41
MIT OpenCourseWare http://ocw.mit.edu 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods January (IAP) 2008 For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.

16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

MIT OpenCourseWare http://ocw.mit.edu

16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods January (IAP) 2008

For information about citing these materials or our Terms of Use, visit: http://ocw.mit.edu/terms.

Page 2: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Lean Thinking

Page 3: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Learning Objectives

At the end of this module, you will be able to:

• Describe the elements of a process

• Draw a process map

• Explain what constitutes value in a process

• List the five fundamental lean principles

• Give a description several concepts and tools for implementing lean principles

Lean Thinking V6.3 - Slide 2 © 2008 Massachusetts Institute of Technology

Page 4: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

What is a Process?

Set of actions which transform inputs to outputs

Inputs Outputs

Process: A series of actions, changes, or functions bringing about a result

Lean Thinking V6.3 - Slide 3 Ref: http://www.dictionary.com, Jan. 8, 2003 © 2008 Massachusetts Institute of Technology

Page 5: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Identify the Customer

• What happens to the outputs of a process?

They go to a CUSTOMER!• External customers - are outside an organization,

money is typically exchanged with external customers

• End users are customers who pay for an operational or consumable product or service

• Internal customers - are inside an organization, money is typically not exchanged directly with internal customers

• Customers also drive the inputs to a process through their needs and requirements

Lean Thinking V6.3 - Slide 4 © 2008 Massachusetts Institute of Technology

Page 6: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Process MapsNew Requirement

Schedule

Review

PR’s

Write EDA

Basic Layout

FAMSCO

Write PS

Assign Task

Detailed Layout

Layout from Config

STRESS

Assy Drawing

Detail Drawing

CHECKBOARD RELEASE CENTER

SIGNOFF

NEAR

DCC Investigate

C/A Board

C/A

Process map for pre lean engineering drawing release

• Only understood processes can be improved

• Understanding a process is easier when it can be visualized

• A Process Map is an organized visualization of all the interrelated activities which combine to form a process

Lean Thinking V6.3 - Slide 5 © 2008 Massachusetts Institute of Technology

Courtesy of Lockheed Martin. Used with permission.Source: "Lean PD Efforts for F-22", LAI Product DevelopmentWinter Workshop, January 27, 2000.

Page 7: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Process Map For Fixing a Hot Dog

Yes

Yes

Store

Customer

Need Hot dog,

bun ?

P pantry

No Cook Hot Dog

Put in bun Add condiments

Hot dog Order Deliver

Order

Last Dog, bun ?

Add to shopping list

Clean up

No

Stop

Symbology

Main process flow Secondary, feeder flow Information flow

Yes No

Supplier, Warehouse Task Inventory, Wait DecisionLean Thinking V6.3 - Slide 6

© 2008 Massachusetts Institute of Technology

Page 8: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Hot Dog Stand Process Map

• With your team, develop a process map for S&A Hot Dogs • Use post-it notes for processes elements• Put post-its on easel chart or white board• Draw lines for process & information flow• Don’t get hung up on symbology

• Identify inputs, outputs & boundary of the process

• In 15 minutes, be prepared to explain your process map to the class

Lean Thinking V6.3 - Slide 7 © 2008 Massachusetts Institute of Technology

Sasha Andy

Page 9: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Process Wrap Up

• Processes underlay everything we do

• The fundamentals of lean thinking provide the foundation to modern process improvement

• Understanding and improving processes is the key to improving productivity

Lean Thinking V6.3 - Slide 8 © 2008 Massachusetts Institute of Technology

Page 10: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Five Lean Thinking Fundamentals

• Specify value: Value is defined by customer in terms of specific products and services

• Identify the value stream: Map out all end-to-end linked actions, processes and functions necessary for transforming inputs to outputs to identify and eliminate waste

• Make value flow continuously: Having eliminated waste, make remaining value-creating steps “flow”

• Let customers pull value: Customer’s “pull” cascades all the way back to the lowest level supplier, enabling just-in-time production

• Pursue perfection: Pursue continuous process of improvement striving for perfection

Lean Thinking V6.3 - Slide 9 Ref: James Womack and Daniel T. Jones, Lean Thinking (New York: Simon & Schuster, 1996). © 2008 Massachusetts Institute of Technology

Page 11: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Value Added and Non Value Added

Value Value Stream Flow Pull Perfection

Value Added Activity

• Transforms or shapes material or information or people

• And it’s done right the first time

• And the customer wants it

Non-Value Added Activity – Necessary Waste • No value is created, but cannot be eliminated based on current

technology, policy, or thinking

• Examples: project coordination, regulatory, company mandate, law

Non-Value Added Activity - Pure Waste • Consumes resources, but creates no value in the eyes of the

customer

• Examples: idle/wait time, inventory, rework, excess checkoffs

Lean Thinking V6.3 - Slide 10 © 2008 Massachusetts Institute of Technology

Page 12: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Inspection: An Example of Waste

Value Value Stream Flow Pull Perfection

Can you see any mistakes?

