Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
10 - 1
10. Economic and Financial Analysis
10.1. Construction Cost
The construction cost for the Sihanoukville Combined Cycle Power Plant is estimated
to be 100.2 Million for Stage 1 and 74.6 Million for Stage 2 as shown in Table 10.1-1
and cost breakdown are shown in Table 10.1-2 and Table 10.1-3.
Table 10.1-1 Summary of Construction Cost
(Million US$)
Stage F/C Portion L/C Portion Total
Stage 1 83.6 16.6 100.2
Stage 2 65.4 9.3 74.6
Total 149.0 25.9 174.8
Note: The estimate construction cost is as of 2001 price level and the associated T/L is exclusive.The total is not matched due to the round off.
The construction costs were estimated on the following basis:
Cost estimates for equipment and materials, which are deemed to be fabricated and im-
ported from foreign countries, are based on international competitive market prices
with referring to actual contract or bidding prices for a similar combined cycle power
plant. Basically most of the mechanical and electrical equipment are assumed to be im-
ported.
Cost of materials, which are available in Cambodia, are estimated on the basis of the
data collected during the study.
The labor costs for erection works for equipment are estimated on the basis of reference
costs in neighboring countries, but the labor costs for civil and architectural works are
based on the cost in actual projects in Cambodia.
Construction cost includes the costs for access road, oil fuel pipeline from Sokimex Oil
10 - 2
Terminal to the plant, improvement of regional road and bridges from Sihanoukville
port to the plant and temporary relocation works for road and railroad nearby the plant
site.
Land acquisition cost
Land acquisition cost is estimated based on the unit land cost which was given by the
Sihanoukville Municipality, i.e. 2.3 US$ per square meter. The required area is esti-
mated 32 ha.
Resettlement fee
At present only four households exist in the plant site area. However, for estimates of
resettlement fee, the number of households are estimated 10, and unit resettlement fee
is estimated 3,000 US$ with referring to the cost used in the transmission project in
Cambodia.
Cost of mine survey
The cost of mine survey is estimated by using the unit cost which was given by CMAC,
i.e. 0.6 $/m2. This unit cost is that for an actual mine sweeping work (named “Level 3”)
which is carried out by CMAC in response to the governmental institution’s request.
F/C L/C Total F/C L/C Total
Mechanical 44,290 3,330 47,620 41,100 3,090 44,190
Electrical 19,250 1,230 20,480 14,610 930 15,540
Civil Works 5,450 6,650 12,100 2,520 3,090 5,610
Building & Structure 3,400 1,830 5,230 1,570 850 2,420
Spare Parts & Others 6,720 0 6,720 3,470 0 3,470
Subtotal 79,110 13,040 92,150 63,270 7,960 71,230
Training 100 0 100 50 0 50
Owner's Administration Fee (3%, 2%) 0 2,600 2,600 0 1,300 1,300
Engineering Consultant Fee (5%, 3%) 4,390 0 4,390 2,040 0 2,040
Land Acquisition 0 740 740 0 0 0
Resettlement & Compensation 0 30 30 0 0 0
Mine Survey 0 190 190 0 0 0
Subtotal 4,490 3,560 8,050 2,090 1,300 3,390
Grand Total 83,600 16,600 100,200 65,360 9,260 74,620
Note : Mechanical, Electrical, Civil Works, Building & Structure, and Spare Parts & Others include Physical Contingency of 5 %.
F/C L/C TotalAssociated Transmission Line(Site ~ Kampot) 8,640 2,160 10,800
Table 10.1-2 Estimate of Construction Cost (as of 2001 )
Stage-1 Stage-2(unit :1,000 US$)
10 - 3
Table 10.1-3 Breakdown of Construction CostUnit: 1000 US$
Item Quantity Cost Quantity Cost TotalMechanical Gas turbine and associated equipment 3 22000 3 22000 44000
Steam turbine and associated equipment 1 6500 1 6500 13000HRSG and associated equipment 3 6600 3 6600 13200Fuel gas supply system L.S. 570 L.S. 570 1140Fuel oil storage and supply system L.S. 580 L.S. 580 1160Cooling water system L.S. 1200 L.S. 1200 2400Plant pipings L.S. 1800 L.S. 1600 3400Water treatment system L.S. 840 L.S. 420 1260Wastewater treatment & incineration L.S. 400 L.S. 50 450Fire prevention and protection system L.S. 1200 L.S. 500 1700Emergency diesel generator 1 130 - 0 130Crane, mobile equipment incl. fire engine L.S. 1700 L.S. 500 2200Other mechanical equipment L.S. 830 L.S. 570 1400Stacks 1 1000 1 1000 2000
Subtotal 45350 42090 87440Electrical Control and instrumentation L.S. 7700 L.S. 6500 14200
Plant electrical equipment L.S. 8900 L.S. 7600 16500In-plant substation L.S. 2900 L.S. 700 3600
Subtotal 19500 14800 34300Civil and Structural Land formation L.S. 430 L.S. 0 430Works River diversion L.S. 420 L.S. 0 420
Equipment foundation and Others L.S. 2160 L.S. 1640 3800Water storage tank proper L.S. 500 L.S. 500 1000Wastewater treatment facilities L.S. 300 L.S. 100 400In-plant road L.S. 910 L.S. 0 910Drainage system L.S. 1580 L.S. 0 1580Cooling water pipe & system L.S. 3100 L.S. 3100 6200Access road L.S. 110 L.S. 0 110Improvement of regional road & bridge L.S. 310 L.S. 0 310Temporary works (relocation of road/railroad) L.S. 1700 L.S. 0 1700Power house 1 3600 Extension 2300 5900Administration building 1 900 - 0 900Other miscellaneous buildings L.S. 450 - 0 450Security fencing, plantation, etc. L.S. 30 - 0 30
Subtotal 16500 7640 24140Spare Parts Spare parts 4000 3000 7000and Others Special tools and workshop machines 1500 0 1500
Laboratory equipment 600 0 600Consumables 300 300 600Subtotal 6400 3300 9700Grand Total of Construction Works 87750 67830 155580
Miscellaneous Training L.S. 100 L.S. 50 150Expense Owner's administration fee 3 % 2600 2 % 1300 3900
Engineering consultant fee 5 % 4388 3 % 2035 6423Fhysical contingency (5%) 5 % 4388 5 % 3392 7780Land acquisition cost (2.3 $/m2) 32 ha 736 0 0 736Resettlement fee (3,000 $/one) 10 houses 30 0 0 30Mine survey cost (0.6 $/m2) 32 ha 192 0 0 192
Subtotal 12434 6777 19211
100,184 74,607 174,791
Stage 1 Stage 2
Total Project Cost
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������
������������������������������������������������������
������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������
������������������������������������������������������
������������������������������������������������
������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
��������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
��������������������������������������������������������
��������������������������������������������������������
����������������������������
������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������
������������������������������������������������������������������������������������
��������������������������������������������������������
10 - 4
10 - 5
10.2. Economic Analysis
10.2.1. Objective
Economic analysis is carried out to verify the economic validity of the implementa-
tion of project from the viewpoint of the whole Cambodian economy.
10.2.2. Methodology of Economic Analysis
The Sihanoukville Combined Cycle Power Plant is proposed currently to meet the
future power demand. If the project is not implemented, the implementation of an al-
ternative power plant, of which installed capacity is equivalent to the project, shall be
required to attain the same objective.
Therefore, the economic validity of the project can be measured in a way of cost
comparison between the project and the alternative power plant.
Concerning the cost comparison, “With - Without” method is commonly used in the
economic analysis for the power sector. “With” means the proposed project (Siha-
noukville Combined Cycle Power Plant) and “Without” means the alternative project
(such as diesel power plant etc.).
10.2.3. Judgment of Economic Validity
The economic validity of the project is verified by using the following economic pa-
rameters:
(1) Economic Internal Rate of Return (EIRR)
The EIRR can be defined as the rate of discount, which equalizes the discounted
gross benefits with the discounted gross costs. It can be explained mathematically
as follows:
∑∑== +
=+
n
kk
kn
kk
k
iC
iB
11 )1()1(
Where; Bk : benefit for year k
10 - 6
Ck : cost for year k
i : discount rate
An EIRR of 10% ~ 12 % is set as the hurdle rate normally by the World Bank
and Asian Development Bank and applied to a power sector in the developing
countries. Therefore, if EIRR derived from the above calculation exceed the hur-
dle rate, the economic validity of the project is verified. Otherwise, additional
support data, such as social impact, which cannot be counted in the monetary
term, will be required to implement the project.
(2) Net Present Value (NPV)
The NPV is the most straightforward discounted cash flow measure of the project
worth. It is simply the present value of the cash flow stream, i.e. the net present
value of benefit less the net present value of cost. NPV can be expressed by the
following formula:
∑= +
−=
n
kkkk
rCBNPV
1 )1(
Where; r : hurdle rate
The project having positive NPV is acceptable economically.
(3) Benefit – Cost Ratio (B/C)
The benefit-cost ratio is computed on the basis of discounting the benefit and cost
streams to their present values. It can be expressed as follows:
∑
∑
=
=
+
+== n
kk
n
kk
kCk
rBk
NPVNPV
CB
1
1
)1(
)1(Cost of
Benefit of
If B/C ratio exceeds 1.0, the project is acceptable economically (1.2 is often used
actually).
10 - 7
10.2.4. General conditions for Economic Analysis
The following conditions are applied to the economic analysis.
(1) The commencement of commercial operation for Stage 1 and Stage 2 is assumed
to be September 1, 2006 and September 1, 2008 respectively based on the opti-
mum power development program in Section 2.2. and expected project imple-
mentation schedule in Chapter 9.
(2) Annual capacity factors are set as shown in Table 10.2-1 based on the results of
optimum power development program in Section 2.2.
Table 10.2-1 Capacity Factors of Sihanoukville C.C. Power Plant
Stage 2006 2007 2008 2009 2010 2011 2012 ~
Stage 1 0.24 0.75 0.55 0.63 0.67 0.70 0.50
Stage 2 - - 0.18 0.63 0.67 0.70 0.50
(3) The project cost expressed in US$ term is assumed to be economic price (border
price) because the construction will be carried out based on the international
competitive bid.
(4) The price escalation3 (inflation), subsidies, duties and taxes are excluded in the
economic analysis because those taxes and duties are regarded merely as the do-
mestic transfer of capital.
(5) Engineering and Administration fees are excluded from the project cost in order
to keep the same cost level as that of alternative thermal plant.
(6) The kW value adjustment of the alternative thermal power plant is calculated by
using the following equation:
3 Escalations are sometimes taken into account when the fuel price escalations are envisaged to be different by fuel type
such as oil vs. coal.
10 - 8
A4)A3)(1A2)(1)(1365A1(1
T4)T3)(1T2)(1)(1365T1(1
kW value−−−−
−−−−=
Where; T1 = Scheduled maintenance days of proposed project (days)
T2 = Forced outage rate of proposed project (decimal)
T3 = Station use of proposed project (decimal)
T4 = Transmission and distribution lines loss of proposed project
(decimal)
A1 = Scheduled maintenance days of alternative thermal plant (days)
A2 = Forced outage rate of alternative thermal plant (decimal)
A3 = Station use of alternative thermal plant (decimal)
A4 = Transmission and distribution lines loss of alternative thermal
plant (decimal)
(7) The kWh value adjustment of the alternative thermal plant is also calculated by
using the following formula:
A4)-A3)(1-(1T4)-T3)(1-(1 ValuekWh =
In the above formulas, transmission and distribution lines loss can be negligible
in the economic analysis because the both losses are the same.
(8) The transmission line cost can be negligible in the economic analysis for the
same reason as item (7) above.
10.2.5. Fuel and Fuel Price
CIF prices (Cost, insurance and freight) are used for oil fuels because the all oil fuels
in Cambodia are imported from overseas at the moment.
The average CIF prices of diesel oil and heavy oil are used based on the actual CIF
price record provided by EDC as shown in Section 3.1.
Concerning the natural gas, of which exploring is expected in future; the estimated
exploring cost is envisaged to be higher than the world market and to be consumed in
the domestic due to the less efficiency of the gas reserve. The natural gas price is es-
10 - 9
timated 4 $/MMBTU at power plant site including the markup provisionally.
Table 10.2-2 Fuel Prices for Economic Analysis
Fuel Type Fuel Price (CIF Price) Remarks
Diesel Oil *1) 237 $/MT Average from 1996 Nov. ~ 2001. July
Heavy Fuel Oil *2) 154 $/MT Average from 1996 Nov.~ 2001. August
Natural Gas 4.0 $/MMBTU Engineer’s assumptions (L.H.V. base)3.5 $/MMBTU and 4.5 $/MMBTU are also testified in theeconomic analysis.
Source: *1) and *2) EDC
Fuel price escalation is not considered in the economic analysis because the same es-
calation rate will be applicable to all fuels.
10.2.6. Fuel Shift
Since some fuel types seem to be applicable to the project at the moment, the follow-
ing fuel scenarios are considered in the economic analysis.
(1) Natural Gas will be used for whole period of 20-years economic lifetime from the
beginning (Base Case).
(2) Diesel Oil will be used for the first 5 years and Natural Gas will be used for the
next 15 years.
(3) Diesel Oil will be used for the first 10 years and Natural Gas will be used for the
next 10 years.
(4) Diesel Oil will be used for whole period of 20-years economic lifetime from the
beginning.
In line with the fuel shift for the above items (2), (3) and (4) , the cost of additional
gas treatment system of 1.2 Million US$ for all stages is also considered.
10 - 10
10.2.7. Project Characteristics and Conditions
The project characteristics, which were revealed in the course of the study, and as-
sumed condition, are summarized in Table 10.2-3.
Table 10.2-3 Project Characteristics and Assumed Conditions
Items Value Unit Remarks
Installed capacity 180 MW 90 MW × 2 stages
Capacity Factor(Average 54%) %
2006 2007 2008 2009 2010 2011 2012 ~ST-1 24 75 55 63 67 70 50ST-2 - - 18 63 67 70 50
Construction cost 164.4 M. $ Excluding Engineering and AdministrationFees
Scheduledmaintenance days 49 Days
Forced outage rate 8.0 %
Station use 2.8 %
For kW and kWh adjustments use only
Fixed O/M cost 20.0 $/kW-year
Natural Gas
Fuel price 4.0 $/MMBTU LHV base, domestic price including markup
Heat rate 6,829 BTU/kWh
Fuel cost 27.32 $/MWh
Variable O/M 1.0 $/MWh
Diesel Oil
Fuel price 6.02 $/MMBTU LHV base, CIF Price for Diesel :237 $/ton
Heat rate 7,030 BTU/kWh
Fuel cost 42.32 $/MWh
Variable O/M 2.5 $/MWh
Construction period 2 Years Disbursement schedule are 40 % and 60 %.
Construction start 2004, 2006 2-staged construction
Operation start 2006, 2008 Each operation of 90 MW
Economic life time 20 Years
10 - 11
10.2.8. Alternative Thermal Power Plant
A diesel power plant with equivalent capacity to the project is set as an alternative
thermal power plant in view of current supply system in Cambodia.
Table 10.2-4 shows the plant properties to be used as the representative of equivalent
diesel power plant.
Table 10.2-4 Characteristics of Alternative Diesel and Assumed Conditions
Items Value Unit Remarks
Installed capacity 197.8 MW 98.9 MW x 2 stages, (Middle Speed)
Annual generation GWh2006 2007 2008 2009 2010 2011 2012~
ST-1 192.8 602.4 441.8 506.1 538.2 562.3 401.7ST-2 - - 144.5 506.1 538.2 562.3 401.7
Construction cost 271.0 M.US$ Excluding Engineering and AdministrationFees
Scheduledmaintenance days 28 days
Forced outage rate 20 %
Station use 4.6 %
Fixed O/M cost 21.0 $/kW-year
Variable O/M cost 3.0 $/MWh
Fuel Price 3.99 $/MMBTU LHV base, CIF Price for HFO: 154.0 $/ton
Heat rate 7,888 BTU/kWh HFO
Fuel cost 31.49 $/MWh HFO
Construction period 2 years Disbursement schedules are 50 % and 50 %.
Construction start 2004, 2006 2-staged construction
Operation start 2006, 2008 Each operation of 90 MW
Economic life time 20 years
kW Adjustment 1.099
kWh Adjustment 1.019
10 - 12
10.2.9. Calculation Cases and Results
(1) Calculation Cases
10 calculation cases, with combination of fuel conversion scenario and natural
gas price, are conducted as shown in Table 10.2-5.
Case Nos. 100s, 200s and 300s are focusing on the timing of natural gas fuel
availability and Case No. 400 represents the case of diesel oil for the whole eco-
nomic life time to understand the economic advantage of the natural gas.
Concerning the natural gas price, 4.0, 3.5 and 4.5 $/MMBTU are assumed.
(2) Calculation Results
Table 10.2-5 also presents the results of economic analysis. Typical cases (Case
No. 100, 300, and 400) are demonstrated in Attachments 3.1 to 3.3
The economic indices show the excellent economic performance of the project
except the Case No. 400 because the construction cost of the project is cheaper
than that of the alternative diesel power plant and the natural gas fuel cost is also
cheaper than the heavy fuel oil.
Concerning Case No. 400, EIRR of 3.81 % indicates that the Net Present Value
of Cost becomes lower than the Net Present Value of Benefit on condition that
the discount rate is bigger than 3.81 % (B - C becomes negative if the discount
rate is less than 3.81%).
“B – C” of Case 100 shows about 4 times and B/C of Case 100 also presents 30%
more in comparison Case 400.
Tabl
e 10
.2-5
C
alcu
latio
n C
ases
and
Sum
mar
y of
Res
ults
1.
C
alcu
latio
n C
ases
Se.N
o.1
23
45
67
89
10C
ase
No.
100
110
120
200
210
220
300
310
320
400
AF
uel C
onve
rsio
n Sc
enar
io(1
)N
atur
al G
as fo
r ful
l 20
year
s◎
○○
(2)
Die
sel O
il 5
year
s + N
G 1
5 ye
ars
○○
○(3
)D
iese
l Oil
10 y
ears
+ N
G 1
0 ye
ars
○○
○(4
)D
iese
l Oil
for f
ull 2
0 ye
ars
○
BN
atur
al G
as F
uel P
rice
(1)
4.0
US$
/MM
BTU
◎○
○(2
)3.
5 U
S$/M
MB
TU○
○○
(3)
4.5
US$
/MM
BTU
○○
○
CD
iese
l Oil
Pric
e (C
IF)
(1)
237
US$
/ton
○○
○○
○○
○
Not
e: ◎
mea
ns B
ase
Cas
e.
2.
Cal
cula
tion
Res
ults
Econ
omic
Inte
rnal
Rat
e of
Ret
urn
(EIR
R)
%N
.AN
.AN
.AN
.AN
.AN
.AN
.AN
.AN
.A3.
81*1
Net
Pre
sent
Val
ue o
f Cos
t M
.US$
249.
323
3.7
264.
227
6.3
266.
528
5.5
299.
029
4.1
303.
632
1.7
Net
Pre
sent
Val
ue o
f Ben
efit
M.U
S$34
5.0
345.
034
5.0
345.
034
5.0
345.
034
5.0
345.
034
5.0
345.
0
B -
C
M.U
S$95
.711
1.3
80.8
68.7
78.5
59.5
4650
.941
.423
.3
B/C
1.38
1.48
1.31
1.25
1.29
1.21
1.15
1.17
1.14
1.07
Not
e: N
et P
rese
nt V
alue
as o
f 200
1 is
dis
coun
ted
valu
e w
ith 1
0 %
dis
coun
t rat
e.
N.A
mea
ns E
IRR
>100
%
*1: F
or th
e C
ase
No.
400
, B-C
bec
omes
pos
itive
on
cond
ition
that
the
disc
ount
rate
is h
ighe
r tha
n 3.
81 %
, unl
ess B
-C b
ecom
es n
egat
ive.
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
���������������������
���������������������
���������������������
���������������������
10 - 13
10 - 14
10.3. Financial Analysis
10.3.1. Objective
Financial analysis is carried out to verify the financial feasibility of the project from
the viewpoint of the project owner and lenders. Therefore, market prices, which in-
clude taxes & duties, and subsidiaries, are used in the analysis.
Financial analysis is conducted in US$ term because US$ currency is prevalent in
Cambodia4 as well as Cambodian Riel.
10.3.2. Methodology and Definition of Financial Analysis
The financial Internal Rate of Return (FIRR) is the most commonly used measure in
financial analysis. FIRR consists of Project Internal Rate of Return (Project IRR) and
Return on Equity (ROE) according to the source of fund. Project IRR presents the ex-
pected rate of return on investment, which is fully prepared by own finance. On the
other hands, ROE presents the expected rate of return on equity portion. Therefore,
the former indicator does not depend on the financial (loan) conditions and presents
the financial characteristic of the project itself. The latter indicator presents the finan-
cial improvement of the project by means of imposing the external fund sources. Ac-
cording to World Bank Discussion Papers5, it is said that power developers normally
require at least 20 to 30 % of ROE.
Debt Service Coverage Ratio (DSCR) is one of the financial indices and the Bankers
are generally most concerned on this factor. According to the World Bank data,
DSCR exceeding 1.5 times is recommended. The DSCR is calculated by using the
following equation:
Payment) Interest Repayment (CapitalRevenue SalesNetDSCR+
=
Where, Net Sales Revenue = Sales Revenue – Operation Cost – Profit Tax
The financial levelised production cost (LPC) is generally compared with the power
4 Invoice of power tariff is made in Cambodian Riel and payment is allowed to be done by Riel or US$ term for an example.5 “Submission and Analysis of Proposals for Private Generation Project in Developing Countries”, 1994
10 - 15
tariff. The financial levelised production cost is derived from the following formula:
RateDiscount 10%h Energy wit Salable of NPVRateDiscount % 10Cost with Total of NPV
=LPC
10.3.3. Annual Generation and Salable Energy
(1) Annual Generation
Annual generation energies can be calculated by the capacity factor, which is re-
sulted from the optimum power development program in Section 2.2.
The capacity factors are set as shown in Table 10.3-1 as well as the economic
analysis.
The average capacity factor for the economic lifetime of 20 years is estimated to
be 54%.
Table 10.3-1 Capacity Factors of Sihanoukville C.C. Power Plant
Stage 2006 2007 2008 2009 2010 2011 2012 ~
Stage 1 0.24 0.75 0.55 0.63 0.67 0.70 0.50
Stage 2 - - 0.18 0.63 0.67 0.70 0.50
Note: Annual generation energy for 2007 results in 591.3 GWh (= 90 MW × 0.75 × 8,760 hrs × 0.001)
(2) Station Use and Transmission Loss
The station use is assumed to be 2.8 % as well as economic analysis.
The transmission line loss is assumed as follows:
- Project Site ~ Takeo : 1.7 % (220 kV × 2 circuits)
- Project Site ~ Phnom Penh : 2.7 % (220 kV × 2 circuits)
- Chau Doc ~ Phnom Penh : 4 % for peak period and 2 % for shoulder period6
The distribution loss in Phnom Penh is set at 13.0%7 based on the EDC’s projec-
6 “Feasibility Study for the First Transmission Link between Phnom Penh and the Southern Region of Cambodia, Project
Review”, page 57, April 2001.7 According to EDC’s information in November 2001, the distribution loss in Phnom Penh around year 2006, EDC proj-
ects 12% ~ 14%.
10 - 16
tion and the total loss from the project site to consumer’s end is assumed to be
15.7% provisionally.
(3) Salable Energy
Based on the above assumptions, the salable energy becomes as follows:
Salable Energy = Generation Energy × (1 – Station Use) × (1 – T/L loss)= Generation Energy × (1-0.028) × (1- 0.157)= 0.8194 × Generation Energy
10.3.4. Construction Cost
The construction cost consists of the construction of the project and the construction
of transmission line from Kampot to the project site (about 83 km). The construction
cost of the transmission line from Phnom Penh to Takeo is assumed to be born by the
World Bank’s Project and from Takeo to Kampot is also assumed to be born by the
German Grant.
The construction cost of the project is estimated by two currencies portion for Stage 1
and Stage 2 respectively.
Table 10.3-2 Estimated Construction Cost (M.US$)
F/C Portion (M.US$) L/C Portion (M.US$) TotalStage No Before
EscalationAfter
EscalationBefore
EscalationAfter
EscalationBefore
EscalationAfter
EscalationStage 1 90 MW 83.6 92.2 16.6 18.2 100.2 110.4Stage 2 90 MW 65.4 75.5 9.3 10.6 74.6 86.1Subtotal 149.0 167.7 25.9 28.8 174.8 196.5220 kVA × 2 lines 8.6 9.4 2.2 2.4 10.8 11.8Total 157.6 177.1 28.0 31.2 185.6 208.3
Note: The above costs exclude duties & taxes, IDC and other financial fees. The total is not matched due to round off.
The price escalation of 2.4 % per annum is considered referring to the ADB Report8.
8 “Provincial Power Supply Project”, Asian Development Bank, November 2000, page 17.
10 - 17
10.3.5. Taxes and Duties imposed on Project
Fig. 10.3-1 presents the taxes and duties imposed on the project. Taxes and duties,
which will be incurred during the construction period, are regarded as the investment
capital of the Royal Government of Cambodia.
Value Added Tax of 10 % is imposed on Foreign and Local Currencies Portion.
Note: STP means Standard Price for Tax Calculation
Note: Profit tax of 20 % is imposed on Year 2001 onwards.
Fig.10.3-1 Taxes and Duties on Project
Import TaxDO:275$/ton x 20%HFO:129$/ton x 7%
FOB + Premium (30 %)
Fuel Price at P/S
Construction Cost F/CPortion
Import of ConstructionEquipment & Material
Import Tax *1)
-15% on Generating Equipment-13% on Distribution Equipment-10% on other imported items
Sales Revenue = Salable Energy x Tariff Rate(Turnover)
Less Operation Expenses - Fixed O/M Cost - Variable O/M Cost - Fuel Cost - Depreciation
Operation Profit/Loss
Other Expenses - Interest Payment
Profit/Loss before TaxProfitProfit Tax
( 20 % of before Tax) Loss
Profit after Tax
Loss after Tax
- Transportation cost- Insurance cost- Margin
CIF Price
Construction
VAT( 10 %)
CommercialOperation
Construction Cost L/CPortion
VAT *1)
( 10 %)
F/C Portion L/C Portion
Profit and LossStatement
Profit Tax Payment
CIF>=STPImport Tax
DO:CIF $/ton x 20%HFO:CIF $/ton x 7%
Import Tax
Social FundSocial Fund
DO:1.40 $/tonHFO:0.81 $/ton
YesNo
VAT *1)
( 10 %)
Note) VAT of 10 % is imposed on Local and Foreign costs excluding Consultant Services
*1) Source: Asian Development Bank "Provincial Power Supply Project", Appendix-5, page1
10 - 18
10 - 19
10.3.6. Power Tariff Forecast
The average power tariff as of 2000 is 554 Riel/kWh9 (or 14.57 ¢/kWh) and the
power tariff rate is shown in Attachment 1.5.
The future power tariff is assumed based on EDC Report, ADB Project Report10 and
the World Bank Project Report11, which are shown in Tables 10.3-3 and 10.3-4.
Table 10.3-3 Future Power Tariff Scenario (Riel/kWh)
2001 2002 2003 2004 2005 2006 2007ADB *1) 652 700 752 728 730 746 778EDC *2) 608 613 620 628 636 646 656
*1) ADB “Provincial Power Supply Project”, November 2000, Appendix-9, Page 4, Table A9.1 *2) EDC Report, page 14
Table 10.3-4 Exchange Rate Forecast (Riel/$) and Power Tariff Forecast (¢/kWh)
2001 2002 2003 2004 2005 2006 2007Exc. Rate *3) 3,971 4,149 4,335 4,530 4,734 4,946 5,169EDC 15.31 14.79 14.31 13.86 13.44 13.06 12.68ADB *4) 16.42 16.87 17.35 16.07 15.42 15.08 15.05World Bank *5) 16.1 16.1 16.1 14.5 13.8 13.4 12.5
*3) EDC Report, page 14 *4) ¢/kWh for ADB portion is calculated by using the above exchange rate. *5) World Bank “Project Overview Report”, Page 58, Table 7
Note: Exchange Rate against US$ is assumed to be devaluated 4.5 % annually by EDC.
Based on the above forecast, the average power tariff from the year 2006 onwards is
assumed to be 13.0 ¢/kWh.
However, the average power tariff consists of the following cost. Therefore, the power
tariff contributing to the project finance is the power tariff less indirect cost.
9 “Prepared and Analyses Study, EDC’s Strategic Planning for Year 2001, 2002 and 2003 within Planning until 2010 “,
Page 14, EDC, November 200010 “Report and Recommendation of the President to the Board of Directors on a Proposed Loan to the Kingdom of Cambo-
dia for the Provincial Power Supply Project” , November 200011 “The World Bank Cambodia Rural Electrification and Transmission Project (PHRD TF025765) Feasibility Study Report
for the Transmission Link between Phnom Penh and the Southern Region of Cambodia, Project Overview”, April 2001
10 - 20
- Direct operation costs (Fuel cost, Fixed O/M and Variable O/M costs)
- Power purchase cost from IPP
- Maintenance cost of transmission and distribution lines
- Overhead cost
Table 10.3-5 data shows the cost related to the power generation of EDC Phnom Penh
Operations from 1997 to 1999.
Table 10.3-5 Cost Related to Power Generation in Phnom Penh Operation (Million Riel)
FY Year 1997 1998 1999
1. Cost Related to Power Generation *1)
Fuel
Diesel Oil 32,255 46,806 23,822
Fuel Oil 5,541 - 10,046
Light Oil & Materials 1,585 1,593 2,429
IPP Purchase 33,133 58,061 73,693
Depreciation 7,780 13,741 11,656
Wages and Salaries 196 818 1,176
Subtotal 80,490 121,019 122,822
2. Total Expenditure *2)
Cost of Sales 74,782 109,918 131,708
Operating Expenses 14,829 40,539 13,776
Cost of Sales + Operating Expenses 89,611 150,457 145,484
Direct Cost Ratio (1/2) 90.32% 80.43% 84.42%*1) Source: Finance and Accounting Department of EDC, September 2001*2) Source: EDC Annual Report 1998, November ,1999, and Finance and Accounting Dpt of EDC, September 2001.
Since the Operating Expenses in 1998 include the provision of bad debt, the direct
cost ratio is estimated by the average of 1997 and 1999 as follows:
% 85 %48.86145,484) (89,611122,822) (80,490 RatioCost Direct ==
++
=
Therefore, power tariff contributing to the project is set at 11.05 ¢/kWh (13 ¢/kWh ×
85% = 11.05).
10 - 21
10.3.7. Fixed and Variable O/M Cost
(1) Fixed O/M Cost
Fixed O/M cost mainly consists of machine repair cost and wage & salaries of the
operation staffs. According to EDC Report, EDC planned the staff costs for the
year 1999 as shown in Table 10.3-6.
Table 10.3-6 EDC Staff Cost in PHN’s for 1999
(Unit: 1,000 US$)
1. Salaries 1,446
2. Social Insurance Charge 232
3. Advantage in kind 63
4. Bonus 176
Total Staff Cost 1,917
Source: “EDC Annual Report 1998, Table 4-8”, Feb. 1999
Since the total staffs in PHN’s as of December 31, 2000 were 1,295 personnel,
the average manpower cost per annum is estimated to be 1,480 US$ per capita
per year provisionally.
On the other hand, proposed staffs for the commercial operation are 151 person-
nel for the two stages. Considering the other related fixed costs, the fixed O/M
cost is assumed as follows:
(a) Stage 1 : Total Fixed O/M cost = 3.62 Million US$ (40.22 $/kW-year)
- Personal Expenses : 1,480 $/capita × 118 person = 0.17 Million US$
- Maintenance cost : 3 % of Plant Cost (ST1) = 101.4 Million US$ × 3%
= 3.04 Million US$
- Insurance etc. : 0.4 % of Plant Cost (ST1) = 101.4 Million US$ ×
0.4% = 0.41 Million US$
10 - 22
(b) Stage 2 : Total Fixed O/M cost = 2.85 Million US$ (31.67 $/kW-year)
- Personal Expenses : 1,480 $/capita × 33 person = 0.05 Million US$
- Maintenance cost : 3 % of Plant Cost (ST2) = 82.2 Million US$ × 3 %
= 2.47 Million US$
- Insurance etc. : 0.4 % of Plant Cost (ST2) = 82.2 Million US$ × 0.4
% = 0.33 Million US$Note : Plant Cost defined here consists of Mechanical Works, Electrical Works, Civil and Structural
Works and Spare Parts.
Since the fixed O/M cost for the associated transmission line is normally 1.0 % of
the investment cost, the fixed O/M cost for the transmission line becomes 0.1
Million US$ (= 11.8 Million US$ × 1 %) and be paid by Stage 1.
(2) Variable O/M Cost
Variable O/M cost is estimated to be 1.0 $/MWh for natural gas-fired and 2.5 $/
MWh for diesel oil-fired respectively referring to the similar plants in the devel-
oping countries in the South-east Asia.
10.3.8. Fuel Cost and Fuel Shift
The fuels applicable to the project are assumed to be diesel oil and natural gas.
(1) Fuel Cost
The fuel prices used in the financial analysis are market prices including the taxes
and duties.
Taxes and duties shown in Table 10.3-7 are considered in the financial analysis.
The import tax for diesel oil is calculated by the standard price of 275 $/ton basis.
10 - 23
Table 10.3-7 Taxes and Duties on Fuel
Fuel Type Import Tax Social Fund VAT
Diesel Oil 20 % 1.40 $/ton 10 %
Natural Gas None *1) 1.40 $/ton 10 %Note: Taxes and duties for natural gas are assumed values.
*1) Natural Gas is assumed to be domestic product.
The fuel cost before taxes and duties are set at 237 $/ton (CIF Price) for diesel oil
and 4.0 $/MMBTU (L.H.V. base) for natural gas. Annual escalation of 2 % is es-
timated for diesel oil and 0 % for natural gas from the year 2001 onwards.
(2) Fuel Shift
As mentioned in the economic analysis, natural gas is expected to be exploited in
Cambodia in future. The timing of fuel shift is assumed as follows as well as
economic analysis.
(a) Natural Gas will be used for whole period of 20-years economic lifetime
from the beginning (Base Case).
(b) Diesel Oil will be used for the first 5 years and Natural Gas will be used for
the next 15 years.
(c) Diesel Oil will be used for the first 10 years and Natural Gas will be used for
the next 10 years.
(d) Diesel Oil will be used for whole period of 20-years economic lifetime from
the beginning.
In line with the fuel shift, the cost of additional gas treatment system of 1.2 Mil-
lion US$ for all stages is also considered.
10.3.9. Depreciation Method
Depreciation method applied to EDC at the moment is accelerated depreciation
method, of which ratios varied from 0 % to 20 % based on the categories as shown in
Table 10.3-8.
10 - 24
Table 10.3-8 Percent of Annual Depreciation
Categories Percents
Land 0 %
Land Improvement 20 %
Administration Building 3 %
Production Building 11 %
Substation 4 %
Generator 11 %
Other Equipment 11 %
Network Equipment 4 %
Vehicle 15 %
Office Furniture 10 %
Source: Finance and Accounting Department of EDC, September 2001
All project cost, including the land acquisition and resettlement, is assumed to be
subject to the depreciation and the average percents of depreciation is also assumed to
be 11 % based on the above table.
10.3.10. Implementation Method
The following two implementation methods for Sihanoukville C.C. Project are con-
sidered.
(1) Option 1 : EDC will implement the project by using official loan.
(2) Option 2 : The private investor will implement the project by his own finance
and loans, and sell the power to EDC based on the Power Purchase
Agreement (BOT).
10 - 25
10.3.11. Finance Arrangement
(1) Finance Sources
The official finance sources such as the Japan Bank for International Cooperation
(JBIC) and the Asian Development Bank, are the most prospective finance
sources for the project in case of Option 1.
For Option 2, the combination of Oversea Investment Loan (OIL) and the com-
mercial bank seems to be applicable.
(2) Loan Conditions and Finance Arrangement
The typical loan conditions offered by official finance sources and commercial
banks are as follows:
(a) JBIC Loan (Yen Loan)
JBIC will finance the 100 % of the foreign currency portion or the maximum
85% of the total project cost.
JBIC loan cannot be applicable to the duties and taxes.
Since Cambodia belongs to the LLDC (Least Less-Developed Country),
RGC (The Royal Government of Cambodia) will be able to borrow the re-
quired fund for the project on the following conditions in case of the stan-
dard loan.
- Interest rate of 1.0 %
- Amortization of 30 years including grace period of 10 years (maximum)
(b) ADB Loan (US$ Loan)
ADB will finance the 100 % of the foreign currency portion or approxi-
mately 90 % of the total project cost including the Interest During Construc-
tion (IDC) based on the “Provincial Power Supply Project”, which was fi-
nanced by ADB. ADB loan also cannot be applicable to the duties and taxes.
The standard loan condition (Special Drawing Right) based on the above
project seems to be as follows:
- Interest rate of 1 % for during the grace period
10 - 26
- Interest of 1.5 % per annum thereafter
- Amortization of 32 years including grace period of 8 years.
(c) Overseas Investment Loan (OIL)
OIL is applicable to the IPP Project, if the Japanese investors are involved in
the IPP. OIL is assumed to finance 60% of the total debt. Other conditions
for US$ Loan are assumed as follows:
- Interest rate per annum = LIBOR + 1.0 % (LIBOR: London Interbank Offered
Rate)
- Amortization of 15 years including grace period of 5 years
(d) Subsidiary Loan
The Loan Agreement will be made between the Banker and the Borrower for
the above a) and b) loans. The Ministry of Economy and Finance (MEF),
Cambodia is the representative of the Borrower.
Besides the above Loan Agreement, MEF will re-lend the loan and the RGC
portion to the executing agency (EDC) under the Subsidiary Loan Agree-
ment.
Fig. 10.3-2 demonstrates the examples of Loan Agreement and Subsidiary
Loan Agreement, which seems to be applicable to the “Sihanoukville Com-
bined Cycle Project”.
Therefore, the financial feasibility of the Project is studied by using the
above Subsidiary Loan Agreement.
Subsidiary Loan-1 is the case when the 85% of total project cost is borrowed
from an official finance source (Source-A), and Subsidiary Loan-2 is the
case when the 90% of total project cost including IDC is borrowed from an
official finance source (Source-B).
Cas
e-1
Japa
n B
ank
for I
nter
natio
nal C
oope
ratio
nC
ase-
2A
sian
Dev
elop
men
t Ban
k"S
ihan
oukv
ille
Port
Urg
ent R
ehab
ilita
tion
Proj
ect"
"Pro
vinc
ial P
ower
Sup
ply
Proj
ect"
JB
IC(B
anke
r)
MEF
(Borr
ow
er)
PA
S
Loan
Agr
eem
ent
(24 S
epte
mber
1999)
Subs
idia
ryLoan
Agr
eem
ent
( 25 A
pril
2000 )
JB
IC(B
anke
r)
MEF
(Borr
ow
er)
PA
S
Loan
Condi
tion
(a) C
onst
ruction W
ork
Inte
rest
Rat
e o
f 1.0
%M
aturity
period
of 30 y
ear
s in
clu
ding
10 y
ear
s gr
ace p
eriod
(b) C
onsu
ltan
t Serv
ices
Inte
rest
Rat
e o
f 0.7
5 %
Mat
urity
period
of 40 y
ear
s in
clu
ding
10 y
ear
s gr
ace p
eriod
Cash Flow
Subs
idia
ry L
oan
Condi
tion
Inte
rest
Rat
e o
f 3.5
% p
er
annum
(a) C
onst
ruction W
ork
Mat
urity
period
of
30 y
ear
s in
clu
ding
10 y
ear
s gr
ace
period
(b) C
onsu
ltan
t Serv
ices
Mat
urity
period
of
40 y
ear
s in
clu
ding
10 y
ear
s gr
ace
period
JB
IC: Jap
an B
ank
for
Inte
rnat
ional
Coope
ration
MEF: The M
inis
try
of Econom
y an
d Fin
ance
PA
S: The P
ort
Auth
ority
of
Sih
anoukv
ille
Cash Flow
Note
:MEF is
desi
gnat
ed
as r
epr
ese
nta
tive
of th
eB
4,1
42 M
illio
n J
¥
4,1
42 M
illio
n J
¥(J
BIC
) +
928 M
illio
n J
¥ (P
AS)
AD
B(B
anke
r)
MEF
(Borr
ow
er)
ED
C
Loan
Agr
eem
ent
(Spe
cia
l O
pera
tion)
(5 A
pril
2001)
Subs
idia
ryLoan
Agr
eem
ent
(29 J
une 2
001)
Pro
ject
Agr
eem
ent
( 5 A
pril
2001)
AD
B(B
anke
r)
MEF
(Borr
ow
er)
ED
C
Loan
Condi
tion
Inte
rest
Rat
e o
f 1.0
% f
or
Gra
ce P
eriod
Inte
rest
Rat
e o
f 1.5
% t
here
afte
rG
race P
eriod
of 8 y
ear
sM
aturity
period
of 32 y
ear
s in
clu
ding
8ye
ars
grac
e p
eriod
Cash Flow
Subs
idia
ry L
oan
Condi
tion
Inte
rest
Rat
e o
f 3.5
% p
er
annum
Gra
ce P
eio
d of 5 y
ear
sM
aturity
period
of 20 y
ear
s in
clu
ding
5 y
ear
sgr
ace p
eriod
AD
B: A
sian
Deve
lopm
ent
Ban
kM
EF: The M
inis
try
of Econom
y an
d Fin
ance
ED
C: The E
lectr
icite d
u C
ambo
dge
Cash Flow
Note
:MEF is
desi
gnat
ed
as r
epr
ese
nta
tive
of th
eB
Note
:The s
ubs
idia
ry L
oan
shal
l be
denom
inat
ed
in U
nited
Sta
tes
dolla
rs a
nd
repa
id b
y ED
C t
o M
EF a
lso in U
nited
Sta
tes
dolla
r. F
ore
ign e
xchan
ge r
isk
shal
l be
born
e b
y ED
C.
15.9
Mill
ion U
S$
15.9
Mill
ion U
S$(A
DB
) +
1.6
Mill
ion U
S$ (M
EF)
Note
:The s
ubs
idia
ry L
oan
shal
l be
denom
inat
ed
in J
apan
ese
Yen, an
d P
AS s
hal
l re
pay
the p
rincip
al a
nd
pay
inte
rest
of th
eSubs
idia
ry L
oan
in J
apan
ese
Yen in a
ccord
ance w
ith t
he
provi
sions
of th
is A
greem
ent.
10 - 27
Fig
.10.
3-2
L
oan
Agr
eem
ent a
nd S
ubsi
diar
y Lo
an A
gree
men
t
10 - 28
10.3.12. Calculation Conditions
Based on the above considerations, the calculation conditions in the financial analysis
are summarized in Table 10.3-9.
Table 10.3-9 Sihanoukville C.C. Project Calculation Conditions
Items EDC Project IPP Project (BOT)
Installed Capacity 90 MW × 2 stages = 180 MW
Annual Capacity Factor(Average 54%)
2006 2007 2008 2009 2010 2011 2012~ST-1 24% 75% 55% 63% 67% 70% 50%ST-2 - - 18% 63% 67% 70% 50%
Station Use 2.8 %
T/L and Distribution Loss 15.7% 0% (Sales at P/S exit)
Salable Energy Generation Energy × 81.94% Generation Energy × 97.2%
Construction Cost for Stage 1 F/C L/C inc. duties and taxes Total (inc. T/L)
After escalation101.6 Million US$
45.3 Million US$146.9 Million US$
Import tax will be exempted.*1)
101.6 Million US$31.9 Million US$
133.5 Million US$Construction Cost for Stage 2 F/C L/C inc. duties and taxes Total (inc. T/L)
After Escalation75.5 Million US$29.5 Million US$
105.0 Million US$
Import tax will be exempted.*1)
75.5 Million US$18.8 Million US$94.3 Million US$
Escalation L/C F/C
2.4 % per annum2.4 % per annum
Disbursement Schedule Stage 1 Stage 2
2004 2005 2006 2007 200822.8% 50.3% 26.9% - - - - 22.2% 51.3% 26.5%
Finance Planning Financial Source Interest Rate (=IDC) Commitment Fee Grace Period Repayment Period Loan Limit Top Front Fee
Finance Source Interest rate (=IDC) Commitment Fee Front End Fee Grace Period Repayment Period Loan Limitation
Subsidiary Loan - 13.5 % per annum-8 years23 years including grace period100 % of F/C or 85 % of the project cost-
Subsidiary Loan - 23.5 % per annum--8 years23 years inc. 5 years grace period100 % of F/C or 90 % of the construc-tion cost inc. IDC
OIL US$ LoanLIBOR+1 % *2) (3.46 + 1 = 4.46)0.25 % of remaining loan5 years15 years60 % of debt portion1.0 % of loan amount
Bank Syndicate LoanLIBOR+2.5 %(3.46 + 2.5=5.96)0.5 %1.25 % of loan amount5 years15 years including grace periodNone
Equity : Debt - 30 % : 70 %
Economic Life Time 20 years
10 - 29
Items EDC Project IPP Project (BOT)
Depreciation Method Accelerated method with 11 % for 20-years economic lifetimePower Tariff as of 2006 ex-cluding maintenance cost ofT/L, D/S and overhead
11.05 ¢/kWh ¢/kWh for PPAPPA: Power Purchase Agreement
Operation Cost Fixed O/M Cost Variable O/M Cost Fuel Cost
ST-1: 40.2 $/kW-year (inc. T/L: 41.5) ST-2: 31.7 $/kW-yearNatural Gas : 1.0 $/MWh Diesel Oil : 2.5 $/MWhNatural Gas : 30.27 $/MWh Diesel Oil : 58.28 $/MWh
Tax and Duties Profit Tax 20% 9 % with 8 years Tax Holiday
*1)
Commencement of Operation Stage 1: 2006 Sep.1 Stage 2: 2008 Sep.1
Discount Rate 10 %
Exchange Rate 1 US$ = 4000 Riel as of 2001
Note : *1) Power Purchase Agreement between Leader Universal Holdings Berhad Delcom Services SDN BHDINTERCORE INC. and EDC, Appendix K, page 94.
*2) LIBOR is 3.46 % as of October, 2001 (Source: www.bankrate.com/brm/news/biz/ratechart.asp)
10.3.13. Calculation Cases and Calculation Results
(1) Calculation Cases
Based on the above considerations, 27 cases as summarized in Table 10.3-10 are
conducted.
(a) Case numbers of 1000s are the cases that the project is implemented by Sub-
sidiary Loan-1.
(b) Case numbers of 2000s are the cases that the project is implemented by Sub-
sidiary Loan-2.
(c) Case numbers of 3000s are the case that the project is implemented by IPP
and the power tariff for PPA, which satisfies the ROE of 20%, is calculated.
Power selling to EDC is assumed at power station outlet.
(d) Case numbers of 4000s are focusing on generation cost excluding VAT and
Profit Tax to compare the power purchase cost from Vietnam and IPP1. And
distribution loss is also excluded for the comparison basis.
In association with the above implementation methods, Table 10.3-11 shows the
summary of the total project cost including all costs.
10 - 30
(2) Calculation Results
Table 10.3-10 also shows the calculation results of the financial analysis and
Case No. 1000, Case No. 2000, Case No. 3000, and Case No. 4000 are demon-
strated in Attachments 3.4 to 3.7.
(a) Project IRR
If the natural gas is used for the full economic lifetime or put into the opera-
tion before the 5th year, the project IRR of 10% is expected. On the other
hand, if the diesel oil is used for the full economic life time, the project IRR
cannot be calculated and the financial attractiveness will be eliminated.
Therefore, from the viewpoint of the project EIRR, the financial attractive-
ness will be expected on condition that the natural gas becomes available
before the 5 years from the commencement of commercial operation.
(b) ROE & DSCR
As shown in Table 10.3-11, since EDC bears IDC portion only under the
Subsidiary Loan Agreement, ROE presents the good performance for any
cases. However, in view of DSCR, the minimum DSCR becomes less than
1.0 or negative if diesel oil is fired more than 10 years during the operation
period. The DSCR less than 1.0 means that EDC has to borrow the addi-
tional loan for the interest payment and principal repayment due to shortage
of own cash.
Therefore, the implementation of the project will be accepted by the Lenders
if the natural gas is warranted to be put into the operation before the 5th year
from the commencement of the commercial operation, unless the implemen-
tation will not be accepted.
(c) Levelised Production Cost
At the priced of natural gas of 4.0 $/MMBTU, levelised production cost in-
cluding taxes and duties under the effective power tariff of 11.05 ¢/kWh
varies from 7.84 ¢/kWh to 9.45 ¢/kWh for the cases that the natural gas will
be put into the project within the first 5 years during the operation period and
10.96 ¢/kWh to 12.85 ¢/kWh if natural gas is put into the project on 11th
10 - 31
year or not put into the project. If the natural gas is available from the begin-
ning of the operation, levelised production cost can be expected to be 30%
less in comparison with the case that the natural gas is put into the operation
on 11th year.
(d) IPP Project
In case of the IPP project, the hurdle rate for the financial feasibility is set at
20 % of ROE. To achieve the ROE more than 20 %, the power tariff selling
to EDC (at P/S exit) requires from 7.70 ¢/kWh to 9.85 ¢/kWh under the con-
dition that natural gas is put into within 5 years and its price is 4.0 $/
MMBTU.
These selling prices will be equivalent to 9.13 ¢/kWh to 11.68 ¢/kWh at con-
sumer’s end level taken into account of T/L and D/L loss of 15.7%.
EDC has to purchase at more expensive cost than that of EDC implementa-
tion because the selling price to EDC at consumer’s end is higher than the
levelised production cost for the case of EDC.
If the diesel oil is used for the full operation period, the selling price of 14.39
¢/kWh to EDC exceeds the expected power tariff of 13.00 ¢/kWh and cannot
be accepted by EDC.
(e) Production Cost without Taxes
- Comparison with the current purchase tariff from IPP1
Attachment 1.3 shows the current EDC’s operation status. EDC purchases
the power from IPP1. in Phnom Penh Operations at 8.94 ¢/kWh (1997) to
10.95 ¢/kWh (2000) based on the PPA. The above purchase prices do not
include the duties and taxes, because EDC bears duties and taxes imposed
on fuel, of which fuel is used by IPP1s, instead of IPP1.
The levelised production cost for Case No. 4000 is excluded duties and
taxes, and profit tax to keep the same cost level with the current purchase
tariff from IPP1.
The levelised production cost of the project of 5.78 ¢/kWh is clearly
lower than the current purchase tariff from IPP1.
10 - 32
- Comparison with the power import from Vietnam
The Royal Government of Cambodia and the Government of Social Re-
public of Viet Nam made an Agreement on Power Sector Cooperation in
June, 1999. Based on the agreement, MIME (Ministry of Industry, Mines
and Energy) and MOI (Ministry of Industry, Viet Nam) entered into
Power Trade Agreement describing the power trade from Vietnam to
Cambodia. According to Power Purchase Agreement signed on July 24,
2000 based on the above agreement, the conditions on the power purchase
from Vietnam are set as follows:
a. Commencement of power purchase : year 200312
b. Source of supply : Thot Not substation via Chau Doc
c. Interconnecting point : Border between Cambodia and Vietnam
d. Metering point : Chau Doc substation
e. Supply capacity : 80 MW between 2003 to 2005
: 200 MW after year 2005
f. Power tariff effectiveness : 5 years
g. Currency in payment : US$
Table 10.3-12 Power Purchase Prices from Vietnam
Peak hours (18:00 ~ 22:00) 8.50 ¢ /kWh
Normal hours (4:00 ~ 18:00) 6.25 ¢ /kWh
Dry Season
(November ~ June 30)
Off-peak hours (22:00 ~ 4:00) 4.50 ¢ /kWh
Peak hours (18:00 ~ 22:00) 8.00 ¢ /kWh
Normal hours (4:00 ~ 18:00) 6.00 ¢ /kWh
Wet Season
(July ~ October 31)
Off-peak hours (22:00 ~ 4:00) 3.00 ¢ /kWh
The average purchase price at the border is estimated to be about 6.0
¢/kWh13.
If the purchase price of 6.0 ¢/kWh at the border price converts to the
12 As mentioned in Section 2.4, available import year seems to be delayed.13 Dry Season = (8.5 x 4 + 6.25 x 14 + 4.5 x 6 )/24 = 6.2, Rainy Season = (8.0 x 4 + 6.0 x 14 + 3.0 x 6 )/24 = 5.6, whole
year = (6.2 x 8 + 5.6 x 4 )/12 = 6.0
10 - 33
equivalent prices at Takeo and at Phnom Penh taking into consideration
of transmission line loss, the above border price will be as shown in Table
10.3-13 in comparison with the levelised production costs of Case No.
4000 and 4100.
Table 10.3-13 Comparison of Purchase Price and LPC
Power PurchaseFrom Vietnam
Levelised ProductionCost (LPC)
At Phnom Penh 6.0 /(1-0.02) = 6.12 ¢/kWh 5.78 ¢/kWh (No. 4000)
At Takeo 6.0 /(1-0.01) =6.06 ¢/kWh 5.73 ¢/kWh (No. 4100)Note) T/L loss from Chau Doc to Phnom Penh and to Takeo is assumed to be 2.0 % and 1.0 % respec-
tively as mentioned before.
Based on the above comparison, it is expected that if the natural gas, of
which exploring cost is 4.0 $/MMBTU, will be put into the operation
from the commencement of the commercial operation, production cost of
the project will be less than the purchase price from Vietnam.
Further more, if the Shihanoukville Industrial Zone is realized in future14,
the project will be more advantageous in virtue of its location.
14 According to ADB information, the improvement of Sihanoukville Air Port from the domestic air port to the interna-
tional air port is under negotiation between RGC and Bangkok Airways to induce the overseas investors.
Tabl
e 10
.3-1
0
Cal
cula
tion
Cas
es a
nd R
esul
ts fo
r Fin
anci
al A
naly
sis
1. C
alcu
latio
n C
ases
Se.N
o.1
23
45
67
89
1011
1213
1415
1617
1819
2021
2223
2425
2627
Cas
e N
o.10
0010
1010
2011
0011
1011
2012
0012
1012
2013
0014
0020
0020
1020
2021
0021
1021
2023
0030
0030
1030
2031
0031
1031
2033
0040
0041
00A
.F
inan
ce S
ourc
es(1
)Su
bsid
iary
Loa
n -1
◎○
○○
○○
○○
○○
○○
○(2
)Su
bsid
iary
Loa
n -2
○○
○○
○○
○(3
)O
IL +
Ban
k Sy
ndic
ate
Loan
○○
○○
○○
○B
Impl
emen
tatio
n M
etho
d(1
)Im
plem
ente
d by
ED
C◎
○○
○○
○○
○○
○○
○○
○○
○○
○○
○(2
)IP
P○
○○
○○
○○
CF
uel C
onve
rsio
n Sc
enar
io(1
)N
atur
al G
as fo
r ful
l 20
year
s◎
○○
○○
○○
○○
○○
○(2
)D
iese
l 5 y
ears
+ N
G 1
5 ye
ars
○○
○○
○○
○○
○(3
)D
iese
l 10
year
s + N
G 1
0 ye
ars
○○
○(4
)D
iese
l Oil
for f
ull 2
0 ye
ars
○○
○D
Nat
ural
Gas
Pri
ce (i
nc. T
axes
)(1
)4.
43 U
S$/M
MB
TU
◎○
○○
○○
○○
○○
(2)
3.88
US$
/MM
BTU
○
○○
○○
○○
(3)
4.98
US$
/MM
BTU
○
○○
○○
○○
ED
iese
l Oil
Pric
e (in
c. T
axes
)(1
)32
6.54
US$
/ton
○○
○F
T/L
from
Kam
pot t
o Si
te(1
) In
clud
ing
T/L
(11.
8 M
.US$
)◎
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○(2
)Ex
clud
ing
T/L
○G
Pow
er c
onsu
mpt
ion
at
(1)
Phno
m P
enh
◎○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
○○
(2)
Take
o○
HV
alue
Add
ed T
ax &
Pro
fit T
ax(1
)N
o V
AT
○
○
(2)
No
Prof
it Ta
x○
○N
ote:
◎
mea
ns b
ase
case
.
2. C
alcu
latio
n R
esul
ts1
Proj
ect I
RR
(%
)
St
age-
111
.612
.710
.56.
67.
15.
93.
03.
42.
6N
.A.
13.2
11.6
12.7
10.5
6.6
7.1
5.9
N.A
.8.
99.
08.
910
.010
.110
.08.
020
.721
.0
St
age-
216
.517
.715
.212
.112
.811
.27.
17.
56.
5N
.A.
16.5
16.5
17.7
15.2
12.1
12.8
11.2
N.A
.14
.114
.114
.216
.917
.116
.712
.327
.628
.0
St
age-
1 &
Sta
ge-2
13.5
14.5
12.3
8.7
9.4
8.1
4.8
5.2
4.3
N.A
.14
.513
.514
.512
.38.
79.
48.
1N
.A.
10.9
11.0
10.9
12.6
12.8
12.5
9.6
23.0
23.4
2R
etur
n on
Equ
ity
(%
)
St
age-
121
022
419
746
4843
14
-2N
.A.
237
210
224
196
4547
43N
.A.
15.0
15.0
14.9
14.7
14.7
14.8
15.0
309
313
Stag
e-2
244
258
230
9194
8833
3531
N.A
.24
424
525
823
091
9488
N.A
.29
.429
.429
.530
.230
.330
.229
.233
734
2
St
age-
1 &
Sta
ge-2
213
226
199
5961
5714
1611
N.A
.23
821
322
619
959
6156
N.A
.20
.020
.020
.019
.919
.920
.020
.131
031
43
Min
. Deb
t Ser
vice
Cov
erag
e R
atio
Stag
e-1
1.0
1.1
0.9
1.0
1.1
0.9
0.1
0.1
0.1
-0.6
1.1
1.0
1.1
0.9
1.0
1.1
0.9
-0.6
1.0
1.0
1.0
0.6
0.5
0.7
0.9
1.8
1.8
Stag
e-2
1.5
1.6
1.4
1.5
1.6
1.4
0.2
0.2
0.2
-0.9
1.5
1.5
1.6
1.3
1.5
1.6
1.3
-0.9
1.5
1.5
1.5
2.3
2.4
2.2
1.2
2.6
2.7
Stag
e-1
& S
tage
-21.
51.
61.
41.
11.
11.
10.
10.
10.
1-0
.91.
51.
51.
61.
31.
11.
11.
1-0
.91.
21.
21.
21.
00.
91.
11.
12.
42.
44
Leve
lised
Pro
duct
ion
Cos
t (¢
/kW
h)
St
age-
18.
127.
778.
4910
.07
9.90
10.2
811
.44
11.3
611
.55
13.0
47.
908.
157.
798.
5310
.10
9.92
10.3
113
.08
7.26
6.89
7.66
9.14
8.94
9.34
11.8
66.
096.
02
St
age-
27.
487.
127.
848.
658.
398.
9110
.34
10.2
110
.48
12.5
97.
487.
497.
137.
868.
668.
418.
9412
.61
6.34
5.96
6.73
7.52
7.25
7.80
11.2
55.
405.
34
St
age-
1 &
Sta
ge-2
7.84
7.48
8.20
9.45
9.24
9.67
10.9
610
.86
11.0
812
.85
7.72
7.86
7.50
8.23
9.47
9.26
9.71
12.8
86.
866.
487.
258.
438.
208.
6611
.59
5.78
5.73
Pow
er T
ariff
for P
PA (¢
/kW
h) a
t P/S
exi
t-
--
--
--
--
--
--
--
--
-7.
707.
328.
099.
859.
