51
1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

Embed Size (px)

Citation preview

Page 1: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

1PFP QSR, 10/19/2010

Particles and Fields PackageQuarterly Status Review (QSR)

October 19, 2010

Dave Curtis, PFP PM

Page 2: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

2PFP QSR, 10/19/2010

SSL Contracting Status

• Phase B/C/D Contract in place.

Page 3: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

3PFP QSR, 10/19/2010

Schedule Status

• No improvement in pre-CDR schedule – Power Converter Layouts started, but still lagging– SWIA/STATIC mechanical still behind but making progress– Due to personnel conflicts with RBSP

• FM1 through environments, FM2 in environmental tests, so end in in sight

• See next chart

• Also the ICDR date has been set, ~3 weeks earlier than previously planned

• Result is the EM system testing completes right about the time of the ICDR.

• No impact to CDR to Delivery margin (19w margin)– Flight build is currently gated by completion of MCDR– Delivery to ATLO moved up 1 week in latest REC-DEL list– MAG currently on critical path

Page 4: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

4PFP QSR, 10/19/2010

Manpower

• Concern with competition with RBSP-EFW for some key people– Power converter design team

• Reorganized team to streamline priority tasks– SWIA/STATIC/LPW boom mechanical engineers

• SWIA/STATIC EM mechanical parts behind• not yet on critical path to EM I&T

– FSW lead• keeping ahead of MAVEN schedule

– Additional parts engineer to be added to QA team• New hire: Job listed, advertized, should be filled soon.

Page 5: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

5PFP QSR, 10/19/2010

Accomplishments

• LPW ‘hingelss whip’ test model built, vibration tested– Passed using latest Atlas 5 loads and new aft deck levels

• 11.9grms random, 1 min.wmv

– Also ran case with additional margin and also a sine vibe, all OK– can eliminate caging system

• All EM and some FM EEE active parts on order, 87% delivered to GSFC– Remaining parts delivery dates meet schedule– Part qualification testing has just started, which adds some schedule

risk in case parts fail screening• PWBs are in layout• Most EM Mechanical parts are in fab

– Some part-level design work still in progress on SWIA/STATIC• PFP FSW Boot code 93% coded; operational code started

• More in instrument sections…

Page 6: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

6PFP QSR, 10/19/2010

Ongoing Work

• Supporting Project planning process• Supporting EMC, Payload, SDT working groups

• Getting the last of the EM parts on order (passives)• Working parts issues with the PCB, getting qualification

tests started.• Completing EM layouts and getting EM mechanical parts

ordered• Preparing for STATIC TOF system acoustic test next

month

Page 7: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

7PFP QSR, 10/19/2010

EM Status Summary

• SSL EM & GSE Layouts (23)– 11 complete– 9 in progress– 3 awaiting final schematic release

• LM Interface Test preparations (3/25/2011):– DCB board layout complete, PWB in fab, parts being kitted at GSFC– GSE & FSW ready to start testing– Current schedule shows ready by 1/5/2011 for the LM test

• EM EEE Parts– All active parts ordered, 87 of 94 types delivered to GSFC– Connectors on order– Passives being ordered

• EM detectors on order (MCP, SSD, foils, magnets)– SWIA MCP, STATIC foils, SEP magnets delivered

• EM Mechanical parts:– SWEA, SEP, LPW Boom (not sensor), STATIC TOF in fab– Remaining SWIA, STATIC parts into fab soon

Page 8: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

8PFP QSR, 10/19/2010

PFP RFA Status

Review Actions Closed %SWEA Peer 20 20 100%

Mechanical Peer 8 8 100%Analyzer Peer 11 11 100%Power Peer 0Digital Peer 4 4 100%FSW Peer 0LPW Peer 11 11 100%MAG Peer 5 5 100%

LPW Mech Peer 7 5 71%

IPDR 6 4 67%

Totals 72 68 94%

Page 9: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

9PFP QSR, 10/19/2010

Trades

• Considering changing LPW boom whip caging– Nick Jedrich Mechanical Peer Review recommendation– Change from caged to fixed whip

• Deletes caging mechanism mass & resources• Deletes whip hinge• Deletes an actuation• Simplifies qualification

– Concerns being investigated• Enhanced vibration on whip, preamp

– Built a demonstration model and completed vibration test to predicted levels plus margin, no problems.

