Alcatel-Lucent GSM
Add a BSS by Moving Existing
Links Through an MFS
MPI96 / MDR2 - CCL
MFS Document
Reconfiguration Method
3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 2/14
Status RELEASED
Short title MPI96 / MDR2
All rights reserved. Passing on and copying of this document, useand communication of its contents not permitted without writtenauthorization from Alcatel-Lucent.
BLANK PAGE BREAK
2 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 3/14
Add a BSS by Moving Existing Links Through an MFS
MPI96 / MDR2 - CCL
Identification
Customer
Country
OMC-R Site Name: Address:
Name: Address:
Alcatel-Lucent Representative (s)
Customer Representative (s)
Customer Contractor Representative (s)
Date, Time and Duration of Work Start End Duration
General Remarks from Customer General Remarks from Alcatel-Lucent
3BK 17430 0962 QZZZA Ed.07 3 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 4/14
Applicable Documents
Fill in the edition of the applicable documents
Document Title Document Reference Edition
Add a BSS by Moving Existing Links Through an MFS 3BK 17430 0962 RJZZA
B10 BSS Methods Handbook 3BK 21268 AAAA PCZZA
BSS Configuration Handbook 3BK 21201 AAAA PCZZA
BSS Surveillance Handbook 3BK 21206 AAAA PCZZA
Network Reconfiguration Recommendations 3BK 21269 AAAA PCZZA
9135 MFS Maintenance Handbook 3BK 21235 AAAA PCZZA
9135 MFS IMT Online Help 3BK 21234 AAAA PCZZA
Extend Ater Mux Interface 3BK 17430 1021 RJZZA
BSC Terminal User Guide 3BK 21220 AAAA PCZZA
Applicable ITL
InformationFill in the site data.
OMC-R Hostname
User Name
Password
4 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 5/14
Cases and Options
Enter a cross for the applicable case or option.
C1.1 9135 MFS not introduced in the network
C1.2 Set / Change synchronization mode to centralized
C1.3 Set / Change synchronization mode to autonomous
C1.4 Change synchronization mode to GPU cascading
C1.5 Subrack extension needed
C1.6 No subrack extension needed, but only GPU extension.
C2.1 MFS 9130 not introduced in the network
C2.2 Synchronization mode is centralized
C2.3 Synchronization mode is autonomous
C2.4 No subrack extension needed, but only GP extension.
C3.1 Moved Ater Mux
C3.2 New Ater Mux.
C4 Dedicated Ater Mux
C5 Gb does not go through TC.
O1 If BSS already configured with GPRS, reconfigure radio resources on cells
O2 In the case of centralized clocking mode on the 9135 MFS (C1.2), define the new GPU
as synchronizing GPU
O3 In the case of centralized clocking mode on the 9130 MFS Evolution (C2.2), define
links as synchronizing ones
O4 Shut down traffic on all Ater of the mixed Ater Mux before setting GPRS on it
O5 Set GPRS traffic on cells
O6 Add new PCM links
O7 External Alarm Box for 9130 BSC Evolution/MFS Evolution
O8 Gb is over FR
O9 Gb is over IP.
3BK 17430 0962 QZZZA Ed.07 5 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 6/14
Software & Documentation Versions
Fill in the appropriate INITIAL and FINAL software versions.
For BSS reshuffling methods, the INITIAL and FINAL versions are equal.For installation methods, the INITIAL version is "-" .
