Upload
hamad-gul
View
223
Download
0
Embed Size (px)
Citation preview
8/13/2019 1 b,b,b,vmbvmvmv
1/73
CONSTRUCTION CONTRACTMANAGEMENT
BY
MUMTAZ HUSSAIN
1
PROJECT DIRECTORCAPITAL DEVELOPMENT
AUTHORITHY
8/13/2019 1 b,b,b,vmbvmvmv
2/73
C .
D , , , . C
.
2
8/13/2019 1 b,b,b,vmbvmvmv
3/73
INTRODUCTION A contract is a formalized means of communication between two parties. This facility is used very commonly by the projectmanager and owner to control the delivery of their
ro ects.
3
A contract has the added advantage of forcing ownersto define their, requirements, organize and arrangetheir thinking, and make a commitment to their
project.
8/13/2019 1 b,b,b,vmbvmvmv
4/73
BASIC REASONS FOR A CONTRACT
BASIC REASONS1. It defines the work and the owners delegation of
responsibilities to the various parties to completethe work
2. It inherently defines the nature and extent of risk to various parties.
3. It defines the transfer of financial incentives to
complete the work.
8/13/2019 1 b,b,b,vmbvmvmv
5/73
CON AC
HE O D CON AC I DE I ED F OM LA IN
O D HICH MEAN D A NOGE HE ;
8/13/2019 1 b,b,b,vmbvmvmv
6/73
WHAT IS A CONTRACT?
A contract may be defined as a voluntary agreementenforceable at law, made between two or more parties,whereby rights are acquired by one party to act or forbearances by the other.
According to the Construction Specification InstituteCSI Manual of Practice, a contract is a romise or a
6
set of promises for the breach of which the law gives aremedy of the performance of which the lawrecognizes a duty (CSI 2008).
The agreement is reached by the acceptance of anoffer made by one party to do something for other for a stipulated consideration.
8/13/2019 1 b,b,b,vmbvmvmv
7/73
ELEMENTS OF A CONTRACT
These are the five basic elements of a contract
OFFER
7
CONSIDERATION ACCEPTANCE
LEGAL PURPOSE LEGAL CAPACITY
8/13/2019 1 b,b,b,vmbvmvmv
8/73
CONTRACT AGREEMENT
The agreement is designed to formalize thecontract. It brings together all the other contract documents by reference to them and is
8
.
8/13/2019 1 b,b,b,vmbvmvmv
9/73
CONTRACT MANAGEMENTThat function of a project which is responsible for conformation of performance within the stipulationsof contract.
CONSTRUCTION CONTRACT
9
A contract under which one party promises to furnish service& materials to build a structure for another party who promisesto pay for the work performed. There are two basic types of construction contracts
Fixed price (or lump sum) Cost type
8/13/2019 1 b,b,b,vmbvmvmv
10/73
CONSTRUCTION CONTRACT (Contd.)The success of a project is often judged on theconstruction performance because this activity ishighly visible. The success of a project is alsoinfluenced by;
The accuracy and details of its documentation
10
The understanding between parties and acceptanceof their particular responsibilities
How professionally and accurately the day to day
administration is handled How conflict or contractual problems are resolved.
8/13/2019 1 b,b,b,vmbvmvmv
11/73
Construction Project DevelopmentPhases
Typical construction project development
phases includes;1. Preliminary planning and feasibility studies2. Preliminar en ineerin and desi n3. Detailed Engineering design4. Procurement5. Construction6. Operation7. Demolition
8/13/2019 1 b,b,b,vmbvmvmv
12/73
Contracts are used during all phases of construction projects.In the first phase , which is the feasibilityphase, contracts are formed between an
firm, or an architectural firm to perform afeasibility and site selection study.In the construction phase contract areformed between an owner and aContractor firm.
8/13/2019 1 b,b,b,vmbvmvmv
13/73
C C DC :
1. C 2. E 3.
. 5. F6. B7. A
8/13/2019 1 b,b,b,vmbvmvmv
14/73
PEC BIDDING DOC MEN Standard Form of Bidding Documents (Civil Works)
(to be used for estimated value of more than Rs. 25 Millions)
Standard Form of Bidding Documents for Procurement of Works (E&M)(to be used for estimated value of more than Rs. 25 Millions)
Standard Form of Bidding Documents for Procurement of Works(For Smaller Contracts)(to be used for all type of procurement for estimated value of not more than Rs. 25Millions)
Standard Form of Contract for Engineering Consultancy Services(For Large Projects) Time Based Assignments(to be used for consultancy fee over Rs. 2 Millions)
Standard Form of Contract for Engineering Consultancy Services
(For Large Projects) Lump Sum Assignments(to be used for consultancy fee over Rs. 2 Millions)
Standard Form of Contract For Engineering Consultancy Services(For Smaller Projects)(to be used for consultancy fee not more than Rs. 2 Millions)
8/13/2019 1 b,b,b,vmbvmvmv
15/73
1. IN C ION O BIDDE2. CONDI ION OF CON AC (GENE AL PA I &
PA IC LA PA II)3. FO M OF ENDE & CON AC EC I IE4. PECIFICA ION & PECIAL P O I ION
A NORMAL SET OF TENDER DOCUMENTS
15
5. BILL OF Q AN I IE O CHED LE OF P ICE6. D A ING7. PPLEMEN A DA A
8/13/2019 1 b,b,b,vmbvmvmv
16/73
STAGES OF CONTRACT MANAGEMENT
A. PRE-REQUISITION OF INVITATION TOTENDER
B. FORMULATION OF TENDER DOCUMENTS
16
.D. CONTRACT ADMINISTRATION
8/13/2019 1 b,b,b,vmbvmvmv
17/73
A - PRE-REQUISITION FOR INVITATION TO TENDER
A-1. COMPLETION OF FEASIBILITY STUDIES TECHNICAL FEASIBILITY ECONOMIC VIABILITY
STAGES OF CONTRACT MANAGEMENT
(Contd.)
17
A-2. DETAILED ENGINEERING DESIGN
DESIGN OF PROJECT COMPONENTS
FINALIZATION OF TECHNICAL REPORTS SPECIFICATIONS COMPUTATION OF QUANTITIES FORMULATION OF ENGINEERS ESTIMATE
8/13/2019 1 b,b,b,vmbvmvmv
18/73
STAGES OF CONTRACT MANAGEMENT(Contd.)
A-3. ADMINISTRATIVE APPROVAL
PREPARATION OF PC-1 PROFORMA APPROVAL BY THE GOVERNMENT
18
A-4. ARRANGEMENT OF FINANCES LOCAL & FOREIGN EXCHANG COMPONENTS
A-5. LAND ACQUISTIONA-6. PREQUALIFICATION OF CONTRACTORS
8/13/2019 1 b,b,b,vmbvmvmv
19/73
B. FORMULATION OF TENDER DOCUMENTS
a. Specificationsb. Detailed Designc. Tender Drawings
STAGES OF CONTRACT MANAGEMENT
(Contd.)
19
d. Estimation of Quantitiese. Decision About Specific Provisionsf. Decision About format-ADB/IDAg. Conditions of Contract - Part 1 & II.
8/13/2019 1 b,b,b,vmbvmvmv
20/73
TENDER DOCUMENTS General Conditions of Contract
These define the legal rights and obligations of the parties
and may be described as the regulations under which thecontract will be performed.
Nominates an independent third person called the
20
General conditions vary from country to country andorganization to organization
Conditions of Contract internationally
Federation Internationale des Ingenieurs- Counseils(FIDIC), Switzerland, 1992.
Pakistan Engineering Council
8/13/2019 1 b,b,b,vmbvmvmv
21/73
Tender Documents (Contd.) Special Conditions of Contract
These are additions to, deletions from or amendments tothe General Conditions to make them project or partyspecific.
S ecifications
21
Give full description of work to be carried out Detail the materials and workmanship that the Contractor is to utilize in the project
Define the quality and standards of workmanship required Act as a legal evidence in the event of litigation
8/13/2019 1 b,b,b,vmbvmvmv
22/73
Tender Documents (Contd.)
Drawings Bill of Quantities
Quantities are estimates only and should have limits of accuracy
Tender
22
orma o er to un erta e t e pro ect. r ce, con t ons anmethod statements are detailed. It should be noted that alldocuments submitted with a tender form part of the tender
Letter of Acceptance Relevant Correspondence
This often include points of clarification of either theTender Documents or a tender.
