Upload
roger-gregory
View
221
Download
0
Tags:
Embed Size (px)
Citation preview
1
Weighing Net Present Value and Other Capital Budgeting Criteria
Chapter 13Fin 325, Section 04 -
Spring 2010Washington State
University
2
IntroductionIn previous chapters we learned how
toCalculate the firm’s cost of capitalEstimate a project’s cash flows
Now, we need to finish the analysis of the project to determine whether the firm should proceed with a potential project.
3
Capital Budgeting TechniquesMost commonly-used methods to evaluate
projects:Net Present Value (NPV)Payback (PB)Discounted Payback (DPB)Internal Rate of Return (IRR)Modified Internal Rate of Return (MIRR)Profitability Index (PI)
NPV is generally the preferred technique for most project evaluations
There are situations where you may want to use one of the other techniques in conjunction with NPV
4
Net Present ValueNPV represents the “purest” of the
capital budgeting rulesIt measures the amount of value created by
the projectNPV is completely consistent with the
overall goal of the firm: to maximize firm value
5
NPV is the sum of the present value of every project cash flow (including the initial investment)
NN
i
CF
i
CF
i
CFNPV
)1(...
)1()1( 11
00
N
nn
n
i
CF
0 )1(
6
NPV BenchmarkNPV includes all of the project’s cash
flows, both inflows and outflowsSince it involves finding the present values
of every cash flow using the appropriate cost of capital as the discount rate, anything greater than zero represents the amount of value added above and beyond the required returnAccept project if NPV > 0Reject project if NPV < 0
7
ExampleA project has a cost of $25,000, and
annual cash flows as shown. Calculate the NPV of the project if the discount rate is 12 percent
0 1 2 3 4
8,500(25,000)
i=12%
12,000 13,500 15,000
8
Financial Calculator solution:CF0 = (25,000)
CF1 = 8,500
CF2 = 12,000
CF3 = 13,500
CF4 = 15,000
I = 12 percentNPV = 11,297.42
9
Interpretation:Do we like this project?
Yes – it has a positive NPVIf the market agrees with our analysis, the
value of our firm will increase by $11,297 due to this project
When will the value-added occur? When the project is complete?NO – it will occur immediately upon the
announcement that we are taking the project
10
11
NPV Strengths and WeaknessesStrengths
NPV not only provides a go/no-go decision, but it also quantifies the dollar amount of the value added
NPV is not a ratioIt works equally well for independent projects and
for choosing between mutually-exclusive projects Accept the project with the highest positive NPV
WeaknessMisinterpretation
Comparing NPV to the cost of the project is wrong! Not understanding that the cost is already incorporated
into the NPV
12
PaybackAnswers the question: How long will it
take us to recoup our costs?Has intuitive appealRemains popular because it is easy to
computeBuilt-in assumptions:
Cash flows are normal Assumes cash flows occur smoothly throughout
the year
13
ExampleRefer to the problem we worked earlier.
Compute the payback.
