    JIT Production

    Henry C. Co

    Technology and Operations Management,

    California Polytechnic and State University

  • 7/29/2019 06 JIT Production

    2/23

    JIT Production (Henry C. Co) 2

    Major MPC Approaches

    Up to the late 1960s, the EOQ/ROP approach

    was the method of choice in production-inventory management (PIM).

    During the 1970s, the American Productionand Inventory Control Society (APICS)

    campaigned to promote MRP. For the 1980s, APICS promotes JIT

    production as the proper method of PIM.

    Another contemporary technique for

    managing production and inventory is theOptimized Production Technology (OPT)system.

  • 7/29/2019 06 JIT Production

    3/23

    JIT Production (Henry C. Co) 3

    EOQ/ROP

    Developed at Westinghouse by F. W. Harris

    in 1915.Event-triggered, uses Calculus to find the

    optimal order quantity

    Q =

    Major deficiencies. Ignores product structure relationships. Does not permit effective rescheduling in response

    to dynamic changes in demand or productionactivities.

    Reactive [backward looking] rather than proactive[forward looking].

    2DS

    H

  • 7/29/2019 06 JIT Production

    4/23

    JIT Production (Henry C. Co) 4

    MRP Resolves EOQ/ROP Deficiencies

    Matched sets. structured bill of material provides

    "matched sets" of components parts fromwhich to build the end items called for bythe master schedule.

    Proactive. Inventory and production management is

    guided by firm orders and forecasts offuture demand.

    orders for parts are matched with thedemand these parts are expected tosatisfy.

  • 7/29/2019 06 JIT Production

    5/23

    JIT Production (Henry C. Co) 5

    Nervousness of MRP

    Steady stream of changes confronted by

    manufacturing companies. Forecasts are wrong!

    bill of materials are revised!

    parts are scraped!

    vendors are late! etc.

    A significant change in the final assemblycreates changed requirements in feederoperations that are usually amplifiedbecause of lot size rules, set-ups, queues,

    and waiting time. A 10% change at assembly could easily

    result in a 100 % change at the front end.

  • 7/29/2019 06 JIT Production

    6/23

    JIT Production (Henry C. Co) 6

    The Toyota Production System

    A manufacturing strategy having a dominant

    theme of constantly reduced inventory and asystem of equipment, procedures andattitudes which eliminate waste and promoterespect for people.

    Just-in-time manufacturing is a productionphilosophy which calls for the production ofprecisely the necessary units, in thenecessary quantities, at the necessary times.

    The kanban system is an MPC system thatsupports JIT manufacturing.

  • 7/29/2019 06 JIT Production

    7/23

    JIT Production (Henry C. Co) 7

    Kanban System

    Developed in the 1970s by Toyota.

    Information system that supports JIT production. Kanban is a card, usually put in a rectangular vinyl

    envelope, that authorizes the production orwithdrawal of materials.

    Consequently, we can think of the kanban system

    as a manufacturing planning and control system. Three categories:

    pickup information,

    transfer information,

    production information.

    The kanban controls the production of morethan $4.8 billion a year!

  • 7/29/2019 06 JIT Production

    8/23

    JIT Production (Henry C. Co) 8

    FUNCTIONS RULES FOR USE

    Provides pick-up or

    transport information.

    Subsequent process picks up the

    number of items indicated by the

    kanban at the preceding stage.

    Provides production

    information.

    Preceding process produces

    items in the quantity and

    sequence indicated by the

    kanban.

    Prevents overproductionand excessive transport. No items are made ortransported without a kanban.

    Serves as a work order

    attached to goods.

    Always attach a kanban to the

    goods.

    Prevents defective

    product by identifying

    the process making the

    product.

    Defective products are not

    attached with a kanban.

    Reveals existing

    problems and maintains

    inventory control.

    Reducing the number ofkanban

    heighten their sensitivity.

