Tracking)Weekly Planning software (Weekly, Or Monthly)Progress reportS CurveInvoiceSCOPE_IDTime sheetProductivityInternal Report Cost Dates by CBSWBSJob CardProcurement registerEngineering Register17Planning softwarePlanning software is used only to manage time, by using the CPM calculation.In the initial baseline, load the physical quantities to level your production output.A hammock can be used to split an Activity assigned to SCOPE_IDThe Frequency of updating the schedule, depend if you want to generate a Forecast curve, Weekly or Monthly. The actual start, actual finish ( the facts) are imported from PRT.There is no magic formula to generate remaining duration, talk to the guy doing the work, he is the best one to provide this information.After scheduling, the new forecast dates are exported to PRT, to generate the forecast data.Any planning tool can be used (MS Project, Primavera, etc).Never Ever input dates directly in Excel !!!!!

Time SheetFor the sake of simplification the spent hours in the site will be recorded only by subcontractor, but in order to have a more accurate Productivity analysis, the hours should be at least recorded at the Subcontractor/ discipline level. The data is recorded in a daily basis, the productivity factor in a weekly basis.The time sheet records the roles by direct and indirect.

CostCost control is a separate process.The cost breakdown structure is implemented using the activity codes in the planning software.The spread of cost by cost account is done using the dates from the schedule.PRT generate progress report by CBS, it should be considered as an approximation, as progress based on cost weight and revenue weight are little bit different.It is important to avoid the use the best guess method in distributing cost data.The more CBS is detailed the more the distribution is accurate.

The Weight FactorEngineering and construction the budget is in manhours.Procurement the budget is the cost.The revenue Factor Revenue = Budget X FactorThe overall Progress (EPC) is based on the contract Value.Reporting FormatThe Primary Progress reports for the client are based on the WBS.For different audience, there is a different reports.By Contractor.By discipline.By Work PackageBy systems.

Effective reporting Separate datasets from the reports.Never Hard Code a reportUnderstand your Primary key.Use codes, standardize your codifications.Always prepare and generate data as database.Pivot table in Excel is very powerful reporting utility.Automatize your workflow, manual data entry is a waste of time.Use both WBS and activity codes for maximum flexibility in reporting.

Change ManagementTwo Approaches1- Keep two revision of PRT.Stable Revision issued to the client, the budget is frozen.An internal live revision incorporating the latest changes from SCOPE.2- update the current schedule with the latest data from SCOPE ( without adding weightage)The period performance ( % complete) does not change, as it is calculated in the JOB CARD using always the latest update from Construction ITEM LISTPS :I added a new Excel file Project dashboard, it is much easier to use, and all the calculation are automated