Click here to load reader
Upload
justin-washington
View
214
Download
0
Embed Size (px)
DESCRIPTION
Beam Energy Tracking Beam Dumping System 4 x DCCT Dipole Current (4/5, 5/6, 6/7, 7/8) RF turn clock Powering Interlock System Quench Protection Power Converters Discharge Switches AUG UPS Cryogenics essential circuits auxiliary circuits Safe LHC Parameters Beam Current Monitors Current Energy SafeBeam Flag Required also for safe beam SPS Extraction Interlocks TL collimators Timing PM Trigger BLMs aperture BPMs for Beam Dump LHC Experiments Collimators / Absorbers NC Magnet Interlocks Vacuum System RF + Damper dI/dt beam current BLMs arc BPMs for dx/dt + dy/dt dI/dt magnet current Operators Software Interlocks Screens Machine Protection System and connected equipment Injection Kickers LHC Beam Interlock System Access Safety System Beam Dump Trigger Required for unsafe beam
Citation preview
1
Commissioning and Early Commissioning and Early Operation – View from Operation – View from
Machine ProtectionMachine ProtectionJan Uythoven (AB/BT)
Thanks to the members of the MPWG
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 2
Commissioning of the Commissioning of the Machine Protection SystemMachine Protection System
The LHC cannot be operated without a Machine Protection System (MPS) which is guaranteed to work properly Significant damage and long downtimes can be the
result of a not properly working MPS The path of commissioning of the MPS
needs to be well defined in advance This will be a recurring task during the
commissioning of the LHC but also after shutdowns, access, etc.
Beam Energy Tracking
Beam Dumping System
4 x DCCT Dipole Current
(4/5, 5/6, 6/7, 7/8)
RF turn clock
Powering Interlock System
Quench Protection
Power Converters
Discharge Switches
AUGUPS
Cryogenics essentialcircuits
auxiliarycircuits
Safe LHCParameters
Beam Current Monitors
CurrentEnergy
Energy
SafeBeamFlag
Required also for safe beam
SPS ExtractionInterlocks
TL collimators
Timing PM Trigger
BLMs aperture
BPMs for Beam Dump
LHC Experiments
Collimators / Absorbers
NC Magnet Interlocks
Vacuum System
RF + Damper
dI/dt beam current
BLMs arc
BPMs for dx/dt + dy/dt
dI/dt magnet current
OperatorsSoftware Interlocks
Screens
Machine Protection System and connected equipment
Injection Kickers
LHCBeam
Interlock System
Access Safety System
Beam DumpTrigger
Required for unsafe beam
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 4
Systems to CommissionSystems to Commission The core of the system
The Beam Interlock System (BIS) The LHC Beam Dumping System (LBDS)
All the systems connected to it BLM QPS – PIC – WIC Collimator System ….
Related systems Hardware
Safe Beam Parameters Beam Presence Flag
Software Post Mortem system Management of critical settings Software Interlock System Sequencer
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 5
Stages in CommissioningStages in CommissioningI. Without BeamI. Without Beam
Commissioning of MPS and connected equipment First test in the laboratory Followed by equipment test in the machine Followed by hardware Commissioning
Equipment tests under ‘normal operating conditions’ Interface between systems
A maximum of functions should be tested without beam Individual equipment, interface between systems, Post Mortem
analysis, Sequencer, Safe Beam Parameters, etc. Also if they can only be tested partially without beam, the partial
tests should be done as soon as possible
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 6
II. With beamII. With beam Many systems, like the BLM, Collimators and the
LBDS, will also need to be commissioned WITH beam Test individual systems with beam Test interface between systems with beam
The tests might need to be repeated at different stages in the commissioning Different beam intensities Different beam energies Different operational states:
Optics (squeeze ) Polarities of the magnets of the experiments Ion operation
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 7
Different Stages of Different Stages of CommissioningCommissioning
Different stages of operation Increasing risk Different operational states, not checked before
After commissioning of a stage, operation should be declared safe for given conditions (intensity, energy, state)
The ‘jump’ to the next stage should be small enough so that the commissioning process itself is safe
Several systems might move into the next stage together, but only one should be commissioned at a time
Step small enough to detect ‘misbehaviour’ but still functioning safely Commissioning of stage for a system
Can be ‘binary’: system not used before, to be used as of that stage Can already be commissioned at an earlier stage than required
Can be ‘continuous’: systems need to be retested to check the effect of larger beam intensities or energy or state on that specific equipment
Need to be re-commissioned at each defined stage
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 8
Definition of StagesDefinition of Stages Different stages
Can be different, and will be probably be more, than the stages as defined by Roger (1 bunch, 43 bunches, energies…)
Will be different for the different systems Injection system will not have different states depending on beam
energy: always at 450 GeV LBDS will have many stages depending on energy and fewer
depending on intensity Different Stages not ‘linear’: not always increasing in
intensity and energy First energy ramp with safe beam intensity, although injection might
already be commissioned for higher intensities Reduce intensity again when change of optics etc.
Complex description of the stages at which the different machine protection elements will need to be commissioned
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 9
Simplification of the Simplification of the Different StagesDifferent Stages
Some ‘main stages’ which can be identified for the different systems Based on possible damage levels
Will need additional sub stages and not always ‘linear’ ( see previous slide)
Used in next talk Jörg Wenninger: ‘What systems request a beam dump?’
Comm. before first beam
First pilot N = 10^12 p+ 43 bunches 156 bunches 936 bunches
0.45 and 7 TeV 0.45 and 7 TeV 0.45 and 7 TeV 0.45 and 7 TeV 0.45 and 7 TeV
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 10
Different SystemsDifferent Systems In this session, details of the
commissioning of the following systems will be presented Injection System (Verena Kain) Beam Dumping System (Brennan Goddard) Collimation System (Ralph Assmann, Guillaume Robert-
Demolaize) Beam Loss Monitoring System (Bernd Dehning)
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 11
Sequence of Sequence of CommissioningCommissioning
For a new stage different systems might need to be commissioned ‘simultaneously’
Can only do one at a time. Proposed logical order of commissioning:
1. Injection System2. Beam Dumping System3. Other Systems – expected or unexpected beam
dependence (BPMs, noise pick-up)4. BLM System5. Collimation System
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 12
Formal TestsFormal Tests Tests should be formalised
Checklist to be established and agreed BEFORE the tests If conditions are not met - tests not successful
not allowed to enter into the next stage To be done without and with beam
Similar as already done for the hardware commissioning
Should be applied to tests foreseen this year CNGS nominal intensity operation (JW) TI 8 (higher intensity?) TT40 high intensity tests with LHC beam (collimator tests) Sector test (low intensity, but important to check functionality)
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 13
Proposal of Machine Proposal of Machine Protection Coordination TeamProtection Coordination Team
Defines the different stages of commissioning of the Machine Protection System
In collaboration with operation team and equipment experts Dynamic specification, will need to change ‘on the way’ But still agreed and no changes ‘over night’
Defines the tests to be performed to go from one stage to the next
Dynamic specification But still agreed and no changes ‘over night’
Declares when a protection system is fully commissioned Participates in the commissioning of the Machine Protection
System Consulted in case of non-standard situations
Certain pre-defined conditions are not met: can operation continue? Still avoid decisions ‘over night’ (during the night)
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 14
Machine Protection Machine Protection Coordination TeamCoordination Team
Small team of Machine Protection Experts 4 – 6 people, always some of them available on short notice If required one contact person can be assigned
on duty for about a week Can be contacted by Machine Coordinator, EiC, etc. Advise on operation outside predefined conditions Will contact Machine Coordinator, EiC, etc.
Bring to attention possible dangers, not foreseen, by following up closely the operation of the machine
They will contact other MPS specialists if required
Jan Uythoven, AB/BT
Chamonix@Divonne 2006, Comm.– view from MP
Page 15
ConclusionsConclusions Commissioning of the machine protection system will take
place in stages Starting without beam during equipment tests and the hardware
commissioning period Followed by many different stages with beam Different for the different types of equipment
The different stages and the formal acceptance will need to be defined and agreed upon before the tests
See talks this session: overview, filling, dumping, collimation, BLMs Creation of a Machine Protection Coordination Team
Formalise the above procedures and validate tests Small team of experts, available for consultation +