00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

Embed Size (px)

Citation preview

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    1/6

    OPTIMAL DISTRIBUTED GENERATION ALLOCATION

    IN MV DISTRIBUTION NETWORKS

    G. Celli Member,

    IEEE, F.

    Pilo, Member,

    IEEE

    Department of Electric and Electronic Engineering

    Universityof Cagliari

    Piazza d

    Armi 09 123

    Cagliari,

    Italy

    Abstract: The necessity for flexible electric systems,

    changing regulatory and economic scenarios, energy savings

    and environmental impact are providing impetus to the

    development of Distributed Generation (DG), which is

    predicted to play an increasing role in the electric power

    system of the future. With

    so

    much new distributed generation

    being installed, it is critical that the power system impacts be

    assessed accurately so that DG can be applied in a manner that

    avoids causing degradation of power quality, reliability and

    control of the utility system. For these reasons, the paper

    proposes a new software procedure, based on a Genetic

    Algorithm, capable to establish the optimal distributed

    generation allocation on an existing MV distribution network,

    considering all the technical constraints, like feeder capacity

    limits, feeder voltage profile and three-phase short circuit

    current in the network nodes.

    Keywords: MV Distribution Networks, Distributed

    Generation, Genetic Algorithms, Network Planning.

    I. INTRODUCTION

    Distributed Generation (DG) includes the application of

    small generators, scattered throughout a power system, to

    provide the electric power needed by electrical customers. DG

    often offers a valuable alternative to traditional sources of

    electric power for industrial, commercial and residential

    applications. DG makes a large use of the latest modern

    technology and can be efficient, reliable, and simple to own

    and operate that it can compete with electrical power systems.

    In some cases DG can offer significantly lower cost and higher

    reliability than a customer can obtain from the electrical grid.

    In others, it can augment the grid so that the combination of

    grid and DG can provide higher performance than either could

    alone. But regardless, it offers an alternative that utility

    planners should explore in their search for the best solution to

    electric supply problems [1-31.

    Power system planning involves identification of the best

    equipment, along with its locations, manner of interconnection

    to the system, and schedule of deployment. Since cost is an

    important attribute in power planning, almost invariably one of

    the planners chief goals is to minimize overall cost [3,

    41.

    Whatever planning philosophy or paradigm is adopted for

    planning a power system, DG can influence other resources

    (i.e. transmission and distribution) and its correct impact is of

    the greatest importance to take the right decisions. In this

    paper, the important task of planning the optimal number and

    position of DG generators has been faced. This optimization

    permits the best location of generators to be found

    so

    that

    power losses in an existing distribution network are minimized,

    and investments for electric grid upgrade, due to the growth of

    the energy demand of loads, can be deferred or reduced.

    Furthermore, the voltage profile and the three phases short

    circuit currents are checked and only those solutions able

    to

    remain within the range imposed by the planner are accepted.

    In order to perform this optimization a new software

    procedure, based on a Genetic Algorithm (GA), has been

    developed and tested on real size MV distribution networks.

    The structure of the paper is the following: in section I1 the

    most important features of DG are briefly described, in section

    some generalities on Genetic Algorithms are provided, in

    section IV the proposed GA for the optimal allocation of DG

    units is presented and, finally, in section V some results are

    shown and discussed.

    11.

    DISTRIBUTED GENERATION

    The need for more flexible electric systems, changing

    regulatory and economic scenarios, energy savings,

    environmental impact and the need to protect sensitive loads

    against network disturbances are providing impetus to the

    development of dispersed generation and storage systems

    based on a variety of technologies.

    In particular, the term DG implies the use of any modular

    technology that is sited throughout a utilitys service area

    (interconnected to the distribution or sub-transmission system)

    to lower the cost of service. DG can comprise diesel and

    intemal combustion engines, small gas turbines, fuel cells and

    photovoltaics. The purpose of these plants is to cope with the

    growing demand for electricity in certain areas and render

    certain activities self-sufficient in terms of power production

    thus achieving energy savings

    [

    1-31.