8/13/2019 1 b,b,b,vmbvmvmv
23/73
INSTRUCTIONS TO BIDDERS
This Contains Information's And Instructions Which AProspective Contractor Is Required To Know Or Abide ByFor Participation In Tendering:-
Name Of Work To Be Constructed
23
ource un s or e or s Eligibility & Qualification Requirement Firms And Persons Authorized To Submit Tender Cost On Tendering Not Reimbursable What Makes A Tender Non-responsive Holding Of Pre-tender Conference, If Required
8/13/2019 1 b,b,b,vmbvmvmv
24/73
Stages of Contract Management (Contd.)
C. TENDERING/EVALUATION
C-1. Tendering
24
Tendering Process Packaging LCB/ICB Tendering
Types of Tender
8/13/2019 1 b,b,b,vmbvmvmv
25/73
Stages of Contract Management (Contd.)
C-2. Evaluation Tender Opening Preliminary Evaluation
25
Procedure for Preference
8/13/2019 1 b,b,b,vmbvmvmv
26/73
C-2 TENDER EVALUATION
C-2.1 AT TENDER OPENING IS TENDER SECURITY ACCOMPANIED
WITH TENDER?
26
,ACCOMPANIED BY?
POWER OF ATTORNEY
JOINT VENTURE AGREEMENT DISCOUNT (IF ANY)?
8/13/2019 1 b,b,b,vmbvmvmv
27/73
TENDER EVALUATION (Contd.)
GENERAL CONFORMITY OF:
Legal & Contractual Evaluation Cost & Financial Evaluation
27
Deviations:
Major
Minor
8/13/2019 1 b,b,b,vmbvmvmv
28/73
C-2.2 PRELIMINARY EXAMINATIONOF ALL TENDERS
TENDER EVALUATION (Contd.)
28
ELIGIBILITY & QUALIFICATION ARITHMETIC CHECK CURRENCY PROPORTION
ADJUSTMENT ON ACCOUNT OF FOREIGNCOMPONENT?
8/13/2019 1 b,b,b,vmbvmvmv
29/73
C-3. Detailed Evaluation Of Substantially
Responsive Tenders Only Detailed Scrutiny Of Minor Deviations:
TENDER EVALUATION (Contd.)
29
LEGAL & CONTRACTUAL ASPECTS TECHNICAL ASPECTS
COST & FINANCIAL EVALUATION
Clarifications (If Required)
Loadings Of Tenders For Minor Deviations
8/13/2019 1 b,b,b,vmbvmvmv
30/73
Legal & Contractual Evaluation
Evaluation for Responsiveness
Evaluation of legal & ContractualAspects
30
ompar son w t Pre-qua cat onStatus
8/13/2019 1 b,b,b,vmbvmvmv
31/73
Cost & Financial Evaluation
Correction of Errors Adjustment of Foreign Currency Components Interest Rate for Dela ed Pa ments
31
Price Adjustments Evaluated Tender Price Balanced Tender
8/13/2019 1 b,b,b,vmbvmvmv
32/73
Technical Evaluation
Program of Work Key Personnel Mobilization
32
Method of Construction Equipment Dewatering
Sub-Contractors Materials
8/13/2019 1 b,b,b,vmbvmvmv
33/73
TENDER EVALUATION (Contd.)
RANKING OF SUBSTANTIALLY
RESPONSIVE TENDERS
COMPARISON OF TENDERS AFTER
33
ALLOWING DOMESTIC PREFERENCE
ISSUANCE OF LOA
PERFORMANCE SECURITY
8/13/2019 1 b,b,b,vmbvmvmv
34/73
D P P D
Advertisement Pre-qualification Criteria
P F List of pre-qualified Contractors
I P B
34
B P P E L E B
Letter of Acceptance Submission of Performance Bond Signing of Contract Agreement Letter of Commencement/ Notice to proceed
Financial Assistance in form of Mobilization Advance
8/13/2019 1 b,b,b,vmbvmvmv
35/73
B C /P B M
Bidder conferences (sometimes called contractor conferences,vendor conferences, and pre-bid conferences) are meetings withall prospective sellers and buyers prior to submittal of a bid or proposal) are meetings with all prospective sellers have a clear and common understanding of the procurement (both technicaland contractual requirements), and that no bidder receivepreferential treatment.
