1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

Embed Size (px)

Citation preview

Page 1: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

1

Permitting of LCPs, Reporting Obligations on LCPs.

ECENA Training Workshop

Bristol, March 2008

Page 2: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

2

Introduction

This presentation, Session 4, addresses: Permitting of LCPs in particular reporting

requirements. Reporting obligations on LCPs. E-PRTR Requirements. Streamlining of reporting obligations under proposed

Directive on Industrial Emissions.

Page 3: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

3

IPPC Process

LCPs are subject to the IPPC directive: Deadline for implementation of IPPC

directive within Member States (EU27) was 30 October 2007.

Estimated that circa. 52,000 installations fell under the directive and at this stage should have an IPPC permit.

Page 4: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

4

Irish IPPC Permits

Irish permits are all available at www.epa.ie E.g. Full file for Bord Gais Eireann’s 440 MWe

Combined Cycle Gas Turbine and, including application and public correspondence: http://www.epa.ie/terminalfour/ippcApril/ippc-view.jsp?regno=P0830-01

Page 5: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

5

Permit to Ensure Integrated Approach Specified in IPPC Directive

waste

Raw materials

SO2

CO2

Hg

BOD

water

energy

VOCs

noise

odour

Page 6: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

6

Permit Conditions

Permit must include Emission Limit Values (ELVs) based on BAT.

For plants not meeting BAT realistic timeframes to achieve BAT need to be defined.

However, techniques or specific technology can’t be specified by permit unless proposed in application, e.g. a management system can be outlined but accreditation to ISO 14001 or EMAS can’t be requested.

Page 7: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

7

BAT Conditions for a Permit

When defining BAT, particularly for an existing installation, the permit writer needs to consider carefully: Cost and benefits analysis. Time for implementation. Prevention of detrimental environmental impacts. Monitoring and reporting obligations. Control of industrial accidents.

Data supporting the above will be in the application.

Page 8: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

8

The Aarhus Convention

Best practice for environmental approval procedures: Access to information. Public participation protocols. Access to justice. Appeals. Confidentiality issues.

Articles 15 and 16 of Codified IPPC Directive 2008/1/EC. Inspector’s report dealing with issues raised by public,

see www.epa.ie for projects which received objections.

Page 9: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

9

First UK IPPC Permit

UK had operated Integrated Pollution Control for 8 years.

New Power Plant (215 MW) using gas turbine for heat and power in large paper factory.

Issued in March 2001 after 5 months and 1 request for information.

Permit was issued by Environment Agency (EA).

Page 10: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

10

Departure form Previous Authorisations

Previous authorisations issued by the EA focused on processes in isolation.

The new IPPC permits take all aspects of the site’s operations into account.

Page 11: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

11

Permit Requirements

Many reports on improvement programmes rather than full information at beginning: 1 month - Commissioning of Turbines 3 months

Demonstrate Energy Efficiency Noise Management Plans

12 months - Annual Environmental Report

Page 12: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

12

Permit Requirements

Report every 3 years on: Potential Environmental Improvements including costs and benefits against BAT criteria.

Page 13: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

13

Permit Requirements

Environmental Management System (EMS) After 9 months the company must submit a report on

progress towards certification to ISO 14001 or EMAS.

Page 14: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

14

Waste

The company EMS must contain procedures to assess the recovery options for each waste stream.

Waste oil is collected for off-site recovery or disposal.

Page 15: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

15

Emissions to Air

Turbine uses natural gas with oil as stand-by. NOX was main concern:

Limits were60 mg/m3 on gas125 mg/m3 on oilAnnual mass 640 t

Page 16: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

16

Emissions to Air

Plant uses low NOX combustion technology. Permit requires continuous monitoring of:

oxides of nitrogen carbon monoxide oxygen

Page 17: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

17

Emissions to Water

Surface water discharge to be continuously monitored for: flow oil in water pH

Page 18: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

18

Emissions to Sewer

Wastewater discharges to drained to oil separator.

Discharges to sewer continuously monitored for: flow oil in water pH

Page 19: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

19

Noise

Permit requires: The use of acoustic enclosures of the gas turbines. The use of air intake and exhaust silencers. Low noise fans on the air cooled condenser system. Acoustic shielding in design of site layout.