    The main reasons for the increasingly widespread use of

    dispersed generation can be summed up as follows:

    DG units are closer to customers so that Transmission and

    Distribution (T&D) costs are avoided or reduced;

    the latest technology has made available plants ranging in

    capacity from 1OkW to 15MW.

    some technologies have been perfected and are widely

    practiced (gas turbines, intemal combustion engines), others

    are finding wider application in recent years (wind, solar

    energy) and some particularly promising technologies are

    currently being experimented or launched (fuel cells, solar

    panels integrated into buildings);

    it is easier to find sites for small generators;

    0-7803-6681-6/01/ 10.00 001

    IEEE 81

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    2/6

    CHP (Combined Heat and Power) groups do not require

    large and expensive heat networks;

    natural gas, often used as fuel in DG stations is distributed

    almost everywhere and stable prices are to be expected;

    usually DG plants require shorter installation times and the

    investment risk is not

    so

    high;

    DG plants yield fairly good efficiencies especially in

    cogeneration and in combined cycles (larger plants);

    the liberalization of the electricity market contributes to

    creating opportunities for new utilities in the power generation

    sector;

    T&D costs have risen while DG costs have dropped, as a

    result the avoided costs produced by DG are increasing;

    DG offers great values as it provides a flexible way to

    choose a wide range of combinations of cost and reliability.

    For these reasons, the first signs of a possible technological

    change are beginning to arise on the international scene, that

    could involve in the next future the presence of a consistently

    generation produced with small and medium size plants

    directly connected to the distribution network (MV and LV)

    and characterized by good efficiencies and low emissions.

    In this context, the need to provide access to the distribution

    network to any company intending to install DG groups

    clashes with the need for utilities to manage these networks,

    maintaining adequate levels of security and quality.

    Consequently, the utilities are now faced not only with the

    technical problems involved in managing the networks that

    have been passing from passive to active (voltage regulation,

    protection policy, disturbances and interfacing problems), but

    also with new tasks. Undeniably, system planning and

    operation have become a much more uncertain task than in the

    past. For example, electric utilities may decide to resort to DG

    in the place of enforcing transmission and distribution plants.

    This will create new problems and probably the need of new

    tools for developing and managing these systems.

    III. GENETIC ALGORITHMS

    Genetic Algorithms are a family of computational models that

    rely on the concepts of evolutionary processes

    [5, 61.

    It is a

    well known fact that according to the laws

    of

    natural selection,

    in the course of several generations, only those individuals

    better adapted to the environment will manage to survive and

    to pass on their genes to succeeding generations.

    Correspondingly, the GAS operate on a set (population) of

    possible solutions (individuals) of a generic problem, applying

    selection and reproduction criteria whereby new solutions

    (offspring) are generated containing the information enclosed

    in the solutions fiom which they originated (parents). Clearly,

    the better the solution, the more possibilities there are of

    reproducing and passing on genes to the offspring.

    The first step to be taken in implementing these algorithms is

    to encode a potential solution in a simple data structure of the

    chromosomal type (generally a vector) in which each element

    is represented by means of a specific alphabet (usually binary).

    Once the initial population has been randomly generated, every

    solution is evaluated by means of the objective function.

    The strategy followed by GAS is very simple. To ensure an

    amelioration in the population, in each generation a selection

    operator sees to it that the solutions with higher fitness have

    greater possibilities

    of

    reproducing. At this point some

    individuals are coupled and cross-bred by means of a crossover

    operator, which recombines the salient information brought by

    the parent structures in a significantly non-destructive way.

    The crossover operator produces offspring, that will then

    replace some of the old individuals of the population. Lastly,

    the strings can undergo mutation, which involves selecting,

    with little probability, a string element and changing the

    symbol contained therein with another symbol of the alphabet

    being used (Fig.

    1).

    Once the procedures performed by the three operators have

    been completed, the offspring produced are evaluated and

    compared with their parents. If the GA is generational, then the

    offspring will replace all their parents, creating a new

    population. If on the other hand the GA is steady state then the

    offspring will replace their parents only if they are better.

    Several parameters normally influence the search for the

    optimum solution by GAS: population size, the probability of

    mutation, the maximum number of generations to be explored,

    etc.. These parameters should be accurately calibrated,

    adapting them to the size of the problem in question.

    IV. GENETIC ALGORITHM

    FOR

    THE OPTIMAL

    ALLOCATION

    OF

    DG UNITS

    The distribution network planning generally considers a

    temporal horizon of 5-20 years. During these years it is

    normally hypothesized that loads draw more energy fiom the

    grid, that new MVILV nodes appear and, eventually, that one

    or more substations can be built. The dynamic nature of the

    problem, jointly with its dimension (normally, thousands

    of

    MVILV nodes should be considered simultaneously), makes

    really difficult to examine all possible network configurations

    to find the optimal network arrangement that minimizes the

    cost of construction, maintenance and energy losses. If the

    network architecture is assumed to be invariable during the

    planning period, changes in load energy demand or the

    appearance of new loads could require investments for network

    SELECTION

    Population

    CROSSOVER

    MUTATION

    Parents Offspring

    Fig.