0 1 2 3 4
8,500(25,000)
i=12%
12,000 13,500 15,000
(25,000)Cumulative (16,500) (4,500)
Payback will occur during the 3rd year
Payback = 2 + 4,500/13,500 = 2.33 years
14
Payback BenchmarkFirms set some maximum allowable
paybackOften set arbitrarily – one of payback’s
greatest weaknesses
Accept project if calculated payback < Maximum allowable payback
Reject project if calculated payback > Maximum allowable payback
15
Discounted PaybackOne of the major problems with
payback is that it ignores the time value of moneyIt treats all cash flows equally regardless of
when they occur
Discounted payback fixes this particular problem
We convert the raw cash flows to their present values, and then calculate payback like before using these discounted cash flows
16
Example
0 1 2 3 4
8,500(25,000)
i=12%
12,000 13,500 15,000
(25,000) 7,589 9,566
Cumulative
CF present values 9,609 9,533
(25,000) (17,411) (7,845)
Discounted Payback will occur during the 3rd year
Discounted Payback = 2 + 7,845/9,609 = 2.82 years
17
Discounted Payback benchmarkLike payback, management will likely set
an arbitrary benchmarkNotice that for normal projects DPB will be
larger than PBThe cash flows that are “chipping away”
at the initial cost are the smaller discounted cash flows, so it takes longer
Hopefully, the arbitrary benchmark would at least take that effect into account
18
PB and DPB Strengths and WeaknessesStrengths:
Easy to calculateIntuitive
Weaknesses:Both methods have severe weaknesses that
make them unsuitable to be the primary method used to select projects
1)PB ignores the time value of money2)Both methods rely on arbitrary accept/reject
benchmarks3)Both methods ignore cash flows that occur after
the payback period. This is perhaps the most serious flaw of all
19
Internal Rate of ReturnIRR is the most popular technique to
analyze projectsOften referred to as “the return on the
project”
IRR is generally consistent with Net Present ValueProblems occur if cash flows are not normalProblems can occur when choosing among
mutually exclusive projects
20
IRR is so closely related to NPV that it is actually defined in terms of NPV
IRR is the discount rate that results in a zero NPV
N
nnIRR
CF
0
0
)1(0
21
Internal Rate of Return benchmarkOnce we calculate IRR, we must compare it
to the cost of capital (investors’ required return) to see if the project is acceptable
We only want to invest in projects where the rate we expect to get (IRR) exceeds the rate investors require (i)
22
ExampleRefer to our previous problem. Calculate
the IRR of the project.
0 1 2 3 4
8,500(25,000)
i=12%
12,000 13,500 15,000
23
Financial Calculator solution:CF0 = (25,000)
CF1 = 8,500
CF2 = 12,000
CF3 = 13,500
CF4 = 15,000
IRR = ? = 30.08%
Do we like this project?
Yes – the IRR is greater than the required return
24
Problems with IRRIRR will be consistent with NPV as long
as:The project has normal cash flowsProjects are independent
NPV profilesThe NPV profile is a graph of NPV versus
different discount ratesIt can help us determine if we may
encounter a problem with IRR
25
For normal cash flows, the NPV profile slopes downward
IRR can be found where the profile crosses the x-axis (i.e. where NPV = 0, the definition of IRR)
26
For non-normal cash flows there will be multiple IRRs for the same projectIRRs represent the solution to a
mathematical series. These solutions are called ‘roots’, and a series will have as many roots as there are sign changes. This is Descartes’ Rule of Signs, discovered in 1637.
For us, this means that there will be as many IRRs as there are sign changes in the cash flows.
27
Examples:In our normal project, we have one IRR
because we have one sign change- + + + +
What if a project involves a cleanup at the end? We might have two sign changes (and two IRRs):- + + + -
What if a project has to shut down in the 3rd year for maintenance, and then starts up again? We might have three sign changes:- + + - + +
28
Here is a sample NPV profile for a project with non-normal cash flows. Notice that the line crosses the x-axis twice:
Fortunately, we can fix the problem of multiple IRRs using a technique called Modified Internal Rate of Return (MIRR)
29
Calculating MIRRCalculating MIRR is a three-step process:
Step 1: Calculate the PV of the cash outflows using the required rate of return.
Step 2: Calculate the FV of the cash inflows at the last year of the project’s time line using the required rate of return.
Step 3: Calculate the MIRR, which is the discount rate that equates the PV of the cash outflows with the PV of the terminal value, ie, that makes PVoutflows = PVinflows
30
ExampleCalculate the MIRR of the following
project:
i = 9%0 1 2 3 4 5
-10,000 4,000 6,000 -5,000 12,000 15,000
31
Step 1: PV of outflows = -13,861Step 2: FV of inflows = 41,497Step 3: Calculate MIRR
MIRR = 24.52%Exceeds the required return of 9%, so
accept project
INPUT 5 -13,861 0N I/YR PV PMT FV
OUTPUT
41,497
24.52
32
Profitability IndexBased on NPV
Measures “bang per buck invested”PI benchmark:
Accept project if PI > 0Reject project if PI < 0
0CF
NPVPI
33
ExampleCalculate the PI of our example
Recall that the NPV = $11,297PI = 11,297 / 25,000 = 45.19%PI indicates that we should accept the
project
0 1 2 3 4
8,500(25,000)
i=12%
12,000 13,500 15,000