    Hearing Topic

    002 E-Plan & MiscellaneousParties and Issues ReportReleased on 21 August 2014 for the Pre-Hearing Meeting

    This report includes information and documents related to the hearing pathway for

    this topic. Reference needs to be made to this report to find out 1) the parties, 2)

    the proposed pathway and 3) documents and information for this topic.

    Pre-Hearing

    Meeting

    2 September2014

    Full Panel

    Mediation

    not required

    Expert

    Conferencing

    not required

    Hearing

    Tentative date 25-

    26 September

    2014

    Full Panel

  • 8/11/2019 002-PIR-21 August 2014

    2/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 1

    Table of Contents

    1. Hearing topic information ............................................................................................ 2

    1.1 The Hearing Topic .......................................................................................................... 2

    2. Submissions received and proposed hearing pathway ............................................ 4

    2.1.Parties to this topic ......................................................................................................... 4

    2.2.Submission Points Pathway Report (SPP) ..................................................................... 4

    2.3 Grouping of submissions ................................................................................................ 4

    2.4 Parties required to attend the pre-hearing meeting ......................................................... 8

    3. Identifying the hearing pathway for submissions...................................................... 9

    3.1 Submitters who wish to be heard ................................................................................... 9

    3.2 Submitters who do not wish to be heard ......................................................................... 9

    3.3 Submission points relating to minor errors and changes ................................................ 9

    3.4 Further submissions ....................................................................................................... 9

    3.5 Further information ......................................................................................................... 9

    4. Documents from the pre-hearing and hearing pathway .......................................... 10

    4.1 Hearing pathway documents ........................................................................................ 10

    4.2 Independent expert evidence ....................................................................................... 10

    5 Summary of pre-hearing pathway outcomes ........................................................... 11

    5.1 Pre-hearing meeting outcome ...................................................................................... 11

    5.2 Expert conferencing outcomes ..................................................................................... 11

    5.3 Mediation outcomes ..................................................................................................... 115.4 Recommendations on minor errors and changes ......................................................... 12

    5.5Agreements reached between parties outside of formal mediation or experts

    conference pathway ............................................................................................................ 12

    5.6 Connecting the outcomes from pre-hearing and hearing pathways .............................. 12

    6 Hearing Session ......................................................................................................... 13

  • 8/11/2019 002-PIR-21 August 2014

    3/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 2

    1. Hearing topic information

    PLEASE READ

    Important Jurisdictional Note

    Most submission points (except for points allocated to the Eplan and Geographic

    renaming pathways) allocated to this hearing topic raise matters that the

    Independent Hearing Panel (the Panel) consider to be out of scope. Out of scope is

    a term used to identify matters that cannot be included in the Proposed Auckland

    Unitary Plan because they are outside of the jurisdiction of the Panel under the Local

    Government (Auckland Transitional Provisions) Act 2010 and the Resource

    Management Act 1991.

    The implication of your submission point being confirmed by the Independent

    Hearings Panel as out of scope is that a recommendation to reject your submission

    point will be made to Auckland Council by the Hearings Panel following the hearing

    on this topic.

    If you disagree that your submission point is out of scope you are strongly

    encouraged to attend the pre-hearing meeting to speak to this jurisdictional matter.

    1.1 The Hearing Topic

    The information provided below outlines the subject, Proposed Auckland Unitary Planprovisions and relevant matters to be considered for this topic.

    HEARING TOPIC - 002 E-Plan and Miscellaneous

    This topic relates to submissions:

    regarding the functionality of the E-Plan of the Proposed Auckland UnitaryPlan, and

    that are outside the scope of the Proposed Auckland Unitary Plan or beyond

    the jurisdiction of the Hearings Panel.

    Proposed Auckland Unitary Plan Provisions

    Not Applicable

  • 8/11/2019 002-PIR-21 August 2014

    4/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 3

    Planning Maps:

    Some E-Plan submission points relate to the functionality of Proposed Auckland

    Unitary Plan on-line maps.

