Upload
britney-taylor
View
216
Download
2
Embed Size (px)
Citation preview
1
SM4 Readiness ReviewTuesday, 9 September 2008, 9:00am -12:40pm
Welcome Hubble Mission OfficeSMOV Program Carl Biagetti, 9-9:30am
Proposal Processing Status Denise Taylor, 9:30-9:45am
Long Range Planning David Adler, 9:45-10am
Contingency Plans for STIS/ACS Neill Reid, 10 - 10:15am
Planning & Scheduling Merle Reinhart & George Chapman, 10:15-10:45am
…Break for 15 minutes…Commanding Alan Welty, 11-11:15am
Data Processing and Archiving Faith Abney, 11:15-11:45am
Calibration Pipeline Processing Warren Hack, 11:45-12:05pm
Operational Readiness Al Holm, 12:05-12:25pm
Infrastructure Contingency Plans Doris McClure, 12:25-12:40pm
2
SM4 Readiness Review
Wednesday, 10 September 2008, 9:00-12:30:
SM4 Observatory Support Chris LongWFC3 Readiness John MacKentyCOS and STIS Readiness Alessandra AloisiACS Readiness Linda SmithNICMOS Readiness Tommy WiklindFGS and OTA Readiness Ed Nelan and Matt LalloOPO and ERO Readiness Mario Livio and Keith Noll
3
SMOV4 Planning Readiness
Carl Biagetti
System Engineering Branch - OED
4
SMOV4 Plan Overview …1
SMOV4 Plan– Provides for the timely commissioning of the
Observatory for science following SM4• Commissions the newly SIs on channel-by-channel basis
– Introduces GO science on a channel-by-channel basis as SMOV progresses
• Recommissions the restored SIs on channel-by-channel basis
• Recommissions serviced Observatory Systems• Performs Early Release Observations (EROs)
– Satisfies the SMOV4 requirements of 21 March 2007• Plan presented, reviewed, and approved 12 Oct. 2007
(SMR-4029, CCR 5248)
5
Generic SMOV Processfollowing each HST Servicing
Early ReleaseObservations
New/Revived Instruments
Instruments Science Calibrations
Focus/Alignment of SI Optics
Instrument PrepsEngineering Check-Outs
OutgassingCooldown
Spacecraft Subsystems
CommissioningPCS/EPS/TCS…
HST Releasefrom Shuttle
SMOV Start
GO Science Ramp-up
As Instruments/ChannelsAre commissioned
6
SMOVs 2 – 4EXTERNAL ORBITS
HISTORICAL COMPARISON
Notes:
1. STIS and NICMOS required more orbits than planned because of the NICMOS thermal short and the opto-coupler resets in both SIs.
2. SMOV4 seems to be the most complex in terms of realtime interactions and in-line analyses.
SMOV2 SMOV2 SMOV3B SMOV4SI/SS PLANNED ACTUAL ACTUAL PLANNEDWFPC2 46 77 31FOC 15 15Spacecraft/FGS 69 61 41 81NICMOS 194 285 77 34STIS 205 267 14 21ACS 186 38WFC3 163COS 164ERO 72 75 70 90 TOTALS 601 780 419 591
7
SMOV4 Plan Overview …2
SMOV4 Plan satisfies the following drivers
• Perform EROs in time for Jan. AAS release– i.e., schedule observations in early
December 2008• Minimize excess FGS3 usage by timely
commissioning of FGS2R2
8
SMOV4 Plan Overview …3
SMOV4 Plan satisfies the following constraints
Long intervals for outgassing and contaminants dissipation– Bright Earth Avoidance (for 21 days from Release)
• to avoid UV-induced polymerization of exposed optics (WFC3 POM)– COS NUV = 10 days from Release (per model) to allow internal pressure
below 20 uTORR, before detector activation– COS FUV = 15 days from Release (per model) to allow internal pressure
below 10 uTORR, before detector activation– WFC3 = 21 days from Release before cal lamp usage and TEC cooldown
Careful, incremental initial high-voltage ramp-ups– COS NUV/FUV– STIS NUV/FUV– ACS SBC
9
SMOV4 Plan Overview …4
SMOV4 Plan prioritizes SMOV activities to allow schedule flexibility
Prioritization (High, Medium, Low)
– Based on realistic assumptions about scheduling rates (external orbits)
– Accommodates ERO schedule and other key dates
– Accommodates non-SMOV (eg., GO, ERS) programs before SMOV completion
10
Prioritization of SMOV activities
• High Priority = activities needed to enable EROs in early Dec.
• Medium Priority = activities needed for enabling GO science
• Low Priority = all other activities– Needed to satisfy all other SMOV4
requirements and reference file generation– Needed for handbook inputs in spring
11
SMOV Prioritization: COS
High Priority Activities (EROs)– Through NUV and FUV Alignment and Focus
Medium Priority Activities (Science enable)– All FUV cals beyond alignment/focus and target acq test– The rest of NUV wavelength scale calibration
Low Priority Activities– Low 1 – needed for reference files and handbook inputs
(data needed by Feb. 1)– Low 2 – desirable but not required for handbook inputs– Low 3 – All others
12
SMOV Prioritization: WFC3
High Priority Activities (EROs)– Through UVIS & IR Fine Alignment– In parallel with EROs
• UVIS/IR/FGS alignment, UVIS/IR plate scales
Medium Priority Activities (for “Easy” GO science)
– Internal flats, flat-field uniformity, photometric zero-points
Low Priority Activities (for “Hard” GO science)
– UVIS/IR image quality, PSF wings, UVIS PSF Core Modulation (shutter test), pointing stability, IR grisms
13
SMOV Prioritization: ACS
High Priority Activities (EROs)– WFC Optimization Campaign (OC), image quality,
sensitivity– SBC turn-on, UV monitor
Medium Priority Activities (GO science)– SBC PSF– HRC image quality, sensitivity, geometric distortion,
coronagraph commissioning
Low Priority Activities– None remaining, but assume the option to delay HRC
commissioning in favor of WFC/SBC in early SMOV
14
SMOV Prioritization: STIS & NICMOS
NICMOS– High Priority Activities (EROs)
• Through Aperture Location activity– Medium Priority Activities (GO science)
• Through Aperture Location activity and SIAF update• Aperture knowledge without SIAF may be sufficient
STIS– High = STIS External Focus Check– Medium = NUV Optical Format Verification, FUV Image
Quality – Low = CCD Spectroscopic Throughput, Image/Pointing
Stability, NUV Image Quality
STIS SCI & ERO ENABLE
ACS SBC SCI ENABLE
ACS HRC SCI ENABLE
ACS WFC SCI & ERO ENABLE, NIC ERO ENABLE, FGS2R2 GUIDING ENABLE
COS FUV SCI ENABLE, WFC3 IR “EASY” SCI ENABLE
WFC3 UVIS/IR ERO ENABLE, UVIS “EASY” SCIENCE ENABLE, NIC SCIENCE ENABLE, COS FUV ERO ENABLE
WFC3 UVIS/IR “HARD “SCI ENABLE
UV IR
COS NUV SCI ENABLE
SMOV4 EXTERNAL ORBITS & ENABLE DATES- Including EROs -
Oct. 10, 2008 Launch -- Assumes 55 - 60 prime observing orbits per week
0
10
20
30
40
50
60
70
1 2 3 4 5 6 7 8 9 10 11 12 13 14
10/20 10/27 11/3 11/10 11/17 11/24 12/1 12/8 12/15 12/22 12/29 1/5 1/12 1/19
SMOV WEEK
ORBITS
ERO
BEA PERIOD (1st 3 weeks)
AVAILABLE SCIENCE ORBITS
FGS
PCS
NICMOS
STIS
ACS
COS
WFC3
16
Critical Operations & Operational Challenges in SMOV
HV Ramp-ups for STIS and COS
Focus & Alignments for COS & WFC3– Iterative processes for each SI in the same weeks
Realtime Commanding– GENSLEWs (Use Offsets)
• Used in several proposals for pointing updates before aperture data (SIAF) is in place
• Needed to meet ERO schedule
– Table uploads, Event flag mgmt, etc.
Fast Data Turnaround (FASTRACK)– Needed in several places for in-line analyses
17
Critical Operations and Operational Challenges in SMOV Weeks 1-7
WEEK
SYSTEM
1 2 3 4 5 6 7
S/C & FGS
BEA, VDT, AMA ADJ, FT1
BEA
AMA ADJ, FT2
BEA VDT
WFC3 OUTGAS OUTGAS OUTGAS, SDB CHK
INIT UVIS ALIGN, INIT IR ALIGN, FT2
INIT UVIS ALIGN, INIT IR ALIGN, UVIS FINE ALIGN, FT3
UVIS/IR FINE ALIGN, FT2
IR FINE ALIGN,
EROs, FT1
COS OUTGAS, SDB CHK
OUTGAS FUV HV, COS/FGS ALIGN, NUV ALIGN, FT2
FUV HV, NUV ALIGN/FOCUS, FUV SENS, FT2
NUV ALIGN/FOCUS, EXT. SPECTRO. PERF., FT1
FUV ALIGN /FOCUS,, FT2
FUV STRUCT/THERM STAB, EROs, FT2
ACS SDB CHK, TEMP SET PNT
WFC OC, FT1
WFC OC, FT4
WFC OC, CCD X-TALK, FT4
EROs
STIS SDB CHK FT1 EROs
NICMOS COOLDOWN COOLDOWN FW TEST, FOCUS/PAM ADJ, FT2
Yellow indicate times of high activity
FTn = Fastrack data delivery requested by n proposals
18
Organization, Management, Reporting during SMOV
SMOV Team– Consists of STScI & Project science & engineering staff– Lead personnel identified for each critical activity– Team to meet regularly (“morning meeting”)
• Daily, for 1st couple of weeks, then at a slowly decreasing frequency
• To assess daily progress, review daily plans• Determine replans• Contributions from each SI and subsystem teams• Daily minutes/reports to be published Project-wide
SMOV TTRB– To assess replan requests– Make recommendations to HST MO and Project
19
SMOV4 Contingency Planning
High-level contingency plans are being worked for each SI/subsystem– Including SMOV OTA focus contingency
20
SMOV PIT EARNED VALUE -- NOV2007 - SEP2008(as of 04SEP08)
0
200
400
600
800
1000
1200
1400
1600
1800
Nov-07 Dec-07 Jan-08 Feb-08 Mar-08 Apr-08 May-08 Jun-08 Jul-08 Aug-08 Sep-08
POINTS (10 pts/proposal)
PLANNED EV(FEB 2008)
ACTUAL EV
10 EV points/proposal– 3 pts for prop submit– 2 pts for 1st PIT mtg– 2 pts for 2nd PIT mtg– 3 pts for prop complete
165 SMOV4 PROPOSALS = 1650 total EV points - 163 PROPOSALS PIT-APPROVEDPIT PROGRESS - 100 % PLANNED EARNED VALUE for Aug. 31 - 99.0 % ACTUAL EARNED VALUE as of Sep 4
SMOV PROPOSAL IMPLEMENTATION TEAM (PIT)EARNED VALUE (EV) as of 4Sep08
21
Credit goes to dozens and dozens of people - STScI, GSFC, COS & WFC3 Teams
For a very good SMOV4 Plan
22
Proposal Processing Status
Denise Taylor, Observation Planning Branch - OED
23
Proposal Processing Status
SMOV Proposals
153 proposals (not including ERO)
35 COS props (164 ext. orb., 111 int. orb.) - 7 props still working 31 ACS props (38 ext. orb., 493 int. orb.) - 1 props still working 42 WFC3 props (163 ext. orb., 370 int. orb.) - All ready 25 STIS props (21 ext. orb., 174 int. orb.) - All ready 12 NIC props (34 ext. orb., 136 int. orb.) - All ready 2 PCS props (24 ext. orb., 26 int. orb.) - All ready 6 FGS props (57 ext. orb.) - All ready
24
Proposal Processing Status
SMOV Proposals (continued)
145 are ready for flight.
8 are being worked:
1 ACS + 1 COS props need to be resubmitted, reprocessed and re-reviewed
6 COS props need CS reviews
25
Proposal Processing Status
ERO Proposals
9 proposals for ERO
4 are ready for flight (16 orbits):One WFPC2 EROOne STIS EROOne ACS EROOne COS ERO
4 have been submitted and are being worked (need CS reviews) (20 orbits):One COS EROOne WFC3 EROOne COS EROOne WFC3 ERO
1 has not been submitted (? orbits)
26
Proposal Processing StatusEarly Science Proposals (132 orbits possible for execution before 31 January 2009)
COS/GTO 11520 - QSO Absorbers, Galaxies and Large-scale Structures in the Local Universe
(26/39 orbits) 11534 - Atmosphere of a Transiting Planet (20/20 orbits)
GO 11566 - Imaging Saturn’s Equinoctal Auroras (6/12 orbits) 11612 - Eta Carinae’s Continuing Instability and Recovery - the 2009 Event (9/16 orbits) 11706 - The Parallax of the Planet Host Star XO-3 (1/6 orbits) 11788 - The Architecture of Exoplanetary Systems (11/63 orbits) 11789 - An Astrometric Calibration of Population II Distance Indicators (11/33 orbits)
ERS 11359 - Panchromatic WFC3 Survey of Galaxies at Intermediate z (28/104 orbits) 11360 - Star Formation in Nearby Galaxies (20/110 orbits)
27
Proposal Processing Status
Cycle 17 General Observer Pool
197 GO proposals including those from HST Cycle 17 TAC, Chandra TAC, and previous HST TACs, for 3627 orbits.
16 SNAP proposals, for 1417 orbits.
24 GTO/COS proposals for 291 orbits. 3 GTO/ACS proposals for 24 orbits. 2 ERS proposals for 214 orbits. 3 GO/PAR proposals for 410 orbits.
28
Proposal Processing Status
Cycle 17 General Observer Pool (continued)
Program Coordinators (PCs) are processing observations in the general pool: ~ 6000 orbits.
Instrument teams have begun reviewing these observations and will have most done before SM4. Remaining will be done according to Long Range Plan schedule.
Currently 9% unschedulable, mostly due to incompatibility of requested scheduling constraints (orients, guide stars, timing links, etc.). This is typical for early ingest; PCs will resolve these issues throughout the coming months.
Final processing steps will wait until after SM4, when the ground system is reconfigured for 3 gyro mode.
29
Proposal Processing Status
After SM4
SMOV proposals and science proposals will be reworked as needed during SMOV.
Remaining Cycle 15 and Cycle 16 proposals will be reworked for 3-gyro scheduling.
Cycle 17 pool will continue processing as usual, to execute observations according to the Long Range Plan.
Begin processing Cycle 17 calibration proposals (Calibration review on 9/25/08; Phase II deadline TBD).
30
The Long Range Plan
David Adler
Science & Mission Scheduling Branch - OED
31
Long Range Planning Group (LRPG) Activity Summary
• Remainder of Cycle 16:– 173 orbits before SM4, 441 orbits after SM4 in Cycle 16 “tail.”
• The LRPG is monitoring remaining Cycle 16 WFPC2 observations.– all but one 3-orbit ToO follow-up should be completed by SM4.
– PI of that program will put in a request to change SI if needed.
• The LRPG has incorporated SMOV, SI commissioning, ERO, ERS, and GTO constraints into the Cycle 17 planning process.
• A preliminary Cycle 17 LRP has been built and verified.
• The LRPG has identified/developed plans for managing SM4 contingencies in Cycle 17 planning.
32
Preliminary Cycle 17 Plan Highlights
• December/January priorities:– High priority SMOV– EROs– ERS/GTOs– Time-critical Cycle 17 science– Medium/low priority SMOV– Cycle 16 GO science
• Cycle 16 planning information for Oct-Dec programs is being maintained in case of launch slip.
• All cycle 16 science planned for Oct-Dec can be replanned for 2009.
• Under-subscription in early 2009 – LRPG is leaving space for Cycle 17 calibration programs, Target of Opportunity programs, DD, HOPR repeats, etc.
Preliminary Cycle 17 LRP – Oct-Feb
launch
ACS SBC ACS WFC/HRC NIC
WFC3 UVIS “easy”COS FUVWFC3 IR “easy”
WFC3 UVIS/IR “hard”SI commissioning
milestones
SM4
STIS
COS NUV
BEA
34
LRPG Transition from SMOV to Cycle 17 Science
• Preliminary Cycle 17 plan is built
• Statistics:
4200 orbits – Cycle 16 and 17 science in working LRP
+600 orbits - SMOV/ERO (not in plan)
+850 orbits - “unplanned” – 2 orbits a day of calibration, HOPR, ToO, etc
---------------
5650 orbits in Cycle 17
-650 orbits - cycle 17 tail – beyond Dec 31, 2009
=5000 orbits from 10/20/08 – 12/31/09 = 11.42 orbits/day = 80 orb/week
• Plan will not be released to the public until a couple of weeks after deployment when the state of the observatory is known.
35
LRPG Contingency PlansIf there’s a launch slip:
• Long Range Plan will be rebuilt to reflect the change.
• For a 1 - 4 week slip, the following can fill the gap:– Existing Cycle 16 science programs– Cycle 17 NIC science that can schedule in 2-Gyro– Cycle 15/16 Snaps– Cycle 17 NIC Snaps that can schedule in 2-Gyro
• 5 + week slip:– Existing science and Snaps, as described above; studies are ongoing to see how
far out this can be extended.– If more science is needed, LRPG will consult with the Science Policies Group
(SPG) for a course of action.
36
Summary - LRPG Readiness for SM4
• Transition plan between Cycle 16 – SM4 – SMOV – Cycle 17 is in place.
• Preliminary Cycle 17 LRP has been built and is ready for execution. It is currently on-hold pending the outcome of SM4.
• The LRP incorporates all constraints/HST orbit resource requirements of all SMOV (including SI commissioning) and ERO/ERS activities.
• Process/policies are in place for updating the Cycle 17 plan in response to SM4 contingencies.
• The LRPG is ready for SM4!
37
Contingency plan if STIS and/or ACS are not available
• The C17 TAC recommended programs based on the assumption that SM4 would be fully successful, i.e., both STIS and ACS would be repaired
• STIS and ACS are scheduled for repair after COS and WFC3 and their repair is more challenging
• Therefore STIS and ACS carry a higher risk of not being available in C17 than COS and WFC3
38
Instrument Contingencies
Neill Reid
Science Mission Office
39
C17 allocation by orbit:
• STIS: 8% of total; includes imaging and spectroscopy
• ACS: 25% of total; includes 1% of SBC use (currently operational)
• Numbers include parallels but no snapshots (1357 snapshot targets awarded in C17; STIS: 140; ACS: 518)
40
C17 proposers were required to address whether their programs could be switched to a different instrument if STIS/ACS were not available
Using this information, the TAC endorsed or rejected an instrument switch and made a recommendation to the Director
41
STIS
• Moderate-resolution UV spectroscopy can often be switched to COS
• Imaging can almost always be done with WFC3 or ACS• Optical spectroscopy, spatially resolved spectroscopy,
high-resolution spectroscopy, etc., need STIS• ~40% of all orbits using STIS can be switched• The Long Range Planning Group has run simulations
showing that when STIS observations are removed, science with other SIs can be front-loaded in the Cycle 17 long range plan
42
ACS
• Standard broad- and narrow-band imaging can be switched to WFC3 in most cases
• SBC observations continue to be available • Optical coronagraphy, polarimetry, high-resolution
imaging, etc., need ACS • ~85% of all orbits using ACS can be switched• The Long Range Planning Group has run simulations
showing that when ACS observations are removed, science with other SIs can be front-loaded in the Cycle 17 long range plan
43
Impact if STIS/ACS are not available
• Using the TAC recommendation as a guide-line and after additional STScI review, PI’s will be notified whether instruments can be switched
• Process similar to that used when ACS failed and observations were switched to WFPC2/NICMOS
• PIs may appeal to the TTRB if switch was rejected• Switch can be done quickly (1 – 2 months)• Scheduling impact: ≤10% of the total orbits (sum of all
C17 orbits) will be lost because the science requirements preclude an instrument switch
• Orbits can be replaced, e.g., by snapshots
44 44
Planning & Scheduling
Merle Reinhart and George Chapman
System Engineering Branch - OED
45
Overview
Merle Reinhart– What is Planning and Scheduling?– SMOV Database Management– P&S Procedures and Tools
George Chapman– Rendezvous Intercept SMS Process– Ephemeris Management– Deploy SMS Process– SMOV Calendar/SMS Build Process– P&S Team Readiness– Pending Changes– Items Still in Work
46
TRANS
What is Planning and Scheduling?Long Range Planning, Short Term Scheduling & PASS
ProposalsPRD
SCIOPSDBInstructions
C&C List
SMS
GSC
HST/TDRSEphemeris
Orbit File
PASS
SCS
SPSS
MOSS
NGSS
FDF
CCS
SPIKE
PRD
47
DatabaseNSSC-1 Flight Software
NSSC-1 FSW updates are required to support SM4
NSSC-1 8.6 supports full complement of SIs during SM4– This will be installed Sep. 10 during SMS 252 (SMS 254
is first use)– Avoids software changes during SM4
NSSC-1 9.0 removes support for COSTAR and WFPCII– This will be installed immediately after SM4 during the
H&S SMS
48
DatabasePRD/SCIOPSDB
OPSPRD 7.0 has been deployed to SMS 254 – First used after NSSC-1 8.6 FSW is loaded– PR 60745: TFPF JWOSCPRM for oscilloscope mode parameters
Planned Updates– PR 60655, 60781: PLCP PIPHTHET, PIHETPHT, PISAFFLT needed
for WFC3– After SM4 rendezvous, but prior to deployment– PRD & SCIOPSDB updates for SMOV4 are included in the OPS/SM4
database merge (described later)– Other planned updates for use on initial H&S SMS
• PR 60663: PLCP PJSAFHLD for ACS safing recovery including TEC commanding
• PR 60739: AGCF and SCHF parameters for switch to 3-gyro mode• PR 60742: Table ODB for NSSC-1 9.0 FSW
– Freeze Waivers will be requested for each update
49
DatabaseSMOV Preparation Environment
SMOV4 development utilizes the same methodology that was successfully used for all previous Servicing Missions.
Use a separate database and disk space from Operations, but the same machines/servers.
– spss_sm4 database for SMOV4 development– spss database for current SPSS Operations
Uses the operational software and tools, but utilizes different PRD/SCIOPSDB and SMS Instructions
– Allows simultaneous Flight Operations and SMOV development– Two environments are isolated
The spss_sm4 database is managed in the same way as the SPSS Operations database.
This SMOV4 environment is used to:– Prepare the SMOV proposals for execution– Create the SMGT products– Create the SMOV4 representative products– Post-SM4 DRM Planning and Scheduling exercise
50
DatabaseThe Merge Process
SMOV environment gets merged into the Operations environment after rendezvous and berthing occurs.
Unload all the SMOV4 and housekeeping proposals from the spss_sm4 database
– This stores the proposals on disk as an sql load file– This part of the process nominally occurs right around launch time and takes
about a day
Get a backup of the spss database– This allows us to easily restore to pre-launch if necessary
Database Administrator moves the contents of specified tables from the spss_sm4 database into the spss database
– This transfers the PRD/SCIOPSDB information and the Instructions needed post-SM4
Load the SMOV4 and housekeeping proposals into the spss databaseDatabase Administrator will rebuild the table indices to ensure good
database performance
51
DatabaseThe Merge Process (cont)
Modify any spss database resident housekeeping visits to 3-Gyro/OBAD mode
PRD/SCIOPSDB group will audit the merged spss database for correctness
OPS will audit the proposals for correctness
End-to-end process generally takes about 2 days.
This Merge process will be tested on September 15th.
52
DatabasePASS Configuration Files
These are files used by the PASS software and configuration controlled by the P&S Operations group.
Command Loader Basefile changes to disable WFPC2 and COSTAR and enable WFC3 and COS (or the appropriate combination).
– In the CLBASE Namelist
• Old: NS_SINAME = 'ACS ', 'NIC ', 'STIS', 'CSTR', 'WFII’
• New: NS_SINAME = 'ACS ', 'NIC ', 'STIS', 'COS ', 'WFC3’
• Old: NSREDUNDV = 'A', 'A', 'A', 'B', 'A', 'A’
• New: NSREDUNDV = 'A', 'A', 'A', 'B', 'A', 'B’
• Old: NSSHPSI = '_NSSHPS4’
• New: NSSHPSI = '_NSSHPS5'
53
DatabasePASS Configuration Files (cont)
MEGG initialization file changes to swap in the appropriate new instruments.– Old: – New:
WFPC standbyCOSTAR holdSTIS operateNICMOS saa_operACS holdNCS CPL_hold
WFC3 holdCOS holdSTIS operateNICMOS saa_operACS holdNCS CPL_holdCOS_NUV holdCOS_FUV hold
54
Planning and SchedulingProcedures
The Procedures are written, configured descriptions of a particular process workflow that describes the tools and actions that should be performed to accomplish that particular workflow.
Procedures that need modification to support post-SM4
– None of these updated procedures will be put into place until after the database merge is complete.
• 3.2.01 - Scheduling Unit Selection– Remove the WFPC2 decon references and add in the WFC3/ACS/STIS
Anneal proposals
• 3.2.02 - Flight Calendar Preparation– Add the STIS Low Voltage management (STISLs) back in
• 3.2.03 - Flight Calendar Building– Remove the special checks for non-functional ACS/STIS detectors
– The following procedures were modified and installed• 3.2.17 - Science Instrument Safe Mode Recovery
– Add WFC3/COS and post_SM4 ACS
– All Visits (excepting WFC3 Soft-Safing) are ready for use
55
Planning and SchedulingTools
The tools are configured programs or scripts that are used to perform certain actions called out in the Procedures used for building the weekly flight calendars.
Tools which have already been modified and being used for the initial SMOV calendar builds
– ccl_gsselect• Selects the guidestars used in the SMS• Don’t allow FGS2R2 to be used as the dominant guider
– su_gaps.sqr• Calendar Visit summary report• Add COS/WFC3
56
Planning and SchedulingTools (cont)
Tools requiring modification for SM4
– data_vol_report.py• Data Volume report for OPUS• Add COS/WFC3 and remove WFPC2
– gimme_snaps.py• Builds the lists of what to schedule on a particular week• Change the default for SI/configs to exclude back to nothing
– Calendar/SMS checklists• Checks correctness of flight calendars and SMS’s• Changes yet to be determined
All of these tools will be put into place operationally after the database merge is complete.
57
RendezvousTransitioning HST to Servicing
Mission 4Objective: prepare HST for rendezvous with the Space Shuttle while
maximizing the science content of the launch week SMS
Methodology: utilize the nominal P&S Intercept capability– A primary science SMS with “transition” visits
– A pre-planned intercept SMS with Gyro-4 test and rendezvous attitude maintenance
– Post-launch switch from science to intercept
Testing:– Previously used for SM3B
– Tested during the System Readiness 4.2 (SR4.2) SMGT• Intercept loaded and executing but stopped prior to Gyro-4 test and
rendezvous attitude maintenance to reduce test duration
58
Rendezvous
rend att rend att
rend att
science
science
science science
G4 Tests
Science SMS
Intercept SMSload breaks
280 287
= execution path if launch occurs
Rend Att Maint
59
RendezvousKey Transition Components
Transition Visit– Slews HST to rendezvous attitude (varies with launch date/time)– Configures SIs to nominal states in preparation for real-time safing– Provides intercept point and 2 hours of “dead time” to facilitate interception
Science SMS– Nominal science SMS– One Transition visit scheduled for each launch window
• Provides for launch delays
– Nominal product delivery to GSFC
Intercept SMS– Same as science SMS up through the Transition visit– Gyro-4 test and attitude maintenance replace science after Transition visit– Products generated and delivered pre-launch (post-science SMS delivery)
• TDRS updates withheld until post-launch
60
RendezvousWhat happens on launch day?
Science SMS is executing
If launch occurs– Intercept the Science SMS
• P&S updates TDRS schedule to match the Intercept SMS• FOT uplinks the Intercept loads
– No science after start of launch window +7h• SIs are safed and NSSC-1 “idled” in real-time at 7h MET via Command
Plan
If launch is delayed– Science SMS continues uninterrupted
• FOT uplinks the next loads from the Science SMS
– P&S generates and delivers an Intercept SMS for the next opportunity
61
Ephemerides
Maintain nominal processing and delivery schedule during servicing mission– Prevents gaps in data
• reduces manual intervention• less disruptive to PASS processing
– Ensures recent data is available in an emergency deploy situation
Support fast turnaround processing and delivery post-deploy– The process is fully automated– P&S personnel will be physically at the STScI for these
critical ephems to deal with any unexpected problems
62
Deploy SMS ProcessFiring Up an Improved HST
The deploy SMS is a Health & Safety SMS generated using the nominal H&S generation process
– 3-Gyro Onboard Attitude Determination (OBAD) = “T”mode– Built using NSSC-1 FSW 9.0
– 36 hour duration– BEA compliant initial attitude provided by PCS– Contains no SI commanding
• Allows installation of NSSC-1 FSW 9.0 and COS FSW– Removes support for COSTAR and WFPC2– Fixes a COS Lamp startup failure issue
• Allows real-time commanding to configure HST for use
Tested during the System Readiness 4.2 (SR4.2) SMGT
First Science SMS– NSSC-1 cold-start due to FSW install in previous SMS – Begin SMOV activities– Based upon preliminary SMOV template calendar
63
SMOV4 Calendar/SMS Builds
Construct representative SMOV products assuming a nominal mission and a nominal SMOV
Products will cover the first 4-5 weeks of SMOV– Determines the scheduling feasibility of the SMOV Plan– Finds any inconsistencies between the different SMOV Proposals
These products will be widely distributed for review– Ensures we haven’t missed or misinterpreted something
Will be the starting point for building the templates the Flight Calendar Builders will use for flight.
Templates will be started by ~T-14 days and handed to the Flight Calendar Builder by their nominal T-11d build start.
Currently have the first 3 weeks built which includes the first four post-BEA days.– As expected, this post-BEA area is oversubscribed in the SMOV plan
64
P&S Team SM4 ReadinessOperations Training
No difference in SPSS and PASS process and procedures between pre and post SM4 operations
Therefore, no special training/instruction required to support post SM4 operations.
All team members participated in training sessions to become familiar with COS and WFC3 characteristics
Team also familiarized with any changes in check tools and procedures related to the return to 3-Gyro operating mode
Planning and Scheduling utilizing the Post-SM4 DRM proposals
65
P&S Team SM4 ReadinessOperations Support
P&S staff will be on-site at STScI to cover critical activities as necessary– Launch to update TDRS schedule– Pre and Post reboost ephem processing– Post-Deploy ephem– HST Attitude from PCS and H&S SMS creation– Follow-on Science SMS creation
Post-deploy scheduling– Resume normal SMS build and delivery schedule for
SMOV following post-deploy H&S and first Science SMS
P&S Team ready for SM4, SMOV and Cycle 17 operations
66
Pending ChangesPRD & SCIOPSDB
Things waiting for SM4 that need pre-approved freeze waivers– PRD & SCIOPSDB updates are included in the
OPS/SM4 database merge– Planned PRD updates
• PR 60655, 60781: PLCP PIPHTHET, PIHETPHT, PISAFFLT needed for WFC3
• PR 60663: PLCP PJSAFHLD for ACS safing recovery including TEC commanding
• PR 60739: AGCF and SCHF parameters for switch to 3-gyro mode
• PR 60742: Table ODB for NSSC-1 9.0 FSW
67
Items Still in Work
Database Merge Test– Sept 15
WFC3 Soft Safing Recovery Procedure and Visits– Analysis completed by Sept 12– Visits created and tested by Sept 19
Create Flight Rendezvous/Transition Visits– Completed by Sept 22
Calendar and SMS Checklist Tool Updates– Review and determination of needed changes by Sept 12– Implementation and testing completed by Oct 3
data_vol_report.py and gimme_snaps.py Tool Updates– Implementation and testing completed by Oct 3
Flight Functional Tests (FT) Support Schedules– Completed by Oct 3
Finish building Representative SMOV Weeks out to at least 5– Completed by Oct 3
68
Commanding
Alan Welty
Commanding Branch - OED
69
Commanding
Front-End Science Instrument Support– Write requirements for PROPINST, APT, TRANS,
and SCIOPSDB related to SI commanding– Write & maintain the IM “Instructions” – code used
to generate most SMS statements– PDB tables and groups used in SI commanding
• Define them, with the SI ops working groups• Create and validate the PDB files
– Certification (see slide 5)– SMS Review Tool
• Checks for CARD & OLD violations• Checks to ensure science data quality
70
Regression Testing1
Bit Validation (“bit busting”) of PDB files– Create PDB files & bitval test instructions– Run SPSS & PASS to generate the bits– Verify that the bits are correct– Deliver PDB files & bitval test instructions to
Ball/GSFC• They also generate the bits & deliver them to us
– Compare STScI and Ball/GSFC products– Do the paperwork
71
Regression Testing2
Bit Validation Status– ACS-R
• New items Done (3 forms yet to be signed)• Items unaffected by repair – In progress
– NICMOS• Done (revalidation not requested - NICMOS is fully operating)
– STIS• TBD (no changes, so no issues are expected)
– COS• Done (3 forms yet to be signed)
– WFC3• GSFC has 2 TBDs and 8 forms to sign• STScI Done (except for signing 10 forms…)
72
Regression Testing3
Certification– Create/update certification test proposal (in APT)
• One proposal for each SI• Typically, each visit tests a different ‘major’ capability• Exercise all legal proposal inputs• Negative testing is left to the Test Team
– Process proposals with TRANS– Load TRANS output on CMD’s dev database– Generate calendars & SMSs– Verify correctness of SMSs
• Make detailed check of any new commanding• Explain any differences in pre-existing commanding
– Update SRT if necessary & run it on the SMSs
73
Regression Testing4
Certification Status– ACS-R
• Last: 05-Sep-08; Up to date– NICMOS
• Last: 15-Jan-08; Up to date– STIS
• Last: 30-Jul-04; Up to date– COS
• Last: 05-Sep-08; Up to date– WFC3
• Last: 09-Jun-08; Recertification in progress
74
Special Commanding
– ACS-R• Tested in SFT/SMGT 06-Sep-08• Optimization Spec Com tested in TV 23-Aug-08
– NICMOS• N/A
– STIS• Tested in SFT/SMGT 24-Jun-08
– COS• Tested in SMGT 08-Sep-07• Liens SMS run in ESTIF 16-Jan-08
– WFC3• Tested in SMGT 11-Feb-08
75
Other Work
– Instruction Audit• SPSS_SM4/IMDB comparison completed 05-Sep-08
– COS & WFC FSW Patchable Constants• Prep for verification/signoff in progress
– Documentation• ACS DM-05 update ready for distribution• COS & WFC3 DM-05 updates in progress (minor)• COS & WFC3 OP-01 updates TBD
– SMS Review Tool• Necessary code is complete; some input data updates
are TBD (related to tracking info, not SMS checking)• To be installed during SM4 (some updates are not
appropriate for pre-SM4 operation of ACS)
76
SM4 Data Management Software Status
Faith Abney
Data Systems Branch - OED
77
What do we mean by “Data Processing” ?
• Receipt of science and engineering data• Reformatting, quality checking, calibration,
to prepare data for archive• Archiving the data• Retrieving the data• Processing & calibration of retrieved data
• Sending data to the user• User access tools
78
Data Ingest Pipeline
79
Data Distribution
80
Raw Data Receipt and Ingest
• PACOR interface code has not changed– Tested with all ground tests including STScI and PACOR
• included all SMGT data– Used daily to support HST operations
• No changes to POD ingest processing– All instruments handled identically– No instrument specific code– Tested with all SMGT data for COS and WFC3– Used daily to support HST operations
• 100% of COS and WFC3 SMGT data have gone through data receipt and ingest processing
• No critical outstanding PRs for this part of the system
81
Data Ingest Pipeline
82
82
OPUS => COREScience Data Processing
83
Core Science Data Processing
• Instrument specific changes in every step • Biggest changes with:
– World Coordinate System is mostly new code for each COS and WFC3
– Generic Conversion for COS is almost all new code
– Generic Conversion for WFC3 reused much of ACS code
84
Core Science Data Processing
• 100% of COS and WFC3 SMGT data make it through– Still have changes to be completed in 2008.4
• 100% of TV went through all relevant stages– TV data has no schedule information so can’t
complete all pipeline stages– Haven’t gone back to rerun all the data with latest
software version• Outstanding SM4 PRs to go into next build
– 59281, 60725, 60640, 60722, 59921, 60240, 60349, 60440, 60630
85
85
OPUS => COREScience Data Processing
59821
60725
60640
60722
59921,60240, 60349, 60440, 60630
Outstanding PRs to go into next build
86
Data Ingest Pipeline
87
Catalog
• Keywords are extracted from data headers and are used to populate the database– Includes searchable parameters such as RA,
DEC, filters, detector, exposure times, etc– Includes instrument specific tables
• Database tables are searched by archive users using StarView or the Web Interface
88
Cataloging for COS and WFC3
• Cataloging is working for COS and WFC3– Cataloged both SMGT and TV data – TV data gets archived to operational archive using
own set of tables– SMGT data archived to the test system
• 100% WFC data is cataloged• 97% of COS data is cataloged
– Shared wavecals don’t work yet• Don’t expect any in SMOV
– Some ACQs still being worked on
89
Cataloging for COS and WFC3
• WFC3 keyword cataloging is complete– May add more keywords after SMOV
• COS first cut at keyword cataloging done– Iterating with the COS team
• To verify catalog contents, an independent verification tool checks the data headers against the catalog– Verifies right values come from the right extensions– Tool has been used for other instruments, recently updated
for COS and WFC3
• One outstanding PR, 60615
90
Database Tables
Instrument # Fields Table Size (KB)WFPC2 405 837644
STIS 783 1401432
NICMOS 746 2095472
ACS 503 448732
COS 455 30
COS_TV 449 14556
WFC3 357 30
WFC3_TV 386 175576
91
Data Ingest Pipeline
1 PR
9 PRs
0 PRs
1 PR
92
Data Distribution
93
Data Distribution Changes
• Added COS and WFC3 to list of known HST instruments• Added definitions of “Calibrated” and “Uncalibrated” data
retrieval keywords for COS and WFC3– Allowed for long extension names from OTFR for COS data (all
other OTFR instruments used 3 char extensions)
• Added more disk space • Distributed 100% of the COS and WFC3 that was ingested
(SMGT & TV)– Includes going through OTFR
• No outstanding critical DADS PRs
94
Keyword Extensions
CALIBRATED UNCALIBRATED
COS asn, corrtag_*, coretag_a, coretag_b, flt_a, flt_b, flt, fitsum, lampflash, spt, trl, x1d, x1dsum1, x1dsum2, x1dsum3, x1dsum4, x1dsum
asn, mdd, pha_a, pha_b, rawaccum_a, rawaccum_b, rawaccum, rawacq, rawtag, rawtag_a, rawtag_b, spt, trl
WFC3 asn, crj, drz, flt, ima, spt, trl asn, raw, spt, trl
An extension will be returned when a particular keyword is requested if that file exists for that dataset or within that association.
95
Data Distribution
96
Retrieval Interface
• StarView was rusty railed 4 years ago– Had support issues with old code and new
databases this spring– Data Retrieval by StarView was less than
3% of total– Usage was largely in-house by data
analysts and instrument scientists
97
Retrieval Interface
• StarView functionality migrates to Web– Retain the name “StarView”– Retrievals for COS and WFC3 are working on the
MAST science searches– Search screens for COS and WFC3 instrument
and engineering searches are not yet ready • Will be delivered as they become ready - not tied to build• Mostly used by instrument scientists and data analysts
98
Outstanding Critical PRs
• WFC3 - NONE• COS
– 59921 – GC changes – 60240 - Exptime when TDF is down– 60349, 60630 - COS ACQ files– 60440 – SPT Headers– 60486 – COS engineering data issue– 60615 - Keywords– 60722 – WCS– 60725 – Grating value
99
Outstanding Critical PRs
• ACS – 59821 - Oscilloscope mode– 60640 – Gain value changes
• STIS– None
NICMOS– 60429 - SAA clean timing issues
100
Outstanding SM4 Critical PRsWFC3 0
COS 9
ACS 2
STIS 0
NICMOS 1
TOTAL 12
101
Build Schedule
• DMS 2008.4– All SM4 critical PRs are in build DMS 2008.4– Also includes 3 non-critical, database table fixes– Enhancements for easier reprocessing in
operations– Installation scheduled for September 30– Each PR approved by HSTMO prior to installation
• Newly discovered critical problems will be delivered as quick fixes after 2008.4
• 2009.1 installation planned in early 2009
102
Routine Maintenance after SM4
• Likely items for DMS 2009.1– Changes based on SMOV experience– COS PulseHeight Histogram– COS Accumulated Images– Pipeline enhancements
• NICMOS Reprocessing – 60595,60597,60598, 60610, 60701
103
Calibration Software Status for SM4
Warren HackScience Software Branch - OED
104
Data Ingest Pipeline
Generate metadata from calibrated datasets
105
Data Distribution
The calibration software also gets provided to the user as part of STSDAS.
106
Current Instruments
The pipeline calibration software for the legacy instruments has been reviewed to see whether any changes were needed to support SMOV activities.
ACS: The ACS pipeline software will require changes to support the new commanded values of the gain.
STIS: No changes required for SMOV support.
NICMOS: The NICMOS pipeline have been enhanced with deliveries to OPUS 2008.3 in order to prepare for reprocessing of pre-SM4 NICMOS data.
WFPC2: All software development has focused on supporting final reprocessing during SMOV, and the version now in place will be sufficient.
107
WFC3CALWF3 Version 0.95 was delivered to OPUS Build 2008.3.
– This version of CALWF3 has been used to successfully process 100% of the relevant ground-test data from Servicing Mission Ground Test (SMGT) through OPUS. It has also been used by the WFC3 team to process all the Thermal-Vac (TV) test data.
• Testing of CALWF3 carried out by OPUS as part of standard regression testing for operational OPUS builds using SMGT data, and through a separate OPUS TV pipeline to process WFC3 thermal-vac data as needed by the WFC3 team.
• OPUS regression testing using SMGT data starts with raw telemetry files (POD files) processes them through Generic Conversion, CALWF3 and ingests the calibrated results in the archive for WFC3 team review.
• OPUS regression testing validates the entire calibration pipeline system from telescope to delivery to the end user, while processing the TV data validates the algorithms used in CALWF3 for the calibration.
– Updates to the non-linearity and bias-level corrections were identified as result of the latest TV data, as well as bugs in CR rejection algorithms.
108
WFC3CALWF3 has been tested using thermal-vac data and SMGT data.
– Thermal-vac data:
• Nearly 60,000 exposures
• Every conceivable detector readout mode, including UVIS Extended Pixel Edge Response (EPER) mode for CTE, and UVIS and IR special warm engineering test readout modes which will be used during the SM4 functional test.
– SMGT data:
• Regression test suite for OPUS/CALWF3 and for complete end-to-end test of all WFC3 front-end and back-end systems.
• 30 visits with 99 exposure lines resulting in 172 individual exposures.
• Wide range of possible exposure modes (binned, unbinned, 1-2-4 amp readout, UVIS and IR subarrays,…)
• 22 associations consisting of pure CR-SPLIT, pure REPEAT-OBS, pure dither for both UVIS and IR, along with IR REPEAT-OBS plus dither associations.
109
COS
CALCOS Version 2.4 has been delivered for OPUS Build 2008.3.
– This version of CALCOS has been tested using thermal vac (TV) data prior to delivery to OPUS.
– Regression testing performed by OPUS relies on the SMGT datasets. These datasets contain blank science arrays, but complete headers.
– OPUS regression testing has validated that 97% of all the COS SMGT data can be processed through the entire calibration pipeline system from telescope to delivery to the end user.
• The only failures coming from the use of shared wavecals.
– The COS Pipeline Verification Team processes the TV data to validate the algorithms used in CALCOS for the calibration.
110
COS
The COS PVT has reported:
– Functional testing has been completed successfully for CALCOS.
– Verification of the pipeline products based on assessment of the calibrated data and the algorithms has been performed using TV data for at least 8 of the 20 modules in CALCOS.
The data used for performing these tests include:
– The TV data from 2006 with more than 2100 exposures, covering the majority (if not all) observing modes.
– The SMGT data with about 40 associations of both ACCUM and TIME-TAG data taken by both NUV and FUV channels.
111
OPUS 2008.4
Work continues on CALCOS, with only a couple PRs which were resolved with the delivery of CALCOS v2.5 for OPUS 2008.4– CALCOS should become an STSDAS package. (PR 60180)– Reference file handling for wavelength calibration (PR 60653)– Use of science exposure SPT for product SPT file (PR 60708)
Recent TV testing of WFC3 has highlighted the need to make some modifications to CALWF3 to support the instrument during SMOV. The following OPRs were resolved with the delivery of CALWF3 V0.99 for OPUS 2008.4.– Cosmic-ray rejection algorithm updates (PR 60727, 60710,
60564)– Produce ‘drz’ files (PR 60674)
112
OPUS 2008.4The repair of ACS will return it to an operational state, and changes will be delivered for testing under 2008.4 to support ACS SMOV activities:
– Support the new commanded gain values for ACS (PR 60729)– Corrections to cosmic-ray rejection (PR 60727, 60710)
113
MultiDrizzle
No issues are expected for pipeline use of Multidrizzle during SMOV.
MultiDrizzle supports all current instruments imaging modes for ACS,STIS,NICMOS, and WFPC2, as well as WFC3 UVIS and IR images.
Multidrizzle will only be used in the ACS and WFPC2 pipelines during SMOV, but not for WFC3.
– It will not be turned on for WFC3 pipeline use due to the fact that on-orbit calibrations will need to be performed in order to generate accurate enough distortion models for WFC3. Verified distortion-correction reference files will be generated by the WFC3 Instrument team based on calibrations taken in Nov 29 for UVIS and Dec 3 for IR.
– SMOV calibration activities will still be able to use any new reference files generated from on-orbit data using the locally installed version of Multidrizzle.
– Pipeline use of MultiDrizzle for WFC3 can be added to OPUS as early as OPUS 2009.1.
114
Post-SMOV Work
Work continues on CALWF3 based on the results of TV testing of the IR channel to update the following processing steps:
• the IR reference pixel subtraction (PR 60657)• the IR non-linearity correction (PR 60659)
A number of issues have been identified for COS and even STIS which should not affect SMOV support. These issues have been given a low priority and will be resolved in time for delivery to OPUS 2009.1.
– COS: Trailer file handling may need to be revised based on experience during SMOV.
– STIS: Zero exposure time members of STIS associations disappear from the calibrated product (PR 60326)
– STIS: CALSTIS should use spectral order when saving the gross count rate (PR 60327)
There will additional issues which come up during SMOV, and those will be prioritized based on the impact to SMOV activities.
115
Routine Maintenance After SM4
Significant testing has been performed to verify that data taken in the most common modes from each instrument will process successfully through the entire pipeline; from raw telemetry through calibration to archive ingest and retrieval from OTFR. However, issues with unexpected situations will arise during SMOV which will require immediate calibration software fixes, and a procedure will be in place to address these issues.
Those isolated calibration pipeline problems which prevent the completion of processing and delivery of data to PIs will be worked with the highest priority during SMOV by SSB.
The SSB developer will assess whether the problem arises from: – a software bug, – reference file problem (which may or may not require a software change), or– input file formatting issue (which may still require a software change).
For fixes which require calibration software changes:1. data causing failure will be provided to SSB 2. software will be revised to address the issue3. functional testing will be performed by SSB along with testing against the
problem data to verify that the problem was adequately resolved while still successfully processing the functional test data.
4. new code will be delivered to OPUS using standard mechanism
116
Routine Maintenance After SM4
Any issue identified as a reference file problem will be reported to the instrument team for resolution, and any relevant software change will be verified using the procedure outlined here.
Any issue involving the input file format will be reported to OPUS for discussion and resolution, and any relevant software change will be verified using the procedure outlined here.
For those issues which do not prevent the processing of data or
impede the deliver of data to the PIs:OPRs will be filed, and the work will be prioritized using current methods and criteria.
– Such issues might include errors in keywords or interpretation of association tables.
117
Operational Readiness
Albert Holm
Data Processing & Archive Services - OED
118
Topics
• Rapid data delivery
• Pointing adjustments
• Activity and staff schedules
• Data release policy implementation
• Metrics/completeness tracking tools
• Anomaly resolution procedure
119
Data Ingest Pipeline
120
Data Distribution
121
Rapid Data Delivery
122
Rapid Data Delivery - 2
Proposals and visits requiring rapid turn around given fast track service – routinely identified via the SMOV4
Proposal Implementation Team (PIT)– 14 ACS, 3 STIS, 2 NICMOS, 7 COS, and 4
WFC3– SM4 functional test data also will be fast-
tracked
123
Rapid Data Delivery - 3Rapid delivery managed with existing DPAS procedure
11.3.3 & Fastrak tool• PIs asked for destination directories for transfer tests in August• ACS oscilloscope mode data requires special preparations
– Resource file overrides– Transfer of ACS memory dumps successfully tested– Oscilloscope tables test awaiting processing capability (PR 59821 in DMS 2008.4)– ITSD created a web interface to allow GSFC engineers to access the data
PR 59582, Fastrak hangs when transferring more than 1 GB of data during session
• Fix planned for DMS 2008.4
124
Pointing Adjustment Support
Genslews allow small pointing adjustments of the telescope to correct for inaccuracies in assumed aperture positions
• Ten SMOV4 proposals requiring Genslews (One ACS and nine COS) identified via PIT
• ACS coronographic apertures move• COS aperture locations may need adjustment from
pre-launch measurements
Genslew ops requests managed via existing DPAS procedure 11.7.9
125
Activity SchedulesActivity schedules for fast track and pointing
adjustments are derived from mission schedule data delivered by SMSB.
• OpusLib java tool automatically generates a table of times for pointing adjustments
• Fast track dump times are determined manually from the RDO files
Staff schedules will be adjusted if needed for critical events
126
Staff SMOV4 Schedules and Kepler
Kepler Operations Readiness Test duties are split up among four DPAS personnel:
• Forrest Hamilton, DMC Ops Lead, manages the test setup and execution, and provides HST trouble shooting
• Deb Kenny and Gustavo Cardona will support the ORTs and SMOV4 data processing operations
• Tracy Ellis will support SMOV4 and will support the ORTs if SMOV activities allow
Only ORT-2a is likely to occur during SMOV• This ORT will simulate a few days during commissioning• Impact upon SMOV activities should be small since this ORT
will require the processing of only 6 Full Frame Images (FFIs)
127
Data release policy implementation
OPB has set initial proprietary period to one year for proposals using either new SIs or serviced modes
• ERO and ERS data will remain proprietary until their press release
• SMOV and calibration data for COS, WFC3, and the serviced modes will remain proprietary until ERO press release
128
Data release policy implementation - 2
Manual process for shortening release dates will continue
• based on proposal ID, not visit or SI mode
GO data taken with new SIs and with serviced modes will be embargoed
• authorization to access data from proposal will be withheld until the PI agrees not to discuss or present the data publicly until after ERO press releases
129
Embargo Agreement Text
130
Metrics/completeness tracking toolsBasic tracking tool recognizes COS & WFC3 data• not thoroughly tested, but should be able to track
whether all expected observations have been received and processed
• supplies HSTMO metric pages HST Science Data Availability and HST Processing Status
More detailed metrics tools and reports still in work and probably will not be ready at start of SMOV4
131
Anomaly resolution procedure
Procedure 11.10.1, Response to Pipeline Processing Problems, will be followed
1. Investigate problem using process log files and trailer files as appropriate
2. If symptoms are of a known problem with an existing workaround, execute the workaround.
3. If the problem is known but no workaround exists, document the error and the dataset.
4. Notify DSB of a previously unknown problem if error occurred in code DSB maintains
5. Notify SSB and the SI team of a previously unknown problem which occurs during calibration
132
Infrastructure Contingency Planning
Doris McClure
IT Services Division
133
Topics Covered
Facilities readiness and failover capabilities– Backup power– Building security
Essential computer equipment– Planning and scheduling systems– Data Management Systems– Science instrument support systems– Visiting instrument teams– Infrastructure: central storage, network, email– Off-hours support during SM4 and SMOV
Internet access/data transfer
134
Backup Power Capabilities
All essential network equipment, servers, and storage are located in computer rooms connected to an UPS (uninterruptible power supply)– Provides 30-45 minutes of backup power
In addition, critical servers and core network switches are attached to power generator– Provides unlimited backup power– Covers Planning and Scheduling systems and Data
Management System
Failover to power generator was successfully tested on 8/15
135
Building Security – Muller Bldg.
Normal operating procedures– Guard stationed at building entrance 24x7– Building open from 7am to 6pm, all visitors must sign in– Access card for entry to building is required outside these hours– First floor (where all critical computer equipment is located) is
locked down from 6pm to 7am weekdays and on weekendsEnhanced security capabilities
– By launch additional access card readers will be in place providing capability to:
• Lock down entire building at a moment’s notice• Lock down selected sections of the building
Plans during SM4– Access through front door will continue to be from 7am to 6pm– First floor access will be controlled, i.e., access card required, 24
hours/day, 7 days/week
136
Essential Computer Systems - 1
Planning and Scheduling systems– Servers protected against power outages by both UPS and
power generator– Desktop systems protected against power outages by UPS– Distributed model ensures that failure of any one system
should not affect operations– If entire site (STScI) becomes unusable, STScI can move
this function to GSFC where offsite backup servers are in place
• Last successful test was performed 10 July 2008
Data Management Systems– Servers and storage are protected against power outages by
both UPS and power generator– No backup/offsite capabilities exist
137
Essential Computer Systems - 2
Science instrument support systems – Systems are primarily individual desktop/laptop systems– Protection against power failures
• Systems in 4th floor South offices are protected by UPS and power generator
• Other offices are not protected• Alternative locations exist (e.g. Rm 111 “Fishbowl”) that are protected
by UPS and power generator in the event of power failure
Visiting instrument teams– Space set up in 135 and N409– Procedure in place to certify visitor systems prior to attaching them
to the STScI network– No protection against power failure
• Can use Rm 111 in the event of power failure
138
Essential Computer Systems - 3
Network equipment and central storage system– Critical network equipment (core switches and routers) and the
central storage system are protected against power failures by UPS and the power generator
– Core switches and routers have failover capability to backup switch/router
– Central storage system has new areas dedicated to SM4/SMOV configured in highly available (RAID6) configuration. Two disks can fail and the storage will continue to function.
Email server– The email server is also connected to the UPS and generator– There is no backup server available, however alternatives will be in
place:• Use of STScI Information Channel (SIC) via web• Contact list includes alternate email addresses for all essential staff
139
Essential Computer Systems - 4
Off-hours support– On site support is provided from approximately
7am to 6pm, Monday through Friday– During mission, extra support will be on site as
required for quick turn around items– On-call procedures in place for unanticipated
failures of essential computer systems• ITSD management will be point of contact and on call
24x7 throughout SM4 and SMOV• Essential IT personnel will be on call and will respond to
emergencies
140
Internet Access/Data Transfer
Internet access is required to:– Send/receive all data between STScI and GSFC
No backup capability exists at STScI Plans in event of unanticipated, extended failure
– Potential use of JHU network for certain data transfers– Data from PACOR would need to be transferred via media (e.g. tape) – Planning and Scheduling operations move to GSFC– Science instrument support staff can go to GSFC
• Laptops are certified and HSTnet ready • Offices at GSFC will be available through the end of January 2009
Plans to address outages– Scheduled outages: NISN sends notices of planned outages well in
advance, usually 1-2 weeks. If timing is bad, we will reschedule with GSFC/NISN.
– Unscheduled outages: STScI will contact GSFC (Simrall) and/or NISN Help Desk in the event of an unplanned outage and work to resolve as quickly as possible.