6810
.04
12.1
3-
-
�� ��
� �
� �
�� ��
� �
� �
� �
�� ��
� �
� �
�� ��
� �
�� ��
� �
�� ��
� �
�� ��
� �
� �
�� ��
�� ��
�� �� ��
� � �
� � �
�� �� ��
� � �
� � �
� � �
�� �� ��
� � �
� � �
�� �� ��
� � �
�� �� ��
� � �
�� �� ��
� � �
�� �� ��
� � �
� � �
�� �� ��
�� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
�� �� �� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
�� �� �� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� �� �� �� ��
� � � � � � �
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
� � � � � � �
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
�� �� �� �� �� �� ��
� � � � � � �
� � � � � � �
�� �� �� �� �� �� ��
�� �� �� �� �� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� �� �� ��
� � � � � �
� � � � � �
�� �� �� �� �� ��
� � � � � �
� � � � � �
� � � � � �
�� �� �� �� �� ��
� � � � � �
� � � � � �
�� �� �� �� �� ��
� � � � � �
�� �� �� �� �� ��
� � � � � �
�� �� �� �� �� ��
� � � � � �
�� �� �� �� �� ��
� � � � � �
� � � � � �
�� �� �� �� �� ��
�� �� �� �� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� ��
� � �
� � �
�� �� ��
� � �
� � �
� � �
�� �� ��
� � �
� � �
�� �� ��
� � �
�� �� ��
� � �
�� �� ��
� � �
�� �� ��
� � �
� � �
�� �� ��
�� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
�� �� �� �� ��
� � � � �
� � � � �
�� �� �� �� ��
�� �� �� �� ��
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�� �� �� ��
� � � �
� � � �
�� �� �� ��
� � � �
� � � �
� � � �
�� �� �� ��
� � � �
� � � �
�� �� �� ��
� � � �
�� �� �� ��
� � � �
�� �� �� ��
� � � �
�� �� �� ��
� � � �
� � � �
�� �� �� ��
�� �� �� ��
��������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������
����������������������������������������������������������������������
������������������������������������������������������������������������������
���������������
�����������������������
����������������������������������������������������������������������������������������������������������������������������
��������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
������������������������������������������������������������������������������������������������������������������������� �� �� �� �� �������������������� � � � � �������������������� � � � � ��������������������� �� �� �� �� �������������������� � � � � ��������������������������������������� � � � � �������������������� � � � � �������������������� �� �� �� �� ���������������������������������������������������������� � � � � �������������������� � � � � �������������������� �� �� �� �� �������������������� � � � � ��������������������� �� �� �� �� �������������������� � � � � �������������������������������������� �� �� �� �� �������������������� � � � � ��������������������� �� �� �� �� �������������������� � � � � �������������������� � � � � �������������������� �� �� �� �� �������������������������������������� �� �� �� ��
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������
���������������������������������������������������������������������������������������������������������
��������������
����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
��������������
����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
��������������
����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
��������������
����������������������
��������������
����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
���������������
�����������������������
��������������
����������������������
��������������
����������������������
��������������
������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�����������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
�������������������������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
������������������
10 - 34
Table 10.3-11 Total Project Cost and Finance Arrangement for Sihanoukville Combined Cycle Project
1. Subsidiary Loan - 1 (Unit :Million US$)
F/C L/C Total F/C L/C Total F/C L/C TotalConstruction Cost 79.9 16.0 95.9 62.4 8.8 71.2 142.3 24.8 167.1Physical Contingency 3.8 0.6 4.4 3.0 0.4 3.4 6.8 1.0 7.8Price Contingency 8.5 1.6 10.1 10.1 1.4 11.5 18.6 3.0 21.6Duties and Taxes 0.0 24.7 24.7 0.0 18.9 18.9 0.0 43.6 43.6IDC by EDC 7.6 0.0 7.6 5.4 0.0 5.4 13.0 0.0 13.0Associated T/L 9.4 2.4 11.8 0.0 0.0 0.0 9.4 2.4 11.8Total 109.2 45.3 154.5 80.9 29.5 110.4 190.1 74.8 264.9
Amount Portion Amount Portion Amount PortionOfficial Finance Source-A 122.2 79.1% 86.1 78.0% 208.3 78.6%RGC 24.7 16.0% 18.9 17.1% 43.6 16.5%EDC 7.6 4.9% 5.4 4.9% 13 4.9%Total 154.5 100.0% 110.4 100.0% 264.9 100.0%
2. Subsidiary Loan - 2 (Unit :Million US$)
F/C L/C Total F/C L/C Total F/C L/C TotalConstruction Cost inc.IDC 81.7 16.0 97.7 63.7 8.8 72.5 145.4 24.8 170.2Physical Contingency 3.8 0.6 4.4 3.0 0.4 3.4 6.8 1.0 7.8Price Contingency 8.5 1.6 10.1 10.1 1.4 11.5 18.6 3.0 21.6Duties and Taxes 0.0 24.7 24.7 0.0 18.9 18.9 0.0 43.6 43.6IDC by EDC 7.6 0.0 7.6 5.4 0.0 5.4 13.0 0.0 13.0Associated T/L 9.4 2.4 11.8 0.0 0.0 0.0 9.4 2.4 11.8Total 111.0 45.3 156.3 82.2 29.5 111.7 193.2 74.8 268.0
Amount Portion Amount Portion Amount PortionOfficial Finance Source - B 124.0 79.3% 87.4 78.2% 211.4 78.9%RGC 24.7 15.8% 18.9 16.9% 43.6 16.3%EDC 7.6 4.9% 5.4 4.8% 13.0 4.9%Total 156.3 100.0% 111.7 100.0% 268.0 100.0%
3. Overseas Investment Loan + Bank Syndicate Loan (Unit :Million US$)
F/C L/C Total F/C L/C Total F/C L/C TotalConstruction Cost 79.9 16.0 95.9 62.4 8.8 71.2 142.3 24.8 167.1Physical Contingency 3.8 0.6 4.4 3.0 0.4 3.4 6.8 1.0 7.8Price Contingency 8.5 1.6 10.1 10.1 1.4 11.5 18.6 3.0 21.6Duties and Taxes 0.0 11.3 11.3 0.0 8.2 8.2 0.0 19.5 19.5IDC & Financial Fee 8.9 0.0 8.9 6.2 0.0 6.2 15.1 0.0 15.1Associated T/L 9.4 2.4 11.8 0.0 0.0 0.0 9.4 2.4 11.8Total 110.5 31.9 142.4 81.7 18.8 100.5 192.2 50.7 242.9
Amount Portion Amount Portion Amount PortionOverseas Investment Loan 59.9 42.1% 42.2 42.0% 102.1 42.0%Bank Syndicate Loan 39.8 27.9% 28.1 28.0% 67.9 28.0%IPP Own Finance 42.7 30.0% 30.2 30.0% 72.9 30.0%Total 142.4 100.0% 100.5 100.0% 242.9 100.0%
Stage-1 & Stage-2
Stage-1 Stage-2 Stage-1 & Stage-2
Stage-1 Stage-2 Stage-1 & Stage-2
Stage-1 Stage-2
Stage-1 Stage-2 Stage-1 & Stage-2
Stage-1 & Stage-2
Stage-1 Stage-2 Stage-1 & Stage-2
Stage-1 Stage-2
10 - 35
10 - 36
10.4. Conclusion
In the course of the economic and financial analyses, the following conclusions are in-
duced under the current assumed conditions.
(1) Total project cost including the duties and taxes, IDC and other financial fees, and
the associated transmission line from the Site to Kampot is anticipated to be 155
Million US$ for Stage 1 and 110 Million US$ for Stage 2 respectively.
(2) If the natural gas is put into the operation before the 5th year from the commence-
ment of the commercial operation, the good economic and financial performances
are expected. On the other hand, if the diesel oil is fired during the full operation
period, the economic and financial feasibility of the project will not be expected.
(3) Especially, if the natural gas is available from the beginning of the commercial op-
eration, production cost of the project will be much lower than the current pur-
chase price from IPP1 and be less expensive than the power purchase from Viet-
nam in future.
(4) Natural Gas price of 4.0 $/MMBTU seems to be rather conservative in comparison
with the current world market prices15. Therefore, if the natural gas price is avail-
able at less than 4.0 $/MMBTU, more economic and financial attractiveness will
be expected.
(5) Based on the above considerations, Fig.10.4-1 presents the various power costs
related to the EDC activities and results of financial analysis. As shown in
Fig.10.4-1, Sihanoukville C.C. power plant with natural gas firing for full 20 years
operation period presents the lowest cost among the each cost level and is expected
to contribute to reduction of future power tariff of EDC remarkably.
(6) The only issue to be overcome by EDC in order to implement the project seems to
be financial problem. As shown in Attachment 1.4, the current management of
15 According to “2001 World Development Indicators, World Bank”, the average price of natural gas from the year 1998
to 2000 is 2.72 US$/MMBTU at Europe and 2.81 US$/MMBTU in US.
10 - 37
EDC has been suffering from a deficit since 1997. Under the current financial
situation of EDC, it seems to be difficult to bear the IDC, even though the EDC
occupies only 5 % of the total project cost. Since Sihanoukville Combined Cycle
Project requires the huge investment amounted to be around 265 Million US$ and
is the first big project for EDC, the improvement of the EDC management will be
desirable until the implementation of the project.
12
34
56
78
910
Pow
er C
ost
Item
s
Leve
lised
Prod
uctio
n C
ost
for
Siha
nouk
ville
C.C
NG
for 2
0 ye
ars
Ave
rage
Impo
rtPo
wer
Tar
ifffr
om V
ietn
am
Ave
rage
Impo
rtPo
wer
Tar
ifffr
om V
ietn
am
Leve
lised
Prod
uctio
n C
ost
for
Siha
nouk
ville
C.C
NG
for 2
0 ye
ars
Pow
er P
urch
ase
Pric
e fr
omSi
hano
ukvi
lleC
.C N
G fo
r 20
year
s by
IPP
Pow
er P
urch
ase
Pric
e fr
om IP
P-1
in 2
000
Prod
uctio
n C
ost
of E
DC
(PH
N's)
in 1
999
inc.
Pow
er P
urch
ase
from
IPP-
1
Leve
lised
Prod
uctio
n C
ost
for
Siha
nouk
ville
C.C
DO
for 2
0 ye
ars
Ass
umed
Pow
erTa
riff f
rom
2006
onw
ards
Ave
rage
Pow
erTa
riff i
n 20
00
Tax
esW
/O T
axes
W/O
Tax
esW
/O T
axes
W/ T
axes
W/O
Impo
rtD
utie
sW
/O I
mpo
rtD
utie
sW
/ Tax
esW
/ Tax
esW
/O V
AT
W/O
VA
T
Cos
t at
Entra
nce
atPh
nom
Pen
h
Bor
der b
etw
een
Vitn
am a
ndC
ambo
dia
Entra
nce
atPh
nom
Pen
hC
onsu
mer
's en
din
Phn
om P
enh
Con
sum
er's
end
in P
hnom
Pen
hIP
P-1
P/S
Exit
Con
sum
er's
end
in P
hnom
Pen
hC
onsu
mer
's en
din
Phn
om P
enh
Con
sum
er's
end
in P
hnom
Pen
hC
onsu
mer
's en
din
Phn
om P
enh
5.78
6.00
6.10
7.84
9.13
10.9
511
.92
12.8
513
.00
14.5
7
0.00
2.00
4.00
6.00
8.00
10.0
0
12.0
0
14.0
0
16.0
0
12
34
56
78
910
Related Power Cost (c/kWh)
10 - 38
Fig
.10.
4-1
C
ompa
riso
n of
Rel
ated
Pow
er C
ost