13828 Spa Newslr

Embed Size (px)

Citation preview

  • 7/29/2019 13828 Spa Newslr

    1/8News 1

    NewsS T R U C T U R A L P R E C A S T A S S O C I A T I O N

    SUMMER 2007

    this issuep2 a towering s tory, Leeds

    car park; p3 stairs lose

    weight; p4 innovative

    residential scheme;

    p5 luxury hotel on Jersey;

    p6 Trafford Centre expansion;

    p7 saving on programme,

    Manchester hotel; p8

    Liverpool arena.

  • 7/29/2019 13828 Spa Newslr

    2/8News 2

    Increasing Leedsparking

    As part of the development of a new Oncology Wingat St James University Hospital in Leeds, a new carpark was required to replace existing surface car parking

    and increase on-site parking. The new 1278-space

    multi-storey car park, designed by Hill Cannon (UK) LLPwith external architecture by Pulmann Associates, is a

    seven-storey structure built by SCC Limited from precast

    reinforced concrete.

    Tower of strength

    The Floors and Precast division of Hanson Building Productshas completed the manufacture and installation for CivicEnvironmental of a variety of structural precast concrete

    components ranging in weight from 2.5 to 17 tonnes for

    incorporation into a digester tower. The tower at Thornley in Co

    Durham, which will be operated by Premier Waste, is the first

    of its type to be built in the UK. The precast components are a

    combination of curved wall panels, floor slabs and large precast

    concrete beams for supporting the intermediate floors and roof

    of the tower.

    The form of construction uses a

    precast portal frame, arranged

    in a modular layout dictated

    by the requirements of parking

    bays and access aisles, giving a

    clear span across the parking

    bays. Vehicle circulation around

    the car park is via Hill Cannons

    patented VCM circulation system

    (vertical circulation module).

    External elevations, which were

    resolved to provide an aesthetic

    finish while maintaining the

    requirement for natural cross-

    ventilation, comprise a mixture

    of precast concrete panels faced

    with terracotta tiles, stainless-

    steel mesh and galvanised-mesh

    screens. The frame consists of

    precast reinforced beam-and-

    column units connected by

    grouted rebar joints. The top

    section of the beam was cast

    in-situ, forming a monolithic

    connection between precast

    slabs, beam and column. Precast

    retaining walls, stair cores

    and perimeter walls were all

    designed to be supported off

    the main structure. The frame is

    built off piled foundations, piles

    extending around 17m.

    The purpose of this prototype

    tank is to sanitise up to 150

    tonnes of domestic refuse every

    12 days. At the end of the

    process, it is sorted and recycled,

    eliminating the need for large-

    volume landfill.

    The completed main structure

    shapes up at approximately 16m

    in diameter by 16.5m tall. The

    precast concrete components

    were manufactured at Hanson

    Building Products Derby and

    Somercotes sites and erected

    on site over four weeks. Theuse of off-site precast concrete

    elements and shorter installation

    times were key to the clients

    choosing this particular build

    method: another plus was the

    overall faster construction

    compared to previously built

    steel tanks.

  • 7/29/2019 13828 Spa Newslr

    3/8News 3

    The Chairmans View

    by Gerry Feenan

    Having only recently been

    appointed chairman I

    appreciate this opportunity

    to acknowledge the very

    significant contributions made

    by my predecessor John Milner

    and our secretary Clive Budge

    who retired on the 31st May.

    John is featured on page 4 with

    Paul Whitham who succeeds

    him as managing director

    at Ebor Concretes and Clive

    is pictured on page 8 with

    Norman Brown who has taken

    over as head of engineering

    services at British Precast.

    I am delighted to welcome

    Aggregate Industries as a full

    member of the association,

    contact details are on page 8.

    A major change within the

    membership is the acquisition

    of Buchan Concrete Solutions

    by Roger Bullivant Ltd, see

    page 7. RBLs optimism for the

    future of precast is matched by

    Milbanks decision to double

    the number of 150m casting

    beds at its new Brandon facility.

    This confidence is well founded

    and illustrated by the wide

    variety of projects proving the

    versatility of precast concrete,

    featured in this issue.

