Upload
jose-miguel-lagumbay
View
264
Download
4
Embed Size (px)
DESCRIPTION
Health, Safety and Environment Management
Citation preview
2011 Chevron U.S.A. Inc. All rights reserved .
Overview and Introduction to the Chevron CHESM Process
Philip Gallaway Chevron Energy Technology Company Seismic Acquisition Services Team IAGC / OGP HSE & Security Forum CGGVeritas Offices, Massy, France 27-28 September, 2011
2011 Chevron U.S.A. Inc. All rights reserved .
What is CHESM?
CHESM Contractor Health, Environment and Safety Management It is a standardized Chevron Operational Excellence process which
Establishes expectation that contractors working across all SBUs are evaluated and managed by the same process.
Applies to all contractors regardless of work location, scope of work, project duration, total cost or contractor experience.
The process is used to qualify contractors by establishing minimum HES requirements each contractor should meet to work at Chevron.
Process to ensure that Contract Companies have safety processes in place before work begins for Chevron.
2
2011 Chevron U.S.A. Inc. All rights reserved .
3
CHESM Implementation Objectives
Promote Injury & Incident Free expectation / culture among contractor workforce.
Clarify Chevron HES expectations. Build teamwork between Chevron and contractors. Support HES capacity building (local content development). Ensure contractor HES capability and performance is properly
documented.
Ensure alignment with Chevron OE processes being implemented Worldwide.
2011 Chevron U.S.A. Inc. All rights reserved .
Scope of CHESM
This process will be applied before any new contracts are issued or existing contracts renewed.
This process will be used to develop Bid List and/or award Projects.
Applies for the term of the contract.
4
2011 Chevron U.S.A. Inc. All rights reserved .
5
CHESM Process Key Elements
World class contractor safety begins with: Leadership Roles & Accountability
Active Contractor Engagement
By establishing a 5-stage process that include: 1. Business Planning
2. Contractor Qualification and Selection
3. Pre-Job Reviews (Site visits, pre-mob planning, mitigation plans, kick off meetings, site audits, training, etc.)
4. Work in Progress (Interim reviews and field inspections)
5. End of Contract Evaluation
2011 Chevron U.S.A. Inc. All rights reserved .
CHESM Process Key Requirements
A set of key performance indicator targets shall be established for each contract.
Chevron shall identify potential HES risks associated with contracting needs.
All selected contractors shall be pre-qualified using the standard procedure.
Pre-job activities shall be held for each contract before start of work.
Interim contractor performance reviews shall be conducted at least once a year.
End of contract performance evaluations shall be completed for every contract at the end of the contract period.
6
2011 Chevron U.S.A. Inc. All rights reserved .
CHESM 5-Step Process
Business Planning Qualification Selection Pre-Job Review Work In Progress End-Of-Contract Evaluation
7
2011 Chevron U.S.A. Inc. All rights reserved .
Business Planning
Purpose: Provide early detection of HES risks. Ensure that a mitigation plan is in place to address the
risks.
8
2011 Chevron U.S.A. Inc. All rights reserved .
Qualification and Selection
Contractor HES Qualification Key Elements are: Initial Communication of HES expectations Collect and Update data Evaluate Contractors Qualification Questionnaire Assign HES Rating to a Contractor Data Management and Feedback
9
2011 Chevron U.S.A. Inc. All rights reserved .
Qualification and Selection CHESM Contractor Rating and Selection Requirements
10
Rating Selection Requirements
A Unrestricted use.
B Unrestricted use. Check a higher-rated supplier.
C Pre-job meeting; mitigation plan required
D Pre-job meeting; mitigation plan documented in database; management approval from BU General Manager of Operations (or designee) in writing; trained HES personnel on-site during work.
F Cannot be used without BU General Director (or designee) approval. All requirements for a D rated contractor apply.
ND * Contractor has not completed the annual Contractor HES Evaluation Questionnaire update. Do not hire until this deficiency is rectified.
2011 Chevron U.S.A. Inc. All rights reserved .
Pre-Job Review
The HES Management Pre-Job Review procedure ensures that contractors have the necessary procedures, risk identification and mitigation plans in place before work starts, in order to do the work safely.
The pre-job review consists of the following elements: Pre-job meeting
Project/Job safety plan
Pre-mobilization review
New contractor orientation program
Site-specific orientation
11
2011 Chevron U.S.A. Inc. All rights reserved .
CHESM Work-In-Progress Procedure
Work-In-Progress Procedure Includes: Interim Performance Review Field Inspection Management Field Visits Joint Safety Meetings Tailgate/Toolbox Meeting Contractor Forum Contractor Improvement Teams Related OE Processes
12
2011 Chevron U.S.A. Inc. All rights reserved .
End-Of-Contract Evaluation
The purpose of the end-of-contract evaluation is to: Formally review the health, environment and
safety (HES) performance of a contractor at the completion of the contract
Capture lessons learned and best practices for improving HES performance of future work and future contractor selection
13
2011 Chevron U.S.A. Inc. All rights reserved .
Application to Chevron Seismic Acquisition Programs
All seismic operations are considered high-risk and the CHESM process applies
How are we implementing this on seismic crews: Pre-job field visits to review ongoing operations
In-depth review of HES plans, work processes, programs
Pre-mob planning phase to insure that all HES requirements are in line with Chevron standards
14
2011 Chevron U.S.A. Inc. All rights reserved .
Application to Chevron Seismic Acquisition Programs (cont)
Challenges with the CHESM process: Applied in various ways across Chevron BUs
Currently does not contain seismic HSE or operational reviews
Adapted by the seismic acquisition team
Non-standard contractor management processes are not easily identified
Joint ventures
Subcontractor relationships
Crew to crew variations
15
2011 Chevron U.S.A. Inc. All rights reserved .
Questions?
16
Overview and Introduction to the Chevron CHESM ProcessWhat is CHESM?CHESM Implementation ObjectivesScope of CHESMCHESM Process Key ElementsCHESM Process Key RequirementsCHESM 5-Step ProcessBusiness PlanningQualification and SelectionQualification and SelectionCHESM Contractor Rating and Selection RequirementsPre-Job ReviewCHESM Work-In-Progress ProcedureEnd-Of-Contract EvaluationApplication to Chevron Seismic Acquisition ProgramsApplication to Chevron Seismic Acquisition Programs (cont)Questions?