Polysius Tangential silo in 9 steps KIH 620, 14.04.2011

16 Tangential Silo En

Embed Size (px)

Citation preview

Titel des Vortrags Änderungen und Richtlinien Datum 24.11.2010 Anlass, Referent Vorstellung des neuen Layout 1 Polysius Polysius

Tangential silo in 9 steps KIH 620, 14.04.2011

Page 1

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 1:

• Casting of the silo structure

Page 2

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 2:

• Install pre-assembled mixing chamber and bin top filter

Page 3

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 3:

• Install silo cone segments

Page 4

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 4:

•Install silo aeration system

•Install pre-assembled pressure relief vents

•Install roof structure/silo slab

Page 5

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 5:

• Install platforms, stairs, ladders etc.

• Install silo access doors, sockets for silo openings, sockets for dedusting etc.

Page 6

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 6:

• Install distribution vessel with trough conveyor, bag filter, overpressure flap, silo pilot etc. on silo roof

Page 7

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 7:

• Install outlet equipment and trough conveyor

• Install rotary blowers

Page 8

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 8:

• Install pipes inside and outside

• Install aeration system for mixing vessel

•Install main pressure pipes

Page 9

Polysius

This document contains a general and rough description of erection activity (in particular for the use of contractors who are inexperienced on the cement plant construction sector). The document does not reflect the details/circumstances of specific projects.

Step 9:

• Install chutes and ducts

• Install ventilation system for silo cone

• Install control system for pneumatic valves and dosing valves