    Savings all round

    Savings have already been made even before shoppers step inside the new shopping centreunder construction in Livingston, Scotland. Fortunately, with the co-operation of structural steelspecialist Severfield Reeve Structures, the design team agreed to Ebors proposal to coffer the soffit

    of the stair which leads to a 30% reduction in the unit weight.

    Owing to the geometry and

    clear span requirements, the

    original design for the 24

    precast concrete stair flights

    suggested a unit weight of 15

    tonnes. However, individual

    items weighing over 12.5 tonnes

    exceeded both the overhead

    crane capacity in the casting

    hall and storage area at Ebors

    Ripon works.

    Further savings included a

    halving of transport costs as two

    flights instead of one per load

    was possible and the use of site

    cranage to handle and place the

    10.5-tonne reduced-weight units

    without the need and expense of

    organising heavier cranage over

    the extended delivery period.

    However, to produce units with

    such a deep coffer, special jacks

    and compressed air systems

    were incorporated into the

    steel soffit former, easing the

    demoulding operation and

    reducing the adhesion stresses

    placed on the early-age concrete

    to a minimum.

    The solution clearly

    demonstrates the benefits of

    early involvement and close

    communication between

    all parties involved in the

    construction process.

    London School of Economics

    Alan Baxter & Associates are designing a new Academic Building

    for the London School of Economics in Lincolns Inn Fields, with

    Geoffrey Osborne Limited as the main contractor and Grimshaw

    as the project architect. The scheme requires large column free

    spaces at the lower levels to accommodate new lecture theatres.

    This has been achieved by hanging floors from a storey deep

    truss at roof level and with the introduction of eight 19m long

    precast concrete beams, each weighing 18 tonnes, which form

    the roof to the main lecture theatre.

    The units, manufactured and installed by Thorp Precast, have a high

    quality acid etch finish and will be one of the main architectural

    features. A 500 tonne mobile crane with a 50m luffing jib was

    used to install the units during a weekend road closure.

  • 7/29/2019 13828 Spa Newslr

    4/8News 4

    Precast doing the rounds

    B

    isons crosswall and hollow-core concrete products have been specified by Countryside

    Properties for an innovative project at Sport City in Manchester. The development of two

    circular buildings, one ten and the other seven storeys, will accommodate 111 one- and two-

    bed apartments. Bisons design and production flexibility is evident as the team have worked

    to integrate their standard hollow-core and crosswall products into the circular building, while

    achieving the essential structural tie detail necessary to stitch the building together.

    Handingover thereins

    Anew chapter for Ebor

    Concretes opens on1 July 2007 as John Milner

    (left) relinquishes his role as

    managing director to Paul

    Whitham. Determined to

    complete his 50 years service

    with Ebor, John will continue

    to support Paul part time for

    the next 1218 months as a

    consultant.

    In welcoming Paul to the board,

    John is confident that it will

    be business as usual following

    successful bedding in during

    the past three months. Paul is

    a Chartered Civil Engineer with

    over 20 years in the precast

    concrete industry. He has held

    a variety of operational and

    commercial roles in Charcon

    Tunnels, Costain Building

    Products and Tarmac Precast.

    Paul commented I am delighted

    to join Ebor and am looking

    forward to continuing the good

    work that John has done over

    the years in making Ebor one of

    the countrys leading suppliers of

    high-quality bespoke structural

    precast.

    Trevor Stack, construction

    director at Countryside

    Properties, comments: This was

    a challenging project conceived

    and designed to look completely

    different and push design

    boundaries. We specified Bisons

    products as its team was able

    to offer high-quality products

    quickly and provided practical

    solutions to practical issues,

    such as bespoke models for the

    external wall panels. The delivery

    and high quality finish of the

    products have been impressive,

    and the project is moving along

    quickly thanks to additional

    aids such as the lifting hooksprovided by Bison. I expect the

    build to be completed within the

    estimated 13-week time scale.

    This speed of construction

    demonstrates how concrete

    effectively meets the demands

    of off-site construction in terms

    of delivery, flexibility and quality.

    Concrete was specified for itsstrength, durability and inherent

    fire resistance. Total quantities

    for the project: walls: 10,500m2 in

    700 units, floors: 8500m2 in 1900

    units, stairs: 60 flight and landing

    units.

    It is expected that the phase will

    be completed by September

    2007, with flats ready the

    following month. Clients

    engineer: Scott Hughes Design.Bisons engineer: Hadfield

    Cawkwell Davidson. Architect:

    Countryside Properties Ltd.

    Hansonaquires

    StructhermHanson Building Products has

    announced the aquisition of

    Structherm based in Meltham,

    West Yorkshire. Established in

    1983 the company designs,

    manufactures and erects

    precast concrete walling

    systems for the housing

    sector, both low and high

    rise, education projects andcommercial buildings.

  • 7/29/2019 13828 Spa Newslr

    5/8News 5

    Fast build bedroomsfor Jersey hotel

    This prestigious and impressive five-star Radisson arrow-shaped hotel at the entrance to the St Helier marina facesdirectly out to sea and will be one of the first to be seen when

    approaching the marina. The joint-venture scheme by Jersey

    Waterfront Hotel Developments Ltd and Ironbridge Estates

    is being built by Cameron Building Contractors, with Bell and

    Webster Concrete supplying 758 precast components each

    weighing up to 12.2 tonnes. The 12-week schedule included the

    construction of 166 bedrooms, including placing all bathroom

    pods, two four-storey stair wells and lift shafts.

    After constructing the first-floor steel frame and the connecting

    knuckle to form the arrow shape, Cameron Building opted for Bell

    and Websters Fast Build Rooms for the bedrooms, stair and lift areas.

    Factory-engineered concrete was used for all walls, floors and the

    inner skin of the external walls, windows being full-height floor-to-

    ceiling. All the precast concrete wall surfaces within the bedrooms

    were ready for final preparation for the decorator.

    Main contractor Cameron Building

    undertook responsibility for

    transport and deliveries, the trip

    taking three days from loading at

    the precast factory in Grantham,

    through delivery to the sea freight

    terminal at Portsmouth, and then

    by ferry to Jersey.

    On site, panels were craned

    into position, all joints being

    designed to enable connectionsto be made with limited use of

    grout and with hidden fixings to

    hide the joints. As wall units were

    positioned, fully fitted bathrooms

    166 in all, weighing up to six

    tonnes were simultaneously

    craned into place. The pods were

    installed to create a vertical riser

    between rooms for mechanical

    and electrical services.

    With bedroom walls, floors and

    pods in place, following trades

    could begin on the first-fix. And

    with cladding effectively off the

    critical path (the structure already

    had the inner skin of the external

    wall as well as a concrete lid)

    external cladding began. The only

    penetrations through the top

    slab were the vertical risers, which

    were capped with polystyrene

    and a thin layer of concrete to be

    core-drilled: these prevent the

    water ingress, which could affectthe following tradesmen. Once

    the windows were installed, the

    structure has a high degree of

    weather-tightness, allowing other

    trades to follow on closely behind.

    Internal decoration consists of

    a sprayed surface finish applied

    directly to the concrete walls. In

    other hotels constructed by this

    technique, the factory-engineered

    concrete walls are painted with

    emulsion and carpet is laid

    directly onto the floors.

  • 7/29/2019 13828 Spa Newslr

    6/8News 6

    Expansion at TheTrafford Centre

    Following on from its previous extensive and successfulwork at the Trafford Centre, Trent Concrete has secured thecontract for the design, detailing, manufacture and installation

    of the reconstructed stone cladding and features on the Barton

    Square Development, part of the new expansion programme at

    the Trafford Centre. The development consists of four L-shaped

    blocks arranged to form a central square, mall and colonnade.

    Bullivantembraces Buchan

    F

    oundation engineering company Roger Bullivant Ltd has

    extended its specialist precast concrete division with theacquisition of Cheshire-based Buchan Concrete Solutions from

    international property and services company AMEC. RBL intends

    to secure the future of the Buchan factory and its 170 employees

    and invest further in the award-winning business.

    Trents 6.4m contract includes

    a variety of unique precast

    elements, some weighing up

    to 24 tonnes. On the external

    elevations, there are storey-

    height pilasters typically 8m high

    (the structure already had the

    inner skin of the external wall

    as well as a concrete lid) 1m

    wide, cornice units typically 8.8m

    long 1.4m high, a band course,and a 10.8m long plinth 445mm

    high. External corner towers

    consist of large raking ashlars,

    each 8m high 10m girth overall

    with brick-faced units above

    typically 2.2m wide 6m high,

    and cornice units.

    The shop fronts on the internal

    malls use double part-brick-

    faced pilaster/cornice units

    typically 2.6m wide and 8m high,

    cornice units and support beams.

    Tapered circular columns 900mm

    diameter and 7.2m high withbeam-and-hollow core flooring

    above form the colonnade

    and a central coliseum feature

    Said Steve Parker, production

    director at RBL, who will manage

    the Buchan operation in addition

    to his existing role Buchan is

    a well-established company

    with an excellent reputationand a good client base. It is

    already in the market place we

    want to expand into prisons,

    schools and hotels and the

    acquisition will make this

    transition smoother. With the

    support of both the Buchan and

    the RBL precast teams we shall

    see the turnover and consequent

    success of the business continue

    to grow.

    Last year, Roger Bullivant

    recorded a turnover of 110m,

    delivering solutions in piling,

    mini-piling, house foundations,

    ground improvement and

    special precast concrete, from

    manufacturing facilities at its

    Burton-on-Trent headquarters

    as well as two other sites. With a

    turnover in excess of 30 million,

    Buchan supplies precast concrete

    to the civil engineering and

    building construction markets.

    Recent projects have included

    prisons, hotels, apartments,

    student accommodation, schools

    and stadiums. In addition,

    the company offers a range

    of standard products for the

    civil engineering and buildingindustry, including tunnel linings,

    shaft segments and jacking

    pipes.

    Newcrosswall

    constructionguide

    Copies of Crosswall construction:

    High performance buildingsusing concrete frames and

    cladding can be downloaded

    from www.concretecentre.com

    23m radius and 10m high is

    constructed from 500 square

    columns 7.2 m high, faced with

    granite, and a curved cornice 8m

    long and 1.4m high arranged in a

    double line.

    The units are cast in a buff-

    coloured reconstructed stone

    mix with an acid-etched finish.

    Trent started the design and

    detailing process in late summer

    2006, manufacturing began in

    November and will continue

    through 2007. Site works started

    on 26 March.

    Principal contractor: Bovis

    Lendlease Ltd; Concept

    architect: Chapman Taylor;

    Architect: Leach Rhodes Walker;

    Structural engineer: Connell Mott

    MacDonald.

  • 7/29/2019 13828 Spa Newslr

    7/8News 7

    Reducing theprogramme

    W

    ith speed of the essence for a new distribution centre for

    Hellioslough being built at Wynyard, Stockton on Tees,

    main contractor Tolent Construction Ltd approached Roger

    Bullivant Ltd.

    Concrete visionFor Milbank Floors, last years new factory which was built fromits own precast concrete products was only a beginning. Bymid summer, the Brandon site aims to meet an ever-expanding

    demand by doubling the number of its 150m casting beds for

    prestressed hollow-core flooring, and the Brandon site is also set to

    further the companys vision of the complete precast solution by

    making wall panels its next area of growth.

    Investment in new curing chambers, casting pallets and upright mouldswill increase capacity for at least 50 grey concrete and concrete-brick

    panels a day by the end of the year.

    Crowne Plaza,Manchester

    This new Crowne Plaza Hotel in Manchester incorporates 228bedrooms, restaurants, meeting rooms and a health club.

    RBs dock leveller pits system

    is constructed from precast

    reinforced concrete sections

    that are combined to form a

    pit into which a wide range of

    dock levellers can be installed.

    This allows the main floor slab

    to be laid faster. The companys

    prowall panels span between

    dock pits, ensuring rapid erection

    and eliminating the requirement

    for traditional areas of cladding

    and steel post/rails. Panels are

    supplied complete with integral

    insulation to provide a U-value of

    0.27W/m2K.

    The concrete wall section is

    a direct replacement for the

    inner skin of blockwork and

    the integral ground beam

    enables panels to span between

    foundation bases.

    All the precast systems were

    installed in 15 working days, a

    time saving of 75% compared to

    traditional build.

    Client: Hellioslough. Main

    contractor: Tolent Construction

    Ltd. Architects: PCP Architects

    Ltd, Harrogate. Consulting

    civil and structural engineers:

    Kennedy Watts, Morpeth.

    The building has a ground level

    entrance with double height

    space up to a structural transfer

    level at approximately 7m above

    the pavement. Above this

    transfer level, the hotel bedroom

    block rises eight storeys, with

    a plant room at roof level, and

    below the footprint extends

    out to accommodate front and

    back of house facilities on both

    ground and mezzanine floors.

    Client is Ician Developments,

    with main contractor Sir Alfred

    McAlpine and precaster Buchan

    Concrete Solutions.

    Milbank Crosswall helps PCE Ltd deliver Countryside Properties Plcs

    demanding programme at St Helens

  • 7/29/2019 13828 Spa Newslr

    8/8

    SPA MembersAggregate Industries

    Telephone: 01455 288280

    Bell & Webster Concrete Ltd

    Telephone: 01476 562277

    Bison Concrete Products Ltd

    Telephone: 01283 495000

    Buchan Concrete Solutions

    Telephone: 01606 843500

    Roger Bullivant Concrete

    Products Ltd

    Telephone: 01283 525045

    Ebor Concretes LtdTelephone: 01765 604351

    Hanson Concrete Products

    Telephone: 01773 602432

    Milbank Floors Ltd

    Telephone: 01787 223931

    SCC Ltd

    Telephone: 0161 432 7700

    Tarmac Precast Concrete Ltd

    Telephone: 01778 381000

    Thorp Precast Ltd

    Telephone: 01782 561155

    Trent Concrete Structures Ltd

    Telephone: 0115 987 9747

    STRUCTURAL PRECAST ASSOCIATION 60 Charles Street, Leicester LE1 1FB. Tel: 0116 253 6161. Fax: 0116 251 4568

    News

    A product group of the British PrecastConcrete Federation Limited

    www.structural-precast-association.org.uk

    Clive handsover

    The end of May was asignificant milestone inthe history of the SPA with

    the retirement of Clive Budge

    from British Precast.

    For the past 12 years Clive hasbeen the secretary of the SPA,

    and from its inception in 1995

    assisted the members and

    successive chairmen in ensuring

    the Associations aims have been

    achieved by promoting the use

    of high quality structural precast

    components.

    Prior to the formation of the

    SPA Clive was also secretary

    of its preceding organisations,the Precast Concrete Frame

    Association, and the Structural

    Concrete Consortium.

    Clives contribution to the

    structural precast concrete

    industry over the past 20 years

    has been significant, and has

    always been highly valued by the

    SPA membership.

    Taking over from Clive (left)

    is Norman Brown who is well

    known within the industry

    having been associated with

    structural precast concrete for

    over 25 years.

    Adding to Liverpool culture

    Custom-designed concrete units from Tarmac Precast are being used to construct a new 10,600-capacity arena that will form a major part of the Kings Waterfront development in Liverpool,the centrepiece for the citys Capital of Culture celebrations in 2008.

    The mixed-use complex

    which will include the main

    arena and a convention centre

    is a major step for project

    partners English Partnerships,

    Liverpool Vision, Northwest

    Regional Development Agency

    and Liverpool City Council in

    attracting future economic

    development to the city. The

    arena will eventually host

    everything from concerts to

    childrens entertainment, as

    well as sporting events, and will

    help transform Liverpool into

    a national and international

    tourism and leisure destination.

    Tarmac Precast has

    manufactured and delivered

    around 3000 custom-made units,

    including terracing units, step

    blocks, vomitory walls and stair

    flights to the development in

    a contract with Bolton-based

    steel contractor Watson Steel

    valued at around 1.6million.

    Tarmacs specialist site team

    worked closely with Watson Steel

    to ensure that the steelwork

    construction progressed in

    parallel with the delivery and

    erection of the precast concrete

    units.

    Alex Harper, contract director

    at Watson Steel, said Having

    previously worked with Tarmac

    Precast on the Emirates stadium

    for Arsenal Football Club, we

    were aware of its track record of

    delivering within time scales. Its

    experience of supplying precast

    units to a number of prestigious

    stadium projects counts for a

    lot.

    Photo: Ian Lawson Photography, English Partnerships, LIVERPOOL VISION