• Potential damage to exposed whips during I&T– Possibly remove whip for some of ATLO

– PFP team believes we should go with the fixed whip• Need to submit a CCR & ECR for this change• Whip fundamental is below 100Hz (~25Hz). LM tells us they don’t

need a Structural Math Model (CDRL SE-05).

Page 10: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

10PFP QSR, 10/19/2010

Issues [1]

• Magnetics– New solar array configuration selected

• U-strings, small increase in ‘diving board’ length– Analysis indicates new configuration meets requirements for

most conditions• Assumes outer-most strings don’t switch• Will see a transient going in and out of shadow• Acceptable

– MAG Team and EMEWG will continue to watch magentics

Page 11: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

11PFP QSR, 10/19/2010

Issues [2]

• SWEA Surface Treatment– Need to modify thermal characteristics of surfaces in SWEA

aperture to avoid excessive heating - candidate solutions in work– Candidate solutions need to be evaluated for Atomic Oxygen

effects, charging effects, thermal properties, and robustness• AO test in complete, waiting on test report, post-test surface

resistivity measurements– Current candidates: DAG213, Ebanol-C, Black Nickel, Black

Chrome, Z307– SWIA and STATIC also interested

• SEP detector Atomic Oxygen effects– Heritage instruments survives AO, but we would like to test a

MAVEN detector if possible.• Included in the test

Page 12: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

12PFP QSR, 10/19/2010

Issues [3]

• Amptek HV801 failures– Solved immediate problem for EM – NGIMS providing parts

• Still pursuing three options for flight– New lot of Amptek parts

• In queue behind MMS– Micropak parts

• Some concern at GSFC about internal spacing of HV parts• May be OK for us as we do not exceed 5kV

– VMI parts• Larger, would require repackaging of SWIA, STATIC

Page 13: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

13PFP QSR, 10/19/2010

Issues [4]

• SWEA Planetary Protection– CESR part of SWEA FM build in progress– A memo has been developed by Project defining Planetary

Protection implementation at CESR which CESR has agreed to.– Issue Closed.

Page 14: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

14PFP QSR, 10/19/2010

Issues [5]

• Launch Loads– Selection of Atlas 5– Launch loads have been reduced significantly– ERD update pending based on acoustics

• SWEA heritage design may be OK with new loads– Depends on how you interpret factors of safety– Discussions ongoing with LM & GSFC

• Remaining instruments are OK with new loads

Page 15: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

15PFP QSR, 10/19/2010

Top Risks

MAVEN PFP RISK MANAGEMENT Chg RANK ID Approach TITLE

1 P-10 Research Operational Heaters

55 10 15 20 25

2 P-17 Watch Parts Qualification

44 8 12 16 20

3 P-04 Watch Solar Array Magnetics

33 8 9 12 15

4 P-01 Mitigate SSL Manpower

22 4 6 8 10

5 P-16 Watch Launch Loads

11 2 3 4 5

6 P-14 Mitigate HV801 Problem

1 2 3 4 5

Criticality Approach

High

Medium

Low

LIKELIHOOD

Improved

Worsening

Unchanged

New this month

Mitigate

Watch

Accept

Research

CONSEQUENCES

L * C Trend

*

P01

P16P4

P14

P10

P17

Page 16: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

16PFP QSR, 10/19/2010

Risks List [1]

ID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments

P-01 SSL ManpowerProject

Execution3 2 M

Delays in RBSP leads to manpower conflicts at SSL

Schedule erosion, cost to recover

Near Term

Hire new people to take routine tasks off key personnel

Mitigate Review in March 2010Add extra Power Converter person 1/2010Add extra ME 2/2010Add extra QA 8/2010

P-04Solar Array Magnetics

Mission Performance

2 4 M

Proximity of MAG sensor to solar arrays results in not meeting the magnetics requriements

Magnetics [MRD84]

