Upload
magdyamdb
View
219
Download
0
Embed Size (px)
Citation preview
7/29/2019 13828 Spa Newslr
1/8News 1
NewsS T R U C T U R A L P R E C A S T A S S O C I A T I O N
SUMMER 2007
this issuep2 a towering s tory, Leeds
car park; p3 stairs lose
weight; p4 innovative
residential scheme;
p5 luxury hotel on Jersey;
p6 Trafford Centre expansion;
p7 saving on programme,
Manchester hotel; p8
Liverpool arena.
7/29/2019 13828 Spa Newslr
2/8News 2
Increasing Leedsparking
As part of the development of a new Oncology Wingat St James University Hospital in Leeds, a new carpark was required to replace existing surface car parking
and increase on-site parking. The new 1278-space
multi-storey car park, designed by Hill Cannon (UK) LLPwith external architecture by Pulmann Associates, is a
seven-storey structure built by SCC Limited from precast
reinforced concrete.
Tower of strength
The Floors and Precast division of Hanson Building Productshas completed the manufacture and installation for CivicEnvironmental of a variety of structural precast concrete
components ranging in weight from 2.5 to 17 tonnes for
incorporation into a digester tower. The tower at Thornley in Co
Durham, which will be operated by Premier Waste, is the first
of its type to be built in the UK. The precast components are a
combination of curved wall panels, floor slabs and large precast
concrete beams for supporting the intermediate floors and roof
of the tower.
The form of construction uses a
precast portal frame, arranged
in a modular layout dictated
by the requirements of parking
bays and access aisles, giving a
clear span across the parking
bays. Vehicle circulation around
the car park is via Hill Cannons
patented VCM circulation system
(vertical circulation module).
External elevations, which were
resolved to provide an aesthetic
finish while maintaining the
requirement for natural cross-
ventilation, comprise a mixture
of precast concrete panels faced
with terracotta tiles, stainless-
steel mesh and galvanised-mesh
screens. The frame consists of
precast reinforced beam-and-
column units connected by
grouted rebar joints. The top
section of the beam was cast
in-situ, forming a monolithic
connection between precast
slabs, beam and column. Precast
retaining walls, stair cores
and perimeter walls were all
designed to be supported off
the main structure. The frame is
built off piled foundations, piles
extending around 17m.
The purpose of this prototype
tank is to sanitise up to 150
tonnes of domestic refuse every
12 days. At the end of the
process, it is sorted and recycled,
eliminating the need for large-
volume landfill.
The completed main structure
shapes up at approximately 16m
in diameter by 16.5m tall. The
precast concrete components
were manufactured at Hanson
Building Products Derby and
Somercotes sites and erected
on site over four weeks. Theuse of off-site precast concrete
elements and shorter installation
times were key to the clients
choosing this particular build
method: another plus was the
overall faster construction
compared to previously built
steel tanks.
7/29/2019 13828 Spa Newslr
3/8News 3
The Chairmans View
by Gerry Feenan
Having only recently been
appointed chairman I
appreciate this opportunity
to acknowledge the very
significant contributions made
by my predecessor John Milner
and our secretary Clive Budge
who retired on the 31st May.
John is featured on page 4 with
Paul Whitham who succeeds
him as managing director
at Ebor Concretes and Clive
is pictured on page 8 with
Norman Brown who has taken
over as head of engineering
services at British Precast.
I am delighted to welcome
Aggregate Industries as a full
member of the association,
contact details are on page 8.
A major change within the
membership is the acquisition
of Buchan Concrete Solutions
by Roger Bullivant Ltd, see
page 7. RBLs optimism for the
future of precast is matched by
Milbanks decision to double
the number of 150m casting
beds at its new Brandon facility.
This confidence is well founded
and illustrated by the wide
variety of projects proving the
versatility of precast concrete,
featured in this issue.