Inspection is not a good way to prevent or eliminate mistakes!

Lean Thinking V6.3 - Slide 11 © 2008 Massachusetts Institute of Technology

ILOVE

PARIS IN THETHE SPRINGTIME

Figures by MIT OpenCourseWare.

Page 13: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

What is a Value Stream?

Value Value Stream Flow Pull Perfection

• A value stream is… • ALL activities that create value

• Starts with raw materials or initial information

• Ends with the end customer/user

product or service

valued by the

customer Material or information or people

Customer needs/reqts., Schedules

Lean Thinking V6.3 - Slide 12 © 2008 Massachusetts Institute of Technology

Page 14: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

What Moves In a Value Stream?

In manufacturing… material flows

In design & services…information flows

In human services…people flow

Value Value Stream Flow Pull Perfection

Lean Thinking V6.3 - Slide 13© 2008 Massachusetts Institute of Technology

Page 15: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Seven Types of Waste

1. Over-production Creating too much material or information

2. Inventory Having more material or information than you need

3. Transportation Moving material or information

4. Unnecessary Movement Moving people to access or process material or information

5. Waiting Waiting for material or information, or material or information waiting to be processed

6. Defective Outputs Errors or mistakes causing the effort to be redone to correct the problem

7. Over-processing Processing more than necessary to produce the desired output

Value Value Stream Flow Pull Perfection

Lean Thinking V6.3 - Slide 14© 2008 Massachusetts Institute of Technology

Page 16: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Making Value Flow

Value Value Stream Flow Pull Perfection

Flow requires: • Understanding of time • Process control • Eliminating bottlenecks and stoppages • Eliminating unplanned rework

Creating flow: • Focus on the product or service that is flowing

through the process • Don’t be limited by organizational or functional

boundaries

Lean Thinking V6.3 - Slide 15 © 2008 Massachusetts Institute of Technology

Page 17: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Time

Value Value Stream Flow Pull Perfection

• Time is an essential metric for lean improvement

• There are different ways to measure time• Wait time • Processing time • Cycle time • Customer Demand or Lead time

• The key is to understand the local definition of how time is measured

Lean Thinking V6.3 - Slide 16 © 2008 Massachusetts Institute of Technology

Page 18: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Wait Time

Wait and Process Time

Value Value Stream Flow Pull Perfection

• Wait time • Time Work in Process (WIP) is idle - in queues,

buffers or storage • Other Names: Queue Time, Delay Time

• Processing time • Time that activities are being performed on WIP • Processing time may consist of Value Added Time

(VAT) and Non Valued Added Time (NVAT) activities. • Other names: Touch time (TT), In Process Time (IPT),

Response Time (RT)

Wait Time VAT NVAT VAT Wait Time

Time Processing Time Lean Thinking V6.3 - Slide 17

© 2008 Massachusetts Institute of Technology

Page 19: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Cycle Time

Value Value Stream Flow Pull Perfection

• The time required to execute activities in a process

• It can be measured for: • A single task or activity • A group of tasks or activities • A single process • A group of processes, e.g., customer order to customer

delivery

• Cycle time includes processing time and wait time

• Other names: Lead time or span time or throughput

Lean Thinking V6.3 - Slide 18

time Cycle Time

Process TimeTime

Wait Time Wait Time VAT VATNVAT

© 2008 Massachusetts Institute of Technology

Page 20: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Hot Dog Stand Times

• Calculate the time in seconds for the 11 process steps and the total cycle time. • Note: make sure to convert everything to time per

order • Allocate the work to each member of the team (balance

the workload - a lean practice!); e.g. • 1 member to record results on flip chart • 1 person calculate T/O for steps 1-3, another for 4-6, a

third for 7-9 and the fourth for steps 10-11. • Give calculated T/O to recorder to calculate CT

Lean Thinking V6.3 - Slide 19 © 2008 Massachusetts Institute of Technology

Sasha Andy

Page 21: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Time Value Charts

Value Value Stream Flow Pull Perfection

• Visual display of the breakdown in time for a given process

• Actual numbers must be measured or estimated

18 days 13 days4 da 4 da10 days

49 days

Work Work Starts Completed

Big cycle time savings comes from removing wait and non-value added time out of a process!

