Client Petro-Canada Netherlands B.V. PIPE STRESS CALCULATION
Project P11-b De Ruyter Production Platform Summary Sheet
Doc. No. 144-111-PI-CAL-0048 Rev. R1 System: SK-048
Page 1 of 1
System Description
Line numbers Connecting Equipment
8 GM 400 003 A41 Cooling Medium Cooler 400-HP-01 / N2
4; 8 GM 400 017 A41 Cooling Medium Drum 400-VB-01 / N1
8 GM 400 008 A41
Status Note
Design Code B 31.3
System designed for blast No
CII Calculation no. - blast case -
CII Calculation no. - design case SK-048A-R1
Process line list Rev. C2
Material specification Rev. C3
Support locations for AFD Yes
Support loads issued AFD Yes
Support detail drawing approved Partly
Flexibility approved Yes
Maximum Stresses Sustained Expansion Occasional Blast
34.8 (25%) 59.5 (29%) 143.2 (78%) x
Equipment Nozzle Loads
Tag no. Node no Approved Notes
400-HP-01 / N2 1310 Yes Standard Nozzle loadings (Doc.No. 144-000-ME-SPE-0004)
400-VB-01 / N1 30 Yes Standard Nozzle loadings (Doc.No. 144-000-ME-SPE-0004)
file:///tt/file_convert/563dba24550346aa9aa30ef4/document.xls document.xls
PIPE STRESS CALCULATION
Note
x