Savings all round
Savings have already been made even before shoppers step inside the new shopping centreunder construction in Livingston, Scotland. Fortunately, with the co-operation of structural steelspecialist Severfield Reeve Structures, the design team agreed to Ebors proposal to coffer the soffit
of the stair which leads to a 30% reduction in the unit weight.
Owing to the geometry and
clear span requirements, the
original design for the 24
precast concrete stair flights
suggested a unit weight of 15
tonnes. However, individual
items weighing over 12.5 tonnes
exceeded both the overhead
crane capacity in the casting
hall and storage area at Ebors
Ripon works.
Further savings included a
halving of transport costs as two
flights instead of one per load
was possible and the use of site
cranage to handle and place the
10.5-tonne reduced-weight units
without the need and expense of
organising heavier cranage over
the extended delivery period.
However, to produce units with
such a deep coffer, special jacks
and compressed air systems
were incorporated into the
steel soffit former, easing the
demoulding operation and
reducing the adhesion stresses
placed on the early-age concrete
to a minimum.
The solution clearly
demonstrates the benefits of
early involvement and close
communication between
all parties involved in the
construction process.
London School of Economics
Alan Baxter & Associates are designing a new Academic Building
for the London School of Economics in Lincolns Inn Fields, with
Geoffrey Osborne Limited as the main contractor and Grimshaw
as the project architect. The scheme requires large column free
spaces at the lower levels to accommodate new lecture theatres.
This has been achieved by hanging floors from a storey deep
truss at roof level and with the introduction of eight 19m long
precast concrete beams, each weighing 18 tonnes, which form
the roof to the main lecture theatre.
The units, manufactured and installed by Thorp Precast, have a high
quality acid etch finish and will be one of the main architectural
features. A 500 tonne mobile crane with a 50m luffing jib was
used to install the units during a weekend road closure.
7/29/2019 13828 Spa Newslr
4/8News 4
Precast doing the rounds
B
isons crosswall and hollow-core concrete products have been specified by Countryside
Properties for an innovative project at Sport City in Manchester. The development of two
circular buildings, one ten and the other seven storeys, will accommodate 111 one- and two-
bed apartments. Bisons design and production flexibility is evident as the team have worked
to integrate their standard hollow-core and crosswall products into the circular building, while
achieving the essential structural tie detail necessary to stitch the building together.
Handingover thereins
Anew chapter for Ebor
Concretes opens on1 July 2007 as John Milner
(left) relinquishes his role as
managing director to Paul
Whitham. Determined to
complete his 50 years service
with Ebor, John will continue
to support Paul part time for
the next 1218 months as a
consultant.
In welcoming Paul to the board,
John is confident that it will
be business as usual following
successful bedding in during
the past three months. Paul is
a Chartered Civil Engineer with
over 20 years in the precast
concrete industry. He has held
a variety of operational and
commercial roles in Charcon
Tunnels, Costain Building
Products and Tarmac Precast.
Paul commented I am delighted
to join Ebor and am looking
forward to continuing the good
work that John has done over
the years in making Ebor one of
the countrys leading suppliers of
high-quality bespoke structural
precast.
Trevor Stack, construction
director at Countryside
Properties, comments: This was
a challenging project conceived
and designed to look completely
different and push design
boundaries. We specified Bisons
products as its team was able
to offer high-quality products
quickly and provided practical
solutions to practical issues,
such as bespoke models for the
external wall panels. The delivery
and high quality finish of the
products have been impressive,
and the project is moving along
quickly thanks to additional
aids such as the lifting hooksprovided by Bison. I expect the
build to be completed within the
estimated 13-week time scale.
This speed of construction
demonstrates how concrete
effectively meets the demands
of off-site construction in terms
of delivery, flexibility and quality.
Concrete was specified for itsstrength, durability and inherent
fire resistance. Total quantities
for the project: walls: 10,500m2 in
700 units, floors: 8500m2 in 1900
units, stairs: 60 flight and landing
units.
It is expected that the phase will
be completed by September
2007, with flats ready the
following month. Clients
engineer: Scott Hughes Design.Bisons engineer: Hadfield
Cawkwell Davidson. Architect:
Countryside Properties Ltd.
Hansonaquires
StructhermHanson Building Products has
announced the aquisition of
Structherm based in Meltham,
West Yorkshire. Established in
1983 the company designs,
manufactures and erects
precast concrete walling
systems for the housing
sector, both low and high
rise, education projects andcommercial buildings.
7/29/2019 13828 Spa Newslr
5/8News 5
Fast build bedroomsfor Jersey hotel
This prestigious and impressive five-star Radisson arrow-shaped hotel at the entrance to the St Helier marina facesdirectly out to sea and will be one of the first to be seen when
approaching the marina. The joint-venture scheme by Jersey
Waterfront Hotel Developments Ltd and Ironbridge Estates
is being built by Cameron Building Contractors, with Bell and
Webster Concrete supplying 758 precast components each
weighing up to 12.2 tonnes. The 12-week schedule included the
construction of 166 bedrooms, including placing all bathroom
pods, two four-storey stair wells and lift shafts.
After constructing the first-floor steel frame and the connecting
knuckle to form the arrow shape, Cameron Building opted for Bell
and Websters Fast Build Rooms for the bedrooms, stair and lift areas.
Factory-engineered concrete was used for all walls, floors and the
inner skin of the external walls, windows being full-height floor-to-
ceiling. All the precast concrete wall surfaces within the bedrooms
were ready for final preparation for the decorator.
Main contractor Cameron Building
undertook responsibility for
transport and deliveries, the trip
taking three days from loading at
the precast factory in Grantham,
through delivery to the sea freight
terminal at Portsmouth, and then
by ferry to Jersey.
On site, panels were craned
into position, all joints being
designed to enable connectionsto be made with limited use of
grout and with hidden fixings to
hide the joints. As wall units were
positioned, fully fitted bathrooms
166 in all, weighing up to six
tonnes were simultaneously
craned into place. The pods were
installed to create a vertical riser
between rooms for mechanical
and electrical services.
With bedroom walls, floors and
pods in place, following trades
could begin on the first-fix. And
with cladding effectively off the
critical path (the structure already
had the inner skin of the external
wall as well as a concrete lid)
external cladding began. The only
penetrations through the top
slab were the vertical risers, which
were capped with polystyrene
and a thin layer of concrete to be
core-drilled: these prevent the
water ingress, which could affectthe following tradesmen. Once
the windows were installed, the
structure has a high degree of
weather-tightness, allowing other
trades to follow on closely behind.
Internal decoration consists of
a sprayed surface finish applied
directly to the concrete walls. In
other hotels constructed by this
technique, the factory-engineered
concrete walls are painted with
emulsion and carpet is laid
directly onto the floors.
7/29/2019 13828 Spa Newslr
6/8News 6
Expansion at TheTrafford Centre
Following on from its previous extensive and successfulwork at the Trafford Centre, Trent Concrete has secured thecontract for the design, detailing, manufacture and installation
of the reconstructed stone cladding and features on the Barton
Square Development, part of the new expansion programme at
the Trafford Centre. The development consists of four L-shaped
blocks arranged to form a central square, mall and colonnade.
Bullivantembraces Buchan
F
oundation engineering company Roger Bullivant Ltd has
extended its specialist precast concrete division with theacquisition of Cheshire-based Buchan Concrete Solutions from
international property and services company AMEC. RBL intends
to secure the future of the Buchan factory and its 170 employees
and invest further in the award-winning business.
Trents 6.4m contract includes
a variety of unique precast
elements, some weighing up
to 24 tonnes. On the external
elevations, there are storey-
height pilasters typically 8m high
(the structure already had the
inner skin of the external wall
as well as a concrete lid) 1m
wide, cornice units typically 8.8m
long 1.4m high, a band course,and a 10.8m long plinth 445mm
high. External corner towers
consist of large raking ashlars,
each 8m high 10m girth overall
with brick-faced units above
typically 2.2m wide 6m high,
and cornice units.
The shop fronts on the internal
malls use double part-brick-
faced pilaster/cornice units
typically 2.6m wide and 8m high,
cornice units and support beams.
Tapered circular columns 900mm
diameter and 7.2m high withbeam-and-hollow core flooring
above form the colonnade
and a central coliseum feature
Said Steve Parker, production
director at RBL, who will manage
the Buchan operation in addition
to his existing role Buchan is
a well-established company
with an excellent reputationand a good client base. It is
already in the market place we
want to expand into prisons,
schools and hotels and the
acquisition will make this
transition smoother. With the
support of both the Buchan and
the RBL precast teams we shall
see the turnover and consequent
success of the business continue
to grow.
Last year, Roger Bullivant
recorded a turnover of 110m,
delivering solutions in piling,
mini-piling, house foundations,
ground improvement and
special precast concrete, from
manufacturing facilities at its
Burton-on-Trent headquarters
as well as two other sites. With a
turnover in excess of 30 million,
Buchan supplies precast concrete
to the civil engineering and
building construction markets.
Recent projects have included
prisons, hotels, apartments,
student accommodation, schools
and stadiums. In addition,
the company offers a range
of standard products for the
civil engineering and buildingindustry, including tunnel linings,
shaft segments and jacking
pipes.
Newcrosswall
constructionguide
Copies of Crosswall construction:
High performance buildingsusing concrete frames and
cladding can be downloaded
from www.concretecentre.com
23m radius and 10m high is
constructed from 500 square
columns 7.2 m high, faced with
granite, and a curved cornice 8m
long and 1.4m high arranged in a
double line.
The units are cast in a buff-
coloured reconstructed stone
mix with an acid-etched finish.
Trent started the design and
detailing process in late summer
2006, manufacturing began in
November and will continue
through 2007. Site works started
on 26 March.
Principal contractor: Bovis
Lendlease Ltd; Concept
architect: Chapman Taylor;
Architect: Leach Rhodes Walker;
Structural engineer: Connell Mott
MacDonald.
7/29/2019 13828 Spa Newslr
7/8News 7
Reducing theprogramme
W
ith speed of the essence for a new distribution centre for
Hellioslough being built at Wynyard, Stockton on Tees,
main contractor Tolent Construction Ltd approached Roger
Bullivant Ltd.
Concrete visionFor Milbank Floors, last years new factory which was built fromits own precast concrete products was only a beginning. Bymid summer, the Brandon site aims to meet an ever-expanding
demand by doubling the number of its 150m casting beds for
prestressed hollow-core flooring, and the Brandon site is also set to
further the companys vision of the complete precast solution by
making wall panels its next area of growth.
Investment in new curing chambers, casting pallets and upright mouldswill increase capacity for at least 50 grey concrete and concrete-brick
panels a day by the end of the year.
Crowne Plaza,Manchester
This new Crowne Plaza Hotel in Manchester incorporates 228bedrooms, restaurants, meeting rooms and a health club.
RBs dock leveller pits system
is constructed from precast
reinforced concrete sections
that are combined to form a
pit into which a wide range of
dock levellers can be installed.
This allows the main floor slab
to be laid faster. The companys
prowall panels span between
dock pits, ensuring rapid erection
and eliminating the requirement
for traditional areas of cladding
and steel post/rails. Panels are
supplied complete with integral
insulation to provide a U-value of
0.27W/m2K.
The concrete wall section is
a direct replacement for the
inner skin of blockwork and
the integral ground beam
enables panels to span between
foundation bases.
All the precast systems were
installed in 15 working days, a
time saving of 75% compared to
traditional build.
Client: Hellioslough. Main
contractor: Tolent Construction
Ltd. Architects: PCP Architects
Ltd, Harrogate. Consulting
civil and structural engineers:
Kennedy Watts, Morpeth.
The building has a ground level
entrance with double height
space up to a structural transfer
level at approximately 7m above
the pavement. Above this
transfer level, the hotel bedroom
block rises eight storeys, with
a plant room at roof level, and
below the footprint extends
out to accommodate front and
back of house facilities on both
ground and mezzanine floors.
Client is Ician Developments,
with main contractor Sir Alfred
McAlpine and precaster Buchan
Concrete Solutions.
Milbank Crosswall helps PCE Ltd deliver Countryside Properties Plcs
demanding programme at St Helens
7/29/2019 13828 Spa Newslr
8/8
SPA MembersAggregate Industries
Telephone: 01455 288280
Bell & Webster Concrete Ltd
Telephone: 01476 562277
Bison Concrete Products Ltd
Telephone: 01283 495000
Buchan Concrete Solutions
Telephone: 01606 843500
Roger Bullivant Concrete
Products Ltd
Telephone: 01283 525045
Ebor Concretes LtdTelephone: 01765 604351
Hanson Concrete Products
Telephone: 01773 602432
Milbank Floors Ltd
Telephone: 01787 223931
SCC Ltd
Telephone: 0161 432 7700
Tarmac Precast Concrete Ltd
Telephone: 01778 381000
Thorp Precast Ltd
Telephone: 01782 561155
Trent Concrete Structures Ltd
Telephone: 0115 987 9747
STRUCTURAL PRECAST ASSOCIATION 60 Charles Street, Leicester LE1 1FB. Tel: 0116 253 6161. Fax: 0116 251 4568
News
A product group of the British PrecastConcrete Federation Limited
www.structural-precast-association.org.uk
Clive handsover
The end of May was asignificant milestone inthe history of the SPA with
the retirement of Clive Budge
from British Precast.
For the past 12 years Clive hasbeen the secretary of the SPA,
and from its inception in 1995
assisted the members and
successive chairmen in ensuring
the Associations aims have been
achieved by promoting the use
of high quality structural precast
components.
Prior to the formation of the
SPA Clive was also secretary
of its preceding organisations,the Precast Concrete Frame
Association, and the Structural
Concrete Consortium.
Clives contribution to the
structural precast concrete
industry over the past 20 years
has been significant, and has
always been highly valued by the
SPA membership.
Taking over from Clive (left)
is Norman Brown who is well
known within the industry
having been associated with
structural precast concrete for
over 25 years.
Adding to Liverpool culture
Custom-designed concrete units from Tarmac Precast are being used to construct a new 10,600-capacity arena that will form a major part of the Kings Waterfront development in Liverpool,the centrepiece for the citys Capital of Culture celebrations in 2008.
The mixed-use complex
which will include the main
arena and a convention centre
is a major step for project
partners English Partnerships,
Liverpool Vision, Northwest
Regional Development Agency
and Liverpool City Council in
attracting future economic
development to the city. The
arena will eventually host
everything from concerts to
childrens entertainment, as
well as sporting events, and will
help transform Liverpool into
a national and international
tourism and leisure destination.
Tarmac Precast has
manufactured and delivered
around 3000 custom-made units,
including terracing units, step
blocks, vomitory walls and stair
flights to the development in
a contract with Bolton-based
steel contractor Watson Steel
valued at around 1.6million.
Tarmacs specialist site team
worked closely with Watson Steel
to ensure that the steelwork
construction progressed in
parallel with the delivery and
erection of the precast concrete
units.
Alex Harper, contract director
at Watson Steel, said Having
previously worked with Tarmac
Precast on the Emirates stadium
for Arsenal Football Club, we
were aware of its track record of
delivering within time scales. Its
experience of supplying precast
units to a number of prestigious
stadium projects counts for a
lot.
Photo: Ian Lawson Photography, English Partnerships, LIVERPOOL VISION