Lean Thinking V6.3 - Slide 20 © 2008 Massachusetts Institute of Technology

Page 22: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

KittingValue Value Stream Flow Pull Perfection

• Combining all relevant material, parts, and/or information into a single package which can be delivered to the point-of-use (POU) in a process

bill of material work instructions

wire bundle tubes in a Source: Lockheed Martin

shadow box Lean Thinking V6.3 - Slide 21 © 2008 Massachusetts Institute of Technology

Source: Lockheed Martin

Two photographs of kits removed due to copyright restrictions.

Page 23: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Mistake Proofing

Value Value Stream Flow Pull Perfection

• A way to prevent errors from occurring and to prevent errors that have occurred from moving downstream in a process or causing accidents

• Examples

• Locating pins to prevent wrong assembly of a die

• Color matching for assembly • Automatic shut off timers on

appliances • Operator activated interlock

switches on power equipment

• Can you think of others? Photo by Earll Murman

Lean Thinking V6.3 - Slide 22 © 2008 Massachusetts Institute of Technology

Page 24: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

What is a Pull System?

Value Value Stream Flow Pull Perfection

• Pull means that no one produces a good or service or processes material or information until someone downstream has requested it

• All value is pulled by the end customer or user of the product or service

• Inherently, there is very little waste in a pull system

• Pull systems are agile and responsive to customer demand

Lean Thinking V6.3 - Slide 23 © 2008 Massachusetts Institute of Technology

Page 25: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Moving from Flow to Pull

Value Value Stream Flow Pull Perfection

Pull requires Flow plus predicable cycle time, using• Takt time • Balanced work • Standard work • Single piece flow • Kanban system • Just in time delivery of all material and information

Creating Pull: • Start with the customer and work backwards through the

system • If cycle time <= lead time then Pull can be

accomplished• If cycle > lead time then buffer inventory is used that

can be pulled immediately

Lean Thinking V6.3 - Slide 24 © 2008 Massachusetts Institute of Technology

Page 26: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Pull System: DELL COMPUTER

Value Value Stream Flow Pull Perfection

• DELL encourages “ORDER PLACEMENT” / “OPTIONS DECISIONS” on-line or via phone

• Credit Card # Initiates the “Pull” Process

• Suppliers are on-line with DELL re: Order Placement / Computer Configuration

• Production Of 27,000 Computers / Day

• Orders Shipped in 1 Day

• Zero Inventory carry costs

Lean Thinking V6.3 - Slide 25 © 2008 Massachusetts Institute of Technology

Page 27: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Takt Time -Measure of Customer Demand

Value Value Stream Flow Pull Perfection

Takt Time is… • from the German word for

meter which establishes the available time

pace or beat Takt Time = customer demand

• a reference number that rate for available time provides a drum beat for the process

Example:The available time is a year or 235 days.There are 40 orders for this year.

What is the Takt time?

235/40 ~ 6 days

Lean Thinking V6.3 - Slide 26 © 2008 Massachusetts Institute of Technology

Page 28: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Hot Dog Stand Takt Time

• What is the takt time for S&H Hot dogs for• 50 customers? • 75 customers?

Lean Thinking V6.3 - Slide 27 © 2008 Massachusetts Institute of Technology

Sasha Andy

Page 29: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Balanced Work

Value Value Stream Flow Pull Perfection

Takt Time example, continued…

To meet Takt time, a product has to be delivered every 6 days. But if it takes 30 days to build, how is this possible?

Lean Thinking V6.3 - Slide 28

Takt Time

6 days

Takt Time

6 days

Cycle Time 30 days

© 2008 Massachusetts Institute of Technology

Page 30: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Standard Work

Value Value Stream Flow Pull Perfection

• Best process currently known, understood, and used today

• Tomorrow it should be better based on continuous improvement

• Standard work is thekey to repeatability

Lean Thinking V6.3 - Slide 29 © 2008 Massachusetts Institute of Technology

Page 31: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Single Piece Flow

Value Value Stream Flow Pull Perfection

Single Piece Flow

• Processing one unit at a time

• Only one unit in work at any step in the process

• Low inventory levels

Batch and Queue

• Processing multiple units at the same time

• Number of units in work optimizes the efficiency at each step in the process

• High inventory levels

Lean Thinking V6.3 - Slide 30 © 2008 Massachusetts Institute of Technology

Page 32: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Kanban

Value Value Stream Flow Pull Perfection

Supplier Process

New Product

Supermarket

Withdrawn Product

"PRODUCTION"Kanban

"WITHDRAWAL"Kanban

Supplier Process

• Visual cuing system to indicate material, parts, and/or information are authorized to move downstream

Lean Thinking V6.3 - Slide 31 Adapted from: Hirohito, "Just In Time" © 2008 Massachusetts Institute of Technology

Figure by MIT OpenCourseWare.