  • 7/29/2019 06 JIT Production

    9/23

    JIT Production (Henry C. Co) 9

    Key Elements of Toyota Production

    Just-in-time production.

    People involvement: Teamwork, Discipline (jobdesign, methods), Supplier involvement.

    Total quality control.

    Kanban-controlled flow.

    Rapid setup to achieve JIT production. Group technology: mixed-model assembly.

    Streamlined plant layout.

    Capacity reserve to support peak production.

  • 7/29/2019 06 JIT Production

    10/23

    JIT Production (Henry C. Co) 10

    Total quality.

    Quality is everyone's job, each has an immediatecustomer. Many quality-related efforts are moved to the

    workers. TQC must become a company culture to be fully

    effective.

    Work simplification. Preventive maintenance. JIT production control: kanban-controlled. Focused factories.

    Supplier network. JIT accounting. Team approach.

  • 7/29/2019 06 JIT Production

    11/23

    JIT Production (Henry C. Co) 11

    Toyota Focuses on Eliminating Waste

    Queues = waste.

    Reduce queues a way to discoverproblems and reduce cost.

    Waste of overproduction and unnecessary

    inventory. Waste of time waiting.

    Waste in transportation.

    Waste of processing (making defective

    products). Waste of movement.

  • 7/29/2019 06 JIT Production

    12/23

    JIT Production (Henry C. Co) 12

    JIT Production

    Uniform production rate.

    Purchasing and producing small lots. Quick, inexpensive setups.

    Multiskilled workers and flexible facilities.

    High quality level.

    Effective preventive maintenance.

    Continuous improvement.Fix it, even if it ain't broke.

    Wake up the sleeping dog! A pull method of coordinating work

    centers (e.g., kanban).

  • 7/29/2019 06 JIT Production

    13/23

    JIT Production (Henry C. Co) 13

    Production Smoothing at Toyota The JIT system works in Toyota because of the unique way

    Toyota structure its master production schedule. Master production schedule in MRP seeks economies and

    efficiencies through economical lot sizes. at Toyota, the master production schedule is prepared with

    the goal of scheduling every product every day. Mixed-model assembly: processing a variety of models of the

    same family on the same assembly line.

    Aggregate production schedule. One-year horizon. Updated monthly; marketing and finance input.

    MPS has a three-month horizon. First month shows daily schedule for the final assembly of

    each model. Next two months lso in daily time-buckets, but in terms of

    model family. Daily schedules are determined by dividing the number of

    units required for the month by the number of working days inthe month.

    Same production for each item each day.

  • 7/29/2019 06 JIT Production

    14/23

    JIT Production (Henry C. Co) 14

    Illustration

    Forecasts for next two weeks:

    50% of the sales will be Product A, 25% will be Product B, and

    25% will be Product C:

    Typical U.S. plant: Make Product A for 5 straight days,

    Change over to Product B for two and a half daysProduce Product C for the balance of the week

    Under the JIT system: make Product A, followed by Product B, followed

    by Product A, followed by Product C, and the cyclerepeats.

    The goal is to schedule every product every day,and in a sequence which intermixes all products.

  • 7/29/2019 06 JIT Production

    15/23

    JIT Production (Henry C. Co) 15

    JIT MPS: Future Resembles Past

    OthersWeek 1 A A A A A A A A A A

    A A A A A A A A A A

    Week 2 B B B B B B C C C C

    B B B B C C C C C C

    Toyota (JIT)

    Week 1 A B A B A B A B A B

    A C A C A C A C A C

    Week 2 A B A B A B A B A B

    A C A C A C A C A C

  • 7/29/2019 06 JIT Production

    16/23

    JIT Production (Henry C. Co) 16

    A Two Card Kanban System

    Consider a multi-stage system.

    The output of workstation A is the input toworkstation B. Each filled container at the outgoing stocking point

    of A has a production (P) kanban; At the incoming stocking point in B, each has a

    withdrawal (W) kanban.

