Upload
jayson-barefield
View
217
Download
0
Embed Size (px)
Citation preview
1
Project SchedulingCP - Chapter 10
Lecture3
2
Project ManagementProject Management How is it different?
Limited time frame Narrow focus, specific objectives
Why is it used? Special needs Pressures for new or improves products or services
Definition of a project Unique, one-time sequence of activities designed
to accomplish a specific set of objectives in a limited time frame
3
Project ManagementProject Management What are the Key Metrics
Time Cost Performance objectives
What are the Key Success Factors? Top-down commitment Having a capable project manager Having time to plan Careful tracking and control Good communications
4
Project ManagementProject Management
What are the tools? Work breakdown structure Network diagram Gantt charts Risk management
5
Project ManagerProject Manager
Responsible for:
Work QualityHuman Resources TimeCommunications Costs
6
Deciding which projects to implement
Selecting a project manager
Selecting a project team
Planning and designing the project
Managing and controlling project resources
Deciding if and when a project should be terminated
Key DecisionsKey Decisions
7
Temptation to understate costs
Withhold information
Misleading status reports
Falsifying records
Compromising workers’ safety
Approving substandard work
http://www.pmi.org/
Ethical IssuesEthical Issues
8
PERT and CPMPERT and CPM
PERT: Program Evaluation and Review TechniqueCPM: Critical Path Method
Graphically displays project activities Estimates how long the project will take Indicates most critical activities Show where delays will not affect project PERT and CPM have been used to plan, schedule, and control
a wide variety of projects: R&D of new products and processes Construction of buildings and highways Maintenance of large and complex equipment Design and installation of new systems
9
PERT/CPMPERT/CPM
PERT/CPM used to plan the scheduling of individual
activities that make up a project. Projects may have as many as several
thousand activities. Complicating factor in carrying out the
activities some activities depend on the completion of
other activities before they can be started.
10
PERT/CPMPERT/CPM Project managers rely on PERT/CPM to help them
answer questions such as: What is the total time to complete the project? What are the scheduled start and finish dates for each
specific activity? Which activities are critical?
must be completed exactly as scheduled to keep the project on schedule?
How long can non-critical activities be delayed before they cause an increase in the project completion
time?
11
Planning and SchedulingPlanning and Scheduling
Locate new facilities
Interview staff
Hire and train staff
Select and order furniture
Remodel and install phones
Furniture setup
Move in/startup
Activity 0 2 4 6 8 10 12 14 16 18 20
12
Project NetworkProject Network
Project network constructed to model the precedence of the
activities. Nodes represent activities Arcs represent precedence relationships of the
activities Critical path for the network
a path consisting of activities with zero slack
13
Project Network – An ExampleProject Network – An Example
A
B
C
E
F
Locatefacilities
Orderfurniture
Furnituresetup
Interview
RemodelMove in
D
Hire andtrain
GS
8 weeks
6 weeks
3 weeks
4 weeks9 weeks
11 weeks
1 week
14
Management Scientist SolutionManagement Scientist Solution
Path Length (weeks)
Slack
A-B-F-G A-E-G C-D-G
18 20 14
2 0 6
Critical PathCritical Path
15
Three-time estimate approach the time to complete an activity assumed to
follow a Beta distribution An activity’s mean completion time is:
t = (a + 4m + b)/6 a = the optimistic completion time estimate b = the pessimistic completion time estimate m = the most likely completion time estimate
An activity’s An activity’s completion time variancecompletion time variance is is 22 = (( = ((bb--aa)/6))/6)22
Uncertain Activity TimesUncertain Activity Times
16
Uncertain Activity TimesUncertain Activity Times
In the three-time estimate approach, the critical path is determined as if the mean times for the activities were fixed times.
The overall project completion time is assumed to have a normal distribution with mean equal to the sum of the means along the
critical path, and variance equal to the sum of the variances along the
critical path.
17
ActivityImmediate
PredecessorOptimisticTime (a)
Most LikelyTime (m)
PessimisticTime (b)
A -- 4 6 8
B -- 1 4.5 5
C A 3 3 3
D A 4 5 6
E A 0.5 1 1.5
F B,C 3 4 5
G B,C 1 1.5 5
H E,F 5 6 7
I E,F 2 5 8
J D,H 2.5 2.75 4.5
K G,I 3 5 7
ExampleExample
18
Management Scientist SolutionManagement Scientist Solution
19
Network activities ES: early start EF: early finish LS: late start LF: late finish
Used to determine Expected project duration Slack time Critical path
Key TerminologyKey Terminology
20
The Network Diagram (cont’d)The Network Diagram (cont’d) Path
Sequence of activities that leads from the starting node to the finishing node
AON path: S-1-2-6-7 Critical path
The longest path; determines expected project duration Critical activities
Activities on the critical path Slack
Allowable slippage for path; the difference the length of path and the length of critical path
21
Network activities ES: early start EF: early finish LS: late start LF: late finish
Used to determine Expected project duration Slack time Critical path
Computing AlgorithmComputing Algorithm
22
Advantages of PERTAdvantages of PERT
Forces managers to organize
Provides graphic display of activities
Identifies
Critical activities
Slack activities1
2
3
4
5 6
23
Limitations of PERTLimitations of PERT
Important activities may be omitted
Precedence relationships may not be correct
Estimates may include a fudge factor
May focus solely on critical path