Upload
kalyan-s-meduri
View
217
Download
0
Embed Size (px)
Citation preview
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 1/25
FINANCING OF SOLAR PV
POWER PROJECTS
Presentation by
K.S.Popli
Indian Renewable Energy Development Agency
25th January 2011
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 2/25
Agenda
• Mission Objectives
• Current status of schemes
• Issues in financing Solar Projects
• Sensitivity analysis
• Existing Solar PV projects in India
• Actual Generation data
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 3/25
Mission Objectives
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 4/25
Mission Objectives
To achieve grid parity by 2022 and parity with coal based thermal
power by 2030.
To achieve JNNSM targets in 3-phases from 2010 to 2022.
Jawaharlal Nehru National Solar Mission has been launched under the
National action Plan on Climate Change with the objective :
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 5/25
Mission Targets
Application
SegmentPhase - I Phase-II Phase- III
2010-13 2013-17 2017-22
Utility grid power 1,000-2,000MW 4000-10,000 MW 20,000 MW
Off- grid
Applications 200 MW 1,000 MW 2,000 MW
Solar Thermal
Collectors Area 7 million Sqm 15 million Sqm 20 million Sqm
Manufacturing Base -- -- 4,000-5,000 MW
Solar Lighting
Systems -- -- 20 million
Solar RPO 0.25% -- 3%
A 3- phase approach has been formulated
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 6/25
Current status of schemes
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 7/25
NVVN Grid connected plants- Current Status
Migration Projects
• 84 MW capacity projects (54 PV & 30 Thermal) allocatedunder Migration part of 1000 MW capacity.
• Total 16 projects selected under Migration scheme
• PPA signed on 15th October 2010.
• Financial closure was to be achieved by 15th January 2011.
The deadline has been extended to 15th February 2011.
• One project of 2 MW already commissioned.
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 8/25
NVVN Grid connected plants- Current Status
Migration Projects
• As per information, around 5-6 projects of approximately 21 MW capacity has tied-up for debt financing.
(Mahagenco sanctioned by IREDA)
• Azure power of 2 MW already commissioned and part capacity of Acme is in advanced stages ofcommissioning.
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 9/25
NVVN Grid connected plants- Current Status
New projects
• PPA for first batch already signed.• 150 MW SPV (30 projects)
• 470 MW Solar Thermal (7 projects)
• Allocation of approx. 300 MW SPV to be done in secondbatch (2011-12)
• The highest discount offered on CERC tariff for 150 MW of Solar PV is Rs.6.26 / unit which translates to a price perunit of (17.91 - 6.96) = Rs.10.95
• The highest discount offered on CERC tariff for 500 MW of Solar Thermal is Rs. 4.26 / unit which translates to a price /unit of (15.31 - 4.82) = Rs.10.49
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 10/25
IREDA- Rooftop and other Small Solar Projects
Current Status
• 78 projects aggregating to 98.05 MW selected in 12 states.
• PPAs for all the projects signed with state utilities in August, 2010.
• In these projects no separate deadline for financial closure.
• Projects to be implemented within 12 months of issuance of RegistrationCertificate. Further, grace period of 6 months has been provided with penalties.
• Tariff ranges between Rs 15.32/kWh (Rajasthan) to 18.45/ kWh (TamilNadu) in various states for PV.
• IREDA received status report of around 40 projects• Debt tie-up done : 7 projects• EPC contractor finalized: 13 projects• Commissioning anticipated by June 2011: 18 projects
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 11/25
Issues in Financing Solar Projects
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 12/25
Issues in Financing Solar Projects
• Main concern of developers was allocation of projects.
• After allocation few developers have approached FIs before completingdue diligence
• Without finalizing project cost : Some project developers have indicatedCERC determined project cost.
• Without finalizing EPC contractor.
• EPC contracts and O & M contracts
• Warranties/ Guarantees from the contractors
• Experience of EPC/ O&M contractors.• Financial Strength of contractors.
• LDs for delay in implementation
• Generation guarantee during O&M period
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 13/25
Issues in Financing Solar Projects
• Module Suppliers
• Installed capacity of module supplier
• Production capacity of module supplier.
• Performance track record of modules/cells.• Limited degradation warranties.
• Compliance to relevant IEC Standards.
• Site specific data
• Irradiance data
• Maximum wind velocity data• Temperature
• Mounting Structures for modules
• Evacuation arrangement
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 14/25
Issues in Financing Solar Projects
• Other Issues:
• Partial Commissioning not allowed in NVVN and delay in meetingcommissioning timelines increases lenders risk.
• Large number of experienced EPC contractors shall be required toimplement projects in time.
• Inadequate Operation and Maintenance experience- Long term
O&M contracts.
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 15/25
Sensitivity Analysis
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 16/25
Sensitivity for Migration Scheme
Interest Rate (% per annum) Equity IRR (post- tax) Average DSCR10.50 13.81 1.4811.00 13.47 1.4611.50 13.14 1.4412.00 12.81 1.4312.50 12.5 1.41
ASSUMPTIONSProject Cost Rs 14 crores /MW
Tariff Rs 17.91/ unitRepayment Period 10 years
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 17/25
Sensitivity for NVVN new projects
ASSUMPTIONSProject Cost Rs 13.5 crores /MWCost of Debt 12% per annum
Repayment Period 10 years
Tariff (Rs. Per unit) Equity IRR (post- tax) Average DSCR10.90 3.24 0.93
11.25 3.74 0.95
11.50 4.10 0.97
11.75 4.46 0.99
12.00 4.82 1.00
12.25 5.18 1.02
12.50 5.55 1.04
12.75 5.91 1.06
13.00 6.28 1.08
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 18/25
Existing Solar PV Projects in India
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 19/25
Existing Solar PV ProjectsPlant* Location Size Finance Cost Tech
Asansol WB 2 MW PFC 35 Cr Crystalline
Azure Amritsar 2 MW IFC + FDI Crystalline
KPCL Kolar 3 MW Self 58 Cr Crystalline
KPCL Belgaum 3 MW Self Crystalline
Moser Baer Sivaganga 5 MW IDBI + IFC 70 Cr Thin Film
MahaGenco Chandrapur 1 MW Self 12.5 Cr Thin Film
Reliance Jodhpur 5 MW Crystalline
NDPL Delhi 1 MW Crystalline
These plants are eligible for GBI from MNRE
* Illustrative List
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 20/25
FIs/ banks active in financing solar
projects• Power Finance Corporation
• Rural Electric Corporation
• IREDA
• State Bank of India
• Yes Bank
• Asian Development Bank
• IOB
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 21/25
Actual Generation Data
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 22/25
Actual Generation from Commissioned Projects
1 MW Azure Solar PV Plant at Amritsar, Punjab
Technology Mono- Crystalline
Month Estimate as per DPR (kWh) Actual Generation
Dec 2009 180000 96975
Jan 2010 160000 60795
Feb 2010 160000 118890
Mar 2010 185000 152715
Apr 2010 185000 149265
May 2010 200000 132780
Jun 2010 190000 144975
Jul 2010 170000 128970
Aug 2010 160000 116190
Projected CUF 24.27%
Actual CUF16.76%
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 23/25
Actual Generation from Commissioned Projects
Analysis of 1.1 MW WBGEDCL SPV Plant at Asansol, West Bengal
Technology Poly- Crystalline
Month Actual Generation
Nov 2011 92400
Dec 2011 85000 Jan 2011 109400
Feb 2011 101300
Mar 2011 116600
Apr 2011 101300
May 2011 98600
June 2011 88600
July 201187000August 2011 84900
September 2011 82700
October 2011 90600
Actual CUF- 11.81%
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 24/25
Actual Generation from Commissioned Projects
Analysis of 1 MW MAHAGENCO Plant at Chandrapur, Maharashtra
Technology Thin Film
Month Actual Generation
June 2010 106860.00
July 2010 96550.00Aug 2010 105890.00
Sept 2010 100390.00
Oct 2010 114770.00Nov 2010 105660.00Dec 2010 112570.00
Actual CUF- 14.53%
8/7/2019 12 - KS Popli
http://slidepdf.com/reader/full/12-ks-popli 25/25
Thank You