View
215
Download
1
Tags:
Embed Size (px)
Citation preview
1
Universities Space Research Association
SOFIA Program Options
SSSC18 February 2010
Mina CappuccioSOFIA Science Project Manager
NASA Ames Research Center
2
Universities Space Research Association
SOFIA Program Options
• Options are things that can be done to get science as early as possible.– During segment 2: Short Science and Basic Science using an
Early Science platform configuration– During segment 3: FOC configuration for commissioning first
generation instruments and performing shared purpose science
• Options get discussed among all SOFIA team members, get vetted for viability, and approved to implement through the Program Management Board (PMB).
3
Universities Space Research Association
Option for Segment 2
• Move TA Characterization/First Light Flight Earlier In Schedule– To achieve science earlier and understand TA capabilities sooner.– Move TA Characterization/First Light Flight after Open Door with TA @ 23 deg
(and TA misalignment flight) but before FORCAST Line Ops #1– No configuration change prior to flight
• Open Door Configuration, which includes MCCS Open Door Final Build
• TA operational (coarse and fine drive)
• URD open
• CECS pre-dry
• Science Instrument on board (FORCAST)
• Predefined flight plan
• Mission Operation crew
• SI crew
– Follow flight with data analysis in parallel with Line Ops #1 with EB4. This also allows more time to get EB4 working.
• Plan to get EB5 for FORCAST Line Ops #1
• Addresses issues and additional capabilities needed
– This requires clearing the envelope right after flights for staff to be on board during the TA Characterization/First Light Flight, instead of after data analysis period
4
Universities Space Research Association
Segment 2 Program Critical Work Flow
Reflects Option 1 PMB decision for TA Characterization / First Light ahead of FORCAST Line Ops #1. IMS update based on Platform re-plan drop. DFRC management reviewing for other adjustments.
TA Characterization
2010TA Misalignment
(daytime)
Science Flight Platform Flight TA Flight Ground Testing Data Analysis Contingency Flight
Created 2/2/2010
ISF
TA Characterization/First Light attempt
5
Universities Space Research Association
Option for Segment 3
• Program working mitigation approaches for longer-term schedule– Established a separate Segment 3 planning and schedule development team– Evaluating several shorter downtimes vs. 1 extended downtime in Segment 3
• Science Project provided inputs at meeting with Program and Platform Project on instrument commissioning requirements to help determine capabilities needed at start of segment 3 flights
6
Universities Space Research Association
7. Cavity Cooling? ≈ 2 months? B 8. Coordinate Transform Updates*9. CDDS upgrades? = 2 months**10. AIU wiring start?11. DAS wiring start?12. MADS upgrades (Alarms/Alerts)
1. Avionics Upgrade ≈ 3 months A2. RVSM 3-4 weeks? A3. TA Upgrades ≈ 2 months A?4. WVM ≈ 2 weeks B5. Insulation ≈ 2 months off a/c C6. Mirror Coating ≈ 2-3 months C
1. Cavity Cooling? (finish?)2. AIU (MCCS) ≈ 2 months A3. FMI (MCCS) ≈ 1 month A4. DAS (MCCS) ≈ 3 months A5. Workstations (MCCS) A
Conceptual Segment 3Downtime Restructure
2011
2012
2012
2013
2013
2014
LOC
FOC
Observing Flights Instrument Commissioning Aircraft maintenance/Observatory upgrade Platform flights
1. Coordinate Transform Updates2. EPO3. CDDS and CECS upgrades
•Get Science data to the community earlier (SSPC recommendation)•Maintains Program momentum•Provides addition risk margin for downtimes
7
Universities Space Research Association
Summary
• Science Project working very closely with Program and Platform Project to come up with options to allow science to happen as early as possible
• Ames Research Center providing technical help to Platform Project to execute installations and testing on Platform