Near Term

Consider ways to increase distance between MAG and cells

Watch Magnetics Working Group working on optionsChange to U-string system, slightly longer bracket. Ananlysis looks good

P-07Delayed LPW

Boom Deployment

Mission Performance

1 3 L

Waiting till after MOI to deploy LPW booms results in them sitting undeployed for over a year, increasing the risk of deployment failure

Potential severe degradation of LPW measurement

Far Term

Investigate if LPW booms can be deployed early

Research Early deployment of LPW booms reduces this risk. Actual risk of failure is very low. Risk that we may be asked to do an expensive verification is moderate

P-08

EUV sensor damaged by exposure to atmosphere

Mission Performance

1 3 L

If EUV does not close its door before deep dips (or any periapsis where EUV points into the RAM direction) sensor can be damaged

Degradation of EUV Lyman Alpha sensor

Far Term

- Include EUV door close to instrument autonomy rules.- Add MOC/SOC flight rule to reduce risk that human error results in incorrect operational script

Mitigate

P-10Operational

HeatersProject

Execution4 4 H

If operational heater reequirement to survive eclipse is significant, could impact power budget

Power Near Term

Pending thermal analysis Research Pending thermal models, spacecraft environments. Analysis in progress.

Page 17: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

17PFP QSR, 10/19/2010

Risks List [2]

ID Title Type P I Crit Risk Statement Impact Term Plan Approach Comments

P-13 Atomic OxygenMission

Performance2 3 L

If atomic oxygen degrades exposed surfaces, thermal, ESC, or other characteristics could be impacted

Thermal, ESC Near Term

Test materials if existing data is insufficient

Mitigate AO test selected materials

P-14 HV801 ProblemProject

Execution2 3 L

If HV801 not available a redesign would be required to use alternate (larger) parts

Schedule, Mass Mid Term

Watch what programs ahead of MAVEN do; look into alternate parts

Mitigate Micropak alternate part in test. EM parts found

P-15SWEA Surface

ChargingMission

Performance2 3 L

If SWEA (and to a lesser extent, STATIC) surfaces charge as STEREO did will lose low energy measurement

Performance Near Term

Do not use material which exhibited charging on STEREO. Verify any new material does not (difficult as the mechanisism for how the material charged is not fully understood)

Mitigate Material also needs to be insensitive to AO (P-13)

P-16 Launch LoadsProject

Execution2 3 L

If launch loads do not come down, will have to redesign instruments

Schedule Near Term

Wait for CLA before redesigning for unrealistically high loads

Watch Expect CLA ~11/2010, in time to redesign by CDR. Atlas selected. Loads inferred from accoustics significantly lower. SWEA marginal.

P-17Parts

QualificationProject

Execution3 3 M

If parts fail qualification then system would have to be redesigned for alternate (which may also have to be qualified and may have lower performance)

Schedule, Cost, Performance

Mid Term

Start parts qualification as soon as possible (but delayed to FY11 for funding)

Watch First round of parts radiation testing in planing

Page 18: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

18PFP QSR, 10/19/2010

PFP Mass

• Added extra radiation shield mass to SWEA– Increases electronics box walls from heritage ~60 mils to 100mils– Not required to meet radiation requirements, but a better use of mass

than ballast– Submitted CCR0228 to add 400g to SWEA NTE (not included above)

• Harness masses increased due to latest lengths provided by LM• LPW mass may decrease ~330g if we eliminate caging mechanism

(CCR pending)

Instrument QuantityCBE Each

[kg]CBE

Total [kg] Cont. (%)Total [kg] (CBE+cnt)

Particles and Fields 23.41 16% 27.19LPW Total 6.50 17% 7.62

LPW Booms 2 5.482 20% 6.578EUV Assembly 1 1.014 2% 1.039

STATIC Total 2.36 35% 3.19SWEA Total 1.94 0% 1.94SWIA Total 2.02 30% 2.62SEP Total 1.27 20% 1.52MAG Total 0.65 20% 0.78PFDPU Total 5.90 -1% 5.86PF Intra-Instrument Harness Total 2.78 32% 3.67

Page 19: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

19PFP QSR, 10/19/2010

Mass Tracking Chart

PFP Mass Trend

15.00

20.00

25.00

30.00

35.00

10/1/2009 11/20/2009 1/9/2010 2/28/2010 4/19/2010 6/8/2010 7/28/2010 9/16/2010

Date

kg

15%

20%

25%

30%

35%

Mass CBE, kg

Mass NTE, kg

Mass Margin %

Page 20: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

20PFP QSR, 10/19/2010

PFP Power

• Liens:– Expect to need operational heat during eclipse

• None allocated for most instruments; amount needed pending thermal analysis

• Preliminary estimates included for MAG and EUV• IPDR numbers for the remaining instruments are up to 13.3W (worst case

cold)– Does not look like LM-provided sinks change this much– Can decrease operational power requirement by ~3W by coupling SWEA to its

ballast mass

Instrument CBE [W] Cont. (%) NTE [W] CBE [W] Cont. (%) NTE[W] CBE [W] Cont. (%) NTE[W]Particles and Fields

Off (heater only) 0.00 0.00 10.58 18% 12.46 10.58 18% 12.46Standby 9.30 35% 12.52 3.81 15% 4.39 13.11 29% 16.91Nominal 19.20 16% 22.29 3.40 15% 3.91 22.60 16% 26.20

Peak 31.90 16% 37.01 15.90 15% 18.29 47.80 16% 55.30Orbit Average 19.31 16% 22.39 3.40 15% 3.91 22.71 16% 26.30

Orbit Average:LPW 4.77 15% 5.49 0.00 0% 0.00 4.77 15% 5.49EUV 0.16 15% 0.18 1.80 15% 2.07 1.96 15% 2.25STATIC 4.39 19% 5.21 0.00 0% 0.00 4.39 19% 5.21SWEA 1.07 15% 1.24 0.00 0% 0.00 1.07 15% 1.24SWIA 2.05 22% 2.50 0.00 0% 0.00 2.05 22% 2.50SEP 2.60 -14% 2.24 0.00 0% 0.00 2.60 -14% 2.24MAG 2.47 15% 2.84 1.60 15% 1.84 4.07 15% 4.68PFDPU 1.78 51% 2.69 0.00 0% 0.00 1.78 51% 2.69

Operational Heater Total

Page 21: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

21PFP QSR, 10/19/2010

PFP Power Trend

PFP Power Trend

15.00

20.00

25.00

30.00

10/1/2009 11/20/2009 1/9/2010 2/28/2010 4/19/2010 6/8/2010 7/28/2010 9/16/2010

Date

W

0%

10%

20%

30%

Power CBE, W

Power NTE, W

Power Margin %

Page 22: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

22PFP QSR, 10/19/2010

PFP Data Rate

• Per 2009-6-9 allocations from Bruce

Rate [bps]Particles and FieldsLPW/EUV 717.0STATIC 2000.0SWEA 600.0SWIA 604.0SEP 160.0MAG 660.0PFDPU 30.0

Total 4771.0

Instrument

Page 23: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

23PFP QSR, 10/19/2010

Requirements Verification Status

• Vibration test of LPW boom model verified hingeless whip will survive launch vibration.

Page 24: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

24PFP QSR, 10/19/2010

MAVEN Magnetometer Status

Oct 12, 2010

Connerney, Sheppard, Schnurr, Oliversen, Espley, etc.

Page 25: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

25PFP QSR, 10/19/2010

GSFC/MAG - Accomplishments Last Month(s)

• All MAG-related RFA’s have been closed (IPDR, Mission PDR).

• Obtained agreement on MAG budget (w/PI, Project, Code 600, 690).

• Received circuit boards for MAG a/c heater circuit; proto heater

controller assembly in fabrication.

• Procurement status of long-lead and limited availability items:– Mil spec CMOS quad bilateral switches (4066’s).

– Received flight LTC1604 ADCs (availability).

– Received /PROTO PWM 5032 parts from Aeroflex (for new heater

design).

– Fabrication of EM sensor assembly parts nears completion (delivery due

Nov 1).

• EM electronics board layout in process, completion by end of month.

• Magnetics piece parts (transformers, inductors) wound & in testing.

Page 26: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

26PFP QSR, 10/19/2010

Near Term Plans & Open Issues

• Complete EM board layout (Goddard PCB designer and SSL Mechanical Lead are finalizing the PCB MICD, expecting sign-off copy soon).

• Release EM PCB for fabrication (pending MICD w/UCB).• Revise MAG schedule to re-align with UCB schedule.• Finalize the baseline instrument command list and telemetry packet

contents. • Continued specification of the magnetometer as documented in the

Specification and User's Manual. • Complete FPGA functional blocks and interface definition.• Begin winding EM sensor ring cores, feedback/sense bobbins,

fabricate sensor terminal boards.

Page 27: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

27PFP QSR, 10/19/2010

MAVEN PFP SWIA Status

October 2010

Jasper Halekas, SWIA Lead

Page 28: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

28PFP QSR, 10/19/2010

SWIA Progress

• Layout Progress– Anode board layout complete, out for quote for fabrication– Preamp/MCP board layout in progress, now top priority– Digital board placed but not routed, likely headed to subcontractor– LVPS layout done, out for quote soon– SWP in progress, settled on shared layout for SWIA/STATIC

• Mechanical Design Progress– First priority: Support layout

• Most mechanical design now done for boards– Settled connector issues on boards shared with STATIC– Some work to be done on HV connectors, but settled on scheme

– Second priority: Flesh out attenuator and Anode/MCP housing• Anode/MCP housing and clamp stack design complete

– Mechanical drawings complete and in review, out for fab soon• Attenuator design next to receive major effort

– Third priority: Detail analyzer design• Settled issues in interface region between analyzer and electronics

box by splitting SWIA/STATIC analyzer designs slightly

• Microchannel plates arrived, testing starting soon

Page 29: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

29PFP QSR, 10/19/2010

SWIA Issues

• Staffing– ME staffing continues to be an issue

• Dalton and Johnson splitting time with RBSP• Situation should ease greatly in ~November

– Layout queue is still tight

• Layout Complications– First anode layout had some potential issues

• Revised layout now complete, but queue set back somewhat– Sweep board required coordination between SWIA and STATIC

• Settled on scheme that works for both (with slightly different schemes for HV connection to inner hemisphere)

• Next hurdle: Working on selecting chamber for MCP testing

Page 30: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

30PFP QSR, 10/19/2010

SWIA Anode Board Layout

Anodes/MCP Contact(Analyzer / Top Side)

Components/Traces(Component / Bottom Side)

Keep-Outs(Component Side)

Page 31: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

31PFP QSR, 10/19/2010

MAVEN PFP SWEA Status

October 2010

Dave Mitchell, SWEA Lead

Page 32: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

32PFP QSR, 10/19/2010

SWEA Status - CESR

• Mechanical– New mechanical sensor parts to upgrade Stereo EM delivered.

Stereo EM MAVEN EM

– EM sensor disassembled and given to mechanical subcontractor to verify/refine hemisphere concentricity and obturator parallelism.

– EM sensor parts returned EM assembly and test in progress (expect to be finished by Oct 22)

• Front-end Electronics (MCP, HVPS)

– Transformers fab & test – done.

– Planetary Protection/AIV procedures in place – clean room testing underway – Amp and HV coupling board fab is next

EM sensor in vacuum

chamber

Page 33: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

33PFP QSR, 10/19/2010

SWEA Status - SSL

• Pedestal Mechanical– Purge redesigned to point in the right direction

• change to CESR mechanical design is very minor

– Wall thickness increased to 0.100” for better margin in Mars radiation environment.

– Drawings complete, fab out for quote. If all goes well, expect delivery in November.

– Design of solar absorber awaiting thermal analysis, but this will not hold up the EM design/fab.

• LVPC– Layout based on STEREO SWEA, with modifications because MAVEN

SWEA does not have a STE component.

– Parts selection done, layout in progress.

• Digital– Design complete, layout engineer selected, PO in process.

Page 34: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

34PFP QSR, 10/19/2010

• Surface Coating for Deflectors and Toroidal Grids– Candidates are: black chrome, black nickel, DAG213, Z307, and

Ebanol-C.

– Laboratory tests at Glen were recently completed to measure electrical properties before and after exposure to atomic oxygen. Expect report within a few days.

– FM parts coating can proceed once material is selected.

• Mechanical Design of Aperture– Estimates of launch loads have come down significantly with selection

of Atlas V and addition of ballast mass to the SWEA boom.

– Previous load tests on STEREO SWEA show that current design may be adequate for MAVEN. Currently working to confirm.

• FM Front-End Electronics– CESR procedures, with minor modifications, are compatible with

MAVEN Planetary Protection Plan. FM board assembly can proceed.

Several Key SWEA Issues Nearly Resolved

Page 35: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

35PFP QSR, 10/19/2010

MAVEN PFP STATIC Status

October 2010

Jim McFadden, STATIC Lead

Page 36: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

36PFP QSR, 10/19/2010

STATIC Accomplishments

• EM thick foils attached to frames returned by Luxel, inspected. • First batch of carbon foil carrier frames with grids returned from

fabrication, inspected, engraved with serial numbers• Second batch carbon foil carrier frames inspected for flatness,

engraved and sent out for grid attachment• EM 15kV-MCP HV board fabricated and ready for inspection• EM Low Voltage Power Supply is laid out, ready for fab• Mechanical design between TOF housing and analyzer

assemblies was detailed by ME• Concept to HV sweep custom connectors worked out, awaiting

detailed design.• Anode, Preamp and TDC board signal routing nearly complete• RFQ sent out for bids on calibration chamber• Calibration chamber design complete, mounting stand design in

process

Page 37: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

37PFP QSR, 10/19/2010

STATIC Open Issues

• Ken Hatch optimization of EM Anode, Preamp and TDC boards undergoing review with McFadden. Layouts will require some of Bruce Dalen’s time for final layout completion.

• Still not getting much ME time on STATIC details due to RBSP, STATIC analyzer and mechanical attenuator still in development

• STATIC HV Sweep layout needs modifications to accommodate external and internal HV connectors – new EE assigned to complete the design.

• STATIC FPGA still in development• Carbon foils received but are tearing when floated - vendor to

send new foils if needed – awaiting new floating tests• Clean room refurbishment (320D) still waiting on campus.• Ion gun for calibration chamber may not allow for automated

computer control – which is desired but not required.

Page 38: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

38PFP QSR, 10/19/2010

MAVEN PFP SEP Status

October, 2010

Davin Larson, SEP Lead

Page 39: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

39PFP QSR, 10/19/2010

SEP Accomplishments

• DFE board has gone out for quote – (quote recv’d too)• DAP board currently in layout

– Competing with STATIC for engineer time• FPGA design contract in place

– Awaiting return of Jianxen Chen from vacation• Preliminary magnet selection has begun – (all

magnetometer equipment has been recovered / software tested)

Page 40: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

40PFP QSR, 10/19/2010

SEP Open issues

• DAP / FPGA pinout subject to change pending layout architecture/ FPGA designer input.

• Cable connector pinout changed due to layout issues – Changes can be expected pending DAP layout.

• Magnet selection to continue following meeting next week.

Page 41: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

41PFP QSR, 10/19/2010

MAVEN PFP PFDPU, Power Converter & GSE Status

October 2010

Dorothy Gordon

Tim Quinn

Peter Berg

Page 42: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

42PFP QSR, 10/19/2010

DCB Status

• PFDPU Processor– Data Controller Board Layout complete

• Board Fabrication in process (expected delivery is 25 October)• Quote for Board Population requested from Digicom• Awaiting parts shipment from GSFC

• FPGA Daughter Cards– FLASH Daughter Board Layout is complete

• Board Fabrication in process (expected delivery is 25 October)• Quote for Board Population requested from Digicom• ETU (FLASH) FPGAs are in-house

– FLIGHT Daughter Board Layout is pending

Page 43: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

43PFP QSR, 10/19/2010

GSE Hardware/Firmware Status

• MISG FPGA Development– The MISG FPGA modules supporting PFDPU Mode have been

completed and verified via simulation and test – Interface to Ethernet controller operational in both directions

• MISG is receiving directives from the Host and sending status and instrument messages back to the Host

• Hardware Level Integration proceeding with STATIC prototype – Both Command and Message Interface have been verified

between the Host – MISG - Instrument• Integration with GSE Software (GSEOS) is proceeding

• MISG Production Status– Two fully populated MISG boards in house

• Quote requested for population of 10 additional boards– Chassis and cabling in development

Page 44: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

44PFP QSR, 10/19/2010

GSE Software Status (1)

• Tested limit checking function with STATIC housekeeping successfully - out of limit conditions are echoed to log file.