35
Responses to questions can be incorporated in to theprocurement documents as amendments.
To be fair, buyers must take great care to ensure that allprospective sellers hear every question from any individualprospective seller and every answer from the buyer.
8/13/2019 1 b,b,b,vmbvmvmv
36/73
TENDER SECURITY/BID BOND
Bid Bonds are used to protect owners when thecontractor that is lowest, responsible , responsive
bidder on a competitively bid project refuses to enter into the contract for the project.
Amount of securit shall be in form of Cash De osit
36
Certified Cheque, Bank Draft, Letter of Credit,Guarantee from a Scheduled Bank in Pakistan or Foreign Bank Acceptable to Employer.
If Tender is not accompanied by an acceptableTender Security (1-3% of Est. Cost, whereas 3% for smaller Contracts). It will be rejected being non-responsive and having major deviation.
8/13/2019 1 b,b,b,vmbvmvmv
37/73
CON AC ADMINI A ION
P B F A /M A A E A P C D M I C 14 P
37
L D
B O C D P C C D L C
8/13/2019 1 b,b,b,vmbvmvmv
38/73
Performance BondsPerformance bonds are guarantees by the surety that a contractor will perform the work as required by all of the conditions and termsof the contractThe Performance Security shall be of an amount equal to 10% of the Contract Price stated in the Letter of Acceptance. Such Securityshall, at the option of the bidder, be in the form of either (a) bankguarantee from any Scheduled Bank in Pakistan or (b) bank
38
guarantee from a bank located outside Pakistan duly counter-guaranteed by a Scheduled Bank in Pakistan or (c) an insurancecompany having at least AA rating from PACRA/JCR.
"Commencement Date" means the date upon which the Contractor
receives the notice to commence issued by the Engineer pursuantto Clause 41.
8/13/2019 1 b,b,b,vmbvmvmv
39/73
The Engineer" means the person appointed by the Employer to act asEngineer for the purposes of the Contract. The Engineer shall
obtain the specific approval of the Employer before carrying outhis duties in accordance with the Clauses mentioned in documente.g.:
Consenting to the sub-letting of any part of the Works underSub-Clause 4.1 Subcontracting.
"Letter of Acceptance" means the formal acceptance by the Employer of the Tender.
8/13/2019 1 b,b,b,vmbvmvmv
40/73
5.2 Priority of Contract Documents
The documents listed at (1) to (6) of the Sub-Clause are deleted and substitutedwith the following:
(1) The Contract Agreement (if completed);(2) The Letter of Acceptance;(3) The completed Form of Bid;
40
-
(5) The Particular Conditions of Contract Part II;(6) The General Conditions Part I;(7) The priced Bill of Quantities (Appendix-D to Bid);
(8) The completed Appendices to Bid (B, C, E to L);
(9) The Drawings;(10) The Specifications; and(11)______ (any other).
8/13/2019 1 b,b,b,vmbvmvmv
41/73
L D
41
F 10%
8/13/2019 1 b,b,b,vmbvmvmv
42/73
BONUS
The Contractor shall in case of earlier completion be paid bonus up-toa limit and at a rate equivalent to 50% of the relevant limit and rate o fliquidated damages prescribed in the Contract.
42
8/13/2019 1 b,b,b,vmbvmvmv
43/73
'
C , C
, E :
( ) ,
( ) ( ),
( ' )
8/13/2019 1 b,b,b,vmbvmvmv
44/73
C
, ,
,
( )
8/13/2019 1 b,b,b,vmbvmvmv
45/73
51.1 Variations The Engineer shall make any variation of the form, qualify or quantity
of the Works or any part thereof that may, in his opinion, be necessaryand for that purpose, or if for any other reason it shall, in his opinion,be appropriate, he shall have the authority to instruct the Contractor todo and the Contractor shall do any of the following:(a) increase or decrease the quantity of any work included in theContract,b omit an such work but not if the omitted work is to be carried
out by the Employer or by another contractor),(c) change the character or quality or kind of any such work,(d) change the levels, lines, position and dimensions of any part of the Works,(e) execute additional work of any kind necessary for the completionof the Works, or (f) change any specified sequence or timing of construction of anypart of the Works.
