04/18/2023 file:///tt/file_convert/563dba24550346aa9aa30ef0/document.xls document.xls
Client Petro-Canada Netherlands B.V. PIPE STRESS CALCULATION
Project P11-b De Ruyter Production Platform Summary Sheet
Doc. No. 144-111-PI-CAL-0043 Rev. R1 System: SK-043
Page 1 of 1
System Description
Line numbers Connecting Equipment Tag no's
2; 4 BD 410 039 A41 G.E.C. Discharge Scrubber 310-VN-02 / N4
8 BD 410 234 A41
1; 4 MG 310 025 B41
Status Note
Design Code B 31.3
System designed for blast Yes
CII Calculation no. - blast case SK-043B-R1
CII Calculation no. - design case SK-043A-R1
Process line list Rev. C2
Material specification Rev. C3
Support locations for AFD Yes
Support loads issued AFD Yes
Support detail drawing approved Partly
Flexibility approved Yes
Maximum Stresses [ MPa]Sustained Expansion Occasional Blast
37,1 (27%) 63,6 (30,1%) 40,1 (21,9%) 162,3 (66,9%)
Equipment Nozzle Loads
Tag no. Node no Approved Notes
310-VN-02 / N4 1240 Yes Standard loads, doc 144-000-ME-SPE-0004.
0
0
0
NOTE: