Upload
claude-holmes
View
218
Download
4
Embed Size (px)
Citation preview
11
WMS Report To TACWMS Report To TAC
September 2008September 2008
22
In BriefIn Brief
Four Working Group ReportsFour Working Group Reports One Task Force ReportOne Task Force Report Three Staff reportsThree Staff reports
33
Working Group ReportsWorking Group ReportsDSWGDSWG
Price Responsive load and RUCPrice Responsive load and RUC Energy Efficiency Project #27647Energy Efficiency Project #27647 NPRR with Zero Floor on RRSNPRR with Zero Floor on RRS
44
Working Group ReportsWorking Group ReportsQSEWGQSEWG
NERC audit of ERCOT scheduled NERC audit of ERCOT scheduled for September 8-11, 2008for September 8-11, 2008
NERC EOP and its Sub-NERC EOP and its Sub-requirementsrequirements
WGRPP Forecast issuesWGRPP Forecast issues WGR only QSE Performance WGR only QSE Performance
MetricsMetrics
55
Working Group ReportsWorking Group ReportsVCWGVCWG
VC Manual and white paperVC Manual and white paper Emissions creditsEmissions credits Implementation PlanImplementation Plan NPRRs 144 (5 RUC) and NPRRs 144 (5 RUC) and
145(PPAs)145(PPAs) FIP analysisFIP analysis
66
ERCOT Staff ReportsERCOT Staff Reports
Market Credit Risk Standard – Market Credit Risk Standard – UpdateUpdate
Procedures for Identifying Procedures for Identifying Resource NodesResource Nodes
OOMC/OOME Deployments and OOMC/OOME Deployments and CostsCosts
77
CCR Credit Policy TFCCR Credit Policy TF
NPRR140 Revision to CRR NPRR140 Revision to CRR Obligation Margin Adder Obligation Margin Adder
Other Market ConcernsOther Market Concerns
88
Working Group ReportsWorking Group ReportsCMWGCMWG
SP Cap recommendation statusSP Cap recommendation status Outage EvaluationOutage Evaluation Competitive Constraint TestCompetitive Constraint Test CSC discussion and actionCSC discussion and action
99
SP Cap Progress & SP Cap Progress & RecommendationRecommendation
CMWG Recommendation: Proceed to CMWG Recommendation: Proceed to Implement Existing System CapabilitiesImplement Existing System Capabilities
3/08 Directed by WMS to look at SP
issue
4/08 ERCOT proposal, SP
cap by kV level
5-6/08 Alternate proposal for penalties based on degree of constraint violation
5-6/08 Comments on
ERCOT Proposal &
Discussion of Alternate Proposal
7/08 CMWG: Implement
Existing Sys Capabilities
7/08 Clarification
on MMS Capabilities
8/27 CMWG: Discuss SP Cap Number
1010
Working Group ReportsWorking Group ReportsCMWGCMWG
SP Cap recommendation statusSP Cap recommendation status Outage EvaluationOutage Evaluation Competitive Constraint TestCompetitive Constraint Test CSC discussion and actionCSC discussion and action
1111
2009 CSCs2009 CSCs What’s not changing?What’s not changing?
General the geographic regions are General the geographic regions are stable: West, North, South, Houstonstable: West, North, South, Houston
What is changing?What is changing? CSC definitionsCSC definitions
For N_H, Singleton is not For N_H, Singleton is not scheduled to be in-service until scheduled to be in-service until May 2009May 2009
1212
2009 CSCs2009 CSCsCSCCSC Scenario 3bScenario 3b Scenario 3gScenario 3g Scenario 3hScenario 3h
N_H*N_H*Singleton-Obrien/ Singleton-Obrien/ Singleton-TH Wharton Singleton-TH Wharton 345-kV double circuit345-kV double circuit
Singleton-Obrien/ Singleton-Obrien/ Singleton-TH Wharton Singleton-TH Wharton 345-kV double circuit345-kV double circuit
Singleton-Obrien/ Singleton-Obrien/ Singleton-TH Wharton Singleton-TH Wharton 345-kV double circuit345-kV double circuit
N_S N_S & & S_NS_N
Lake Creek-Temple/ Lake Creek-Temple/ Tradinghouse-Temple Tradinghouse-Temple Pecan Creek 345-kV Pecan Creek 345-kV double circuitdouble circuit
Lake Creek-Temple/ Lake Creek-Temple/ Tradinghouse-Temple Tradinghouse-Temple Pecan Creek 345-kV Pecan Creek 345-kV double circuitdouble circuit
Lake Creek-Temple/ Lake Creek-Temple/ Tradinghouse-Temple Tradinghouse-Temple Pecan Creek 345-kV Pecan Creek 345-kV double circuitdouble circuit
W_N W_N & & N_WN_W
Graham-Benbrook/ Graham-Benbrook/ Graham-Parker 345-kV Graham-Parker 345-kV double circuitdouble circuit
Graham-Long Creek/ Graham-Long Creek/ Graham-Cook Field Graham-Cook Field Road 345-kV double Road 345-kV double circuitcircuit
Sweetwater-Long Sweetwater-Long Creek/ Abilene Mulberry Creek/ Abilene Mulberry Creek-Long Creek 345-Creek-Long Creek 345-kV double circuitkV double circuit
1313
Two kinds of constraintsTwo kinds of constraints
It is generally understood that the western It is generally understood that the western most CSC (3h) will probably result in easier most CSC (3h) will probably result in easier operations for thermal constraints.operations for thermal constraints.
It is generally understood that the eastern It is generally understood that the eastern most CSC (3b) will probably result in easier most CSC (3b) will probably result in easier operations for stability constraints.operations for stability constraints.
ERCOT can reliably manage either option, but ERCOT can reliably manage either option, but has indicated they are less comfortable with has indicated they are less comfortable with the amount of generation that option 3h the amount of generation that option 3h moves from West to North.moves from West to North.
1414
Benefits of Scenario 3bBenefits of Scenario 3b
Provides Market Stability:Provides Market Stability:1.1. CSC for W-N and N-W has been 345kV double CSC for W-N and N-W has been 345kV double
circuit Graham-Parker/Graham-Benbrook circuit Graham-Parker/Graham-Benbrook since inception of ERCOT Zonal Marketsince inception of ERCOT Zonal Market
2.2. Changing the CSC will re-cluster 785MW Changing the CSC will re-cluster 785MW (20% of total) West zone load into North (20% of total) West zone load into North zone, zone, BUTBUT this load will move back to the this load will move back to the West upon Nodal Market implementation per West upon Nodal Market implementation per nodal protocols 4.1-4.2.nodal protocols 4.1-4.2.
1515
Benefits of Scenario 3bBenefits of Scenario 3b
Ensures Robust Competitive Solution Ensures Robust Competitive Solution for Resolution of N-W Congestionfor Resolution of N-W Congestion
1.1. Scenario 3h moves 33% of scheduled (non-Scenario 3h moves 33% of scheduled (non-
wind) resources from the West to the North:wind) resources from the West to the North:A.A. Oklaunion Oklaunion 649 MW649 MWB.B. GrahamGraham 611 MW611 MWC.C. North DC TieNorth DC Tie 220 MW220 MWD.D. Wichita FallsWichita Falls 77 MW77 MWE.E. Morris SheppardMorris Sheppard 24 MW24 MW
2.2. Of the remaining scheduled West zone Of the remaining scheduled West zone resources, Luminant will own 54% of the resources, Luminant will own 54% of the capacity.capacity.
1616
Benefits of Scenario 3hBenefits of Scenario 3h
W-N transmission topology for 2009 W-N transmission topology for 2009 was reconfigured on June 3, 2008 with was reconfigured on June 3, 2008 with the completion of the Long Creek the completion of the Long Creek substation, significantly changing substation, significantly changing flows on both the east side & west flows on both the east side & west side of Long Creek.side of Long Creek.
As a result of this topology change, As a result of this topology change, thermal congestion since June 3 has thermal congestion since June 3 has been primarily on Abilene Mulberry been primarily on Abilene Mulberry Creek – Long Creek. Creek – Long Creek.
1717
On June 3 W-N transmission topology significantly On June 3 W-N transmission topology significantly changeschanges
Configuration before June 3
Configuration after June 3
Note increase after June 3
Note flows equalize after June 3
Long Creek Substation was looped into Long Creek Substation was looped into Sweetwater Cogen - Graham 345 kV line on Sweetwater Cogen - Graham 345 kV line on June 3, 2008. This change 1) equalized flows June 3, 2008. This change 1) equalized flows on Graham – Long Creek circuits #1 and #2, on Graham – Long Creek circuits #1 and #2, 2) increased the flow on the Mulberry Creek 2) increased the flow on the Mulberry Creek – Long Creek, and 3) exacerbated the – Long Creek, and 3) exacerbated the congestion on the Mulberry Creek – Long congestion on the Mulberry Creek – Long CreekCreek..
1818
Historical cost is highest along Mulberry Creek – Long Historical cost is highest along Mulberry Creek – Long CreekCreek
West To North Congestion ChargesJun 3 - Aug 10, 2008
Occurrences - Days
SCKT Fisher Road – Oklaunion & Bowman
345 kV
DCKT Graham – Benbrook & Parker 345
kV
DCKT Graham – Long Creek 1&2 345 kV
Dynamic Stability
Abilene Mulberry Creek – Long Creek 345 kV - 3h 3h - 13 days
Graham –Murray 138 kV line - 3g 3g - 1 day
Willow Creek - Parker 345 kV line - 3b 3b - 6 days
Dynamic Stability 3 days
Total Occurrences 23 days
Congestion Cost - $
SCKT Fisher Road – Oklaunion & Bowman
345 kV
DCKT Graham – Benbrook & Parker 345
kV
DCKT Graham – Long Creek 1&2 345 kV
Dynamic Stability
Abilene Mulberry Creek – Long Creek 345 kV - 3h $12,278,903
Graham –Murray 138 kV line - 3g $104,044
Willow Creek - Parker 345 kV line - 3b $2,290,343
Dynamic Stability $1,577,897
Total Charges $16,251,187
OV
ER
LO
AD
OV
ER
LO
AD
OUTAGE
OUTAGE
Source: Congestion charges from ERCOT website
Proposal 3h accounts for 75% of all congestion since June 3.
1919
WMS Report To TACWMS Report To TAC