8/13/2019 1 b,b,b,vmbvmvmv
46/73
O
:
Ability to influence cost over time
8/13/2019 1 b,b,b,vmbvmvmv
47/73
Ability to influence cost over time
Greatest potential to influence cost is during thepre-construction design phase
Claims avoidance begins during pre-construction Design phase
Intensive re aration and review of contract
documents Careful consideration of methods and
equipment = consider overall constructability
8/13/2019 1 b,b,b,vmbvmvmv
48/73
In the event of:
(a)the amount or nature of extra or additional work,
(b)any cause of delay referred to in these Conditions,
,
(d)any delay, impediment or prevention by the Employer, or
(e)other special circumstances which may occur, other than through adefault of or breach of contract by the Contractor or for which he isresponsible ,
8/13/2019 1 b,b,b,vmbvmvmv
49/73
C C , C
E E ,
D LP .
8/13/2019 1 b,b,b,vmbvmvmv
50/73
The Contract shall not be considered as completed until aDefects Liability Certificate shall have been signed by theEngineer and delivered to the Employer, with a copy to theContractor, stating the date on which the Contractor shall havecompleted his obligations to execute and complete the Works
and remedy any defects therein to the Engineer's satisfaction.
The Defects Liability Certificate shall be given by the Engineer within 28 days after the expiration of the Defects LiabilityPeriod, or, if different defects liability periods shall becomeapplicable to different Sections or parts of the PermanentWorks, the expiration of the latest such period, or as soonthereafter as any works instructed, pursuant to Clause 49 and50, have been completed to the satisfaction of the Engineer.Provided that the issue of the Defects Liability Certificate shallnot be a condition precedent to payment to the Contractor of the second portion of the Retention Money in accordance withthe conditions set out in Sub-Clause 60.3.
8/13/2019 1 b,b,b,vmbvmvmv
51/73
ADMINI E P OC EMEN :
C AC
,
. , ,
51
, , ,
, .I ,
(AD ) C .
.
8/13/2019 1 b,b,b,vmbvmvmv
52/73
CON AC CLAIM
C C .
: D
D I A A D
C
8/13/2019 1 b,b,b,vmbvmvmv
53/73
Claims Avoidance producing comprehensive, accurate, contract documents
constructability review clear understanding of contract requirements prior to
bidding having good administrative procedures in place
open and honest communication timely troubleshooting
Claims avoidance begins in the pre-constructionphase
8/13/2019 1 b,b,b,vmbvmvmv
54/73
53.1 Notice of Claims
Notwithstanding any other provision of the Contract, if the Contractor intends to claim any additional payment pursuantto any Clause of these Conditions or otherwise, he shall give notice of his intention to the Engineer with a copy to theEmployer, within 28 days after the event giving rise to the claim has first arisen.
53.2 Contemporary Records Upon the happening of the event referred to in Sub-Clause 53.1, the Contractor shall keep such contemporary records
as may reasonably be necessary to support any claim he may subsequently wish to make. Without necessarilyadmitting the Employer's liability, the Engineer shall, on receipt of a notice under Sub-Clause 53.1, inspect suchcontemporary records and may instruct the Contractor to keep any further contemporary records as are reasonable andmay be material to the claim of which notice has been given. The Contractor shall permit the Engineer to inspect allrecords kept pursuant to this Sub-Clause and shall supply him with copies thereof as and when the Engineer soinstructs.
53.3 Substantiation of Claims
Within 28 days, or such other reasonable time as may be agreed by the Engineer, of giving notice under Sub-Clause53.1, the Contractor shall send to the Engineer an account giving detailed particulars of the amount claimed and thegrounds upon which the claim is based. Where the event giving rise to the claim has a continuing effect, such accountshall be considered to be an interim account and the Contractor shall, at such intervals as the Engineer may reasonablyrequire, send further interim accounts giving the accumulated amount of the claim and any further grounds upon whichit is based. In cases where interim accounts are sent to the Engineer, the Contractor shall send a final account within28 days of the end of the effects resulting from the event. The Contractor shall, if required by the Engineer so to do,copy to the Employer all accounts sent to the Engineer pursuant to this Sub-Clause.
D
8/13/2019 1 b,b,b,vmbvmvmv
55/73
D
&
8/13/2019 1 b,b,b,vmbvmvmv
56/73
67.1 '
I E C , , C ,
C , , , ,
E , , , E , . C . N E E C .
