28
1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: •Massachusetts Institute of Technology (MIT) •University of Illinois •Electricity Authority of Cyprus

1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

Embed Size (px)

Citation preview

Page 1: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

1

Findings and Recommendations of the CSP-DSW Study

C.N. Papanicolas

PRINCIPAL RESEARCH PARTNERS:

•Massachusetts Institute of Technology (MIT)

•University of Illinois

•Electricity Authority of Cyprus

Page 2: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

2

• Climate Change, need for reduction of CO2 emissions

•EU places central importance to reducing dependence on fossil fuels

•The launch of the Mediterranean Solar Plant of the newly founded Union for the Mediterranean (UPM)

•Stimulus packages and Research funding in both the EU and the US for cultivate new “green” technologies

Recent growth of interest in RES:

The CSP-DSW Project

Page 3: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

3

The Study Focused on:

The CSP-DSW Project

• An examination of current technologies for Desalination and Electricity Production using Concentrated Solar Power.

• An assessment of the maturity of the available technologies for implementation in a pilot and subsequently in a commercial plant.

•Defining the operational parameters, capacity and a conceptual design of a pilot plant. (constraint: budget of 18 MEuro + land)

•Providing an economic assessment, feasibility and viability of the proposed technology.

Page 4: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

4

The CSP-DSW Study comprises:A techno-economic assessment study of the current status

of technology in the co-production of electricity and desalinated using Concentrated Solar Power (CSP)

The CSP-DSW co-generation scheme utilises thermal energy from the Power Cycle and the Solar Harvesting for the desalination process

The CSP-DSW Project

Page 5: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

5

• Solar energy is harvested by a field of Heliostats on a hilly, south facing, location near the sea.

• The reflected solar energy will be captured by a central receiver and converted to heat and stored in a salt container of conventional or novel design.

• Storage initially is proposed at temperatures of 500 to 600ο C. A more advanced and challenging design operating at 600 to 1000ο C provides an excellent future solution for use with a supercritical CO2 cycle.

A Conceptual Design of a CSP-DSW plant:

The CSP-DSW Project

Page 6: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

6

• Steam is generated from the heat reservoir of the salt container; this production is augmented by collecting “waste” heat from the various subsystems of the entire unit.

• Electricity will be produced using commercially available steam extraction turbine.

• Desalinated water will be produced using an innovative Multiple Effect Distillation (MED) with a Thermal Vapour Compressor, principally from the heat output of the steam turbine and other heat sources of the system.

Design of a CSP-DSW plant:

The CSP-DSW Project

Page 7: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

FINANCIAL ANALYSIS OF THE CSP-DSW SYSTEM

Pursued by:

Indradip Mitra, George Tzamtzis & CNP.

7

Page 8: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

8

•A detailed Financial Assessment of the proposed conceptual pilot plant has been modelled

•The initial hypothesis about the advantageous nature of the co-generation scheme and the promise that RES hold for the future is confirmed

•A number of improvements in the incentives (principally feed in Tariffs) for the promotion of RES in Cyprus have become obvious.

Financial Analysis

Page 9: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

9

Financial Analysis

The financial analysis was carried out based on a Discounted Cash Flow (DCF) model

Four different desalination configuration options were examined for the CSP-DSW project, giving an insight on the choice of preference between MED and RO

The main Financial Indicators considered were:•Net Present Value (NPV)•Internal Rate of Return (IRR)•Benefit cost ratio (also known as profitability index)•Revenue cost ratio

Page 10: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

10

Financial EnvironmentProject Lifetime: 20 years

Construction time: 2 years

Annual Discount Rate: 6%

Inflation rate:2%

Debt interest rate: 6%

Income tax: 10% on the gross profit

Currency conversion rate: 1 Euro = 1.43 USD

Assumptions and Considerations

Financial Analysis

Page 11: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

11

Income and PerformanceElectricity selling price to grid: 0.26 €/kWh (Cyprus FIT for CSP)

Water selling price: 0.92 €/m3 (not FIT exists for “green” water)

Capacity factor: 85% (50,60 and 70% for first 3 years)

Clean Development Mechanism (CDM) benefits

GHG emission factor: 0.8 Ton/MWh

Benefit: 14 Euros per Ton of CO2

Assumptions and Considerations

Financial Analysis

Page 12: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

12

CSP-DSW System Parameters

Financial Analysis

Heliostat System

Storage System

Power Block Desalination

Capital Cost (mil. Euros)

15.0 1.1 5.4 0.77

O&M Cost (% of capital cost)

5% 5% 1% 5%

Replacement Cost (% of capital cost)

15% 35% 100% 100%

Lifetime (years)

10 15 20 20

Page 13: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

13

CSP-DSW System Parameters

Financial Analysis

OTHER COSTSUtilities: 1.5 Million EurosSite works: 1.5 Million EurosPiping: 1.5 Million EurosSalt: 0.46 Million Euros

Land RequirementsRequired land area: 214,000 m2 Land cost: 2.1 million Euros

Personnel Costs per year Salaries: 670 k Euros (30 people, technicians and administrators)

Annual ProductionElectricity Production: 25.7 GWhWater Production: 310,870 m3

For further studies the price of land needs to be more precisely defined, here the figure assumed is quite low and corresponds to high-inclination land

This system employs a very small MED unit for water production. This is to maximize profit since the FIT for electricity favours its production over water

Page 14: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

14

Financial Analysis

Page 15: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

15

Financial Analysis

Page 16: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

16

Financial AnalysisFinancial Analysis Results

With GHG benefits the financial performance is further enhanced!

Page 17: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

17

Financial AnalysisThe CSP-DSW system is attractive from a financial point of view!

The particular system was designed to yield minimum water, in order to make it more profitable.

