1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

Embed Size (px)

Citation preview

Page 1: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

1

Lecture 45

Project Procurement, Contract Management,

andEthics

in Project Management

Page 2: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

2

Lecture 44 contents

• What is Risk?• Primary Components• Tolerance of Risk• Risk Management• Cat of Risk• Risk Planning• Risk Assessment (identification and analysis)• Risk Handling• Risk Monitoring• Qualitative Risk Rating

Page 3: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

3

Lecture 45 • Procurement

• Procurement Cycles– Requirement cycle– Requisition Cycle– Solicitation cycle– Award Cycle– Admin cycle

• 2. Type of contract– Six Categories of Contract

• Ethics in Project Management

Page 4: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

4

“Self-pity is our worst enemy &

if we yield to it,

we can never do anything wise in this world”

- Helen Keller

Page 6: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

6

“Treat people as if they were what they ought to be,

& you help them to become

what they are

capable of being”

- Johann Wolfgang von Goethe

Page 7: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

7

The quality of a person's life is in direct production to

their commitment to excellence,

regardless of their chosen field of endeavor.

Page 8: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

8

The race is not always to the swift...

but to those

who keep

on running.

Page 9: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

9

In three words, I can sum up everything I've learned about life: It goes on.

- Robert Frost

Page 10: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

10

Action in Your Project

“Action may not

always bring

happiness,

but there is

no happiness

without Action”

- Benjamin Disraeli

Page 11: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

11

Procurement

Acquisition of goods/services. Procurement (& contracting)is a Process that involves-Two Parties with: Different objectives Who Interact in a given market segment.

Page 12: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

12

Good Procurement Practices includes

Corporate profitability by:Taking advantage of:1. Quantity discounts, 2. Minimize Cost/Financial

Problems, 3. Seeking out Quality Suppliers.

Page 13: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

13

As Procurement Contributes To Profitability Procurement is Often Centralized,

-Results in “Standardized practices”

-”Lower Paper work Cost”

Page 14: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

14

Objectives of Procurement Planning are to select one of following for the Procurement of all Goods/Services:

1. From Single Source.2. From Multiple/source.3. Procure only small portion of

Goods/Services4. Procure none of Goods/Services

Page 15: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

15

Environment in which Procurement Take Place is Critical factor.Critical factor.

There are two environments: 1. Macro & 2. Micro.

Macro environment includes General external variables that can Influence “How & When” we do Procurement and it Includes:– Recessions, – Inflation, – Cost of borrowing money, – Unemployment.

Page 16: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

16

Micro environment is the internal to Firm Include “Procurement /Contract System” five cycles:

Requirement Cycle: Defines boundaries of Project

Requisition Cycle: analysis of sources

Solicitation Cycle: Bidding process

Award cycle: Contractor selection & Contract Award

Contract Admin Cycle: Managing subcontractor until Completion of the Contract.

Page 17: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

17

Several Activities of Procurement Process that overlaps Several of Cycles.

These cycles are conducted In parallel, especially “Requisition & Solicitation”.

Page 18: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

18

1. Requirement Cycle

First Step in Procurement Process “Definition of Project Specifically ‘Requirements”

Page 19: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

19

Requirement Cycle Includes1. Defining the need for the project

2. Development of the statement of work, specifications, and work breakdown structure

3. Performing a make or buy analysis

4. Laying out the major milestones and the timing/schedule

5. Cost estimating, including life-cycle costing

6. Obtaining authorization and approval to proceed

Page 20: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

20

Specifications

Written Pictorial or graphic Information describe define or specify services/item to be procured:

1. Design (physical Characteristics)

2. Performance (measurable capabilities)

3. Functional Specification ( subset of Functional , risk is on contractor)

Page 21: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

21

2. Requisition Cycle

Once the “Requisition identification”, ‘Requisition form’ sent to Procurement to begin “Requisition Process”.

Page 22: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

22

Requisition cycle Include:

1. Evaluation confirming specification.

2. Confirming sources

3. Reviewing past performance of sources

4. Producing Solicitation Package (S/P)

Solicitation Package sent to each possible “Supplier for Playing” Field is level.

Page 23: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

23

Specification Package Includes:1. Bid documents (usually standardized)

2. Listing of qualified vendors (expected to bid)

3. Proposal evaluation criteria

4. Bidder conferences

5. How change requests will be managed

6. Supplier payment plan

Page 24: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

24

3. Solicitation Cycle

Selection of “Acquisition Method” is the Critical Element in “Solicitation Cycle”.

Three Acquisition Methods :

• Advertising

• Negotiation

• Small Purchases (off supplies)

Page 25: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

25

Advertising company goes out for sealed bids.

There are no negotiations. Competitive market forces determine the price and the award goes to the “lowest bidder”.

Page 26: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

26

Negotiation is when the price is determined through a bargaining process. In such a situation, the customer may go out for a:– Request For Information (RFI)

– Request For Quotation (RFQ)

– Request For Proposal (RFP)

The request for Proposal (RFP) is the most costly endeavor for the vendor.

Page 27: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

27

Large proposals contains:

separate volumes for cost, technical Performance, Management History, Quality, facilities, subcontractor Management, & Others.

Page 28: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

28

On Large contracts the Negotiation Process may Also Includes Price, Quantity, Quality & Timing.

Vendor Relations are critical during contract negotiations.

Can Shorten Process due to: 1. Integrity of relationship & 2. Previous history

Page 29: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

29

Award Cycle (A/C)

Result in a “signed contract”. Several types of Contracts.

So Negotiation process also Include “selection” of the Type of Contract.

Page 30: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

30

Objectives of Award Cycle is to negotiate a contract:

-Type & Price

-Result in reasonable “Contractor risk” & Provide Contractor risk with Greatest Incentive for Efficient & Economic Performance.

Page 31: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

31

There are certain basic elements of most contracts.• Mutual Agreement: There must be an offer and

acceptance.• Consideration: There must be a down payment.• Contract Capability: The contract is binding only if

the contractor has the capability to perform the work.

• Legal Purpose: The contract must be for a legal purpose.

• Form Provided By Law: The contract must reflect the contractor's legal obligation, or lack of obligation, to deliver end products.

Page 32: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

32

The Two Most Common Contract Forms are completion contracts and term contracts.

• Completion Contract: The contractor is required to deliver a DEFINITIVE END PRODUCT. Upon delivery and formal acceptance by the customer, the contract is considered complete, and final PAYMENT CAN BE MADE.

Page 33: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

33

2. Term contract:

The Contract Is Required To Deliver A Specific "Level Of Effort," Not An End Product.

The effort is expressed in Woman/Man-days (Months Or Years) over a Specific Period Of Time using Specified Personnel Skill Levels And Facilities.

When The Contracted Effort Is Performed, the contractor is under no further obligation. Final payment is made, irrespective of what is actually Accomplished Technically.

Page 34: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

34

Final Contract also called

“Definitive contract”,

Follows normal Contracting Procedures. E.g. Negotiation of all Contractual “Terms & Condition” on Cost & Schedule prior to “Initiation of Performance”.

Page 35: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

35

Negotiating of contract and preparing it for signatures may require months of preparation. If the customer needs the work to begin immediately or if long-lead procurement is necessary, then:

Page 36: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

36

“Customer may provide the contractor” with a letter contract or letter of intent (LOI). The letter contract is a preliminary written instrument authorizing the contractor to begin immediately:

1. The Manufacture Of Supplies Or

2. The Performance Of Services.

Page 37: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

37

Final contract price

Must be negotiated

after performance begins,

‘Definitive contract”

must

still be negotiated.

Page 38: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

38

Types of contract selection based upon following:

1. Overall degree of Cost & Schedule Risk2. Type & complexity of Requirement (technical Risk)3. Extent of Price Competition4. Cost/Price Analysis5. Urgency of Requirements6. Performance period7. Contractor's Responsibility (and Risk)8. Contractor's Accounting System (Report Earn Value

reporting?)9. Concurrent Contract (contract take A back seat to existing

work?)10. Extent of Subcontracting (how much work contractor out

source?)

Page 39: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

39

General six types of contracts :

Fixed-price (FP),

Cost -plus-fixed-fee (CPFF),

Cost-plus-percentage-fee (CPPF),

Guaranteed Max-Shard Savings (GMSS),

Fixed-price Incentive- Fee (FPIF),Cost-Plus-Incentive-Fee (CPIF)

Page 40: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

40

First Category

Fixed-price or

Lump-sum contract

Page 41: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

41

Contractor carefully “Estimate Target Cost”.

Contractor required to Perform work at negotiated Contract Value.

Page 42: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

42

If “Estimated target cost” is low then “Total Profit reduced” & may vanish.

Contractor may not be able to “underbid competitors” So Contractor assumes a Large risk.

Page 43: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

43

Lump-sum

Provides “Max Protection to Owner” for ultimate “Cost of Project”.

Disadvantage:Requiring a Long Period For

Preparation & Adjudications of Bids.

Page 44: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

44

Because of a Lack of knowledge of

Local conditions, all contractors Include

Excessive Contingency.

Page 45: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

45

Chang Requested

By owner after “Award of contract” Lead to Troublesome &

Sometimes “Costly extras”

Page 46: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

46

2nd Category

Cost-Plus-

Fixed-Fee

(CPFF)

Page 47: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

47

Cost Plus Fixed Fee (CPFF)

If Accurate Pricing Not Possible in Any Other way.

So we use CPFF, so Cost may vary but Fee remains same.

Contractor agrees only to use Best Efforts to Performance

Good/Poor Performance

Rewarded equally.

Page 48: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

48

Total Rs/$ Profit likely To Produce Low “Rate of Return” reflects Small “Amount of Risk” By contractor.

Fixed Fee - small % Age Of “Tot/true Cost”.

CPFF Required Company books be audited.

Page 49: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

49

3: Cost-Plus-Percentage

– fee Contract

Page 50: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

50

Provides Maximum flexibility to owner Permits “Owner & Contractor” to work together cooperatively on All “Technical, Commercial, Financial Problems”.

-No Financial Assurance of “Ultimate Cost”.

Page 51: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

51

“No financial incentive to contractor” this because of “High building cost” (Compared with other forms).

Only meaningful Incentive can be:

1. Inc competition &

2. Prospects for

Follow-on contracts.

Page 52: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

52

4th Category of Contracts

“Guaranteed

Maximum-Share Savings”

Page 53: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

53

Contractor-Gets “Fixed Fee” for his “Profit” and Reimbursed for the “Actual Cost” of Engineering, Materials, Construction Labor, all Other Job Costs,

But only up to “Ceiling figure established” as “Guaranteed maximum"

Page 54: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

54

Savings below the" Guaranteed Maximum” are Shared between “Owner & Contractor”, where as Contractor Assumes the Responsibility

For any “Overrun beyond” Guaranteed “Maximum Price”.

Page 55: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

55

Contract form Combines advantages as well as disadvantages of Both “Lump Sum” & “Cost-Plus Contracts”.

Best form for Negotiated Contract as it Establishes a Maximum Price At Earliest Possible Date

Page 56: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

56

Though contract awarded without “Competitive Tenders”.

-Yet Protects owner Against being Overcharged,

Page 57: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

57

Unique in that “Owner & Contractor” share Financial Risk & Both have Real incentive To Complete Project At lowest “Possible Cost”.

Page 58: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

58

5th Category of Contract

Fixed-Price-

Incentive-fee Contracts

Page 59: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

59

These are Same as “Fixed-Price contracts” Except have some “Provision for Adjustment” of the “Total Profit” by a formula.

This Formula Depends on “Final Total Cost” at Completion of Project

Page 60: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

60

Formula “Agreed to” in advance By “Owner & Contractor”.

To use this Both “Project or Contract” Requirements Must be firmly established

Page 61: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

61

Provides An incentive to Contractor To:

a) Reduce Cost

b) Increase profit

Both “Owner & Cost” Share in “Risk & Savings”.

Page 62: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

62

6th Cat.

“Cost-Plus-Incentive-

Fee Contracts”

Page 63: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

63

Same as: “Cost” Plus Contracts, Except have “Provide for” Adjustment of “Fee as” Determined By a Formula:

Compares “Total Project Cost to Target Cost”.

Formula agreed to in advance by “Owner & Contractor”. Used for “Long Duration” or “R&D Type Project”.

Page 64: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

64

5. Contract Admin Cycle

Contract Administrator is Responsible for Compliance By the Contractor to Contract's “Terms & Conditions”

To Make Sure Final Product is “Fit for Use”.

Page 65: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

65

Functions of contract administrator Include:Change ManagementSpecification interpretationAdherence to Quality WarrantiesSubcontractor ManagementProduction surveillanceWaiversContract breachResolution of disputesProject TerminationPayment “Schedule” Project Closeout

Page 66: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

66

• Part Two

• Ethics

Page 67: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

67

Ethical OriginsEthical OriginsSocietal Ethics:

Standards of Members of Society

use when dealing with each other.Based on

“Values & standards”

Page 68: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

68

Societal Ethics:

Found in Society’sLegal Rules,

Norm, & Mores.Codified in the “Form of Law”

& Society Customer.

Page 69: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

69

Norms dictate how people

Should behave.Societal ethics vary based

On a given Society.Strong beliefs in one

country differ elsewhere.

Page 70: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

70

Professional Ethics:

“Values & standards used by

Group of Managers in workplace”.

Applied when Decision

not “Clear-Cut Ethically”.

Physicians/Lawyers

Professional Associates – (PMA, Bar Council)

Page 71: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

71

Values

An individual’s Basic

convictions of

What is “Right & Wrong”

Page 72: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

72

Values

Basic beliefs About what

one should or

should not do?

& What is &

is not important?

Page 73: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

73

Individual Ethics:

Values of an individual

resulting from their

family & upbringing.

Page 74: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

74

Behavior

not illegal,

Yet People still

disagree

If not

ethical.

Page 75: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

75

Ethics of top Project Manager

–set the –tone for –Project

Page 76: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

76

Ethics Codes

& Policies

Provide sign of top Management’s desires in

Project Based

Organizational culture

Page 77: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

77

Why Behave Ethically?Why Behave Ethically?

Project Manager should behave ethically

To Avoid Harming others. Managers Responsible for

“Protecting & Nurturing Resources”

In their Charge.

Page 78: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

78

“Leadership, Culture, Incentive

Compensation Plans” help Shape

“Individual Ethical behavior”

in Project Management

Page 79: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

79

Promoting EthicsPromoting Ethics

“Evidence” Showing “Ethical

Managers” benefit

over long term .

Page 80: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

80

Ethical Control System in Project Management

Formal System to encourage

Ethical Management.

Project Management Firms appoint an Ethics Ombudsman to monitor practices. “Communication standards”

To all employees.

Page 81: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

81

Ethical culture: firms increasingly seek to make good ethics part of norm & organizational culture.

Page 82: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

82

Ethical decisions involve

Normative Judgment implies “something is good or bad,

right or wrong, better or worse.”

Morality Society’s accepted norms of behavior

Page 83: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

83

Should you pay compensation pay to laid off workers?

– May December Stakeholder Return.

– Should you buy goods from overseas firms that hire children?

If you don’t Children may not earn enough money to eat.

Page 84: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

84

Views of Ethical Decision-Making

Decision makersseek to impose

and enforce rulesfairly and impartially

Decisions madesolely on the basis

of outcomes orconsequences

Decisions areconcerned with

respecting and pro-tecting basic rights

of individuals

Page 85: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

85

Code of Ethics

Professional organizations Project Management Institute

(PMI)

Taking a serious look at developing

Requirements for a Professional Project manager.

Page 86: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

86

Ethics obligation matrix.

Page 87: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

87

CODE OF ETHICS FOR PROJECT MANAGERS

PREAMBLE: Project Managers, in the pursuit of their profession, affect the quality of life for all people in our society. Therefore, it is vital that Project Managers conduct their work in an ethical manner to earn and maintain the confidence of team members, colleagues, employees, clients and the public.

Page 88: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

88

ARTICLE I: Project Managers shall maintain high standards of personal and professional conduct.

a) Accept responsibility for their actions.b) Undertake projects and accept responsibility only if qualified

by training or experience, or after full disclosure to their employers or clients of pertinent qualifications.

c) Maintain their professional skills at the state -of-the-art and recognize the importance of continued personal development and education.

d) Advance the integrity and prestige of the profession by practicing in a dignified manner.

e) Support this code and encourage colleagues and co-workers to act in accordance with this code.

f) Support the professional society by actively participating and encouraging colleagues and coworkers to participate.

g) Obey the laws of the country in which work is being performed.

Page 89: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

89

ARTICLE II: Project Managers shall, in their work:

a) Provide the necessary project leadership to promote maximum productivity while striving to minimize costs.

b) Apply state-of-the-art management tools and techniques to ensure schedules are met and the project is appropriately planned and coordinated.

c) Treat fairly all project team members, colleagues and co-workers, regardless of race, religion, sex, age or national origin.

d) Protect project team members from physical and mental harm.

e) Provide suitable working conditions and opportunities for project team members.

f) Seek, accept and offer honest criticism of work, and properly credit the contribution of others.

g) Assist project team members, colleagues and co-workers in their professional development.

Page 90: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

90

ARTICLE III: Project Managers shall, in their relations with employers and clients:

a) Act as faithful agents or trustees for their employers or clients in professional or business matters.

b) Keep information on the business affairs or technical processes of an employer or client in confidence while employed, and later, until such information is properly released.

c) Inform their employers, clients, professional societies or public agencies of which they are members or to which they may make any presentations, of any circumstances that could lead to a conflict of interest.

d) Neither give nor accept, directly or indirectly, any gift, payment or service of more than nominal value to or from those having business relationships with their employers or clients.

e) Be honest and realistic in reporting project cost, schedule and performance.

Page 91: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

91

ARTICLE IV: Project Managers shall, in fulfilling their responsibilities to the community:

a) Protect the safety, health and welfare of the public and speak out against abuses in those areas affecting the public interest.

b) Seek to extend public knowledge and appreciation of the project management profession and its achievements.

Page 92: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

92

•Part Two ends

Page 93: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

93

Social Responsibility

Social Power

Social Responsibility Concept

Project Management Organization must behave Proactively Business has certain social responsibility because power it wieldsBe a “Good Corporate Citizen”

Page 94: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

94

Social Responsibility Pyramid

Obey the Law

Make Enough Money To Survive

Good Corporate Citizen

Do What is Right, Just

Page 95: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

95

Levels of Social Responsibility

Reactive (Obstruction)

ProactiveDefensive Accommodative

Level of Social ResponsibilityLow High

Page 96: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

96

•Accommodative Response: Managers realize need for social responsibility. – Try to balance interests of all S/H.

Proactive response: Manager actively embrace social responsibility.

– Go out of their way to learn about & help Stakeholders

– “Good Corporate Citizen”

Social ResponsivenessSocial Responsiveness

Page 97: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

97

Why be Responsible?Why be Responsible?

Managers accrue benefits by being responsible.– Workers & Society benefit.– Quality of Life in Society improve.– It is the right thing to do.

Whistleblowers: a per reporting illegal

or unethical acts.

Now protected by law

Social audit: Managers specifically take ethics & business into account when making decisions.

Page 98: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

98

The Social AuditThe Social Audit

ProfitabilityNegative Low Medium High

NegativeNegative

LowLow

MediumMedium

HighHigh

Favored Strategies

Soc

ial R

etu

rns

Page 99: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

99

Arguments For Social Responsiveness

Business is

involved in

social issues

Page 100: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

100

Business resources to

tackle today’s complex societal

problems

Page 101: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

101

A better society means

a better environment for doing business

Corporate social action

will prevent

Government intervention

Page 102: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

102

How Firms Can Improve Their Social Responsiveness (Ethical Performance)

• Establish and publish their own Code of Ethics• Ombudsmen - (committee, task force) to review the

corporate past behavior• Protect whistle-blowing - when an employee

discloses an illegal, immoral, or unethical action committed by a member of the organization

• Training programs - ethical sensitivity training• Controlling compliance - corporate social audit (or

ethics audit)• Leadership - demonstrate commitment from

leaders• Involve personnel at all levels

Page 103: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

103

• Part Three

• Recap of the course

Page 104: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

104

• Management• Project Management • Project Manager• Project Proposal• Project Feasibility• Project Selection Method• Project Planning• Scope• Charter• Quality ( 3-4 )• Productivity

Page 105: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

105

• Leadership• Communication• Ethics• Costing• Pricing• Risk Management• Procurement• Close out Note

Page 106: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

106

• Part Four

• Project Management Institute (PMI)

Page 107: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

107

• Procurement Management Processes• Project Procurement Management involves

engaging in a systematic process to purchase or acquire the needed products, services, or results from an outside source which will perform the work. Procure Management encompasses contract management and control processes necessary to administer contracts or purchase orders. It also includes processes which assist in administering a contract to assure the buyer/seller relationships are properly managed. The procurement management processes are:

Page 108: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

108

• Plan Purchases and Acquisitions – Plan Purchases and Acquisitions process involves ascertaining what is needed, and when it is needed. Then how to assure you have what you need when you need it. (Novel concept!) This is completed as a part of the planning process group.

Page 109: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

109

• Plan Contracting – The Plan Contracting process involves documenting the products, services, and results requirements and identifies potential sellers. Plan Contracting is commonly first engaged in the planning process group.

Page 110: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

110

• Request Seller Responses – Request Seller Responses process obtains information, quotations, bids, offers, or proposals from sellers as appropriate. This is a part of the executing process group

Page 111: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

111

• Select Sellers – The Select Sellers process is where the offers are reviewed, and a chosen vendor rises to the top of the Analytical Hierarchy Process. Commonly negotiations are started in written form. This is commonly a part of the executing process group.

Page 112: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

112

• Contract Administration - The Contract Administration Process manages all aspects of the contract and the relationship between the buyer and the seller including managing seller performance and changes, providing a basis for future work, and managing the relationship with the project’s buyer. This is a part of the monitoring and controlling process grouping.

Page 113: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

113

• Contract Closure - The Contract Closure Process assures completion and settling terms of any contracts including resolving any open items and closing each contract.

Page 114: 1 Lecture 45 Project Procurement, Contract Management, and Ethics in Project Management

114

• Each Procurement Management process results in a specific deliverable which is used as the foundations for the subsequent process. Combined the procurement management processes provide a best practice pattern for managing contracts and vendor relationships on a project.