Page 20: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

20

Land Contamination

Application form showed some contamination because of former use as steelworks. The Permit prohibits releases to land.

Requires operator to get approval from the Agency for changes to the site.

Page 21: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

21

Reporting Obligations - Operators

Article 13 of LCP Directive 2001/80/EC requires that the operator informs the competent authority within reasonable time limits about: Results of continuous measurement. Checking of the measuring equipment, required by

Annex VIII at least every year. The individual measurements and all other

measurements carried out for compliance.

Page 22: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

22

Reporting Obligations - Authorities

Annex VIII of LCP Directive 2001/80/EC requires that the Member States shall establish each year an: An inventory of SO2, NOx and dust for each plant.

The competent authority shall obtain for each plant: Total annual emissions of SO2, NOx and dust. Total annual energy input in categories of fuel: Biomass, other

solid fuels, liquid fuels, natural gas, other gases. Year by year plant data to be made available to the

Commission on request.

Page 23: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

23

Reporting Obligations - Authorities

Annex VIII of LCP Directive 2001/80/EC requires that the Member States shall provide to the Commission an annual report on ‘End of Life’ plants, Article 4(4): A record of used and unused time allowed for the

plants’ remaining operational life. Same annual report required for plants on

derogations; Article 5 or Annex III and VIA.

Page 24: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

24

Reporting Obligations - Authorities

Article 15 of LCP Directive 2001/80/EC requires that the competent authority provide the Commission with a summary report on the progressive reduction of total annual emissions from existing plants: At the latest one year after the end of the different phases for

reduction of emissions from existing plants. An intermediate report is required

in the middle of each phase.

Page 25: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

25

Reports – Where do they end up?

Most of the reports submitted on environmental data from Member States and other European Countries can be found on European Environment Agency’s data repository: http://cdr.eionet.europa.eu/

Note first annual LCP submission was 31/12/07.

Page 26: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

26

EPER Map of South Western UK

Page 27: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

27

EPER E-PRTR

50 Pollutants

56 IPPC Activties

Reports every 3 Years

Emissions into Air and Water

Emissions into Water (indirect)

91 Pollutants

65 Annex I-Activities

Annual Reporting

Emissions into Air, Water and Land

Accidential Release

Transfer of Pollutants into Waste Water

Waste Transfer (non-haz./haz. waste)

Emissions from diffuse Sources

Public Participation

EPER E-PRTR

Page 28: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

28

Relevant E-PRTR Compounds for LCPs

Main Compounds Carbon monoxide: CO Carbon dioxide: CO2

Nitrogen oxides: NOx/NO2

Sulphur oxides: SOx/SO2

Particulate Matter: PM10

Trace compounds Heavy metals such as Hg, Cd. Dioxins

Page 29: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

29

Annual Reporting E-PRTR

1. Report2007 2008 2009

Reported year15.6.08

(31.7.08)

Operator to Competent Authority

Competent Authority to National Authority

National Authority to EU COM

15.2.2009

30.6.2009

2. Report2008 2009 2010

Reported year 31.5.09(30.6.09)

31.12.2009

31.3.2010

n. Reportn n + 1 Jahr n + 2 Jahre

Reported year 31.5.n+1(30.6.n+1)

31.3.n+2

31.12.n+1

29

Page 30: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

30

Useful Links on E-PRTR

Commission PRTR Site: http://ec.europa.eu/environment/ippc/eper/index.htm

German PRTR site: www.prtr.de Irish PRTR Site: http://

www.epa.ie/whatwedo/enforce/lic/prtr/ EPER Site: http://www.eper.ec.europa.eu/eper/

Page 31: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

31

Comparison EPER vs E-PRTR

EPER represents the basis for E-PRTR Supplementary information in E-PRTR

Additional + Pollutants, Waste, etc. Diffuse Emission Sources

Traffic, Agriculture, Aviation, etc. E-PRTR involves more that the operators & Authorities Annual Reporting More Data

Page 32: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

32

Reporting Requirements for New Directive on Industrial Emissions

EU recognises that existing requirements are bureaucratic with duplication of effort.

Goal of new directive is to streamline reporting requirements for both operators and authorities: Estimated savings €105 to €255 million per year.

Page 33: 1 Permitting of LCPs, Reporting Obligations on LCPs. ECENA Training Workshop Bristol, March 2008

33

Questions?