    At workstations B (the customer): As each container is opened, B detaches the W-

    kanban and deposits it in a withdrawal post(either a box or a board).

    At fixed intervals (e.g., 2 hours), a material

    handler (called "mizusumashi" at Toyota) picks upthe W-kanban at the withdrawal post; takes theW-kanban and the corresponding number ofempty containers to the outgoing stock point atworkstation A.

  • 7/29/2019 06 JIT Production

    17/23

    JIT Production (Henry C. Co) 17

    Order-Picking at the outgoing stocking point ofWorkstation A: The material handler:

    Picks up the corresponding number of filled containers.

    Detaches the P-kanban from each filled containers atthe outgoing stock point.

    Deposits the detached P-kanban in a receiving post.

    Attaches a W-kanban to each of these filled containers. Transports the filled containers to Workstation B.

    Production at Workstation A: Each kanban card deposited in the P-kanban post

    authorizes workstation A to produce one container.

    Attaches the production kanban to each filledcontainers, store at the outgoing stock point.

  • 7/29/2019 06 JIT Production

    18/23

    JIT Production (Henry C. Co) 18

    Two Card Kanban

  • 7/29/2019 06 JIT Production

    19/23

    JIT Production (Henry C. Co) 19

    Pull & Push Systems

    Push system (conventional production system).

    To maintain a high level of utilization (i.e., to keep theworkstations working), materials are pushed from eachstage to the succeeding stage(s).

    When something goes wrong in some intermediatestage, inventory builds up in the up-stream stages.

    Pull system (kanban-controlled) Production at each stage is triggered by its successor

    stage(s), and this process is carried all the way to theraw material acquisition stage.

    Production is controlled (i.e., pulled) by demand, asinformation of demand flows backwards from the finalstage (the final assembly) to the initial stage (the raw

    material acquisition). at each work center, all requests for production are

    made through the kanban cards.

  • 7/29/2019 06 JIT Production

    20/23

    JIT Production (Henry C. Co) 20

    Number of kanban Needed

    Number of kanban cards =

    AD = average daily demand for the month. WT = waiting time.

    PT = processing time for one container. CQ = container quantity -- limited to

    maximum of 10% of day's demand. PV = policy variable (determined by

    management) up to 10% of day's demand. WT + PT = time interval between order

    picking.

    ( ) ( )CQ

    PVPTWTAD ++ 1

  • 7/29/2019 06 JIT Production

    21/23

    JIT Production (Henry C. Co) 21

    Kanban and EOQ/ROP

    Observations by Walter Goddard of

    Oliver Wight Educational Associates,Inc.

    Both are reactive systems designed to

    replenish inventory -- the quantityused is the quantity ordered -- not inanticipation of future orders (MRP).

    Kanban system: linked replenishment.

  • 7/29/2019 06 JIT Production

    22/23

    JIT Production (Henry C. Co) 22

    Linked Replenishment

    The conventional EOQ/ROP system ignored

    the product structure/bill-of-materialsrelationships among the component parts.the demand of each component item isassumed to be independent of each other.Hence, items are replenished independently.

    With the kanban system, production of anitem is "pulled" by the demand for the itemat the succeeding stage. Last stage = the final assembly, which is planned

    in the master production schedule. If something is not used in the final assembly, no

    replenishment action will take place. Replenishment is therefore linked with the master

    production schedule, just like in MRP.

  • 7/29/2019 06 JIT Production

    23/23

    JIT Production (Henry C. Co) 23

    Quick Setups at Toyota

    To make:

    10,000 coronas a month, consisting of5,000 sedans, 2500 hardtops, and 2500wagons.

    20 days/month means producing 250

    sedans/day, 125 hardtops/day, and 125wagons/day.

    Die-change time

    In 1940's die-change time was 2-3 hours. In the late 1960's, it was cut to 3

    minutes.

    A 50 fold decrease!