Initial Version Final Version
OMC-R
NPA
RNO
LASER
BSS
MFS
DocumentationVersion
6 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 7/14
Results Table
Fill in the Results Table according to the following rules: YES: Put a cross here if the task was performed NO: Put a cross here if the task was not performed
N.A: Put a cross here if the task is not applicable S.A: Enter the number of solved anomalies N.S.A: Enter the number of non-solved anomalies
Scenario Description
Initial Checks
YES NO N.A S.A N.S.A
Initial Checks
Performed by Site Date Start Time End Time Duration
Preparation
YES NO N.A S.A N.S.A
O6: Add New PCM Link
Declare MFS to OMC-R
Configure Site Parameters
Performed by Site Date Start Time End Time Duration
Insert GPU / GP Board
YES NO N.A S.A N.S.A
C1.5, C1.4: Extend Subrack for 9135 MFS
C1.6, C1.4: Extend GPU
C2.4: Extend GP
Performed by Site Date Start Time End Time Duration
3BK 17430 0962 QZZZA Ed.07 7 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 8/14
Associate BSC / MFS
YES NO N.A S.A N.S.A
Associate BSC / MFS
Performed by Site Date Start Time End Time Duration
Configure Transport at MFS
YES NO N.A S.A N.S.A
C3: Configure Mixed Ater Mux
C4: Configure Dedicated Ater Mux
Set Synchronization Clocking Mode for an 9135 MFS
Set Synchronization Clocking Mode for an 9130 MFSEvolution
Performed by Site Date Start Time End Time Duration
C3.1: Move Existing Ater Mux through MFS
YES NO N.A S.A N.S.A
Reduce Ater Mux Traffic
Physically Connect Ater Mux
Set Traffic on Ater Mux
Test Call Service
Performed by Site Date Start Time End Time Duration
8 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 9/14
Configure GPRS
YES NO N.A S.A N.S.A
C3.2, C4: Configure Ater Interface on PCM without Traffic
C3.1: Configure Ater Interface on PCM in Traffic
Configure Gb Interface
Configure Radio Interface
Performed by Site Date Start Time End Time Duration
Set in Traffic
YES NO N.A S.A N.S.A
C3.2: Set Traffic on Mixed Ater Mux
C4: Set Traffic on Dedicated Ater Mux
O5: Set GPRS Traffic
Performed by Site Date Start Time End Time Duration
Test Call and GPRS Services
YES NO N.A S.A N.S.A
Test Call and GPRS Services
Performed by Site Date Start Time End Time Duration
Final Checks
YES NO N.A S.A N.S.A
Final Checks
Performed by Site Date Start Time End Time Duration
3BK 17430 0962 QZZZA Ed.07 9 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 10/14
Reverse Procedure
O5: Stop GPRS Traffic
YES NO N.A S.A N.S.A
O5: Stop GPRS Traffic
Performed by Site Date Start Time End Time Duration
Delete GPRS Resources
YES NO N.A S.A N.S.A
Delete Radio Resources
Delete Gb Resources
C3.1: Delete Ater Resources on Moved Ater Mux
C3.2, C4: Delete Ater Resources on New Ater Mux
Performed by Site Date Start Time End Time Duration
C3.1: Move Mixed Ater Mux into Direct Ater Mux
YES NO N.A S.A N.S.A
Reduce Ater Mux Traffic
Physically Connect Ater Mux
Set Traffic on Ater Mux
Disconnect MFS-SGSN Link
Performed by Site Date Start Time End Time Duration
10 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 11/14
Test Call Service
YES NO N.A S.A N.S.A
Test Call Service
Performed by Site Date Start Time End Time Duration
Physically Disconnect New Ater Mux
YES NO N.A S.A N.S.A
Physically Disconnect New Ater Mux
Performed by Site Date Start Time End Time Duration
Delete Transport at MFS
YES NO N.A S.A N.S.A
Delete Transport at MFS
Performed by Site Date Start Time End Time Duration
Dissociate BSC / MFS
YES NO N.A S.A N.S.A
Dissociate BSC / MFS
Performed by Site Date Start Time End Time Duration
3BK 17430 0962 QZZZA Ed.07 11 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 12/14
C1.1, C2.1: Remove MFS from OMC-R
YES NO N.A S.A N.S.A
C1.1, C2.1: Remove MFS from OMC-R
Performed by Site Date Start Time End Time Duration
Remove GPU Board
YES NO N.A S.A N.S.A
Remove GPU Board
Performed by Site Date Start Time End Time Duration
Remove GP Board
YES NO N.A S.A N.S.A
Remove GP Board
Performed by Site Date Start Time End Time Duration
Final Checks
YES NO N.A S.A N.S.A
Final Checks
Performed by Site Date Start Time End Time Duration
12 / 14 3BK 17430 0962 QZZZA Ed.07
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 13/14
Unavailability Duration Sheet
Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the unavailability occured Unavailability type T for traffic interruption , R for traffic reduction , S for loss of supervision
(T,R and S could be held simultaneously)Equipment Equipment with its number (eg BTS-1)Date Date expressed as: yy/mm/dd Start time Start time expressed as: hh/mm/ss End time End time expressed as: hh/mm/ss
UnavailabilityType
Equipment Date Start Time End Time
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
Section Title
3BK 17430 0962 QZZZA Ed.07 13 / 14
8/13/2019 174300962 Cc Le 07
http://slidepdf.com/reader/full/174300962-cc-le-07 14/14
Anomaly Sheet
Fill in the unavailability duration sheet according to the following rule: Section Title Title of the paragraph where the anomaly occured Brief description of the anomaly Summarize the anomaly (details must be in anomaly report)
Anomaly report Anomaly report was sent or no Solved by Name of the technician who solved the anomaly Date of anomaly solving
Description Solved by
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
Section Title:
Brief description of the anomaly:
Anomaly report: Y/N
Name:
Date:
14 / 14