    Overlays:

    Not included in this hearing topic

    Appendices: Relevant diagrams/figures:

    Some E-Plan submission points relate to

    the functionality of Proposed Auckland

    Unitary Plan on-line appendices.

    Not included in this hearing topic

    Provisions that took legal effect at

    notification (Section 86B RMA):

    None

    Proposed Auckland Unitary Plan

    provisions identification (Section

    80(8) RMA):

    Not Applicable

    OTHER RELEVANT DOCUMENTS

    None

  • 8/11/2019 002-PIR-21 August 2014

    5/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 4

    2. Submissions received and proposed hearing pathway

    2.1. Parties to this topic

    The following table provides an overview to the submissions made to this topic.

    Total number of primary submissionpoints

    1733

    Total number of primary submitters who

    wish to be heard

    479

    Total number of further submission

    points

    Not available until after 5thSeptember 2014

    Total number of further submitters who

    wish to be heard

    Not available until after 5thSeptember 2014

    Further Submissions NoteAt the time of the pre-hearing meeting on 2 September

    2014 the details of further submitters have not been made available by Auckland Council.

    Once these details are made available on 5 September 2014 this Parties and Issues

    report will be updated and further submitters allocated to submissions and any applicable

    pre-hearing processes.

    2.2. Submission Points Pathway Report (SPP)

    The primary submission points in this hearing topic are categorised in the submissionpoints pathway report. You can find a copy to the SPP for hearing topic 002- Eplan and

    Miscellaneous in theAUPIHP website.

    2.3 Grouping of submissions

    The Panel has directed that the submission points for this hearing topic be grouped to the

    matters listed in the table below. The allocation of a submission point to a matter listed in

    the table below is shown in the issue/provisions column in the submission points

    pathway report (SPP).

    SPP issue

    column

    reference

    Issues raised (Refer to the

    SPP to check allocation)

    Panel Preliminary Position (The

    matters in italics are the Panels

    preliminary indication of its

    approach to submission points

    allocated to this issue)

    Auckland Design

    Manual

    Request changes to content

    and administration of

    Auckland Design Manual

    website.

    Not a statutory planning matter and

    is not part of the PAUP

    http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/
  • 8/11/2019 002-PIR-21 August 2014

    6/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 5

    SPP issue

    column

    reference

    Issues raised (Refer to the

    SPP to check allocation)

    Panel Preliminary Position (The

    matters in italics are the Panels

    preliminary indication of its

    approach to submission points

    allocated to this issue)

    Bylaws Request new bylaws or

    changes to existing bylaws.

    Includes Sale of Liquor Act

    matters.

    Outside jurisdiction of RMA

    Central

    Government

    Request changes that relate

    to legislation other than the

    RMA or LGATPA. Alsoincludes requests for central

    government interventions or

    new policy approaches.

    Outside jurisdiction of RMA

    Consultation Seek additional consultation,

    engagement or

    communications

    Auckland council matter, cannot

    direct consultation.

    Development

    Contributions

    Matters related to the taking

    or use of Development

    Contributions under the Local

    Government Act 2002.

    Outside jurisdiction of RMA, not

    part of the PAUP

    Economic

    Development

    Seek Council support for

    named employment sectors or

    local economic development.

    Panel has no authority over funding

    or projects

    E-Plan Changes to E-Plan to improve

    accuracy and functionality.

    Refer to council

    Fluoride Seek the removal of fluoride

    from municipal water supply

    Outside jurisdiction of RMA

  • 8/11/2019 002-PIR-21 August 2014

    7/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 6

    SPP issue

    column

    reference

    Issues raised (Refer to the

    SPP to check allocation)

    Panel Preliminary Position (The

    matters in italics are the Panels

    preliminary indication of its

    approach to submission points

    allocated to this issue)

    Geographic

    naming

    Seek the renaming of a

    location within the Proposed

    Auckland Unitary Plan maps.

    Refer to council

    Governance Concerns functioning of

    Auckland Council

    governance, overall strategy

    framework, prioritisation offunding, property

    management, new revenue

    opportunities

    Outside jurisdiction of RMA

    Infrastructure &

    Environment

    Seek changes to Councils

    asset management and

    environmental management

    functions. Includes assets of

    Watercare Services ltd.