Nevertheless, even if the small MED system is replaced with the large MED-TVC system presented earlier by Prof. Georgiadis, it still is profitable:

Without GHG benefitsNPV: 15.1 Million Euros IRR: 11.35%

Revenue cost ratio: 3.02Simple non-discounted payback: 8.7 yearsIncrease in capital costs: 3 Million Euros

This is a clear indication that water production from RES is not favoured in the current FIT system. Co-generation schemes are heavily penalised for water production

Page 18: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

18

Financial AnalysisThe CSP-DSW system in a non-FIT environment

The FIT currently in place introduces a market distortion.Interesting results are obtained if the FIT is omitted (assumed selling price for electricity 0.10 Euros/kWh)

The CSP-DSW system was examined with 3 options on the desalination unit:-A standard MED unit with daily production capacity of 1000 m3 of water-An Advanced MED TVC system with daily production capacity of 5000 m3 -An RO of equal capacity with daily production capacity of 5000 m3

Standard MED unit

RO unit Advanced MED TVC system

NPV (million Euros)

-20.5 -18.8 -18.1

Page 19: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

19

Financial AnalysisThe CSP-DSW system in a non-FIT environment

• All cases are financially non-viable. This is expected as at the moment RES are not competitive with fossil fuel

• The MED-TVC System is better than the other options: in these conditions, the co-generation scheme is preferable

• Comparison of RO and MED-TVC indicates that MED is preferable to RO on a financial level for the CSP-DSW system

Page 20: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

20

Financial AnalysisLevelized cost of productionDetermining the cost of electricity and water in a dual purpose plant is a complex issue.

Levelized Cost of Water (LCOW) through the Escaped revenue method:

e cg

W

Revenue RevenueLCOW

Production

eRevenue

cgRevenue

WProduction

is the revenue from electricity of the single purpose plant

is the revenue from electricity of the dual purpose plant

is the water production during the plants whole lifetime.

The difference of possible revenue streams between an electricity only plant of same characteristics and the cogeneration plant was thought to have occurred because of introducing the desalination facility into the electricity only system

Page 21: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

21

Financial AnalysisCSP-DSW system variations

3 options on the desalination unit were examined:-A small MED unit with daily production capacity of 1000 m3 of water-A MED TVC system with daily production capacity of 5000 m3 -An RO of equal capacity with daily production capacity of 5000 m3

Small MED unit RO unit MED TVC system

Capital Costs (million Euros)

25.4 28.5 28.5

Electricity produced (kWh per day)

83040 70296 69672

Water Production (m3 per day)

1000 5000 5000

In the above production values, a factor of 85% as operational availability has been used for financial calculations.

Page 22: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

22

Financial AnalysisLevelized cost of production

The Levelized Cost of Electricity (LCOE) for the dual purpose plant, is calculated after the LCOW is subtracted from the total levelized costs of the plant.

Small MED unit

RO unit MED TVC system

LCOE (Euro cent/kWh)

17.85 18.82 18.31

LCOW (Euro cent/m3)

193 104 107

Once again the FIT tariff for Electricity distorts the picture. Water production is penalised hence the low LCOE for maximum electricity production and large LCOW for the first case.

Page 23: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

23

Financial AnalysisFinancial Analysis Conclusions

From a commercial point of view CSP-DSW project is attractive

Water production induces a heavy penalty by reducing electricity production which is sold at a very attractive tariff

Without a feed-in tariff and GHG benefits all cases produce a loss: the technology is not yet ready to compete with fossil fuel

While the FIT stays fixed, O&M costs increase annually causing the net positive annual cash flow to decrease. The FIT should be linked to inflation to make investments in RES more attractive

A rough estimate of an optimized 50 MWe plant, indicates that the cost will be reduced to below 13 cent Euro/kWh.

Page 24: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

STUDY CONCLUSIONS AND

RECOMMENDATIONS

24

Page 25: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

25

• The concept of CSP co-generation is sound both from an engineering point of view and from an economic –policy point of view.

• The advantages of CSP-DSW are realized only when the power and desalination cycles are optimized together.

• The Heliostat – Central Receiver technology with a substantial storage capability is judged to be the most suitable. Desalination employing Multi Effect Distillation possibly in hybrid mode with Reverse Osmosis for added flexibility is recommended.

Recommendations

Page 26: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

26

• Given the currently available turbine technology a minimum size of 4MWe is required. A capital investment approaching 25 Million Euros (excluding the cost of land) will be needed.

• The utilization of a south facing hilly terrain on the

south coast of Cyprus as the preferred location to site such a plant is recommended. While the use of hilly terrain is a novelty, we recommend this option.

• A detailed and sophisticated business model reveals that such a plant, will be economically profitable.

STUDY CONCLUSIONS

Page 27: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

27

• A preliminary investigation of the commercially available components reveals that key components are not readily available for the particular application (e.g. conditions of saline humid costal environment).

• We judge that the unavailability of some components will introduce

unnecessarily high risk and imparting unacceptable financial risk.

• A number of “custom” solutions that need to be engineered for the particular application, such as the receiver and storage units, which are at the conceptual level sound and promising, have not yet been demonstrated or tested to a sufficient degree so as to present acceptable risk for an investment to a pilot plant.

STUDY CONCLUSIONS

Page 28: 1 Findings and Recommendations of the CSP-DSW Study C.N. Papanicolas PRINCIPAL RESEARCH PARTNERS: Massachusetts Institute of Technology (MIT) University

28

The CSP-DSW ProjectReccomendation:

The technological choices recommended provide a sound basis for the commencement of research and engineering studies for a 4 MWe CSP-DSW demonstration plant.

A decision to proceed with the construction of such plant presents high risk

We strongly recommend the pursuit of testing and demonstration of critical subsystems to assess the robustness and suitability of the technologies chosen in an island environment