Page 33: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Visual Control and Andon

Value Value Stream Flow Pull Perfection

• Visual control helps identify the status of the process at a glance • Makes the process apparent

to everyone involved with or observing it

• Only valuable if used for active process management

• Andon is a specific visual control device, typically a group of lights indicating the current status of the process • Each step has a set of lights which indicates whether the

step is proceeding as planned, needs monitoring, or requires immediate attention

• In a pull system, if action is required, the entire process stops to correct the problem Lean Thinking V6.3 - Slide 32

© 2008 Massachusetts Institute of Technology

Photograph of work control board removeddue to copyright restrictions.

Page 34: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Andon Systems Help Prevent Mistakes

Value Value Stream Flow Pull Perfection Employee has found a part that doesn't fit right.

The employee pulls on the line-stop cord overhead.

LINE STOPPED!

Team leader sees the lamp and comes to help.

The team leader discovers a ring that has slipped out of place. He solves the problem before the production line reaches the next fixed position. The line continues moving.

Lean Thinking V6.3 - Slide 33 © 2008 Massachusetts Institute of Technology Source: http://www.toyota.co.jp

Photographs illustrating each of these steps removed due to copyright restrictions.

Page 35: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Pursuing Perfection

PerfectionValue Value Stream Flow Pull

• Let customer demand pull value through the value stream

• Completely eliminate waste in a process

• Design and build quality into the product and service

• Ensure transparency to everyone involved

• This is a journey…don’t give up!

Lean Thinking V6.3 - Slide 34 © 2008 Massachusetts Institute of Technology

Page 36: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

5 Whys Help Achieve Perfection

PerfectionValue Value Stream Flow Pull

5 whys can be used to help determine the root cause of mistakes

5 Whys Example:

The Jefferson Monument is deteriorating!

Why? It gets washed all the time.

Why? It always has bird droppings on it.

Why? The birds come into the monument to feed on spiders.

Why? The spiders are there feeding on gnats.

Why? The gnats are there because the lights are left on all the time.

Lean Thinking V6.3 - Slide 35 © 2008 Massachusetts Institute of Technology

Page 37: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Lean Concepts Introduced So Far

Value Value Stream Flow Pull Perfection

• Value and non-value added

• 7 types of waste • Value Stream • Cycle time • Wait time • Process time • Time value charts • Takt time • Balanced work

• Single piece flow

• Standard work

• Kitting

• Kanban

• Visual control

• Andon

• 5S

• Mistake proofing

• 5 Whys

Lean Thinking V6.3 - Slide 36 © 2008 Massachusetts Institute of Technology

Page 38: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Five Lean Fundamentals Work Together

1 Customer

Value 2

Value Stream

3 Flow

4 Pull

5 Perfection

Lean Thinking V6.3 - Slide 37© 2008 Massachusetts Institute of Technology

Page 39: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Take Aways

• The concepts of process, customer and value are essential to lean thinking

• There are fundamental principles behind lean thinking based on making value flow

• A number of simple tools and concepts underlie lean thinking

Lean Thinking V6.3 - Slide 38 © 2008 Massachusetts Institute of Technology

Page 40: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Reading List

Murman, E., Allen, T., Bozdogan, K., Cutcher-Gershenfeld, J., McManus, H., Nightingale, D., Rebentisch, E., Shields, T., Stahl, F., Walton, M., Warmkessel, J., Weiss, S., and Widnall, S., Lean Enterprise Value: Insights from MIT’s Lean Aerospace Initiative, Palgrave, New York, 2002

Rother, M. and Shook, J. Learning to See, v1.2, The Lean Enterprise Institute, Cambridge, MA June 1999

Womack, J. and Jones, D., Lean Thinking, Simon & Shuster, New York, 1996

Lean Thinking V6.3 - Slide 39 © 2008 Massachusetts Institute of Technology

Page 41: 16.660 / 16.853 / ESD.62J Introduction to Lean Six Sigma Methods · 2019-09-12 · Identify the Customer • What happens to the outputs of a process? They go to a CUSTOMER! • External

Acknowledgements

• Venkat Allada - University of Missouri-Rolla

• Sharon Johnson - Worcester Polytechnic Inst.

• Earll Murman - MIT

• Bo Oppenheim - Loyola Marymount University

• Alexis Stanke - MIT

• Ed Thoms - The Boeing Co., IDS

Lean Thinking V6.3 - Slide 40 © 2008 Massachusetts Institute of Technology