Upload
kaviprakash6992
View
2.789
Download
1
Embed Size (px)
DESCRIPTION
my me dissertation on repetitive scheduling
Citation preview
A DISSERTATION
ON
SCHEDULING OF MULTI SPAN BRIDGES: AN APPLICATION OF REPETITIVE SCHEDULING
METHOD
Submitted to Rajiv Gandhi Prodhyogiki Vishwavidhyalaya, Bhopal (MP)
For Partial fulfilment of requirements of Master of Engineering (Civil)
with specialization in Construction Technology and Management
2009
Submitted byKAVI PRAKASH
Department of Civil Engineering MADHAV INSTITUTE OF TECHNOLOGY AND SCIENCE (An autonomous Institute under R.G.P.V., Bhopal)
Gwalior (MP)
MADHAV INSTITUTE OF TECHNOLOGY AND SCIENCE (An autonomous Institute under R.G.P.V., Bhopal)
Gwalior (MP)
2009
RecommendationThis dissertation work entitled “SCHEDULING OF
MULTISPAN BRIDGES: AN APPLICATION OF
REPETITIVE SCHEDULING METHOD” submitted by
KAVI PRAKASH for partial fulfilment of the requirement of
Master of Engineering Civil with Specialization in Construction
Technology and Management is satisfactory account of his
dissertation work and recommended for the award of degree
Dr. S.K. JainProfessor and Head Department of Civil EngineeringM.I.T.S., Gwalior-5
Dr. M.M. PandeProfessor Department of Civil Engineering and Dean (Academic)M.I.T.S., Gwalior-5
Prof. Y P SinghDirectorM.I.T.S., Gwalior-5
CANDIDATES DECLARATION
I hereby declare that the work, presented in the dissertation
entitled “ Scheduling of Multispan Bridges : An Application of
Repetitive Scheduling Method” in partial fulfilment of the requirement
Master of Engineering Civil with specialization in Construction
Technology and Mangment is an authentic record of my own work carried
out under the guidance of Dr. M. M. Pande , Professor of Civil
Engineering and Dr. S .K. Jain , Professor and Head , Department of Civil
Engineering, Madhav Institute of Technology and Science, Gwalior.
The matter embodied in this dissertation has not been submitted by me for
award of any other degree or diploma
KAVI PRAKASH
This is to certify that the above statement of the candidate is true to best
of our knowledge
Dr. S K JainProfessor and Head Department of Civil EngineeringM.I.T.S. Gwalior-5
Dr. M M PandeProfessor Department of Civil Engineering and Dean (Academic)M.I.T.S. Gwalior-5
ABSTRACT
The scheduling problem posed by multi span bridge has the characteristics of
problem posed by linear repetitive construction however the repetitive units in
this case of bridge may vary greatly in work from one unit to the other. The
network methods are not effective to address such problems. When two
activities are independent of each other, network techniques are incapable of
scheduling the activities logically. Additional artificial constraints are required
to schedule the activities which have constant production rate. These methods
are not efficient in addressing problems of continuous utilization of resources.
Line of Balance (LOB) is well suited for repetitive activities where different
crews performs the activities one after the other; however this is not effective
in scheduling multi span bridges where large numbers of activity are
dependent on each other. Further, LOB is primarily a technique with emphasis
on continuous utilization of resources and therefore is not ideally suited for
scheduling bridges where activities and quantum of work varies from one unit
to another.
Linear scheduling Method developed primarily for scheduling linear activities,
like pipelines, highways etc. This method uses different type of activities viz
bar, line and block activities which are scheduled using a graph with time and
distance as axes. An algorithm developed for linear scheduling method for
repetitive projects known as Repetitive Scheduling Method makes use of
precedence diagram for repetitive unit attempting to provide advantages of
both Line of Balance and CPM techniques. The method takes care of both
resource continuity constraint as well technical constraints. This study deals
with application of Repetitive Scheduling Method for scheduling of multispan
bridges. The effectiveness of this method for scheduling of multispan bridge is
analysed by comparing it with other scheduling method like precedence
diagramming and Line of Balance Technique. Results obtained from the
different methods show that use of repetitive scheduling method provides
more effective scheduling addressing both, continuous utilization of resources
and minimum schedule duration.
Acknowledgement
I feel great pleasure in expressing my heartfelt indebtedness and gratefulness to
Dr. M.M. Pande, Professor, Department of Civil Engineering and Dean (Academic),
MITS, Gwalior who has guided and encouraged me at all stages of this work. The
confidence which he instilled and precious advise he gave can not be acknowledged
through words. The efforts and cooperation provided by him and enriching
suggestions given are gratefully acknowledged.
I am very thankful and indebted to Dr. S.K. Jain, Professor and Head, Department of
Civil Engineering, MITS, Gwalior for all the careful efforts, kind cooperation and
benevolent behaviour. The confidence which he posed in me and highly valued
inputs which he provided has lead to current shape of this dissertation. It is a
pleasure acknowledging his invaluable help and support.
I sincerely thank all the faculty members of Department of Civil Engineering who
willingly provided assistance and learning when ever it was needed. I will ever to
indebted to them for all their advice. I also express thankfulness to all the staff
member of Department of Civil Engineering, MITS, Gwalior, for all their help.
Any work requires time. I thank my wife, Deepika and son, Kavvya for allowing use of
their share of time for this work. I also thank my parents, Dr. Manorama and Dr.
Prakash Chandra Mahajan for their spirited support. I express my gratefulness for my
family members and friends who have helped in completing this dissertation by the
way of encouragement and cooperation.
In the end I thank all those who have knowingly or unknowingly helped me with this
work.
Kavi Prakash
Contents
CERTIFICATE ...…..…..…………………………………………………………………………………………………i
CANDIDATES DECLARATION.......................................................................................... ii
ABSTRACT..................................................................................................................... iii
Acknowledgement.........................................................................................................v
Contents....................................................................................................................... vi
List of Figures..............................................................................................................viii
List of Tables................................................................................................................. ix
List of Abbreviations......................................................................................................x
Chapter 1 INTRODUCTION.......................................................................................1
1.1 General...........................................................................................................1
1.2 Process of Planning.........................................................................................3
1.2.1 Pre Tender Planning................................................................................4
1.2.2 Post Tender Planning...............................................................................5
1.2.3 Operational or Detailed Planning............................................................5
1.3 Project Management and Scheduling.............................................................6
1.4 Purposes of scheduling...................................................................................8
1.5 Element of Project Scheduling........................................................................9
1.6 Work Break down Structure.........................................................................10
1.7 Scheduling Requirements in a Bridge Project...............................................10
1.8 Objective and Scope of Study.......................................................................12
Chapter 2 SCHEDULING TECHNIQUES & THEIR FEATURES.....................................14
2.1 General.........................................................................................................14
2.2 Bar Charts and Milestone Charts..................................................................15
2.3 Network Analysis Techniques.......................................................................16
2.4 Line of Balance..............................................................................................18
2.5 Linear Scheduling Method............................................................................19
2.6 Other Scheduling Method.............................................................................23
2.6.1 Computer Based Modelling of Project Schedule...................................23
2.6.2 Critical Chain Project Management.......................................................24
2.6.3 4 D CAD..................................................................................................24
2.7 Concluding Remarks.....................................................................................25
Chapter 3 REPETITIVE SCHEDULING METHOD.......................................................26
3.1 Introduction..................................................................................................26
3.2 RSM ACTIVITY LOGIC.....................................................................................26
3.2.1 Activity Logic Constraints.......................................................................27
3.3 RESOURCE CONSIDERATIONS.......................................................................27
3.3.1 Production Rates...................................................................................28
3.4 Control Points and Activity Relationships.....................................................29
3.5 Procedure for creating RSM schedule...........................................................32
3.5.1 First Stage of RSM..................................................................................32
3.5.2 The second stage of RSM.......................................................................32
3.6 Concluding Remarks.....................................................................................33
Chapter 4 APPLICATION OF RSM TO A BRIDGE......................................................34
4.1 General.........................................................................................................34
4.2 Salient Features............................................................................................34
4.3 Work Breakdown Structure (WBS)................................................................35
4.4 Resource Constraint......................................................................................40
4.5 Scheduling Using Precedence Diagramming.................................................40
4.6 Scheduling using Line of Balance Technique.................................................42
4.6.1 LOB chart for sub structure...................................................................42
4.6.2 LOB diagram for Superstructure............................................................44
4.7 Scheduling Using Repetitive Scheduling Method..........................................46
4.7.1 RSM Diagram of Substructure...............................................................47
4.7.2 RSM DIAGRAM of Superstructure..........................................................48
4.8 Results and Discussion..................................................................................53
4.8.1 Duration.................................................................................................53
4.8.2 Additional information..........................................................................53
4.8.3 Critical Path...........................................................................................54
Chapter 5 Conclusion.............................................................................................55
Bibliography................................................................................................................ 57
Annexure I......……………………………………………………………………………………………………….…60
List of FiguresFigure1.1 Ability to influence Cost 2
Figure 1.2 Planning Process 4
Figure 1.3 Project Management Triangle 7
Figure 3.1 Delay in Activities due to resource considerations 30
Figure 3.2 RSM diagram for three Units 31
Figure 4.1 Schematic Diagram of Digaru Bridge Plate 1
Figure 4.2 Bar Chart of Substructure Unit Plate 2
Figure 4.3 LOB diagram of Substructure Plate 3
Figure 4.4 Bar Chart of Superstructure Unit Plate 4
Figure 4.5 LOB diagram of Superstructure Plate 5
Figure4.6 Network Diagram of Substructure Plate 6
Figure 4.7 RSM Graph of Substructure Plate 7
Figure 4.8 Activity Logic Diagram 49
Figure 4.9 Activities in Soffit 50
Figure 4.10 Activities in Web 51
Figure 4.11 Activities in Deck 52
Figure 4.12 RSM Graph of Superstructure Plate 8
List of Tables
Table 1.1: Phases in Construction of Bridge____________________________________________2Table 2.1 Different Methods and suitability for different projects __________________________22Table 3.1 Activity relationship and Control Points_______________________________________31Table 4.1 Salient Features of Bridge__________________________________________________35Table 4.2 Work Breakdown Structure of Bridge_________________________________________36Table 4.3 WBS of Abutment /Pier ____________________________________________________36Table 4.4 WBS of PSC Box Girder ___________________________________________________39Table 4.5 Availability of Resources___________________________________________________40Table 4.6 Available and Allocation of resources after levelling____________________________41Table 4.7 Activity Table Substructure_________________________________________________43Table 4.8 Activity table superstructure________________________________________________45Table 4.9 Activities and Associated Resources_________________________________________46Table 4.10 Activities in Substructure Unit______________________________________________47Table 4.11 Activities in Soffit_________________________________________________________50Table 4.12 Activities in Web_________________________________________________________51Table 4.13 Activities in Deck_________________________________________________________51Table 4.14: Project Duration from different techniques__________________________________53
List of AbbreviationsCPM Critical Path MethodFF Finish to FinishFS Finish to StartLob Line of BalanceLRP Linear repetitive ProjectLSM Linear Scheduling MethodLSMh Linear Scheduling ModelPM Precedence DiagrammingPSC Pre Stressed ConcreteRSM Repetitive Scheduling MethodSF Start to Finish SS Start to StartWBS Work Breakdown Structure
Chapter 1
INTRODUCTION
1.1 General
Bridges are structures that cross over a body of water, traffic, or other
obstruction, permitting the smooth and safe passage of vehicles. In highway
transportation systems, the term “bridge” is usually reserved for structures
over bodies of water. Other terms like flyovers, overbridge, underbridge are
used where the highway across another highways or railway. The construction
of bridge has strong positive impact on economical and social development of
the areas to be served. This along with reliability of connection is the major
factor affecting the decision to invest in bridges. Major bridges represent
significant investment and considerable social political involvement is required
for deciding on making a bridge (Ostenfeld, et al. 2000).
