110729 P6 Dates and Time Issues

Embed Size (px)

Citation preview

  • 8/2/2019 110729 P6 Dates and Time Issues

    1/17

    Eastwood Harris Pty Ltdr mavera

    Issue Presentation

    Page 1

  • 8/2/2019 110729 P6 Dates and Time Issues

    2/17

    Aim

    The aim of this presentation shows how a P6 user

    may end up with a Actual Start and Actual Finish,

    The problems when this happens,

    ,

    Plus outlining some other P6 Date and Time issues,

    that you may simply follow to recreate the same

    situation.

    Page 2

  • 8/2/2019 110729 P6 Dates and Time Issues

    3/17

    Setting the User Preferences

    From P6User

    Preferences form

    the Time:

    Page 3

  • 8/2/2019 110729 P6 Dates and Time Issues

    4/17

    Create a New Project

    and a Finish on Friday 10 Jan 2014.

    The user does not know that P6 has picked by defaultP6 picks 00:00 as the Start time and Finish time:

    Page 4

  • 8/2/2019 110729 P6 Dates and Time Issues

    5/17

    Create One Activity

    Create a 5 day activity,

    Reschedule,

    You will notice 1 days Negative Float,

    If the Project Finish Date is the 10 Jan there should

    be a Total Float Value of 0:

    Page 5

  • 8/2/2019 110729 P6 Dates and Time Issues

    6/17

    Why One Day Negative Float?

    This is generated because when the time you will is

    displayed you will see the Finish Date and Time is,

    Leaving the User one day less than they expected:

    Page 6

  • 8/2/2019 110729 P6 Dates and Time Issues

    7/17

    Shorten the Duration to One Day,

    Schedule,

    ,Float as one would expect from the displayed datesand Project Finish Date of 10 Jan:

    Page 7

  • 8/2/2019 110729 P6 Dates and Time Issues

    8/17

    Update the Activity as Complete Assume the Activity actually started and finished on 2

    Jan.

    Check the Actual Start box and then set to a date to

    ,

    Then check the Actual Finish Date to the 2 Jan,

    on midnight of the same day with an actual durationof zero days:

    Page 8

  • 8/2/2019 110729 P6 Dates and Time Issues

    9/17

    Preferences

    Now go to the

    User Preferences

    Time in 24 hourformat:

    Page 9

  • 8/2/2019 110729 P6 Dates and Time Issues

    10/17

    Back to the Activity Now back to the activity,

    You will see that P6 selects 00:00 (Midnight at the Start

    of the Day) as a default time when updating tasks whene user oes no s ow e me n e ser re erences:

    Page 10

  • 8/2/2019 110729 P6 Dates and Time Issues

    11/17

    s ea ng ega ve oaCalculations Add another 5 day activity, schedule, display the Total

    Float Column and Total Float bar using the Primavera Bar.

    The Total Float value for Activity A1000 is Null but thereis a Total Float Bar assi ned to this com leted activit

    which would not normally be expected:

    Page 11

  • 8/2/2019 110729 P6 Dates and Time Issues

    12/17

    Assign Suspend and Resume A similar roblem occurs with Sus end and Resume

    The picture below had the Suspend and Resume

    Dates set with the time hidden,

    One would expect the Actual Duration to be 2 days,not 1 day, from the Actual Start and Suspend Date:

    Page 12

  • 8/2/2019 110729 P6 Dates and Time Issues

    13/17

    Now we can see the issue when the time is displayed,

    Suspend and Resume times have been selected at

    00:00 when the time is hidden:

    Page 13

  • 8/2/2019 110729 P6 Dates and Time Issues

    14/17

    er uspen an esume ssues When time is displayed you need to always check the

    uspen an esume mes,

    Suspend is often set at 08:00 and should be 16:00, ,as per the picture below,

    Resume is often set at 16:00 and should be 08:00,

    people do not go to work last thing in the afternoonto start work, which in the experience of the authorsometimes ha ens:

    Page 14

  • 8/2/2019 110729 P6 Dates and Time Issues

    15/17

    Solution

    To prevent all these

    issues a user must

    time when scheduling,

    Also I recommend at

    the user also displaysthe Duration Label

    -may easily see if thereare any non round

    .

    Page 15

  • 8/2/2019 110729 P6 Dates and Time Issues

    16/17

    Questions

    Any Date and Time questions.

    Page 16

  • 8/2/2019 110729 P6 Dates and Time Issues

    17/17

    Eastwood Harris Pty LtdPrimavera P6

    P6 DATE AND TIME

    ISSUE PRESENTATIONCopyright of Eastwood Harris Pty Ltd

    Page 17