Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269 Revision Implementation
Utility Line Clearance Contractors Perspective
Joseph F. Tommasi Corporate Director of Safety – The Davey Tree Expert Company President – The Utility Line Clearance Coalition Chair – Rigging and Tree Removal Task Group ANSI Z133 Committee
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
The Utility Line Clearance Coalition
Asplundh Tree Expert Company, Burford’s Trees, Inc., The Davey Tree Expert Company Lewis Tree Service, Inc., Lucas Tree Experts, Inc. McCoy Tree Surgery, Inc., Nelson Tree Service, Inc. Penn Line Service, Inc. Townsend Tree Service, Inc. Trees, Inc. Wright Tree Service, Inc.
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
Line Clearance Arborist at Work
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
Line Clearance Work Methods
Pruning and Sectional Removal from Aerial Device
Pruning and Sectional Removal by Climbing Crew
Tree Removal by a Felling Team from the Ground
Mechanical Pruning with Boom Mounted Saws
Manual Brush Cutting & Mechanized ROW Mowing
Herbicide and Tree Growth Regulator Treatment
Site or Project Specific per Contract w/ Utility
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
Line Clearance
Section 1910.269(x) defines line-clearance tree trimming as “[t]he pruning, trimming, repairing, maintaining, removing, or clearing of trees, or the cutting of brush, that is within the following distance of electric supply lines and equipment: (1) For voltages to ground of 50 kilovolts or less – 3.05 meters (10 feet); (2) For voltages to ground of more than 50 kilovolts – 3.05 meters (10 feet) plus 0.10 meters (4 inches) for every 10 kilovolts over 50 kilovolts.”
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269 Application for Line Clearance
Paragraphs (a)(2), (a)(3), (b), (c), (g), (k), (p), and (r) of this section apply to line-clearance tree-trimming operations performed by line-clearance tree trimmers who are not qualified employees. (a)(2) Training (a)(3) Information Transfer (b) First Aid (c) Job Briefing (g) Personal Protective Equipment (k) Materials Handling and Storage (p) Mechanical Equipment (r) Line Clearance Tree Trimming Operations
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(a)(2) Training
LCTT employees: Safety practices of 1910.269 that pertain to
their respective job assignments Determine Live Parts, Nominal Voltage, MAD,
and Safe Practices to maintain MAD Emergency Response Procedures Other necessary safety practices, see ANSI
Z133-2012 Arboricultural Operations – Safety Requirements, Training Outline
Risk Exposure and Work Method Based Continued Voluntary Documentation of
Demonstrated Proficiency by Employers
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(a)(2) Training
Education and Skills On-Job-Training
Use of e-LMS expands but is supplemental
Regular supervision and annual inspection to determine compliance
Follow-up training and retraining: New work procedures or equipment
Tasks performed infrequently
Performance based
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(a)(3) Information Transfer
New provisions require the host and line clearance contractor to share safety-related information
Of importance to the LCTT from the Host Utility
Locations of Circuits and Equipment
Nominal Voltages and Utility Specific MADs
Emergency Contacts and Procedures
Line Crew work activity that could affect our LCTT operations or vice versa
Process to Request De-energize, Ground and Test
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(a)(3) Information Transfer
Sharing Information from LCTT to the Host Utility
LCTTs do not work on the lines
They may not recognize the same hazardous conditions as a line worker
Would share information about downed lines, or broken poles that might be observed
Would share information about work activity such as tree removal risk and procedure, and staying out of the LCTT work area if host employees are present
Communications are usually verbal, email, or by Host specified means and process
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(c) Job Briefing
Subjects: Hazards associated with the job, work procedures
involved, special precautions, energy-source controls, and personal protective equipment requirements
Information learned from Host that pertains to specific job / project performed by LCTT Contractor
Number of briefings: Before start of work for each day or shift
Additional job briefings if significant changes occur
Based on nature and complexity of work
Job planning for one-person crews
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(g) Personal Protective Equipment
Employer PPE Hazard Assessment
Eye, Head, Hearing
Aerial Lift Fall Protection Fall Restraint, or Fall Arrest Systems???
LCTT Employer Must Assess, Determine, and Implement System by December 31, 2015
OSHA does not consider trees and wires lower level, however, we work over buildings, etc.
Minimize Possibility of Fall to Lower Level
Lanyard short as practicable, no more than 6ft.
Tree Climbing Fall Protection - (r) and Z133
Chainsaw Leg Protection - Z133
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(r): Line Clearance Tree Trimming Operations
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(r)(1)(iii) Electrical Hazards
Inspection of site and tree prior to work LCTT shall maintain Minimum Approach Distance Paragraph (l) does not apply to LCTT, nor do the FR
or arc-rated protective clothing requirements apply to LCTTs
Aerial devices, and ladders maintain MAD (r)(1)(iv) Insulated Pole Tool vs. Conductive Tool
Branches contacting energized conductors or within MAD may only be removed using insulating equipment
Tools constructed of a material with insulating qualities employer can demonstrate meet (j)(1)
Conductive tool (chainsaw) used after MAD is attained
If LCTT cannot maintain MAD, request the line be De-energized, Grounded & Tested by the Utility
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
1910.269(r)(1)(iii) Electrical MAD
Historically LCTT MAD Tables Published In ANSI Z133, 2012 current edition, 5 yr. cycle
MAD Tables and Z133 are Under Revision OSHA Verified Phase to Ground Exposure Tables R-6 and R-7 Alternative MADs Includes Altitude Correction to 5, 10, 14k Ft Current Table Distances are similar to or
greater than R-6 and R-7 Customer Provided MADs
EEI Fall 2015 OSH Committee Conference 1910.269, Utility Line Clearance Contractors Perspective
Arborist Tools and Equipment
Chainsaws, also see 1910.266(e) No Drop Starting
Two Handed Grip
Leg Protection Required For Ground Operations - Z133
Climber Fall Protection
Rope, climbing, and rigging
Brush chippers
Sprayers for Herbicide Applications
Stump cutters
Brush Saws
The Z133 Standard contains Arborist Safety Requirements for Work Aloft, Pruning, Rigging, Tree Removal, Ground Work