12 Contractor HSE Management

Embed Size (px)

DESCRIPTION

Health, Safety and Environment Management

Citation preview

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Overview and Introduction to the Chevron CHESM Process

    Philip Gallaway Chevron Energy Technology Company Seismic Acquisition Services Team IAGC / OGP HSE & Security Forum CGGVeritas Offices, Massy, France 27-28 September, 2011

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    What is CHESM?

    CHESM Contractor Health, Environment and Safety Management It is a standardized Chevron Operational Excellence process which

    Establishes expectation that contractors working across all SBUs are evaluated and managed by the same process.

    Applies to all contractors regardless of work location, scope of work, project duration, total cost or contractor experience.

    The process is used to qualify contractors by establishing minimum HES requirements each contractor should meet to work at Chevron.

    Process to ensure that Contract Companies have safety processes in place before work begins for Chevron.

    2

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    3

    CHESM Implementation Objectives

    Promote Injury & Incident Free expectation / culture among contractor workforce.

    Clarify Chevron HES expectations. Build teamwork between Chevron and contractors. Support HES capacity building (local content development). Ensure contractor HES capability and performance is properly

    documented.

    Ensure alignment with Chevron OE processes being implemented Worldwide.

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Scope of CHESM

    This process will be applied before any new contracts are issued or existing contracts renewed.

    This process will be used to develop Bid List and/or award Projects.

    Applies for the term of the contract.

    4

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    5

    CHESM Process Key Elements

    World class contractor safety begins with: Leadership Roles & Accountability

    Active Contractor Engagement

    By establishing a 5-stage process that include: 1. Business Planning

    2. Contractor Qualification and Selection

    3. Pre-Job Reviews (Site visits, pre-mob planning, mitigation plans, kick off meetings, site audits, training, etc.)

    4. Work in Progress (Interim reviews and field inspections)

    5. End of Contract Evaluation

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    CHESM Process Key Requirements

    A set of key performance indicator targets shall be established for each contract.

    Chevron shall identify potential HES risks associated with contracting needs.

    All selected contractors shall be pre-qualified using the standard procedure.

    Pre-job activities shall be held for each contract before start of work.

    Interim contractor performance reviews shall be conducted at least once a year.

    End of contract performance evaluations shall be completed for every contract at the end of the contract period.

    6

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    CHESM 5-Step Process

    Business Planning Qualification Selection Pre-Job Review Work In Progress End-Of-Contract Evaluation

    7

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Business Planning

    Purpose: Provide early detection of HES risks. Ensure that a mitigation plan is in place to address the

    risks.

    8

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Qualification and Selection

    Contractor HES Qualification Key Elements are: Initial Communication of HES expectations Collect and Update data Evaluate Contractors Qualification Questionnaire Assign HES Rating to a Contractor Data Management and Feedback

    9

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Qualification and Selection CHESM Contractor Rating and Selection Requirements

    10

    Rating Selection Requirements

    A Unrestricted use.

    B Unrestricted use. Check a higher-rated supplier.

    C Pre-job meeting; mitigation plan required

    D Pre-job meeting; mitigation plan documented in database; management approval from BU General Manager of Operations (or designee) in writing; trained HES personnel on-site during work.

    F Cannot be used without BU General Director (or designee) approval. All requirements for a D rated contractor apply.

    ND * Contractor has not completed the annual Contractor HES Evaluation Questionnaire update. Do not hire until this deficiency is rectified.

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Pre-Job Review

    The HES Management Pre-Job Review procedure ensures that contractors have the necessary procedures, risk identification and mitigation plans in place before work starts, in order to do the work safely.

    The pre-job review consists of the following elements: Pre-job meeting

    Project/Job safety plan

    Pre-mobilization review

    New contractor orientation program

    Site-specific orientation

    11

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    CHESM Work-In-Progress Procedure

    Work-In-Progress Procedure Includes: Interim Performance Review Field Inspection Management Field Visits Joint Safety Meetings Tailgate/Toolbox Meeting Contractor Forum Contractor Improvement Teams Related OE Processes

    12

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    End-Of-Contract Evaluation

    The purpose of the end-of-contract evaluation is to: Formally review the health, environment and

    safety (HES) performance of a contractor at the completion of the contract

    Capture lessons learned and best practices for improving HES performance of future work and future contractor selection

    13

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Application to Chevron Seismic Acquisition Programs

    All seismic operations are considered high-risk and the CHESM process applies

    How are we implementing this on seismic crews: Pre-job field visits to review ongoing operations

    In-depth review of HES plans, work processes, programs

    Pre-mob planning phase to insure that all HES requirements are in line with Chevron standards

    14

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Application to Chevron Seismic Acquisition Programs (cont)

    Challenges with the CHESM process: Applied in various ways across Chevron BUs

    Currently does not contain seismic HSE or operational reviews

    Adapted by the seismic acquisition team

    Non-standard contractor management processes are not easily identified

    Joint ventures

    Subcontractor relationships

    Crew to crew variations

    15

  • 2011 Chevron U.S.A. Inc. All rights reserved .

    Questions?

    16

    Overview and Introduction to the Chevron CHESM ProcessWhat is CHESM?CHESM Implementation ObjectivesScope of CHESMCHESM Process Key ElementsCHESM Process Key RequirementsCHESM 5-Step ProcessBusiness PlanningQualification and SelectionQualification and SelectionCHESM Contractor Rating and Selection RequirementsPre-Job ReviewCHESM Work-In-Progress ProcedureEnd-Of-Contract EvaluationApplication to Chevron Seismic Acquisition ProgramsApplication to Chevron Seismic Acquisition Programs (cont)Questions?