    1.

    GAoperators

    82

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    3/6

    upgrade. DG, in addition to the advantage of reducing power

    losses, can be a valuable option for the planning engineer to

    defer or reduce investments for grid upgrade. Moreover, the

    greater attention should be paid in the siting and sizing of DG

    units because their installation in non optimal locations can

    result in an increasing of power losses having opposite effects

    than those described. For these reasons, optimization tools,

    able to find the correct siting and sizing of DG units in a given

    network, can be a valid aid for the planner who has to face with

    the worldwide growth of DG penetration. In the paper, a GA

    optimization technique has been developed for the optimal DG

    allocation in MV distribution networks that is deeply described

    in the following sections.

    A . Coding of the solution

    The first important aspect of a correct implementation of the

    GA is the coding of the potential solution. Considering that the

    network structure is fixed, all the branches between nodes are

    known, and the evaluation of the objective function depends

    only on size and location of the DG units. For this reason each

    solution can be coded by using a vector, whose size is equal to

    the number of nodes, in which each element contains the

    information on the presence or not of a DG unit. In order to

    perform not only the siting but also the sizing of DG, a

    prefixed number

    NDG)

    of generator sizes have been assumed

    and classified (e.g. size number 1 corresponds to a 100 kVA

    DG unit, size number 2 corresponds to a

    200

    kVA DG unit,

    etc.). Therefore, each element of the vector solution is

    represented by means

    of

    the following alphabet:

    no DG located on the node;

    size index of the DG installed in the node.

    0

    1,

    .

    NDG

    Of course, the vector elements corresponding to the HV/MV

    primary substations are fixed to 0.

    The type of code used is suitable for every kind of network

    structure (radial, meshed, etc.), that influences only the

    assessment of the usual technical constraints (voltage profile

    and thermal feeder capacity) considered during the evaluation

    of the objective function, but does not affect the optimal

    allocation procedure. In the paper the algorithm has been

    applied to open loop distribution networks, that are

    commonly used in Italy, described in subheading D.

    B.

    GA Implementation

    is randomly generated by means of the following procedure:

    In the first phase, an initial population of possible solutions

    for each solution a value of DG penetration is chosen

    between

    0

    and a maximum limit of DG penetration, fixed

    by the planner on the ground of economical and network

    security justifications;

    a number of DG units of different sizes is randomly

    chosen until the total amount of power installed reaches

    the DG penetration level assigned;

    the DG units are randomly located among the nodes of

    the network;

    the objective fimction (OF) for each solution is evaluated

    verifying all the technical constraints; if one of them

    is

    violated, the individual is discarded.

    Regarding the population size, the best results have been

    found assuming it equal to the dimension of the problem, i.e.

    the number of nodes in the network.

    In the second phase, the genetic operators are applied in

    order to produce the new solutions. In the paper the following

    implementation details for the operators have been considered:

    Selection: the remainder stochastic sampling without

    replacement scheme has been adopted, whereby the

    number of selections of each individual is calculated in

    the following way: expected individual count values are

    calculated as a fraction between the OF value of the

    individual and the average of

    OF

    value of the whole

    population. Then integer parts of the expected numbers

    are assigned, and fiactional parts are treated as

    probabilities. For example, a solution with an expected

    number of copies of

    1.4

    would receive one sure single

    copy and another with probability 0.4. This process

    continues until the population is hll .

    Crossover: the uniform crossover is adopted, by which

    each allele is swapped with probability

    0.5.

    Mutation: all the vector elements are mutated, according

    to a small mutation probability, choosing a different value

    in the defined alphabet.

    Each offspring is accepted if all technical constraints are

    verified and the total amount of DG does not exceed the

    maximum level of DG penetration.

    After several tests, a generational GA model has been

    implemented, because it seems to guarantee better solutions

    than the steady state model, even if with a greater number of

    iterations. Therefore, the offspring replaces all their parents,

    creating the new population. The procedure terminates when a

    maximum number of generations has been explored.

    C. Evaluation ofthe objective unction

    The objective function to be optimized within the technical

    constraints refers

    to

    the total cost of the network which

    considers [7,

    81:

    site of the substations and loads

    geographical, geological and urbanistic features of the area

    concerned

    power demands of the loads and their growth versus time

    duration of the planning period

    some cost parameters such as inflation and interest rates

    unit cost of kWh lost due to Joule effect (cost of losses)

    construction and maintenance costs of feeders of different

    cross-sections and for different types of lines (overhead,

    underground).