C .
C , C , C E
E , .
C 67.1,
. P , , ,
8/13/2019 1 b,b,b,vmbvmvmv
57/73
P ICE ADJ MEN IN
CON C ION CON AC
8/13/2019 1 b,b,b,vmbvmvmv
58/73
INCREASE OR DECREASE OF COST I E
, .
I
58
, E
.
8/13/2019 1 b,b,b,vmbvmvmv
59/73
S.No. MATERIAL MARKETPRICE
MARKET PRICE Difference
Dec-07/
Jan 0831 st May-08 %
1 Cement 240 300 25.00
59
2 Reinforcement 47000 84000 78.72
3 Diesel 37.8 50.21 32.83
4 Bitumen 36395 48195 32.42
5 Labour (unskilled) 250 300 20.00
8/13/2019 1 b,b,b,vmbvmvmv
60/73
PRICE INCREASE
DEC 07/Jan 08to
March 2008to
60
31 st May 2008 31 st May 2008
39.40% 21.29%
8/13/2019 1 b,b,b,vmbvmvmv
61/73
Why a formula? M (
)
61
; M ;
M .
8/13/2019 1 b,b,b,vmbvmvmv
62/73
1. COMPLETION PERIOD OF THE CONTRACT
O .
2. CO OF HE CON AC
62
P A
PEC C C
( . 30 M ).
8/13/2019 1 b,b,b,vmbvmvmv
63/73
P C C P II
C 70 I D CA F
63
P = A+ *L /L + *F /F + *C /C +* / + *E /E + *M /M ..
APPENDI C
8/13/2019 1 b,b,b,vmbvmvmv
64/73
APPENDI C
CostElement
Description BaseCost
Weightages
Applicable index
(i) Fixed Portion - 0.35
(ii) Labour Government of Pakistan (GP)Federal Bureau of Statistics(FBS) Monthly Statistical
64
.
(iii) Cement- in bag FBS
(iv) Reinforcement Steel Pakistan Steel Mills/ FBS
(v) HSD PSO
(vi) Bricks FBS
(vii) Bitumen Attock/National Refinery
Total 1.0
8/13/2019 1 b,b,b,vmbvmvmv
65/73
3. DECI ION ABO ELEMEN O BE CO E ED
4. EIGH AGE OF EACH CO ELEMEN
65
5. ELEC ION OF O CE
I F B , B
E .
8/13/2019 1 b,b,b,vmbvmvmv
66/73
6. BA E CO P ICE
28 .
66
8/13/2019 1 b,b,b,vmbvmvmv
67/73
67
M P C
8/13/2019 1 b,b,b,vmbvmvmv
68/73
M P C
Quality and Cost Based Selection (QCBS) Least Cost Selection (LCS) Fixed Budget Selection (FBS)
68
Quality Based Selection (QBS) Single Source Selection (SSS)
M D B
8/13/2019 1 b,b,b,vmbvmvmv
69/73
P J ?
A ,
. A .
A , ,
, . O ,
.
Executing Project Procurement Management
8/13/2019 1 b,b,b,vmbvmvmv
70/73
Plan ContractingProcurement documents:
Request for Proposal (RFP) - requests a detailed proposal on how the work will be done, who will do it, . . . , basically a Project Execution Plan from thecontractor
Invitation for Bid (IFB, or RFB) - requests one price to do all the work.
Re uest for uotation RF - Re uests a rice uote er item, er hour charges, etc.
Test yourself:
Procurement Document Contract Type Scope of Work
RFP
IFB
RFQ
Cost Reimb. (CR)Fixed Price (FP)
Time/Matl (TM)
PerformanceDesign
Any
C
8/13/2019 1 b,b,b,vmbvmvmv
71/73
C
8/13/2019 1 b,b,b,vmbvmvmv
72/73
Employer
Contractor Consultant
Engineers Representative
M P C
8/13/2019 1 b,b,b,vmbvmvmv
73/73
M P C
Quality and Cost Based Selection (QCBS) Least Cost Selection (LCS) Selection Based on Consultants Qualifications
73
Single Source Selection (SSS) Fixed Budget Selection (FBS) Quality Based Selection (QBS)
Individual Consultants