Typical process for construction of large civil engineering structures like
bridges is given in the Table 1.1.These phases are also referred to as project
life cycle (Burke 2001). Planning is done for different phases. Proper planning
affects the cost of the project. The Figure 1.1 shows the influence of planning
on cost. Impact of planning reduces as the project is being constructed. If
correct choices are not made at the concept stage the resultant of cost are
increased much more than at a later stage.
Bridge project like other infrastructure projects are characterized by long
duration, large budget, and complexity. Construction of bridge projects is a
complex process that inherits uncertainty since the construction is executed in
different job conditions. These conditions includes unusual or complex works,
equipments breakdown, unfavourable weather conditions, and unexpected site
conditions. (Mazrouk, Zein and AlSaid 2006).
1
Table 1.1: Phases in Construction of Bridge
Phase Conceptual Planning and Feasibility Study
Design and Engineering
Procurement and Construction
Detailed Design and Startup
Execution Commissioning and Operation
Purpose Find out Needs, demands etcSocial, Economic, Environment feasibility
Designing the layout
Estimating of scope of work
Obtaining provider, contractor
Design of Bridge
Preparation of Drawings
Actual Execution
Bridge in Use
Outcome To build or not to build
What to Build Who will build Working Drawings
Bridge Proper
Return on Investment
.
Until a bridge is commissioned there is no return on investment for the owner.
An incomplete bridge is as good as no bridge hence successful construction of
bridge is utmost important for owner. Due to is very nature bridge are subject
2
Figure 1.1 Ability to Influence cost (Hendrickson 1989)
to large number of contingencies which if foreseen can save a lot of money.
Thus planning for bridge is very important.
At the Concept and Feasibility stage, selection of different type of bridge is
dependent on various factors like availability of resources, cost, time, and
nature of crossing. Bridges are classified according to different criteria. Span
arrangement of bridge is typically used to identify the bridge even after its
completion. On the basis of span arrangement bridges can be single or multi
span. A multi span bridge consists of one or more of foundation piers or
columns in addition to abutments. Generally, the span lengths of different
spans of bridge are same.
Once the decision for construction of a bridge is taken the planning for
construction of bridge is taken up. Essential aspects of construction planning
include the generation of required activities, analysis of the implications of
these activities, and choice among the various alternative means of performing
activities. Construction planners choose the best among numerous alternative
plans. Without planning the course of action may become somewhat aimless
with a succession of random changes in direction (Hendrickson 1989). The
plan of construction is generally included as a contract condition and work is
rarely started without a construction plan approved. Payment for bridge
construction contract and progress of work is monitored using construction
plan submitted and approved.
1.2 Process of Planning
The planning process is explained inFigure 1.2. During the project life cycle
this process is repeated for different phase of project life cycle. Planning for a
construction project can be divided in three main stages in the overall planning
cycle of construction project; pre tender planning, post tender planning and
operational planning, each associated with different stages in lifecycle (Sahai
2002).
3
Analyse Method Draft Sequence
Reject Impractical method Evaluate remaining methods within the draft sequence
Select Final Method,modify, select final sequence on the basis of overall cost
Prepare plan for Communication
Objective To determine the most economical method, sequence of each operation
Figure 1.2 Planning Process (Sahai 2002)
1.2.1 Pre Tender Planning
It primarily enables the estimator to determine the costs involved. The required
information concerning methods, plants, materials etc. is required by the
estimator in a concise form (i.e. data sheets and tables) in order that a quick
4
assessment can be made for higher management to decide on further action.
A secondary purpose of the “tender plan” is to provide a basis for the
subsequent contract plan. The amount of detail entered into at this stage of
tender planning will thus include both the time available and the degree of
competitive pricing of the tender for obtaining the contract. Scheduling in the
Tender Plan is generally to establish milestones.
At the tender stage sponsoring agency informs the executives regarding the
main objectives that are the extent of construction and the required completion
date. These call for an early assessment on aspects like methods to be used;
preparation entailed; scheduling and phasing of operations; available
resources; purchasing and supplies; and schedule of payments. These will all
be interdependent to various extents; without such assessments; any estimate
becomes a matter of conjecture, site management becomes mainly labour
supervision, and financial matters become crucial.
1.2.2 Post Tender Planning
After the tender stage planning much of the information required for planning
and scheduling becomes available. Planning at this stage goes into the details
of flow of funds with the associated progress of work. A check is then made
to ensure that the final ‘contract plan’ is at least as economical as that
submitted at the tender stage : It should be such that all company data on both
detailed tasks and overall stages of operation are based on the some
information, preferably obtained from reliable sources. The contract plan is
provided to site executive based on which the operations are planned.
1.2.3 Operational or Detailed Planning
The objective of the operational or detailed planning is to ensure that the most
economical method and sequence is used for each operation in compliance
with data is used in planning and estimation for the overall program of work. It
5
also becomes necessary to determine the timing of plant used, labour
requirements and availability of materials. The information can be recorded
either by a stage period planning which covers stages of construction. The
later is program setting which entails the detail plan for a period of perhaps
four to six weeks. In this way a forward view of at least three to four weeks
work is always maintained.
Planning subsequent to detail planning is stage planning. Stage planning is
used whenever it considered necessary to enlarge a section of contract plan.
Except for the stage planning being for a small part the process for stage
planning is same as for detailed planning
1.3 Project Management and Scheduling
A project schedule is so important that it is a customer specified requirement.
A schedule is conversion of project action plan into a operating time table
(Meredith and Mantel Jr 2003). Planning and Scheduling are often used
synonymously in context of project. Scheduling is part of the project planning
process. Planning can be used in a wider context with different objectives like
financial planning.
Project planning is the heart of proper project management because it
provides the central communication for the work of all parties. A bridge project
is undertaken to satisfy the goal of establishing connectivity. Satisfying a
project goal requires three constraints. Traditionally, these constraints have
been listed as "scope," "time," and "cost". These are also referred to as the
"Project Management Triangle” as shown in Figure 1.3 where each side
represents a constraint. One side of the triangle cannot be changed without
affecting the others (Lester 2003) & (Leach 2000).
Resources and Quality shown in the centre affects all the three constraint. The
schedule constraint refers to the amount of time available to complete a
6
RESOURCESQUALITY
COST
SCOPE SCHEDULE
project. The cost constraint refers to the budgeted amount available for the
project. The scope constraint refers to what must be done to produce the
project's end result. These three constraints are competing constraints. The
effect of changing three constraints is summarized as follows (Lester 2003):
(i) Increase in scope leads to increase in both cost and time;
(ii) Tight time schedule results in reduced scope with increased
cost;
(iii) Tight budget causes reduced scope with more time.
Figure 1.3: Project Management Triangle (Leach 2000) &
(Lester 2003)
It is the role of project planning team to prepare methods and layout statement
and work schedule to comply with these managerial requirements.
The final expression of planning is the documentation referred to as the ‘the
plan’ which consists of charts and schedules showing the various programs
required and is accompanied by a method ‘statement’ for the project.
Submission of Work plan and its approval is generally a contract condition.
This is also termed as master schedule.
7
1.4 Purposes of scheduling
Schedules cannot be 1:1 scale models of the construction process. The
schedule provides following information regarding the project:
i. Minimum stipulated requirements of project
The most common reason for the use of schedules today is to meet the
owner’s requirements to provide a monthly schedule update. In this
case, schedules are typically created by off-site scheduling consultants
who never discuss the project with the contractor or subcontractors.
After the submission of the initial schedule, it is updated monthly to
identify activities’ percentage complete.
ii. Checking the progress of the project by earned value analysis
Earned Value analysis requires that the schedule track both the time
and cost completion of each activity. First this means that the activities
in the schedule updates must reflect those tasks that are actually taking
place on the job site. Second, it means that each activity is required to
report two values: Percent Cost Completion, and Remaining Duration.
Separating cost from time allows activities that have large up-front costs
for equipment to correctly accrue costs. Another way that earned value
analysis can help the team understand what is a happening on the
project is to identify when work is falling behind schedule.
iii. Activities in progress
On complex projects, one of the most difficult coordination efforts is to
ensure that subcontracting crews arrive at the job site to complete their
work in an efficient sequence with other workers. One contractor out of
step results in rework. The coordination required is not a technology
problem it is a communication problem. The communication can,
however, be made more clear through the use of schedules. If
schedules specifically identify subcontractor activities, then the timing
for the arrival, scope of work, and departure of subcontractor crews can
be clearly described to the whole team. Using the schedule as a
8
communication vehicle may help decrease miscommunications. If there
are delays or scheduling conflicts, then the impacts of these delays on
following contractor and/or subcontractor activities may be clearly
identified.
iv. Effect of changes in schedule
If the baseline schedule accurately reflects the way that the prime and
subcontractors plan to do the work, and that the schedule is updated as
the project goes along, then the schedule can be used to evaluate what
would happen if changes are introduced to the plan. Schedule changes
will directly add or remove specific activities and may also impact other
activities or the overall completion of the schedule. A schedule that
accurately reflects the changes during the project will allow the entire
team to quickly understand the context in which a problem occurred
and the impact of that problem on other activities and the project
completion. Having an up-to-date schedule when a problem occurs will
assist the project team to resolve the issue and impacts rapidly and
then get on with the work. Usefulness of construction schedule helps to
predict progress of the projects, its completion time, task time, the
conflicts in work to sequence, and lastly to satisfy contractual
requirements.
1.5 Element of Project Scheduling
Basic elements of project scheduling are (Adeli and Karim 2001):
1. Creating the work breakdown structure where the total work needed for the
project is divided into recognizable and logical chunks of work called tasks.
2. Assigning resources to the tasks and estimating their durations.
3. Specifying scheduling constraints, which can be resource constraints or
logic constraints between the tasks.
4. Generating the optimal schedule by using an algorithm to appropriately
sequence and time each task in the project.
9
1.6 Work Break down Structure
The fundamental technique used for planning and managing a project is to
break down the scope of work into manageable tasks. This breaking of larger
tasks into smaller ones begins early in the project. This breaking develops
from the initial scope statement in a top down fashion, much like beginning at
the top of a pyramid and expanding downward (Ahuja 1984). The purpose of
the work breakdown structure (WBS) is to sub-divide the scope of work into
manageable work packages which can be estimated, planned and assigned to
responsible person or department for completion. The work breakdown
structure provides a structured breakdown of the scope of work into
manageable work packages which can be further developed into a list of
activities (Burke 2001) (Kimmons 1990). In case of a multi span bridge
construction project many activities are required to be repeated for
construction like shuttering and concreting. Thus a multi span bridge
comprises of partly repetitive activities for certain part while for other parts it
may not be repetitive.
1.7 Scheduling Requirements in a Bridge Project
Linear repetitive projects (LRP) (Ipsilandis 2006) are projects which involve
repetitive units of construction elements. Examples of linear repetitive projects
include high rise buildings, tunnels, highways, and pipelines. The repetitive
construction of these can monitored and planned in terms of number of floors,
tunnel rings, road sections, and joints of pipe, respectively. (Lutz and Hijazi
1993) Repetitive units can be further broken down into a sequence of
processes which are repeated for each unit of the project. For example, the
sequence of processes for a bridge having multiple spans include form
erection, steel placing, concrete placement, stressing, wearing coat,
expansion joints.
10
Here linear refers to construction projects the activities of which are repeated
continuously like highways, bridges, tunnels, railways, pipelines, sewers, and
follow one after the other. Repetitive is used for works like high-rise buildings,
mass housing. The repetitive nature of linear repetitive projects along with the
construction industry’s emphasis on standardization and modularization has
led to development of various planning techniques dealing with LRP.
Repetitive projects such as multi-span bridges require a different approach to
planning. In order to allow the optimum use of resources, crews and
equipment are required to yield the same production rate, in terms of
construction units. If activities are planned to be built in this way, all activities
could become critical since delay in one shall affect all subsequent activities.
When planning is based in construction units (floors, apartments, meters etc.)
and production rates, repetitive construction subdivisions can be considered.
The schedule can then be developed to generate the same work rate for all
crews. The number of crews is to be selected so that all crews will perform the
same amount of construction units in the same period of time. Various authors
have listed concerns in scheduling of repetitive projects (Arditi, Tokdemir and
Suh 2002) (Yang and Ioannou 2004).
Resources may have variable production rates and variable work
quantity at different work locations.
An activity may utilize multiple crews simultaneously. A crew may
perform multiple activities.
Activities may have multiple predecessors and successors. There may
be multiple relationships between each pair of predecessor and
successor.
The construction process, as defined by a set of activities and
relationships, need not be the same at every work location.
A full set of relationships (Finish-to-Start, Finish-to-Finish, Start-to-Start,
and Start-to-Finish) should be available.
11
Labour and equipment may change progress direction (east-to-west,
up-to-down, etc.) or have complex work sequences.
One activity may link to another activity at non-contiguous locations. For
example, a drywall activity on a specific floor should not start until the
completion of two higher floors of the preceding glazing activity to
ensure a weather-tight environment.
Activities may require space-buffer (lead-distance) in addition to time-
buffer (lead-time). The space-buffer may be non-integer, e.g., 1.5 km or
1/2 houses.
Activities may need resources that work back-and-forth in an area
within a certain period, such as excavation or traffic control. Other
resources may not work in this area at the same time.
Work interruption should be allowed.
The non-repetitive portion of project work should be incorporated into
the framework of repetitive scheduling.
Activity may have space-dependency like shuttering, placing steel and
concreting and time-dependency like stressing and concreting.
1.8 Objective and Scope of Study
The objectives of this study are outlined as follows:-
(i) To study different scheduling methods, which can be used to
schedule work execution of a multi span bridge,
(ii) To analyse the effectiveness of different methods of scheduling a
bridge consisting of repetitive activities,
(iii) To apply and examine Repetitive Scheduling Method which has
been proposed for repetitive works, and
(iv) Compare the result with the currently well known techniques of
Precedence Diagramming and Line of Balance technique.
12
The bridge was scheduled using precedence diagramming with the use of MS
Project 2002 while MS Excel spreadsheet software was used for Line of
Balance Technique and Repetitive Scheduling Model. The study concentrates
on scheduling of work on site without consideration towards procurement
action of materials resources like cement, steel etc. Study is limited in
application of scheduling methods to repetitive works activities required for
construction of foundation, substructure and superstructure. Scheduling was
not done for non repetitive activities where precedence requirement required
completion of work on approach road, guide bunds.
13
Chapter 2
SCHEDULING TECHNIQUES & THEIR
FEATURES
2.1 General
Attitudes toward the formal scheduling of projects are often extreme. Many
owners require detailed construction schedules to be submitted by contractors
as a means of monitoring the work progress. The actual work performed is
commonly compared to the schedule to determine if construction is
proceeding satisfactorily. Many field supervisors dislike formal scheduling
procedures and regard them irrelevant to actual operations and time
consuming distraction.
Use of formal scheduling procedures is advantageous whenever the
complexity of work tasks is high and the coordination of different workers is
required. After the completion of construction, similar comparisons between
the planned schedule and the actual accomplishments may be performed to
allocate the liability for project delays due to changes requested by the owner,
worker strikes or other unforeseen circumstances. Different bases exist for
preparation of schedules (Sahai 2002).
i. Arbitrary basis
In this basis the owner will best attain his or her objectives by telling the
contractors “what to do” and by restricting direction on “how to do it” the
matters of real significance. In this basis the owner will give the total
start and end time of major elements of the project.
ii. Intuitive Basis
14
In this basis of scheduling the contractor mostly uses his/her
experience and “gut feelings”. This basis is not useful when the project
is large because the complexity increases.
iii. Scientific Basis
Here the contractor breaks whole projects into some elements and
considers all factors such as man, machine, and material required,
critical time, start and finish time of all elements as well as his
experience.
Scheduling Approaches can be primarily classified as resource oriented and
time oriented scheduling techniques. For resource oriented scheduling, the
focus is on using and scheduling particular resources in an effective fashion.
For time oriented scheduling, the emphasis is on determining the completion
time of the project given the necessary precedence relationships among
activities. Hybrid techniques for resource levelling or resource constrained
scheduling in the presence of precedence relationships also exist.
2.2 Bar Charts and Milestone Charts
Bar charts were designed by Henry Gantt as a visual aid in planning and
controlling his ship building projects. In a bar chart the activities are first
plotted against the time axis. The scheduling of each activity is represented by
a horizontal line. The length of line is proportional to estimated duration of the
activity. For tracking the progress a second line is drawn beside the first line.
This second line was drawn as to indicate the actual status of work. The
relative position of these lines indicated the actual progress of the activity with
respect to planned progress (Burke 2001).
The purpose of a milestone schedule is to highlight the dates of significant
events. Milestones should be critical events which have serious schedule
15
implications (Ahuja 1984). Milestones are usually represented by single points
or diamonds. These represent dates when a particular event shall occur.
Bar charts have various disadvantages for scheduling complex projects. There
is no indication of interrelationships among activities. In developing a bar
chart, little analysis is done to find out how much time will be required. No
information about level of effort requirements is available. Despite these
shortcomings the Bar Chart continue to be used since Bar Charts are simple
to construct and easy to comprehend. Bar Chart can be summarized for any
desired level of WBS. With the advent of computer bar charts can be easily
updated (Bennet 2003).
2.3 Network Analysis Techniques
As a management tool, especially in project management of large capital
construction projects, network techniques are unsurpassed, if the activities
have been arranged in a logical, practical and easily identifiable manner by
experienced people (Lester 2003).
Basically the network is a flow diagram showing the sequence of operations of
a process. Each individual operation is known as an activity and each meeting
point or transfer stage between one activity and another is an event or node. If
the activities are represented by straight lines and the events by circles, it is
very simple to draw their relationships graphically, and the resulting diagram is
known as the network (Lester 2003).
Network analysis, as the name implies, consists of two basic operations:
1) Drawing the network and estimating the individual activity times
2) Analysing the activity times to find the critical activities and the float
in the non-critical ones. (Lester 2003)
16
The predominant technique used in building construction today is the Critical
Path Method (CPM). This technique has evolved over the past several
decades into highly sophisticated and computerized applications. This method
calculates the minimum completion time for a project along with the possible
start and finish times for the project activities.
The critical path itself represents the set or sequence of
predecessor/successor activities which will take the longest time to complete.
The duration of the critical path is the sum of the activities' durations along the
path. Thus, the critical path can be defined as the longest possible path
through the "network" of project activities, hance the name Network Analysis.
The duration of the critical path represents the minimum time required to
complete a project. Any delays along the critical path would imply that
additional time would be required to complete the project (Kerzner 2001).
Formally, critical path scheduling assumes that a project has been divided into
activities of fixed duration and well defined predecessor relationships. A
predecessor relationship implies that one activity must come before another in
the schedule. No resource constraints other than those implied by precedence
relationships are recognized in the simplest form of critical path scheduling.
When the activities in Critical Path Method are shown as node with arrows
connecting them the Network Diagram is known as Precedence Diagram.
Precedence diagram has advantage over CPM in the since four types of
activity relationship can be represented (i.e. Finish to Start, Start to Start,
Finish to Finish, Start to Finish ) . Another advantage is that there is no use of
dummy activities as in CPM (Gray and Larson 2001).
Programme Evaluation and Review Technique (PERT) differs from CPM in
having three time estimate instead of one activity duration. Thus PERT
incorporates uncertainty in activity durations in analysis (Mahdi 2003).
17
Graphical Evaluation and Review Technique (GERT) is another modification
which allows for loops in the network (Moder, Philips and Davis 1964).
Network analysis offers all the advantage of being able to analyse the planning
data by holding the data in computer files. The planning data in a network is
linked through the logic that defines the relationship between the activities.
Thus changes can be made in the data relating to individual activities, i.e. the
duration, the resources etc. or changes can be made in the logical relationship
between activities and the consequences recalculated and represented. In
addition the steps to produce and process a network plan are more clearly
defined, self contained and offer a more rigorous approach to planning
complex operations.
Despite their extensive use due to obvious advantages these methods have a
number of shortcomings. Primarily these are due to their inability to address
continuity of work which may result in crews being idle. Multiple-crew strategy
is difficult to implement in the network methods. The network diagram is not
suitable for monitoring the progress of a project. Network methods do not
provide an efficient structure for the representation of repetitive tasks. There is
no consideration of the location of work in the scheduling (Adeli and Karim
1996). For all practical purposes Precedence Diagramming has superceded
CPM for scheduling due to its extensive use in computer softwares.
2.4 Line of Balance
Line of Balance is primarily a production management method. Used primarily
for repetitive projects, a Line of Balance (LOB) chart does not show direct
relationships between individual activities. It shows an output relationship
between different operations in that one operation must be completed at a
particular rate for the subsequent relationship to proceed at the required rate.
Only the critical are important activities are included for the purpose of
scheduling through Line of Balance chart (Chitkara 1998).
18
This technique has been applied in construction work mainly in building of
houses and to a lesser extent for jetty work and in conjunction with networks of
roads. Line of Balance is a planning technique for repetitive work, and the
principles employed in it are taken from the planning and control of
manufacturing process. The basis of the technique is to find the required
resources for each stage of operation so that different stages are not
interfered with and the target output could be achieved. The completed
schedule is based on chosen resources; therefore the rate of construction
calculated takes account of these resources. This is difficult for the network
calculations, with separated logic and resource allocation.
The main concept of LOB is the work continuity of the labour teams over the
construction units. The purpose of this technique is to calculate the required
resources for each stage of production so that the following stages are not
delayed and target output is achieved (Harris and Ioannou 1998).
Updating a LOB schedule is difficult once the project has started, and if the
rates of the construction prove to be different from those of calculated values.
This difficulty arises from the fact that the resources, that is teams of men with
different skills, are already on site. Various challenges in adoption of Line of
Balance techniques in construction industry have presented (Arditi, Tokdemir
and Suh 2002). However the method has been adopted by some large
construction firms (Henrich and Koskela 2006).
2.5 Linear Scheduling Method
Alternate techniques to bar charts and networks that were developed in the
last 30 years are known under the generic term, ‘‘linear scheduling method.’’
The general consensus is that linear scheduling methods are well suited to
projects that are composed of activities of a repetitive nature. (Arditi, Tokdemir
and Suh 2002). Indian Roads Congress (IRC SP:14 1979) suggests for use of
19
CPM in case of highways by dividing each activity into small portion and
schedule as a separate activity. This gives a ladder like schedule.
Linear Schedule is a simple diagram to show location and time at which a
certain crew will be working on a given operation. Linear Scheduling Method
(LSM) is a graphical scheduling method focusing on continuous resource
utilization in repetitive activities. LSM is used mainly in construction industry to
schedule resources in repetitive activities commonly found in highway,
pipeline, and high-rise building projects. These projects are called repetitive
projects or linear projects. The main advantage of LSM over Critical Path
Method (CPM) is its underlying idea of keeping resource work continuously. In
other words, it schedules activities in such a way that:
i. Resource utilization is maximized.
ii. Interruption in on-going process is minimized, including hiring-and-
firing.
iii. Effect of learning curve phenomenon is minimized.
In LSM the activities are plotted on Graph where time is one axis and distance
is the other axis. The controlling path is obtained by linking the least distance
point between the activities. Linear construction consists of a group of
operations that involve repetitive ‘‘units’’ of construction elements. Highways,
high-rise buildings, tunnels, and pipelines are good examples that exhibit
repetitive characteristics where the same basic unit is repeated several times.
Multiple-dwelling, multiple-floor, or linearly progressive projects allow
construction to proceed in a repetitive fashion, allowing for cost and time
efficiencies. To achieve these possible efficiencies, it is necessary to balance
the crews. By such scheduling, a construction manager achieves continuity in
the placement of all repetitive elements, thus maximizing the productivity of
labour and equipment. In Linear Scheduling Method three types of activities
are recognized (Harmelink and Rowings 1998)
i. Linear Activity
20
Linear activities are activity which has a production rate. These
activities tend to progress continuously over length or units utilizing
same crew and resources.
ii. Bar Activity
Bar Activities are those which occupy small space and large time.
These activities do not allow any other activity to proceed for some
time.
iii. Block Activity
Block Activities are those which occupy both space and time. A block
activity generally means that the activity in progress is discrete and
cannot be assigned a production rate while it progress over some
distance or unit.
LSM diagram resembles the Objective Diagram of LOB technique. While
Objective Diagram is used to schedule or record the cumulative events of unit
completion LSM is used to plan or record progress on multiple activities that
are moving continuously in sequence along the length of a single project. This
method aims to provide a graphical view more efficiently representing linear
construction activities like highway and pipeline construction.
Linear activities have a production rate depending on resources required and
available. The activity is shown as line on the linear schedule graph with
production rate as slope of the line .The sequence of the activity to be included
in linear schedule is determined along with the time buffer and space buffer.
Time buffer is the time required between the start of succeeding activity and
end of proceeding activity. Space buffer is the distance required to allow two
activities to proceed without affecting is each other. The minimum time
constraint denotes the minimum time buffer between two activities—e.g., the
minimum time buffer between concreting and formwork removal allowing for
curing of concrete. The minimum distance/location constraint denotes the
21
minimum allowable distance between two activities to allow for the correct or
safe execution of work (Alexandros, John and Sergios 2007)
Linear Scheduling Method has been proposed by different names by different
authors. Different methods have been proposed for specific objectives by
different authors (Harris and Ioannou 1998)
Suitability of methods described in preceding sections for various purposes
has been studied (Harmelink and Yamin 2001). The Table 2.2 shows
suitability of the above described methods for different types of projects.
Table 2.2 Different Methods and suitability for different projects (Harmelink and Yamin 2001)
Type of project Scheduling method Main characteristic
Linear and continuous projects (pipelines, railroads, tunnels, highways)
Linear scheduling method
•Few activities all occurring at one place one after the other
Multiunit repetitive projects (housing complex, buildings) Line of Balance •Similar unitsHigh-rise buildings
Hard logic for some activities, soft for others,
Large amount of activities
Every floor considered a production unit LOB, VPM, PM • Repetitive activities
Refineries and other very complex projects
Complex design Activities discrete in
nature Crucial to keep project
in critical path PERT/CPM , PM
Complex Relationship Extremely large
number of activities
Simple projects (of any kind)Relatively few activities Bar/Gantt chart
• Indicates only time dimension (when to start and end activities)
22
Different models for identifying critical path or critical sequence for LSM have
been proposed by various authors namely the repetitive scheduling method
(RSM) by Harris and Ioannou, the linear scheduling model (LSMh) by
Harmelink and Rowings, the critical path linear scheduling method by Ammar
and Elbeltagi, and the repetitive project model by Kallantzis and Lambropoulos
(Alexandros, John and Sergios 2007). Repetitive Scheduling Model has been
described in detail in next chapter.
2.6 Other Scheduling Method
In addition to the methods described above, other scheduling methodologies
have been developed in recent years. Some of the methods are described in
subsequent paragraphs.
2.6.1 Computer Based Modelling of Project Schedule
With the availability of more powerful computers and software, the use of
advanced scheduling techniques is becoming easier and of greater relevance
to practice. (Hendrickson 1989) These techniques address some important
practical problems, such as:
scheduling in the face of uncertain estimates on activity durations,
integrated planning of scheduling and resource allocation,
Scheduling in unstructured or poorly formulated circumstances.
PERT and CPM can be modelled as linear programming problem with the
objective of minimizing project duration (Taha 2005). The growing availability
of computers allows computing power to solve larger mathematical models.
Computer models allow for both time and resource constraints while
modelling. Neural Network Technique has been developed for use in schedule
and cost optimization of projects (Adeli and Karim 1996). Multi objective
optimization has been suggested for scheduling linear repetitive projects
(Ipsilandis 2006). The success of computer based techniques is dependent on
23
proper modelling of the problem. Another advantage offered by use of
computers is in incorporating uncertainty in activity duration (Hendrickson
1989) by means of use of simulation.
2.6.2 Critical Chain Project Management
Critical Chain Project Management is based on the Theory of Constraint
developed by Eliyahu M Goldratt as applied to project management (Goldratt
1997). Theory of constraint says that there is generally one or two constraints
in a system. By concentrating on bottleneck the output can be maximised. This
is applied to project environment considering critical chain as bottleneck and
time available as inventory. Buffers are provided wherever required. The
critical chain can cater for both technical as well as resource constraints.
Critical Chain Project Management is a method of planning and managing
projects that puts more emphasis on the resources required to execute project
tasks. This is in contrast to the more traditional Critical Path and PERT
methods, which emphasize task order and rigid scheduling. A Critical Chain
project network will tend to keep the resources levelly loaded, but will require
them to be flexible in their start times and to quickly switch between tasks and
task chains to keep the whole project on schedule. CCPM is not a new
scheduling techniques instead adopts PERT/CPM. CCPM scheduling
provides for buffer before the critical path (bottleneck) but not anywhere else in
the network thus no float is given to any activity but rather float of all activity
are placed as a buffer before the critical path (Steyn 2002) (Leach 2000).
2.6.3 4 D CAD
This approach involves the combination of 3D design data with the added
dimension of time. Extending the traditional planning tools, visual 4D models
combine 3D CAD models with construction activities to display the progression
of construction over time. 4D CAD systems originated from the construction of
processing, power, and offshore plants where 3D modelling has long been
used for checking space conflicts of the complex piping systems.4 D CAD is
24
used for scheduling by including use of GIS in modelling construction. 3D
CAD is development of 3D Model on computer of a facility being designed.
The 4th dimension of time is applied so that this model shows the state of
works as the work progresses. In 4D CAD for planning of works it is attempted
to note location where a crew shall be working at a particular time by
modelling the construction sequence. The planning takes care that the crew
while working gets enough space for working and progress is not hindered by
other crews in vicinity. While great achievements have been made in applying
4D CAD to the construction of industrial facilities and commercial buildings
little has been done in road and bridge construction. This may be due to
limited computer support for construction planning of transportation
construction projects. Formally speaking 4D CAD is addition of time dimension
to standard 3 D models which are now commonly used in construction.
2.7 Concluding Remarks
Above methods are used in different types of construction works depending on
the availability of necessary information. The choice of scheduling method
depends on the requirements of the project. The use of computer based
modelling and simulation requires knowledge of modelling, the use of 4D CAD
requires availability of 3D CAD drawings, and the Critical Chain Project
Management requires details regarding details of buffers available for different
activity. These methods cannot be used since the necessary information was
not readily available. In comparison Repetitive Scheduling Method proposed
by Harris and Ioannou uses the data required for precedence diagramming
and can be utilized wherever precedence diagramming is used. Repetitive
Scheduling Method has been used in this study and same has been described
in details is the following chapter.
25
Chapter 3
REPETITIVE SCHEDULING METHOD
3.1 Introduction
Harris and Ioannou presented Repetitive Scheduling Model (RSM) as a
generalized approach to scheduling of linear and repetitive projects than Line
of Balance and Precedence Diagramming. It uses Precedence Diagramming
for planning of unit network. All the activity types (linear, bar, block) as used in
LSM are accepted in RSM. (Harris and Ioannou 1998).
An RSM schedule is shown as an X-Y graph where the axes represent units,
and time. In general for clearly delineating schedule information, in case of
construction of high-rise buildings, the units can be conveniently shown by
plotting on Y axis and time along X axis. The work progress of horizontal
construction projects e.g. highways, pipelines, canals, tunnels, bridges can be
plotted along X axis since unit represent length. A logical sequence is adopted
for representing the units of projects which are repetitive in nature.
3.2 RSM ACTIVITY LOGIC
The identification of the precedence constraints amongst the units is essential
in addition to establishing the pattern of repetitive units. A CPM precedence
network is drawn for each repetitive unit. A list of all the time consuming
activities is prepared for establish unit activity logic. A name and identification
symbol is assigned to each activity in the list for finding suitable relationship
with regards to related units, there by reducing redundancies. On examination,
the activity list will show a set of similar activities occurring repeatedly. A logic
diagram is prepared after all the activities of each repetitive unit are identified.
The precedence form is generally preferred but arrow network can also be
26
used. Each unit network should contain all technical logic relationships among
the activities. The main purpose of this diagram is to establish logical
relationships among the activities, resource considerations within this unit can
be temporarily ignored. Actual projects have complex relationships among
their activities which may be difficult to properly detail without a standard
procedure outlined above.
3.2.1 Activity Logic Constraints
The activities within a repetitive unit must be logically related as well as they
also must be logically related from unit to unit. The two types of constraints
that control unit-to-unit logic in RSM diagrams:
i) Technical Precedence Constraint
A particular work activity in the network of one unit must be
followed by a similar work activity in the network of a succeeding
unit to ensure that the flow of the technical work between the units is
maintained.
ii) Resource Availability Constraint
The resource assigned to an activity in one unit also must be
assigned to the similar activity in the succeeding unit to ensure that
the resource required in the first unit is available when needed by
the second unit.
The continuous resource utilization is neither ensured nor forced in the
schedule.
3.3 RESOURCE CONSIDERATIONS
Every activity requires the application of resources for its performance. Most
activities require that several resources like man, material, machine be
employed together. RSM assumes that only the most significant resource is
associated with an activity and all activities are defined using this assumption
(Harris and Ioannou 1998).
27
To cater for a second assumption that the same resource will be used for like
activities in successive repeating units, each activity’s resource must be
consistent from unit to unit. If an activity needs several significant resources
for its performance, different activities in parallel can be assigned for each
resource/crew. If several activities within a repetitive unit require the same
resource, the several activities are grouped into one common activity using
that resource to avoid the appearance of interruptions in resource usage
between units.
3.3.1 Production Rates
There are two important production rates associated with each activity, a
resource production rate and a unit production rate. (Harris and Ioannou 1998)
The resource production rate for an activity is defined as the amount of work
that can be done by the resource per unit of time. Resource production rate is
obtained from available databases. Resource production rate is an attribute of
the resource and thus remains constant in any unit involving the same activity.
The unit production rate is the number of repetitive units that can be
accomplished by a resource during a unit of time. The unit production rate is
the slope of a production line in an RSM diagram. The unit production rate is
directly proportional to the activity’s resource production rate and inversely
proportional to the quantity of work in the unit. In cases where activity duration
are known unit production rate is inverse of duration.
When the quantity of work in activities that repeat from unit to unit is not the
same in every unit, the unit production rates will vary depending upon the
amount of the work in each unit. Similarly, if the activity duration is not same in
different units, unit production rate changes.
28
3.4 Control Points and Activity Relationships
In an RSM graph activities are represented as continuos lines with interruption
indicating the interruption in utilization of the resource associated with that
activity. These lines are termed as production lines. The slope of this line is
proportional to unit production rate of the activity.
Production line of different activity can be parallel, diverging or converging.
Parallel production line indicates that both activities are progressing at the
same rate. Diverging production line indicate that rate of production of
successor is less than that of predecessor. Converging production lines mean
that rate of production of successor is greater than that of predecessor.
Resource is utilized continuously across different units with each resource
being associated with one activity. If an activity Y1 (where Y indicates activity
and 1 indicates unit) follows an activity X1 and has greater duration than its
predecessor, the resource associated with activity Y1 shall not be available for
the activity Y2 in subsequent unit till its utilization in first unit is not complete.
This will result in delay in start activity Y2 in second unit in spite of
predecessor activity X2 being complete in second unit. Similar for the activity
Y3 in third unit this delay is greater due to effect of delays in both unit 1 and
unit 2. The Figure 3.4 shows bar chart of how activities are delayed due to
resource continuity requirements in RSM.
In RSM graph the activity are represented as lines. The Figure 3.5(Harris and
Ioannou 1998)Figure 3.5 RSM diagram for three Units (Harris and Ioannou
1998)shows the activity shown in Figure 3.4 in RSM diagram. Due to non
availability of resource required for activity Y the project is duration is
increased. The location of activities Y1, Y2, Y3 is determined by the start of
activity Y3 and this point is the control point. In order to achieve continuos
resource utilization the activity Y1 and Y2 have to be delayed. The location of
Activity Y2 and Y1 is determined by the location of start of activity Y3. This
29
X1
X2
Y2
Y3
X3
Y1
Activity Y2 delayed due non availability of resources due to non-completion of Activity Y1
Delay in Activity Y3 greater than that of Activity Y2 due to addition of delays of previous units
Repetitive U
nits
point is defined as control point for activity X and Y since activities in other unit
are controlled by it. If production rate is of Activity X is increased the control
point will shift. With this the production line of activity Y will shift. If production
rate of activity X is changed the location of control point will not change
however the slope of production line will change. In this situation the
production line will rotate about the control point.
A control point in RSM can be defined as a point which can be used to
determine the location of all the activity of the same type in the project. These
point are required to be established to plan for increase and decrease in
production rates of the activities. Location of control point is determined by
production rates of activity and relationship between the activities. The Table
3.3 shows location of control point and activity relationship. The controlling
path or sequence is drawn by connecting the control points along the
production lines starting from the last activity
Figure 3.4 Delay in Activities (Harris and Ioannou 1998)
30
0 1 2 3 4 5 6 7 8 9 10 11
3
2
1
Repetitive Units X2
Y3X3
Y2
Y1X1
0 1 2 3 4 5 6 7 8 9 10 11
Figure 3.5 RSM diagram for three Units (Harris and Ioannou 1998)
Table 3.3 Activity relationship and Control Points
Activity Relationship
Slope of Production Line
Location of Control Point
Effect of change of Production rate of predecessor
Effect of change of production rate of successor
Finish to Start Convergence Start of successor in last unit
Shift in successor activity
Rotate about control point
Finish to Start Divergence End of successor in first unit
Shift of successor activity
Rotate about control point
Start to Start Convergence Start of successor in last unit
Shift of successor activity
Rotate about control point
Start to Start Divergence End of successor in first unit
Shift of successor activity
Rotate about control point
Finish to Finish Convergence Start of successor in last unit
Shift of successor activity
Rotate about control point
Finish to Finish Divergence End of successor in first unit
Shift of successor activity
Rotate about control point
31
Successor Activities delayed due to resource consideration
Control Point determines the start of Activity Y in all units
3.5 Procedure for creating RSM schedule
RSM schedule is created in two stages (Yang and Ioannou 2001)
3.5.1 First Stage of RSM
In the first stage, the forward pass computations of CPM are performed. The
first stage of RSM includes the following five steps:
(1) Establish the position and slope of production line of each activity by
assuming it starts at time zero..
(2) For each predecessor, determine the activity’s shifted position based
on each relationship (link) in every possible unit.
(3) Calculate the shift that is the difference between the shape starting at
time zero and the shifted position.
(4) Select the maximum shift over all units, all incoming relationships, and
all predecessors.
(5) Move the activity being scheduled to the position that results from the
maximum shift.
3.5.2 The second stage of RSM
The second stage is used to model the pulling effect of work continuity
automatically. It is built on an important assumption: each activity would have
no more than one ‘continuity predecessor’. This is one of the basic
assumptions of RSM. The activities linked by continuity relationships can form
a continuity activity chain. A continuity activity chain can be considered a
summary activity that utilizes the same crew. For each continuity activity chain,
upstream activities are pulled by the sum of lags within the chain to eliminate
gaps and ensure the continuous utilization of the resource from one activity to
the next. If gaps (work interruptions) are desired between activities, this stage
may be skipped. This stage consists of following steps:
32
(1) Locate continuity activity chains and sort them according to the
precedence order. This is similar to the topological sorting of
activities in the first stage.
(2) Increase the start time of the first activity in a continuity activity
chain by the sum of lags within the chain so that first activity is
continuous over all units and schedule other activities based on
the new start time of the first activity.
(3) First stage is required to be repeated for all activities other than
first activity.
(4) If the start time of the last activity in the continuity activity chain
increases, postponing the first activity in the chain would delay
the start time of the last activity and hence lead to a cycle.
Therefore in such a case this chain should be skipped and the
next chain taken up. If there is no effect on start time of last
activity in chain, change the start times of all activities in the
chain can be changed to the calculated ones and proceed to the
next chain.
3.6 Concluding Remarks
RSM considers resources continuity as well technical precedencies. In
projects availability of resources and their continuous utilization is very
important for project managers. A scheduling method which incorporates
continuous resource utilization can well and truly takes care of requirement of
project management especially for resource planning. RSM thus seems to be
a useful and efficient method which can be easily applied for scheduling of
bridges projects. Attempt is made to study the method for scheduling a
multispan bridge. The same bridge is also scheduled with other method to test
feasibility of the method for scheduling multispan bridge projects to compare
relative advantages and disadvantages of different methods
33
Chapter 4
APPLICATION OF RSM TO A BRIDGE
4.1 General
A 720 meter multispan bridge under construction, comprising of 16 spans, was
taken up for the purpose of study. The bridge is currently under construction
by defence in eastern sector. The total work involved in the bridge project
includes construction of a bridge over a meandering river along with its
approaches and guide bunds for river training.
All the superstructure spans and pier shaft and wells for abutments and piers
were alike with only minor difference. This meant that similar type of work was
to be repeated 16 times making this bridge a good case to apply scheduling
methods developed for repetitive works. Sixteen (16) Prestressed Concrete
Box Girders for superstructure and seventeen (17) solid piers over circular
wells as substructure are included as part of study. Other activities not being
repeated many times were not included in study due to time limitations.
Activity durations have been obtained from site executives and by experience.
These have been used from another nearby bridge under construction by the
same organisation and also from other bridge in the vicinity.
4.2 Salient Features
A bridge under construction over river Digaru in Arunachal Pradesh is used for
the purpose of study. The bridge is located on a meandering river with multiple
channel necessitating large length with multiple spans in a sparsely populated
forest area. Design details and construction methodology is elaborated in
Table 4.4. A schematic diagram of the bridge is attached as Figure 4.1.
34
Table 4.4 Salient Features of Bridge Feature Details
Length of Bridge 720 meters
Span Arrangement 16 span 45 meter each
Type of Superstructure Prestressed Concrete (PSC) Box Girder
Method of Prestressing Post Tensioning
Type of Substructure Solid Pier both for Abutments and Intermediate Piers
Type of Foundation Circular Well foundation for Piers and Abutments
Methodology of Construction Cast In situ
Proposed date of Completion 31 March 2010
Date of Start of Construction at site 26 Nov 2006
Working Period Throughout the Year
Founding RL of Wells 145.00 meter (from the temporary bench mark established
Top of Well 162.50 meters
RL of Soffit 167 meter
RL of Deck 170 meter
Width of Soffit 7.00 meter
Height of Web 2.75 meter
4.3 Work Breakdown Structure (WBS)
The work break down structure has been prepared, keeping in view the
reporting requirements. Each Abutment/Pier was divided in 10 main activities.
Some activities were further divided in sub activities. Each PSC Box girder
was divided into 7 main activities some of which were further divided into sub
activities. The division of activities into sub-activities was done in consultation
with site executives. The dependency relationship and duration were obtained
from other bridge being constructed in vicinity and from experience of bridge
site staff. The following tables (Table 4.5, Table 4.6,Table 4.7) give the details
of WBS of the bridge. Activities in WBS level 3, 4, 5 and 6 are shown in Table
4.6 for substructure and Table 4.7 for superstructure.
Table 4.5 Work Breakdown Structure of Bridge
35
BRIDGE (WBS level 0) Activities to be reported (WBS level 3)
SUB STRUCTURE (WBS level 1)
Abutment/Pier (WBS level 2) (repeated 17 times)
1 Making of island and placing of cutting edge
2 Casting of well kerb
3 Casting of well steining
4 Well sinking
5 Bottom plugging
6 Top plugging
7 Sand filling in well
8 Casting of well cap
9 Casting of abutment/pier
10
Casting of pier cap
SUPERSTRUCTURE (WBS level 1)
PSC Box Girder (WBS level 2) (repeated 16 times)
1 Fixing of bearing
2 Casting of PSC BOX Girder (including Erection of Shuttering and Concreting and stressing)
3 Casting of wearing coat
4 Casting kerb & handrail
5 Load Testing
6 Site Clearance
7 Fixing of expansion joints & drainage sprouts
Table 4.6 WBS of Abutment /Pier (highest level not included, shown for only one Abutment/Pier)
S No.
WBS Code
Activity Duration Precedence Relationship
1 1 Abutment/Pier 306.5 days2 1.1 Making of Island and Placing of
Cutting Edge 16 days3 1.1.1 Making of Island 1 day4 1.1.2 Placing and Fabrication of Well
Kerb 15 days3
5 1.2 Casting of well curb 21 days6 1.2.1 Erection of Shuttering 2 days 4
7 1.2.2 Cutting of Steel 0.5 days8 1.2.3 Placing of Steel 1 day 6,7
9 1.2.4 Pouring of Concrete 1 day 8
36
S No.
WBS Code
Activity Duration Precedence Relationship
10 1.2.5 Removal of Shuttering 1 day 9
11 1.3 Casting of well steining 231 days12 1.3.1 Casting of 1st Lift 50.5 days13 1.3.1.1 Erection of Shuttering 2 days 57
14 1.3.1.2 Cutting of Steel 0.5 days 7
15 1.3.1.3 Placing of Steel 1 day 13,14
16 1.3.1.4 Pouring of Concrete 1 day 15
17 1.3.1.5 Removal of Shuttering 1 day 16
18 1.3.2 Casting of 2nd Lift 80 days19 1.3.2.1 Erection of Shuttering 2 days 58
20 1.3.2.2 Cutting of Steel 0.5 days 14
21 1.3.2.3 Placing of Steel 1 day 19,20
22 1.3.2.4 Pouring of Concrete 1 day 21
23 1.3.2.5 Removal of Shuttering 1 day 22
24 1.3.3 Casting of 3rd Lift 109.5 days25 1.3.3.1 Erection of Shuttering 2 days 59
26 1.3.3.2 Cutting of Steel 0.5 days 20
27 1.3.3.3 Placing of Steel 1 day 25,26
28 1.3.3.4 Pouring of Concrete 1 day 27
29 1.3.3.5 Removal of Shuttering 1 day 28
30 1.3.4 Casting of 4th Lift 61 days31 1.3.4.1 Erection of Shuttering 2 days 60
32 1.3.4.2 Cutting of Steel 0.5 days 22
33 1.3.4.3 Placing of Steel 1 day 31,32
34 1.3.4.4 Pouring of Concrete 1 day 33
35 1.3.4.5 Removal of Shuttering 1 day 34
36 1.3.5 Casting of 5th Lift 90.5 days37 1.3.5.1 Erection of Shuttering 2 days 61
38 1.3.5.2 Cutting of Steel 0.5 days 32
39 1.3.5.3 Placing of Steel 1 day 37,38
40 1.3.5.4 Pouring of Concrete 1 day 39
41 1.3.5.5 Removal of Shuttering 1 day 40
42 1.3.6 Casting of 6th Lift 120 days43 1.3.6.1 Erection of Shuttering 2 days 62
44 1.3.6.2 Cutting of Steel 0.5 days 38
45 1.3.6.3 Placing of Steel 1 day 43,44
46 1.3.6.4 Pouring of Concrete 1 day 45
47 1.3.6.5 Removal of Shuttering 1 day 46
37
S No.
WBS Code
Activity Duration Precedence Relationship
48 1.3.7 Concreting 7th lift 150 days49 1.3.7.1 Erection of Shuttering 2 days 63
50 1.3.7.2 Cutting of Steel 0.5 days 44
51 1.3.7.3 Placing of Steel 1 day 49,50
52 1.3.7.4 Pouring of Concrete 0.5 days 51
53 1.3.7.5 Shuttering for False Steining 1 day
52
54 1.3.7.6 Pouring of Concrete 0.5 days 53
55 1.3.7.7 Removal of Shuttering 0.5 days 54
56 1.4 Well Sinking 235.5 days57 1.4.1 Well Sinking 0-2.1 25 days 10
58 1.4.2 Well Sinking 2.1 -4.2 25 days 17
59 1.4.3 Well Sinking 4.2-6.3 25 days 23
60 1.4.4 Well Sinking 6.3- 8.4 25 days 29
61 1.4.5 Well Sinking 8.4-10.5 25 days 35
62 1.4.6 Well Sinking 10.5 – 12.6 25 days 41
63 1.4.7 Well Sinking 12.6 – 14.7 25 days 47
64 1.4.8 Well Sinking 14.7- 15.5 25 days 55
65 1.5 Bottom Plugging 3 days 64
66 1.6 Sand Filling 3 days 65FS+21 days
67 1.7 Top Plugging 1 day 66
68 1.8 Well Cap 203.5 days69 1.8.1 Cutting of Steel Reinforcement
for well cap and pier 10 days50
70 1.8.2 Casting of Well Cap 1 day 69,67
71 1.9 Casting of Pier 6 days72 1.9.1 Shuttering 1st lift 1 day 70
73 1.9.2 Concreting 1st lift 1 day 72
74 1.9.3 Shuttering 2nd lift 1 day 73
75 1.9.4 Concreting 2nd lift 1 day 74
76 1.9.5 Shuttering 3rd lift 1 day 75
77 1.9.6 Concreting 3rd lift 1 day 76
78 1.10 Casting of Pier Cap 16 days79 1.10.1 Shuttering 7 days 76
80 1.10.2 Cutting of Steel 7 days 79
81 1.10.3 Concreting 2 days 80
38
Table 4.7 WBS of PSC Box Girder (highest level not included, shown for only one PSC box Girder)
S No.
WBS Code
Activity Duration Precedence Relationships
1 1 PSC BOX GIRDER 92 days2 1.1 Fixing Of Bearing 2 days3 1.1.1 Fixing of Bearing 1 day 9SS+3 days4 1.1.2 Casting of Pedestal 1 day 35 1.2 Casting of BOX GIRDER 85 days6 1.2.1 Erection of Staging and Shuttering 45 days7 1.2.1.1 Levelling of Ground 1 day8 1.2.1.2 Staging for Soffit 7 days 79 1.2.1.3 Shuttering for Soffit 10 days 810 1.2.1.4 Staging for Deck 7 days 711 1.2.1.5 Shuttering for Web 7 days 16,1012 1.2.1.6 Shuttering for Deck 7 days 1713 1.2.2 Casting of Superstructure 55 days14 1.2.2.1 Cutting of Steel for Soffit and Web 7 days15 1.2.2.2 Placing of Steel for Soffit 7 days 9,14,23FF+1 day16 1.2.2.3 Concreting of Soffit 3 days 15,23,2617 1.2.2.4 Concreting of Web 3 days 11,2718 1.2.2.5 Cutting of Steel for Deck 3 days 1419 1.2.2.6 Placing of Steel For Deck 7 days 18,1220 1.2.2.7 Concreting of Deck 3 days 19,2821 1.2.3 Cutting and Placing of Cables 16 days22 1.2.3.1 Cutting of Cables 8 days23 1.2.3.2 Placing of Cables 3 days 22,24,4,824 1.2.3.3 Making of End Block 12 days25 1.2.4 Crushing of Chips 20 days26 1.2.4.1 Crushing of Chips for Soffit 6 days27 1.2.4.2 Crushing of Chips for Web 6 days 2628 1.2.4.3 Crushing of Chips for Deck 8 days 2729 1.2.5 Stressing of Cables 9 days30 1.2.5.1 Stressing of Cable 1 day 20FS+21 days31 1.2.5.2 Grouting of Cables 1 day 30FS+7 days32 1.3 Casting of Wearing Coat and Crash Barrier 7 days33 1.3.1 Casting of Wearing Coat 5 days 3034 1.3.2 Casting of Crash Barrier 2 days 3335 1.4 Casting of Kerb and Hand Rail 2 days36 1.4.1 Casting of Kerb 1 day 2037 1.4.2 Casting of Handrail 1 day 3638 1.5 Load Testing 1 day 32
39
S No.
WBS Code
Activity Duration Precedence Relationships
39 1.6 Site Clearance 1 day 38,40
40 1.7Fixing of Expansion Joints and Drainage Sprouts 14 days
41 1.7.1 Fixing of Drainage Sprouts 6 days 3342 1.7.2 Fixing of Expansion Joints 14 days 30
4.4 Resource Constraint
Various resources are required for construction of bridge. Resources are not
available in infinite quantity. Availability of resources for the project is limited.
Major of resources required for the construction of bridge and maximum
quantity available is given in Table 4.8.
Table 4.8 Availability of ResourcesRESOURCE NAME MAXIMUM AVAILABILTY
Winch and Grab Bucket arrangement (used for sinking of well by grabbing in the well)
7 numbers
Crushing unit 1 no. 6-10 Tonnes Per Hour Capacity Volumetric Output 15 cu. m./day
Concreting Capacity 30-40 cu m per day using 5 batch mixers (each mixer capable of providing about 5-7 cu. m. of concrete per day/ depending on mix design
Circular Shuttering forms for well 2 sets
Welding set 1 No.
Skilled Manpower (1) Limited availability of Highly skilled, manpower due to which highly complex operations cannot be executed
(2) Semi skilled manpower available can be used as multi skilled personnel
Shuttering Forms for PSC box girders 4 sets
4.5 Scheduling Using Precedence Diagramming
The schedule contains nearly 2000 activities. Scheduling of the bridge is done
using precedence diagramming method with the help of MS Project 2002
software. Duration for one abutment/pier is 306.5 days as seen in Table 4.6
and duration for one box girder is 92.5 as seen from Table 4.7. Without using
resources levelling the project duration obtained is 399.5 days which is the
sum of duration of time required for completion of one abutment/pier and one
40
PSC box girder. Scheduling data obtained from MS Project software is
attached as annexure 1. The resource levelling tools available in the software
was then implemented. The duration of activities was kept fixed. The schedule
as obtained from the software after resource levelling is attached as
annexure 1. The software was not able limit allocation of resources up to the
maximum limit. The Table 4.9 shows the allocation and maximum quantity
available in percentage. There is an over allocation of resources which is
required to be resolved by delaying activity in the network.
Table 4.9 Available and Allocation of resources after levelling
Name of Resource Peak Requirements
Maximum Unit
Shuttering 800% 400%
Steel Cutting 600% 300%
Winch and Grab bucket arrangement 800% 700%
Concreting 1,300% 600%
Cutting Edge team 100% 100%
Welding Set 300% 100%
Jack 200% 100%
Grouting Pump 200% 100%
Cable Cutting 200% 100%
Stone Crusher 100% 100%
Steining form set 400% 200%
Girder Form set 600% 400%
Carpenter 100% 100%
Dozer 200% 100%
In precedence diagramming resource considerations are applied after network
has been prepared. Thus at the start of resource levelling procedure there is
an over allocation. After preparing the network the resources are levelled, by
delaying the activity within the slack/ float available. The rescheduling of
activities results in reduction in peak requirement of resources. Maximum
availability of resources cannot be enforced with the levelling procedure
resulting in over allocation. Since maximum resource constraint are fixed this
makes the schedule infeasible.
41
In case the resource constraints have to be fulfilled extensive reworking by
addition of artificial precedence relationships between different activities is
required. The additional dependencies between activities cater for continuous
utilization of resources from one activity to another in subsequent units are
needed to ensure and allow for resource continuity. This is not done in this
work due to limitations of time. The inability of network diagramming
techniques to handle resource utilization adequately is highlight in scheduling
repetitive projects.
4.6 Scheduling using Line of Balance Technique
The same Bridge was scheduled using Line of balance Technique. In the
bridge the substructure activities are repeated 17 times while superstructure
PSC box Girder is repeated 16 times. For applying Line of Balance technique
substructure and superstructure have to be dealt with separately to obtain
balance in the progress rate. This process of segmentation in superstructure
and substructure is required to avoid resources overlap and confusion in
decision making. Accordingly, two production diagrams and LOB chart have to
be prepared for substructure and superstructure.
4.6.1 LOB chart for sub structure
Activities in the superstructure have been revised from the precedence
diagram Table 4.6 of one unit due to some activities being necessarily
required to move at same pace. The revised activities are shown in Table
4.10. These activities have a time dependency due to the nature of work.
Activities like concreting and shuttering progress at rates equal to each other
since concreting can only be done when shuttering has been completed. As a
result, some of resources required these activities will have forced idle time,
especially concreting and reinforcement (placing of steel). Activities where
progress of one is dependent upon progress of another activity have been
42
replaced by one activity thereby reducing the number of activities.
Dependencies between the activities have been revised keeping in view of
reduction in number of activities. Activities have been grouped such that
duration of combined activity takes care of time required for all the activities
grouped together.
Table 4.10 Activity Table Substructure
S No
Activity Predecessor Duration
Crew
Start Day
End Day
Start Day
End Day
Start Day
End Day
First Seven Wells
Second Seven Wells
Last Three Wells
1 Making of Island and Placing Cutting Edge
15 1 0 105 254 359 541 586
2 Casting of well curb 1 5 1 66 111 329 364 576 591
3 Casting of 1st Lift 2FS+25 days 5 1 104 141 359 394 606 621
4 Casting of 2nd Lift 3FS+25 days 5 1 134 171 389 424 636 651
5 Casting of 3rd Lift 4FS+25 days 5 1 164 201 419 454 666 681
6 Casting of 4th Lift 5FS+25 days 5 1 194 231 449 484 696 711
7 Casting of 5th Lift 6FS+25 days 5 1 226 261 479 514 726 741
8 Casting of 6th Lift 7FS+25 days 5 1 256 291 509 544 756 771
9 Concreting 7th lift 8FS+25 days 5 1 286 321 539 574 786 801
10 Bottom Plugging 9FS+25 days 3 1 334 349 581 602 820 829
11 Sand Filling 10FS+21 days 3 1 358 373 605 626 844 853
12 Top Plugging 11, 1 1 373 380 620 627 851 854
13 Well Cap 10,12FF+3day 11 1 365 442 612 689 843 876
14 Casting of Pier 13 6 1 611 653 653 695 864 882
15 Casting of Pier Cap 14 9 1 620 693 693 756 870 897
Winch and Grab bucket arrangement is fixed for each well to be sunk, hence
well sinking is not considered as an activity, instead a finish to start
relationship between castings of lift with a buffer of 25 days has been used.
Due to limit on number of Winch and Grab bucket arrangement, seven wells
have been planned to be followed by seven wells and three wells. Table 4.10
gives the results of application of LOB technique. Cutting of steel is not
included as an activity since time required for the activity is very small and the
43
activity is not critical. The crew involved for cutting of steel will have a large
period of forced idleness. Production diagram of one unit is of substructure is
shown in Figure 4.2. Total duration of one well is 301 days. The details
obtained are used for Line of Balance calculations.
Objective Diagram for sub structure is shown in Figure 4.3. Total Duration for
Sub Structure Work is 897 days.
4.6.2 LOB diagram for Superstructure
As in substructure, in superstructure PSC box girder too revision is made to
activity details. Activity details in Table 4.11 have been revised from the
precedence Table 4.7 due to certain activity being necessarily required to
move at same pace. The nature of work of requires activity like concreting and
shuttering to progress at rates equal to each other as such these activity have
been replaced by one activity. These activities will have forced idle time for
crews since especially for concreting and reinforcement (placing of steel).
Dependencies of the activity have been revised keeping in view of reduction in
activity. Activities have been grouped such that duration of the activity taking
maximum time is treated as duration of the grouped activity. The nature of
work of requires activity like concreting and shuttering to progress at rates
equal to each other as such these activity have to be replaced by one activity.
These activities will have forced idle time for crews since especially for
concreting and reinforcement (placing of steel). Production diagram for one
unit of superstructure is shown in Figure 4.4. Total duration for one
superstructure span is 99 days. Four crews have been planned for casting of
box girders since four sets of shuttering forms are available.
Objective Diagram of the Superstructure (LOB chart) has been made such that
none of the activities cross each others path and have a balanced rate. Activity
44
Table 4.11 gives details of balance start and finish date for superstructure.
Objective diagram is shown in Figure 4.5.
Total Duration of Superstructure obtained is 478 day.
Table 4.11 Activity table superstructure
S No
Activity Duration Precedence Number Of Crews
Total Time Reqd.
Balance Start date
Balance Finish Date
1 Cutting of Steel 10 days 1 160 0 160
2 Casting of BOX GIRDER 55 days 3FF+4,1FF+10,4FF+38,5FF+38
4 220 36 324
3 Crushing of Chips 20 days 1 320 0 320
4 Cutting of Cables 8 days 1 128 0 128
5 Making of End Block 12 days 1 192 0 192
6 Forms in Place 78 days 2SS 4 312 36 348
7 Casting of Wearing Coat and Crash Barrier
10 days 6,10FF 1 160 188 358
8 Casting of Kerb and handrail
7 days 2 1 112 219 331
9 Site Clearance 1 day 10 1 16 462 478
10 Fixing of Expansion Joints and Drainage Sprouts
20 days 6 1 320 178 476
When the two LOB Diagrams are superimposed it can be seen that site is
required for superstructure on 36thth day from start of superstructure work
since shuttering activities start on 36th day (refer Table 4.11) while other
activities which can be executed else where can start by then. Work of last
three box girders is dependent on completion of last three wells. The
shuttering for last box girder shall finish by 348 days and hence will start on
270th day (refer Figure 4.4) after start of super structure work. To allow
uninterrupted progress of super structure work this can happen only after all
piers of substructure have been completed. This work is complete by 897 th day
(refer Figure 4.3). Superstructure Work can start 270 days before this on 627 th
day to allow for uninterrupted working in superstructure. In case the work is
started earlier there shall be a break in progress of superstructure work.
Total Project Duration is 627 + 476 = 1105 days
45
The duration is more than what obtained through precedence diagramming but
there is no over allocation of resources since production rate of resources is
balanced. Some operational problems are not ruled out since all activities
have not been included in unit plan. Activities having time or space
dependency will result in forced idleness for crew since such activities have
been included as a combined activity.
4.7 Scheduling Using Repetitive Scheduling Method
In RSM one resource is associated with one activity. Continuity in availability
of this resource in similar activity of subsequent unit is ensured. For purpose
implementing RSM a precedence diagram is first required. Each activity in this
precedence diagram is associated with one resource. Accordingly Activities
have been associated with resources. Same is shown in Table 4.12.
Table 4.12 Activities and Associated Resources
Activity Associated ResourceSinking of Well DD winch and Grab Bucket
arrangementConcreting of Lifts Shuttering crew and form work Shuttering of Wells Form work for WellConcreting Concreting EquipmentCrushing Crushing UnitSteel Cutting Steel CuttingPlacing of Steel(including fixing of Bearing and Placing of HT Strands)
Blacksmith and Welder
Shuttering of PSC Box girder Shuttering Crew and Formwork for Box Girder
Stressing JackGrouting Grouting PumpExpansion Joint and Drainage Sprouts Welding
4.7.1 RSM Diagram of Substructure
For drawing RSM diagram a single unit precedence diagram is required. This
diagram for typical substructure unit i.e. abutment/pier is same as that of
46
single unit precedence diagram for LOB. From Table 4.8 we know that seven
Winch and Grab bucket arrangement are available. In order to plan use of
seven available Winch and Grab bucket arrangements for 17 wells it is
obvious that Winch and Grab bucket arrangements have to be used twice or
thrice. Three Winch and Grab Bucket arrangements will be required to be
used thrice while remaining four will have to be used twice. In order to draw
RSM diagram first production lines for first unit are drawn. Production lines for
other units are similar. Activities in subsequent unit are pushed to new position
depending on the resource continuity by shifting the production lines on the
RSM graph.
Table 4.13 Activities in Substructure UnitS No. Activity Duration Predecessor
1 Making of Island Placing of Cutting Edge 16 days
2 Casting of well curb 5 days 1
3 Casting of 1st Lift 5 days 2FS+25 days
4 Casting of 2nd Lift 5 days 3FS+25 days
5 Casting of 3rd Lift 5 days 4FS+25 days
6 Casting of 4th Lift 5 days 5FS+25 days
7 Casting of 5th Lift 5 days 6FS+25 days
8 Casting of 6th Lift 5 days 7FS+25 days
9 Concreting 7th lift 5 days 8FS+25 days
10 Bottom Plugging 3 days 9FS+25 days
11 Sand Filling 3 days 10FS+21 days
12 Top Plugging 1 day 11
13 Well Cap 11 days 10,12FS+3 days
14 Casting of Pier 6 days 1315 Casting of Pier Cap 9 days 14
It is also known that two set of forms for well are available. Due to this it is
possible to divide the work in two parts. Accordingly for the purpose of drawing
RSM diagram the work is converted in to two parts: Three machines to be
used thrice for 9 wells and four machines to be used twice for 8 wells.
Continuos utilization of two shuttering crews is not enforced. Single Unit
Diagram for RSM has been drawn by precedence diagramming and is shown
47
as figure 4-6. RSM Diagram has been drawn accordingly and shown in Figure
4.7. 17th well and pier will be completed by 852nd days.
4.7.2 RSM DIAGRAM of Superstructure
Planning is done for four set of forms being used for four girders shuttering for
each girder is independent and hence not required to be considered for
resource continuity. Two construction joints are permissible after concreting of
soffit and web. Thus casting of soffit, web, and deck can be done in three
phases. For four span activities Concreting, Crushing and Shuttering each are
required for casting of soffit, web and deck. Steel Cutting and Placing is
required for deck and Soffit while auxiliary works are required only prior to
shuttering of deck. This allows for Soffit, Web and Deck to be taken as three
repetitive activities. The activity logic diagram is drawn as Figure 4.8 shows
that treating the three parts of deck separately as a typical repetitive unit is
possible.
4.7.2.1 Activities for Box Girder
Figure 4.8 shows that the casting of PSC box girder can be restructured in
three parts with similar activities and relationship namely Soffit, Web and
Deck. Each PSC box girder can be understood to consist of three similar
repetitive units, each typical unit comprising of shuttering, crushing of chips,
and concreting with other activities not repeating either in deck unit or soffit
units. This means that the superstructure work can be said to comprise of 48
units (each of the 16 box girders replaced by three units). Work for four spans
can be started simultaneously due to availability of four sets of forms (refer
Table 4.8). Scheduling for following four spans will be done when forms are
available for reuse after stressing is completed.
Shuttering activity is associated with two resources. To cater for underlying
assumption that one resource is required for each activity, activity of shuttering
has been replaced in two activities shuttering and formwork in place.
48
Auxiliary Works and Levelling
Shuttering
Placing of steel
Concreting
Crushing of Chips
Shuttering
Concreting
Crushing of Chips
Shuttering
Placing of steel
Concreting
Crushing of Chips
Finishing Activities
SOFFIT WEB DECK
Formwork in place will have a start to start relationship with shuttering and
finish to finish relationship with concreting since forms will be required till
concreting is complete. Shuttering activity for web requires 7 days after casting
of concrete for soffit. In RSM activities in subsequent unit are connected by
resources. In order to ensure shuttering is not commenced till concreting of
soffit is done the activity formwork in place, included with resource being
forms, has start to start relationship with shuttering which has shuttering crew
as its resource. Continuity of shuttering is not enforced. Similar situation occur
in shuttering of deck before concreting of web hence the activity formwork in
place has been introduced in deck also. Shuttering activity will for the duration
of concreting accordingly continuity of shuttering has not been enforced for
planning.
Figure 4.8 Activity Logic Diagram
4.7.2.2 Activities in Soffit
49
The Table 4.14 tabulates the activities for soffit and Figure 4.9 shows the
precedence diagram for them.
Table 4.14 Activities in Soffit
S. No Activity Duration Precedence
1 Levelling of Ground 1 day
2 Shuttering for Soffit 13 days 1
3 Formwork in place for soffit 23 days 2SS,8FF
4 fabrication of End block 12 days
5 Crushing of Chips 6 days
6 Cutting of Steel 7 days
7 Placing of Steel 7 days 6,2,4
8 Concreting of Soffit 3 days 7,5,2
Figure 4.9 Precedence diagram for Soffit
4.7.2.3 Activities in WebThe Table 4.15 tabulates the activities for web and Figure 4.10 shows the
precedence diagram for them.
50
Table 4.15 Activities in WebS. No Activity Duration Precedence1 Shuttering for Web 10 days
2 Formwork in place for Web 13 days 1SS,4FF
3 Crushing of Chips for web 6 days
4 Concreting of Web 3 days 1,3
Figure 4.10 Activities in Web
4.7.2.4 Activities in DeckThe Table 4.16 tabulates the activities for deck and Figure 4.11 shows the
precedence diagram for them.
Table 4.16 Activities in DeckS. No. Activity Duration Precedence
1 Cutting of Steel 3 days
2 Crushing of Chips 8 days
3 Placing of Steel 7 days 1
4 Formwork in place for Deck 17 days 5SS,6FF
5 Shuttering 7 days
6 Concreting 3 days 3,5
7 Kerb and hand rail 4 days 6
8 Stressing 3 days 6FS+21 days
9 Grouting 1 day 8FS+7 days
10 Wearing Coat and Crash Barrier 7 days 8
11 Expansion Joint and Drainage Sprout 20 days 10
51
Figure 4.11 Activities in Deck
RSM graph drawn for the superstructure is shown as Figure 4.12. From the
figure we can see that use of shuttering forms starts from 14 th day and
stressing for first span is complete by 115th day. After stressing is completed
shuttering can be reused, so one set forms can be reused after 102 days. Four
spans are complete in 187 days. For the super structure to complete total 494
days are required which is less than that obtained by LOB technique.
Start of superstructure work is dependent on completion of substructure work.
The substructure work will complete on 852nd day. Start of Shuttering for last of
the girders is planned from 337th day while for the first has been planned 14th
day from the start of shuttering work. From above it is clear that the
superstructure work should be so planned that shuttering of last girder may
start by 852nd day.
Thus total time required for bridge will be 852 – 337 + 494 = 1009 days.
While this duration is more than that of PM but there is no resource
constraint/conflict in the project unlike PM where resource utilization after
levelling is more than available resources.
52
4.8 Results and Discussion
4.8.1 Duration
Project duration obtained with the use of different methodologies is given in
the Table 4.17. It can be seen that duration obtained is least from precedence
diagramming. Time obtained with the use of RSM is greater than PM but less
than LOB.
Table 4.17: Project Duration from different techniquesMethod Total Time
ObtainedResource Constraint Remarks
PM 814.5 Over allocation not resolved
Additional time will be required to resolve over allocation
LOB 1105 No over allocation Maximum Time
RSM 1009 No over allocation All activities could not be considered
4.8.2 Information available
Soffit, Web, and Deck parts of superstructure are not same. Considering
similarity in activities (shuttering, formwork in place, concreting and crushing of
chips being part of each) these are used as repetitive units since in RSM there
is no requirement of all units to be same. Use of this repetitive pattern for
scheduling allows for continuity in use of different activities.
Graphical information is available in form of charts in LOB and RSM
techniques. From the graph the schedule start or finish date for an activity can
be read quickly. Precedence diagram could not be plotted in the same size of
paper to provide any worthwhile information.
On drawing RSM Graph as shown in Figure 4.12, it can be seen that two
shuttering crew can be used for shuttering of four spans using four sets of
forms. This information was not available from PM or LOB. Availability of
shuttering forms for reuse can also be seen from the graph.
53
Use of repetitive patterns as units allows planning for continuous use of
machines. This makes RSM more supportive to mechanization, since
advantages of mechanization can be achieved with continuous repeated
utilization of resource/ machine.
4.8.3 Critical Path
Critical Path is defined by the activities having no float. Complicated
dependencies in precedence diagram lead to large amount of float in various
activities, if all the activities are scheduled at early start. This means that a
large number of activities will be started but complete over a long time
resulting in confusion in monitoring progress. LOB technique does not show
any critical path. RSM has a concept of controlling sequence. The activities on
controlling path are to be monitored to avoid delay in the project. These
activities may or may not be critical as per precedence diagram. This indicates
which activities should be monitored to avoid delay on the project.
54
Chapter 5
Conclusion
The present investigations was undertaken to provide an elaborate study of
Repetitive Scheduling Method applied to a multispan bridge. This study also
entails a study of Precedence Diagramming and Line of Balance methods and
comparison of these methods with Repetitive Scheduling Method. The
following conclusions are drawn from the present study:-
1) Repetitive scheduling takes care of continuous utilization of resources
as compared to precedence diagramming. Repetitive Scheduling can
be implemented to take care of maximum resource availability. This is
not possible for both Line of Balance Technique and Precedence
Diagramming. The maximum availability of resources is often fixed for a
project. The advantage offered by repetitive scheduling method by
considering reuse of resources takes care of maximum availability
constraint in project scheduling makes it a candidate for use in case of
linear and repetitive projects where same resource has to be used
repetitively. The inability of Network techniques to address resource
constraints is especially obvious in repetitive projects. The reason for
this is that initial scheduling for all the activities have been made with
out resource consideration. Resource availability is considered to
readjust the activities.
2) RSM allows only one resource per activity. This is an impractical
assumption since in real life there will be more then one resource
associated with each activity. Precedence diagram of single unit drawn
for PM cannot be used for LOB and RSM. Reworking by taking care of
different constraints and reducing number of activities is required for
generating single unit precedence diagram bar chart. Lesser details are
included in Line of Balance technique. Precedence Diagramming allows
55
for maximum details to be incorporated. Details included in RSM are
less than PM but more than LOB.
3) Critical path allows managers information about where to concentrate.
Line of balance method does not have a critical path. This shortcoming
is adequately dealt by RSM. Controlling path of RSM can have activities
which not critical as per critical path network scheduling methods. This
is due to resource constraints.
4) More mechanization is possible if more work is done by repeated use of
similar unit i.e. repetitive work. Scheduling Technique which considers
necessity of continuous utilization of the resources is required in greater
number of projects as the complexity of project increases., in order to
achieve advantages of mechanisation. RSM has the potential to
address this problem which is not adequately done by network
diagramming.
5) RSM algorithm is complicated then both LOB and CPM however the
advantages in use of RSM make it a practical method which can be
utilized extensively. More information can be obtained from the RSM
graph, as compared to the network diagram or LOB chart.
56
Bibliography
1. Adeli, H, and A Karim. “Scheduling/Cost Optimization and Neural Dynamics Model for const optimization.” Journal of Const Engg and Mgmt 122, no. 3 (September 1996).
2. Adeli, Hojjat, and Asim Karim. Construction Scheduling,Cost Optimization and Management. London: Spon Press, 2001.
3. Ahuja, Hira N. Project Management: Techniques in Planning and Controlling Construction Project. New York: John Wiley and Sons, 1984.
4. Alexandros, Kallantzis, Soldatos John, and Lambropoulos Sergios. “Linear versus Network Scheduling: A Critical Path Comparison.” Journal of Construction Engineering and Management (American Society of Civil Enigneering) 133, no. 7 (2007).
5. Arditi, Davi, Onur B Tokdemir, and Kangshuk Suh. “Challenges in Line of Balance Scheduling.” Journal of constrution Engineering and Management (American Socity of Civil Engineering) 128, no. 6 (2002).
6. Bennet, F Lawrence. The Management of Constrcution A Project Life Cycle Approach. Oxford: Butterwoth Heinmann, 2003.
7. Burke, Rory. Project Management Planning and Control Techniques. New York: John Wiley and Sons, 2001.
8. Chitkara, K K. Construction Project Management. New Delhi: Tata McGraw Hill, 1998.
9. Goldratt, Eliyahu M. Critical Chain. Great Barrington: North River Press, 1997.
10. Gray, Cliffrod, and Erik Larson. Project Management Mangerial Process. New York: McGraw Hill International, 2001.
57
11. Harmelink, David J, and Yamin. “Comparison of LSM and CPM.” Journal of Construction Engineering and Management (American Society of Civil Engineer), 2001.
12. Harmelink, David, and James E Rowings. “Linear Scheduling Model: Development of Controlling actitivty path.” Journal of Constrcution Engineering and Management (American Society of Civil Engineers) 124, no. 4 (1998): 263-268.
13. Harris, R B, and Photis G Ioannou. “Scheduling Project with Reptitive Activities.” 1998, 269-278.
14. Hendrickson, Chris. Project Management for Construction. Prentice Hall, 1989.
15. Henrich, G, and Lauri J Koskela. “Evolution of Production Mangement Method in Construction.” Published Conference Proceeding :Construction in the XXI Century: local and global challenges ARTEC . SEEK publication, 2006.
16. Ipsilandis, Pandelis G. “Multiobjective optimization in Linear Repetitive Project Scheduling.” Operation Research: An International Journal 6, no. 3 (2006): 255-269.
17. IRC SP:14. Use of CPM in Highway. New Delhi: Indian Roads Congress, 1979.
18. Kerzner, Harold. A Systems Approach to Approach to Planning, Scheduling and Controlling. John Wiley and Sons, 2001.
19. Kimmons, R L. Project Management BAsics. Marcel Dekker, 1990.
20. Leach, Lawrence P. Critical Chain Project Management. Boston: Artech House, 2000.
21. Lester, Albert. Project Planning and Control. Elsevier, 2003.
22. Lutz, James D, and Adib Hijazi. “Planning Repetitive Project: Current Practice.” Construction Mangement and Economics 11 (1993): 99-110.
23. Mahdi, Ibrahim M. “A new LSM Approach for planning repetitive housing projects.” International Journal of Project Management 22, no. 4 (2003).
24. Mazrouk, Mohammed, Hisham Zein, and Moheeb AlSaid. “BRIDGE_ SIM: FRAMEWORK FOR PLANNING AND OPTIMIZING BRIDGEDECK CONSTRUCTION
58
USING COMPUTER SIMULATION.” 2006.
25. Meredith, Jack R, and Samuel J Mantel Jr. Project Management A Managerial Approach. New Delhi: John Wiley and Sons, 2003.
26. Moder, Philips, and Davis. Project Mangement with CPM PERT and Precedence Diagramming. Reinhold, 1964.
27. Ostenfeld, Klaus H, Dietrich L Hommel, Dan Olsen, and Lars Hauge. “Planning for Major Fixed Links.” In Bridge Engineering Handbook, edited by Wah Fai-Chen and Lian Duan. Boca Raton: CRC Press, 2000.
28. Sahai, Devendra Kumar. “Scheduling of Project with Repetitive Type of Work.” ME Thesis, Department of Civil Engineering, Rajiv Gandhi Prodhyogiki Vishwavidhyalaya, 2002.
29. Steyn, H. “Projet Managment Applications of the Theory of Constraints beyond Critical Chain Scheduling.” International Journal of Project Management (Pergamon) 20 (2002).
30. Taha, Hamdy A. Operation Research. New Delhi: Tata McGraw HIll, 2005.
31. Yang, I-Tung, and Photis G Ioannou. “Resource Driven Scheduling For Repetitive Construction Project: A Pull System Approach.” International Group for Lean Construction. Singapore: National Singapore University , 2001.
32. Yang, I-Tung, and Photis G Ioannou. “Scheduling Systems with focus on Practical Concerns in Repetitive Project.” Construction Mangement and Economics, July 2004: 619-630.
59