    Due to the current Italian standard, that does not admit

    islanded portion of MV network directly supplied by DG, the

    most common reliability indices for long interruptions are not

    modified by DG units and thus no service quality

    improvements can be achieved by normal customers. For this

    reason, the costs of disruptions are not considered in the

    83

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    4/6

    objective function. Of course, each customer with DG units can

    use them to supply, totally or partially, its loads during gnd

    faults or scheduled interruptions, increasing the availability of

    energy and reducing the number and duration of interruptions.

    The objective function to be minimized in the problem at

    hand is thus represented by the total cost

    CO, of

    the generic

    network, with present value taken at the beginning of the whole

    planning period of N years. This cost can be expressed by

    using the sum:

    N

    COG= C c o j (1)

    j = l

    where N T ~ ~s the number of network nodes, Ncp is the

    number of substations, NTorNcphe number of branches in the

    network and C the present cost of the branch.

    The cost of every branchj is the sum of the construction,

    residual, management costs, and cost of losses in the

    subperiods, transferred o the cash value at the beginning of the

    planning period by using economical expressions based on the

    inflation rate, the interest rate and the load growth rate (all

    of

    them constant) [7]

    The cost of every branch can be expressed by using:

    k = l

    where C is the total cost of the branchj Cwphe portion of

    cost independent of power flow, CoMk he cost term

    proportional to the power flow through the branch in the Ph

    subperiod (cost of losses) and

    m

    is the number of subperiods

    into which the planning period ofN years has been divided.

    COG

    s the constructioncosts,

    R , is the residual value,

    CO@s the management costs,

    ej is a binary factor that is equal to

    1

    for a resized branch

    and

    0

    for an existing one.

    the cost

    C

    independent of power, can be written by using

    Denoting with:

    (3):

    Coil

    = e .

    cocj Roj )

    +

    C0g-j

    (3)

    The cost of resizing the branch Cod akes into account the

    year of reconstruction to transfer the cash value to the

    beginning of the planning period, while the residual value R ,

    considers the fact that the planning period does not coincide

    with the life durationof the component.

    The cost of Joule losses in the h subperiod opjkan be

    calculated transferring, to the cash value at the beginning of the

    planning period, the annual cost of such losses

    CHk

    evaluated

    by using:

    c p j k =CkWh. 38760.coeffrj.Lj.ccpj z : k ) 4)

    where:

    Ckwhs the cost of kWh,

    coeff is the utilization factor

    of

    energy losses under full

    load, different for overhead and underground,

    8760

    are the number of hours per year,

    yj is the resistance per mof line [ 2/km],

    Lj is the branch length

    [km],

    4 k is the phase current in thefh branch [A] at the beginning

    of the

    Ph

    subperiod,

    ccpj is a corrective coefficient of the losses due to the

    simultaneityof loads.

    D. Distribution Network Structure

    Distribution networks always have a radial structure and are

    often subdivided into two different levels: trunk feeders and

    lateral branches.The degree of reliability obtainable with this

    network arrangement is limited by the fact that a fault in one

    part of the network results in outage in a large number of load

    points. To improve service reliability, emergency ties provide

    alternative routes for power supply in case of outages or

    scheduled interruptions. Emergency ties end with an open

    switch so that radial structure is maintained during normal

    conditions; firthermore trun s are subdivided in some

    segments by means of normally closed switches, generally

    positioned in

    MVILV

    nodes. During emergencies segments

    can be reswitched to isolate damaged sections and route power

    around outaged equipment to customers who would otherwise

    have to remain out of service until repairs were made [9].

    n

    important class of such networks are the open loop networks

    which are usually employed in urban power distribution

    systems.

    If

    there are no laterals (pure open loop networks)

    then service restoration is ensured through the emergency tie

    that connects the ends

    of

    the feeder. n intermediate

    alternative is to install laterals (spurious open loop networks)

    in which top priority customers are supplied through the main

    feeder and can be completely re-energized in the event of a

    fault. The main characteristic of both open loop networks is

    that only two branches can converge in a trunk node

    (topological constraint)

    [lo].

    Automatic switching devices

    along trun feeders and emergency ties may reduce both the

    duration of service interruption and the number of customers

    affected thereby (Fig.

    2) [9,

    101.