    Excludes parks and

    community facility assets and

    management.

    Panel has no authority over funding

    or projects

    Parks and

    Community

    Parks and community facility

    assets, management and

    acquisitions.

    Panel has no authority over funding

    or projects

    Rates Matters related to rating

    amounts, allocation, rebates.

    Panel has no authority

    Referendum Seek that Council undertake a

    referendum on a variety of

    issues.

    No power to recommend a

    referendum

  • 8/11/2019 002-PIR-21 August 2014

    8/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 7

    SPP issue

    column

    reference

    Issues raised (Refer to the

    SPP to check allocation)

    Panel Preliminary Position (The

    matters in italics are the Panels

    preliminary indication of its

    approach to submission points

    allocated to this issue)

    Section 32 Seek changes to all aspects

    of the Section 32 report on the

    Proposed Auckland Unitary

    Plan.

    Outside jurisdiction of RMA

    Southern Hauraki

    Gulf Islands

    Requests specific to matters

    excluded from the Proposed

    Auckland Unitary Plan relatedto the Southern Hauraki Gulf

    Islands.

    Out of jurisdiction as the PAUP

    district provisions do not apply to

    the Southern Hauraki Gulf Islands.

    Special Housing Changes specific to special

    housing areas or potential

    special housing areas.

    Includes matters related to the

    Housing Accords and Special

    Housing Areas Act 2013.

    Outside jurisdiction of RMA

    Titles and survey Seek changes to private titles,

    legislative changes related to

    titles.

    Outside jurisdiction of RMA

    Transport/Parking Focus on transportation

    infrastructure, routes,administration, and parking

    structures/land. Approximately

    354 submissions pertaining to

    Tamaki Drive.

    Outside jurisdiction of RMA

    UP Administration Requests related to resource

    consent operations,

    Amendments to variousaspects of the Councils

    Outside jurisdiction of RMA

  • 8/11/2019 002-PIR-21 August 2014

    9/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 8

    SPP issue

    column

    reference

    Issues raised (Refer to the

    SPP to check allocation)

    Panel Preliminary Position (The

    matters in italics are the Panels

    preliminary indication of its

    approach to submission points

    allocated to this issue)

    approach to generating the

    Unitary Plan and allocation of

    resources. Also includes

    support for the use of

    mediation practices in hearing

    procedures.

    Other Other issues outside of thescope of the Proposed

    Auckland Unitary Plan

    Outside jurisdiction of RMA

    2.4 Parties required to attend the pre-hearing meeting

    The Panel requires the Auckland Council to attend the pre-hearing meeting for this topic.Please refer to the SPP report for the specific points.

  • 8/11/2019 002-PIR-21 August 2014

    10/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 9

    3. Identifying the hearing pathway for submissionsTo identify the proposed hearing process (pathway) for your submission points, you need

    to find your submission point(s) in the attached Submission Points Pathway report (SPP).

    For further submitters please refer to section 3.4 below.

    3.1 Submitters who wish to be heard

    Submitters who do not agree with the proposed pathway within the SPP report need to

    attend the Pre-hearing meeting.

    3.2 Submitters who do not wish to be heard

    Submitters who have indicated that they did not wish to be heard have been recorded as

    consider in the pathway column in the SPP. These submission points will be read and

    considered by the Panel during the hearing.

    3.3 Submission points relating to minor errors and changes

    All submission points relating to E-Plan and Geographic naming have been recorded as

    refer to Council in the pathway column of the SPP. These matters will be referred

    directly to the Council for its consideration. The Council will be required to report the

    recommended outcomes for these submission points back to the Panel prior to the

    commencement of the hearing sessions.

    If the Council does not agree with the submissions being recorded as minor errors or

    changes, they can refer these back to the Panel at the Pre-hearing meeting. If the Panel

    agrees with the Council it will consider the submission point/s, and if the submitter

    indicated they wished to be heard, re-allocate the submission point/s to mediation, expert

    conferencing or to a hearing.