• All commanding echoed to log file

• New python module for issuing commands from command line or procedure. Just prefix "cmd." before mnemonic command. Example: >>> cmd.isg_arm_act()

• Integrated new plotting function into GSEOS. The new plotting function uses the Python plotting library matplotlib. Selected telemetry values are routed to time-value ordered files, which are plotted by running the function plot_prep(value). The resulting plot screen has zoom and panning capabilities.

Page 45: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

45PFP QSR, 10/19/2010

GSE Software Status (2)

• Added display log to SSG interface: RTS and DTR events echoes to log

• Data and svn server maven hooked up to UPS and configured for graceful shutdown

• GSEOS configured and tested to control 2 power supplies. Additional power supplies will be added to reflect max case for instrument testing. Voltage and current values for each supply are saved to files for display with new plotting feature.

• GSEOS successfully connected and commanding MISG

Page 46: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

46PFP QSR, 10/19/2010

Power Converter Status

• Low Voltage Supplies – Both the SWIA Low Voltage Power Converter and STATIC Low

Voltage Power Converter ETU have been laid out, quoted, and a supplier recommended.

– SWEA LVPS layout in process (expected completion is 18 Oct)

• STATIC Accelerator Board – The STATIC Accelerator and MCP board laid out and fabricated– Board are in-house

• REG Board– Layout is in process

• IIB Schematics in process – The IIB prototype circuits undergoing test/verification– Schematic completion expected by the end of next week (22 Oct)

Page 47: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

47PFP QSR, 10/19/2010

MAVEN PFP Flight Software Status

October 5 2010

Peter Harvey

Page 48: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

48PFP QSR, 10/19/2010

Schedule Tracker

Progress Points=Telecons with GSFC. 1 pt for each telecon, 0 if the telecon did not happen.

Management Effort. Expected 10% or less, but has required phase A requirements and plans to be written in phase B.

Milestone PDRDescription Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10Product Characteristics

Project Name MAVEN MAVEN MAVEN MAVEN MAVEN MAVENLanguage C C C C C C

Software Domain (FSW) FSW FSW FSW FSW FSW FSWSLOC Expected 9180 9180 9180 9180 9180 9180

SLOC To Date 0 0 771 1645 2841 2841Software Progress

Major Events Planned 1 1 1 0 0 0Major Events Actual 1 1 1 0 0 0

Progress Points Planned 1 1 1 1 1 1 1 1 1Progress Points Actual 0 1 0 1 1 1

Effort-Software Planned 90% 90% 90% 90% 90% 90% 90% 90% 90%Effort-Software Actual 0% 0% 24% 45% 51% 7%

Risks (Low) 0 3 4 4 4 4Risks (Med) 0 0 0 0 0 0Risks (High) 0 0 0 0 0 0

Project PlanningCost/Schedule Revs Planned 0 0 1 0 0 0

Cost/Schedule Revs Actual 1 0 1 0 0 0Effort-Management Planned 10% 10% 10% 10% 10% 10% 10% 10% 10%

Effort-Management Actual 24% 79% 37% 10% 5% 10%Software Functionality

Requirements Planned 8.1 16.2 24.3 32.4 40.5 55.75 71Requirements Actual 0 0 19 28 51 51

Software QualityFSW Defect Count 0 0 0 0 0 0 0 0 0

non-FSW Defect Count 0 0 0 0 0 0Inspections Planned 0 0 0 0 0 0 1 0 0

Inspections Actual 0 0 0 0 0 0Effort-Quality Planned 0 0 0 0 0 0 0.2 0 0

Effort-Quality Actual 0 0 0 0 0 0Configuration Management

VDD Reviews Planned 0 0 0 0 0 0 1 0 0VDD Reviews Actual 0 0 0 0 0 0

CM Meetings Planned 0 0 0 0 0 0 0 0 0CM Meetings Actual 0 0 0 0 0 0

Requirements ManagementRequirements Changes 0 0 2 0 1 0

Requirement TBDs-STATIC 0 0 0 0 0 0Requirement TBDs-SEP 0 0 0 0 0 0

Requirement TBDs-SWIA 0 0 0 0 0 0Requirement TBDs-SWEA 0 0 0 0 0 0

Requirement TBDs-LPW 0 0 0 0 0 0Requirement TBDs-MAG 0 0 0 0 0 0

Requirement TBDs-TOTAL 0 0 0 0 0 0Effort-Engineering 24% 0% 3% 0% 0% 3%

Page 49: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

49PFP QSR, 10/19/2010

Technical Status

Technical Developments (Boot) HSK module : Analog Mux #4 added IV&V : Provided comments on the L4 and L5 requirements Supported Fault Protection Telecons Reviewed another DCB specification (revF)

Technical Developments (Operational) Reviewed another DFB specification (10/09/27) : Issues involved

Telecon to discuss DFB/DCB Interface 10/11/2010 PWR module: LVPS control logic (specification needed) PWR module: HVPS control logic inc/ ramping, enables. (FPGA CDIs needed) Software tests being performed using Code Warrior simulator, breakpoints, etc.

Page 50: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

50PFP QSR, 10/19/2010

Technical Margins

Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10DCB

Spec A D E E E EPROM SIZE 32 32 32 32 32 32

EEPROM SIZE 256 256 256 256 256 256FLASH TABLES 512 512 512 512 512 512

RAM SIZE 3072 3072 3072 3072 3072 3072CPU Cycles/sec 16777216 16777216 16777216 16777216 16777216 16777216CPU Cycles/int 65536 65536 65536 65536 65536 65536

CMD UART bps 57600 57600 57600 57600 57600 57600TM UART bps 57600 57600 57600 57600 57600 57600

FSWVERSION 0.0 0.0 0.0 0.0 0.0 0.0

PROM 0.00 0.00 0.00 4.44 7.46 7.46EEPROM 0.00 0.00 0.00 0.03 0.03 0.03

FLASH 0.00 0.00 0.00 0.03 0.03 0.03RAM 0.00 0.00 0.00 6.59 14.80 14.80

CPU Cycles/4s 6710886 6710886 6710886 6710886 6710886 6710886CPU Cycles/Int 6550 6550 6550 6550 6550 6550

CMD UART% 1000 1000 1000 1000 1000 1000TLM UART% 27000 27000 27000 27000 27000 27000

MARGINS 50% 50% 50% 49% 48% 48% 47% 46% 45%PROM 620% 329% 329%

EEPROM 819100% 819100% 819100%FLASH 1638300% 1638300% 1638300%

RAM 46517% 20656% 20656%CPU Cycles/4s 150% 150% 150% 150% 150% 150%CPU Cycles/Int 901% 901% 901% 901% 901% 901%

CMD UART% 5660% 5660% 5660% 5660% 5660% 5660%TLM UART% 113% 113% 113% 113% 113% 113%

Page 51: 1 PFP QSR, 10/19/2010 Particles and Fields Package Quarterly Status Review (QSR) October 19, 2010 Dave Curtis, PFP PM

51PFP QSR, 10/19/2010

1-Page Fever Chart

BOOT Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10RequirementsSpecificationsSoftware DevelopmentTesting

OPERATIONAL Apr-10 May-10 Jun-10 Jul-10 Aug-10 Sep-10 Oct-10 Nov-10 Dec-10RequirementsSpecificationsSoftware DevelopmentTesting

LegendGreat. Ahead of ScheduleConcern about somethingProblems!

1. Boot Requirements changes in the works2. Boot Specification (Fault protection) changes in the works3. Boot Development halted4. DCB ETU board unavailable for test of Boot FSW.