    Emergency connection

    A Pure open loop network with no lateral MV nodes

    mergency connection

    B) Spurious open loop network with lateral MV nodes

    Fig. 2. Open loop

    networks

    84

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    5/6

    E.

    Technical

    Constraints

    Cost of investments

    Cost of losses

    Each individual produced by GA operators has to comply

    with all technical constraints usually adopted by planning

    engineers, i.e. the voltage profile along the network trun s and

    the three-phase short circuit currents in the network nodes

    [

    11,

    121. Indeed, the presence of generation nodes in the

    distribution system can cause a voltage drop or an overvoltage

    in some points of the network. This situation depends

    particularly on the transformer control system used. Generally

    speaking, the connection of a generator to a network can result

    in an increase in the voltage that depends on the power

    supplied by the generator. For this reason, in the proposed

    methodology the voltage profile is checked and only those DG

    allocations able to maintain the voltage within prefixed ranges

    both in normal and emergency situations are evaluated.

    Calculations are performed by determining the impedance

    matrix 2 of each feeder examined and by calculating the

    voltage in each node of the network. The calculation of

    Z

    can

    be noticeable simplified considering the particular network

    architecture (open loop network).

    The presence of DG can change the magnitude, duration,

    and direction of the fault current. The fault current is modified

    since the connection of rotating generators modifies the

    characteristics (impedance) of distribution networks. In this

    context, one needs to verify that the alteration in magmtude,

    duration and direction of the fault current due to dispersed

    generation groups does not affect the selectivity of protection

    devices. In fact, the selectivity must be checked for each

    connection of a new generator to the distribution network. In

    the paper, fault currents are calculated for each DG

    configuration examined by using the diagonal elements of the

    short circuit matrix and the voltages in each node. Again all

    those situations which do not comply with this technical

    constraint cannot be accepted.

    With DGithout DG

    1,000,000US 5,000 US

    626,000 US 486,000

    US

    V. RESULTS AND DISCUSSION

    In order to show the capability of the proposed

    methodologies, an area of the real M Y Italian network has been

    considered. As shown in Fig. 3, it is constituted by 48 nodes

    divided into 3 HVMV substations and 145 MVLV trun

    nodes. The whole chosen area covers a surface of about 600

    km. The period taken into consideration for the planning study

    is 20 years long, with all nodes existing at the beginning of the

    period. For each

    MVLV

    node, a constant power demand

    growth rate of 3% per year has been assumed; the size of the

    installed transformer ranges from 100 kVA to 630 kVA. The

    majority of the branches is of the overhead type, but some

    buried cables exist. The thermal capacity constraint is verified

    for all the branches at the beginning of the planning period, but

    some of them will have to be resized according to the growing

    energy demand.

    In order to test the proposed methodology, DG units have

    been considered, ranging between 100-500 kVA. It is

    straightforward noticing that there are no limits on the size of

    DG units that can be treat by the optimization procedure

    MV/LV node with DG unit

    Fig.

    3.

    Test network 154 nodes

    proposed. The maximum level of DG penetration rate admitted

    for the study is

    20%

    of the total amount of power demand.

    The cost of Joule losses has been taken as

    0.05

    US /kWh,

    the cost for section unity has been assumed 0.3 US /* for

    buried cables and

    0,5 US /mm

    for overhead lines (no

    adjunctive costs for digging or poles, considering that no new

    paths are built).

    In Table I,

    the costs of investments for grid upgrade and of

    power losses are reported for the network in Fig. 3, without DG

    and with the optimal arrangement of DG units obtained with

    the proposed GA.

    It is worth noticing that DG units allow reducing both costs

    considerably. In particular, the greater saving is represented by

    the reduction of the investments for upgrading the existing

    branches. This is really an important result, considering that

    T&D costs represent almost 30-50 % of the kWh cost and the

    deferment of investments will produce benefits to both utilities

    and final customers regardless the type of distribution energy

    market adopted.

    Table I.

    Comparison

    between costs for the

    MV distributionnetwork inFig. 3

    Total cost 1,626,000US 491,000 US

    8

  • 7/25/2019 00932323_optimal Distributed Generation Allocation in Mv Distribution Networks_2001

    6/6

    VI.

    CONCLUSIONS

    DG is predicted to play an increasing role in the electric

    power system of the near future. In fact, studies have predicted

    that distributed generation may account for up to

    20%

    of all

    new generation going online by the year 2010. With so much

    new

    distributed generation being installed, it is critical that the

    power system impacts be assessed accurately so that these DG

    units can be applied in a manner that avoids causing

    degradation of power quality, reliability, and control of the

    utility system. On the other hand, DG has much potential to

    improve distribution system performance and it should be

    encouraged. For this reason, it is really important that

    distribution planners can have useful and efficient tools to take

    into account the opportunities of DG, avoiding costly and time

    consuming impact studies. On the basis of these

    considerations, the paper deals with the important task of

    finding the optimal siting and sizing of DG units for a given

    network

    so

    that the cost of power losses during a prefixed

    period of study can be minimized and investments for grid

    upgrades can be deferred. As shown in the discussion, the GA

    developed by the authors can be successfully applied in real

    size scenarios with several hundreds of nodes. The examples of

    application show that considerable savings can be achieved

    simply by adding some generation units in the right position.

    Further studies will deal with the development of new models

    for DG units that can consider not only synchronous

    generators, but also generation units with electronic power

    conditioners for network interfacing.

    VII. REFERENCES

    [l] CIGRE WG 37-23: Impact of increasing contribution of

    dispersed generation on the

    power

    system

    -

    Final Report. Electra,

    September 1998.

    [2] CIRED WGO4: Dispersed generation - Preliminary Report,

    CIRED'99, Nizza (Fr), 2-5 Giugno1999.

    [3] H. L. Willis, W. G. Scott, Distributed Power Generation, Marcel

    Dekker, New York, 2000.

    [4] Muscas, F. Pilo, W. Palenzona: Expansion of large MV

    networks: a methodology for the research of optimal network

    configuration, Proc. of CIRED96 Conference, Buenos Aires,

    Argentina, pp. 69-74.

    [5] D. E. Goldberg, Genetic Algorithms in Search, Optimization&

    Machine Learning, Addison Wesley, 1989.

    [6] T. Back, D. Fogel,

    Z.

    Michalewicz, Handbook of Evolutionary

    Computation, Oxford University Press, New York, 1997.

    [7] Invemizzi, F. Mocci, M. Tosi: Planning and Design Optimization

    of MV Distribution, Proc. of T&D World '95 Conference, New

    Orleans, USA, 1995, pp. 549-557.

    [SI F. Mocci, C. Muscas,

    F.

    Pilo: Network planning and service

    reliability optimization in MV distribution systems, Proc. of

    ESMO95 Conference, Columbus (U.S.A), 95CH35755, pp. 36-

    46.

    [9]

    G.

    Celli, F. Pilo: Optimal Sectionalizing Switches Allocation in

    Distribution Networks, IEEE Trans. Power Delivery, vol. 14, no.

    [IO] B. Cannas,

    G.

    Celli, F. Pilo: Optimal MV distribution networks

    planning with heuristic techniques, Proc. of AFRICON'99

    Conference, Cape

    Town

    (South Afiica), 28 Sept.-1 Oct. 1999,

    [ I] N. Hadisaid, J.

    F.

    Canard, F. Dumas: Dispersed generation

    impact on distribution networks, IEEE Computer Applications in

    Power, Vol. 12, No. 2, April 1999, pp. 22-28.

    [12]

    P. P. Barker, R. W. de Mello: Determining the Impact of

    Distributed Generation on Power Systems: Part

    I -

    Radial

    Distribution Systems Proc. of IEEE PES Summer Meeting,

    Seattle (USA), 16-20 July 2000, vol. 3, pp. 1645-1656. ISBN 0

    3, July 1999, pp.1167-1172.

    pp. 995-1000.

    7803-6420-1.

    VIII.

    BIOGRAPHIES

    Gianni Celli

    (M 1999) was bom in Cagliari,

    Italy, in 1969. He graduated in Electrical

    Engineering at the University of Cagliari

    in

    1994.

    He became Assistant Professor of Power System

    in 1997 at the Dept. of Electrical and Electronic

    Engineering of the University of Cagliari. Current

    research interests are in the field of MV

    distribution network planning optimization,

    power quality and use of neural Networks in the field of Power

    System. He is IEEE member.

    Fabrizio Pilo

    (M 1998) was bom in Sassari,

    Italy, 1966. He received the Dr. Eng. degree in

    Electrical Engineering at the University of

    Cagliari in 1992 and the Ph.D. at the University

    of Pisa in 1998. Since 1996 he has been Assistant

    Professor of Electrical Engineering at the

    Department of Electrical and Electronics

    Engineering of the University of Cagliari. His

    current research interests include electrical power systems, network

    planning and optimization and neural networks. He is IEEE and EI

    member.

    86