    3.4 Further submissions

    Further submission points follow the pathway of the primary submission point to which

    they relate. Refer to the Further Submission Report for 002 EPlan and Miscellaneous

    which is available on theAUPIHP website.(Notethis will not be available until after

    the 5thof September 2014)

    3.5 Further information

    For further information on these hearing pathways refer to thefactsheetson mediation,

    expert conferencing, pre-hearing meetings, evidence and hearings. TheHearing

    Proceduresdocument also contains information on the hearing pathways.

    http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/procedures/http://www.aupihp.govt.nz/procedures/http://www.aupihp.govt.nz/procedures/http://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/documents/docs/aupihphearingprocedures.pdfhttp://www.aupihp.govt.nz/procedures/http://www.aupihp.govt.nz/hearings/
  • 8/11/2019 002-PIR-21 August 2014

    11/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 10

    4. Documents from the pre-hearing and hearing pathway

    4.1 Hearing pathway documents

    This section includes the agendas, meeting records and joint statements for this topic.

    This table will be updated prior to the heading for this topic.

    Stages of hearing pathway and

    documents details

    Meeting

    Date

    Visit the AUPIHP website

    002 Eplan and Miscel laneous

    Pre-Hearing Meeting 1 2 September

    2014

    Pre-Hearing Meeting 2

    Pre-Hearing Meeting Report

    Mediation 1

    Mediation 2

    Mediation Report / Joint

    Statement

    Expert Conferencing Facilitator

    report

    Expert Witnesses Joint

    Statement

    Hearingevidence

    4.2 Independent expert evidence

    The Panel may request independent expert evidence to assist in the understanding of

    hearing topics. If the independent evidence is obtained a copy of the evidence will be

    made available from the link provided below.

    http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/http://www.aupihp.govt.nz/hearings/
  • 8/11/2019 002-PIR-21 August 2014

    12/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 11

    5 Summary of pre-hearing pathway outcomesPlease note- Section 5.1 will be updated after the pre-hearing meeting. Sections 5.2

    5.6 will be updated prior to the hearing for this topic.

    5.1 Pre-hearing meeting outcome

    This section provides an overview of the outcomes from the pre-hearing pathway for this

    topic.

    Pre-hearing meeting:

    Hearings Panel direction from

    pre-hearing meeting:

    Changes made to the Parties and

    Issues Report following pre-

    hearing meeting:

    5.2 Expert conferencing outcomes

    Note: Expert conferencing may not be undertaken for all topics, in which case N/A has

    been recorded.

    Issue 1

    Outcomes

    Issue 2

    Outcomes

    5.3 Mediation outcomes

    Note: Mediation may not be undertaken for all topics, in which case N/A has been

    recorded.

    Issue 1

    Outcomes

    Issue 2

    Outcomes

  • 8/11/2019 002-PIR-21 August 2014

    13/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 12

    5.4 Recommendations on minor errors and changes

    This section records the recommendations from Auckland Council in relation to thesubmissions that are coded as minor errors and changes.

    Submission points

    1

    Recommendations

    5.5 Agreements reached between parties outside of formal mediation orexperts conference pathway

    This section records the agreements reached between parties which were submitted tothe Panel during the pre-hearing pathway.

    Issue 1

    Outcomes

    Date received

    5.6 Connecting the outcomes from pre-hearing and hearing pathways

    The outcomes from pre-hearing pathways, or resulting from other hearing topic pathways,

    may not always connect, for example:

    between negotiated outcomes

    with other provisions in the Proposed Auckland Unitary Plan

    with outcomes from other related hearing pathways

    with consequential hearing outcomes.

    The connections between outcomes that need to be considered for this topic are:

    Note: This is not a definitive list and does not prevent any party to raising matters in this

    regard.

  • 8/11/2019 002-PIR-21 August 2014

    14/14

    002 E-Plan & Miscellaneous released on 21 August for the Pre-hearing MeetingPage 13

    6 Hearing Session

    002 E-Plan and Miscellaneous

    This topic will be heard by a Full Panel

    Date hearing commenced: Tentative 25 and 26 September 2014

    Date hearing completed: