Upload
maud-morris
View
220
Download
1
Embed Size (px)
Citation preview
2
Overheads
Overhead includes a large number of types of indirect costs
Direct cost are identifiable to cost units, but overhead which are often considerable, cannot be related directly to cost units
3
Two-stage method to allocate overhead to products Overheads are assigned to the cost centres
such as department An allocation base is selected for allocating
production centre expenses to products
4
Procedures of overhead allocation to product Assign all factory overheads to cost centres Reallocate service-centre overheads to
production cost centres Calculate separate overhead absorption rate
for each cost centre Assign cost-centre overhead to products
7
Cost allocation
Where a cost can be clearly identified with a cost center or cost unit, then it can be allocated to that cost center or cost unit
8
Cost apportionment
It is not possible to identify a discrete item of cost with a cost center and it is necessary to split a cost over several cost centers on some agreed basis
9
Bases of apportionment
Apportionment of indirect expenses to cost centers must be made on fair and reasonable bases
Different types of expense require different bases according to their individual characteristics
10
Base of apportionment Costs
Area Rent and rates, heat and lighting, insurance of lighting
Machine value Depreciation, machine insurance
No. of employees Wages of supervisors, canteen cost
Example textbook P.183
12
Reallocate service-centre overheads to production cost centres Service departments are not directly involved in
production They only support service to other production
departments in order to facilitate the production process
Therefore, it is necessary to reallocate the service-centre overheads to production departments so that all production costs can be absorbed into production.
Typical bases are listed as follows:
13
Typical bases are listed as follows:
Service departments Possible bases of apportionment
Maintenance Maintenance labour hours, machine value
Stores Value or weight of materials issued, number of requisitions
inspection No. of employees, no. of jobs
Example textbook P.183
15
Calculate separate overhead absorption rate for each cost centre To determine the overheads to be absorbed
by a cost centre, it is necessary to establish an overhead absorption rate (OAR)
OAR =Total overhead of cost centre
Total number of units of absorption base applicable to cost centre
16
An appropriate OAR should reflect the effort or time taken to produce the products
Some commonly used absorption bases are listed as follows:
Direct labour hours It is frequently used in the labour intensive department because overheads assigned to this department are closely related to the direct labour hours worked
Machine hours It is most appropriate for the appropriate for the machining department since most of the overheads are closely related to machine hours
17
Direct wages It is only suitable in the department where the uniform wage rate is applied
Direct materials This method is not recommended unless the majority of overheads incurred in a department are related to materials instead of time
Units of output This method is suitable only where all units produced in a period are identical in the production process and time. Therefore, this application is very rare
Example textbook P.183
19
O/H Apportionment Total Production dept. Service dept.item Basis Maching Assembly Finishing Stores Maintenance
Indirect Actual 727 200 199 185 20 123material
$000 $000 $000 $000 $000 $000
Indirect Actual 510 200 200 80 10 20wages
Rent& Area 200 40 20 60 60 20RatesMachine Machine 30 16 10 2 1 1Insurance ValueDep. Machine 300 160 100 20 10 10
ValueHeat & Area 100 20 10 30 30 10Light
Production No. of 160 48 32 48 16 16Supervisor Employees
2027 684 571 425 147 200
20
O/H Apportionment Total Production dept. Service dept.item Basis Maching Assembly Finishing Stores Maintenance
$000 $000 $000 $000 $000 $000
2027 684 571 425 147 200
Reallocationof service-centreoverheads
Stores Materials issued 100 40 7 (147)Maintenance Maintenance 100 60 40 (200)
Work
2027 884 671 472 - -
21
Calculation of overhead absorption rates:
Maching Assembly Finishing
Overhead absorption basis
Machine hours
Machine hours Labour hours
Overhead absorption rates
$884000/200000 hrs
= $4.42/hr
$671000/100000 hrs
= $6.71 /hr
$472000/40000 hrs
= $11.8/hr
23
Assign cost-centre overheads to products The final step is to charge the overheads to
the products passing through the production departments
25
The facts are the same as those in Example on slide no. 18. The number of hours needed to finish the products are listed as follows:
Departments Product A Product B
Machining 4 hours 5 hours
Assembly 2 hours 1 hour
Finishing 1/10 hour 1/10 hour
26
Departments Product A $
Machining 4 hours at $4.42 per mach. hr. 17.68Assembly 2 hours at $6.71 per mach. hr. 13.42Finishing 1/10 hour at $11.88 per labour hr. 1.19Total overhead charged per unit 32.29
Departments Product A $
Machining 5 hours at $4.42 per mach. hr. 22.10Assembly 1 hours at $6.71 per mach. hr. 6.71Finishing 1/10 hour at $11.88 per labour hr. 1.19Total overhead charged per unit 30.00
28
Predetermined overhead absorption rates (POAR) The overhead absorption rates are usually
computed in advance of operations In practice, most absorption rates are only
predetermined because the actual overheads are not known until the end of the period
If the actual overheads are used to compute the OAR, the product cost can only be obtained at the end of the accounting period
A delay in product cost calculation will also affect the pricing setting, the profit calculation and stock valuation
29
POAR = Budgeted total overheads
Budgeted total number of units of absorption base
The formula are as follows:
The formula of POAR
30
Under-absorption and over-absorption base Since the POAR are based on the estimated
production and estimated overheads, the overheads absorbed seldom agree with the actual overheads incurred for the period
Under-absorption occur when overhead absorbed are small than the actual overheads
Over-absorption occurs when the overhead absorbed are greater than actual overheads
31
For financial accounting, under- or over-absorption of overheads should be treated as period cost and written off against the profit and loss account in the current accounting period
The under- or over-absorption of overheads should be debited or credited to the profit and loss account
The under-absorbed overheads should be deducted from profit and vice versa
33
Example
Estimated annual overheads $400 Estimated machine hours 200 machine hour
POAR = $400200 hrs
= $2 per machine hour
34
Product 1 Product 2 Product 3 Product 4
Actual overheads incurred
$400 $400 $300 $500
Actual machine hours
250 hrs 160 hrs 200 hrs 200 hrs
Overhead absorbed
Under- or over-absorption
$2 * 250 hrs= $500
$2 * 160 hrs= $320
$2 * 200 hrs= $400
$2 * 200 hrs= $400
Over-absorbed$100
Under-absorbed$80
Over-absorbed$100
Under-absorbed$100s
36
Blanket overhead rate
According to the overhead allocation procedure, the overheads are allocated to departments and each department calculate its own OAR and allocate the overheads to products passing through that department
Alternatively, some firms do not assign overheads to departments. Rather, they adopted a single overhead rate, i.e. a blanket overhead rate, that is assigned to all products produced within the whole factory
37
The use of the blanket overhead rate is not recommended as many products are produced in different production centres, and products consume cost-centre overheads in different proportions
39
The annual overhead costs of a factory with three production departments are shown as follows:
Dept. A Dept.B Dept. C Total
Overheads $20000 $400000 $180000 $600000
Direct machine hours
100000 100000 100000 300000
Departmental overhead rate per direct machine hour
$0.2 $4 $1.8
Blanket overhead rate pre machine hour
$2
40
If the production of product X only requires 10 direct machine hours in department A, the overheads absorbed will be computed as follows:
Using departmental overhead rate
Using blanket overhead rate
Overhead absorbed $0.2 *10
= $2
$2 *10
= $20
In this example, the production of product X does not consume Large amounts of overheads in department B and C. Therefore, there will be over-absorption of overheads if the blanket overheadrate is used