19/5/2004 LHC-b OTR PRR 1
Schedule and Resources
Jan SpeltJan Spelt
19/5/2004 LHC-b OTR PRR 2
This presentation
Sequence of activitiesSequence of activities
Activities and manpowerActivities and manpower
Critical activitiesCritical activities
Production scheduleProduction schedule
Manpower budgetManpower budget
Remarks to concludeRemarks to conclude
19/5/2004 LHC-b OTR PRR 3
Panel assembly sequence
19/5/2004 LHC-b OTR PRR 4
Module assembly sequence
19/5/2004 LHC-b OTR PRR 5
Activities & manpower
Straw preparationStraw preparation 1 day, 1 man, 64 straws1 day, 1 man, 64 straws Panel assemblyPanel assembly 0.5 day, 2 men0.5 day, 2 men Panel wiringPanel wiring 1.5 days, 2 men1.5 days, 2 men Panel measurement & repair &Panel measurement & repair & 0.5 day, 2 man0.5 day, 2 man
panel to module preparationpanel to module preparation Side wall preparationSide wall preparation 0,25 day, 1 man0,25 day, 1 man Module assemblyModule assembly 0.5 day, 2 to 3 men0.5 day, 2 to 3 men Module completionModule completion 0.5 day, 1 man0.5 day, 1 man Leak test & repairLeak test & repair 0.75 day, 1 man0.75 day, 1 man 9090 Sr scan test Sr scan test 2 days, 0,5 to 1 2 days, 0,5 to 1
man man
19/5/2004 LHC-b OTR PRR 6
Straw preparation
Time in minutes Daily hours Effectiveness % Number5 8 75 724 8 75 903 8 75 120
Straw preparation independent from module assemblyBufferHave to gain experience about real possible speed
Aim: At least one 128 straws per day
Tune preparation processMore then 8 hours a dayExtra tooling and personnel in parallel
19/5/2004 LHC-b OTR PRR 7
Panel wiring
Very time consumingVery time consuming
Not suitable for improvementNot suitable for improvement
Do wiring partly in parallel (synchronized with panel gluing)Do wiring partly in parallel (synchronized with panel gluing)
Extra tooling and personnelExtra tooling and personnel
Practice may shorting this activity a little bitPractice may shorting this activity a little bit
19/5/2004 LHC-b OTR PRR 8
Schedule
Date 30/06/2004 30/09/2004 31/12/2004 31/03/2005 30/06/2005 30/09/2005 31/12/2005 31/03/2006Work days 20 45 60 60 60 45 60 60Del. speed 6 6 4 3 3 3 3 3Total 3 11 26 46 66 81 101 121
Del. speed 6 6 4 3 3 2 2Total 3 11 26 46 66 88 118
Module delivery
0
25
50
75
100
125
RealisticOptimistic
19/5/2004 LHC-b OTR PRR 9
Man power budgetDate 30/06/2004 30/09/2004 31/12/2004 31/03/2005 30/06/2005 30/09/2005 31/12/2005 31/03/2006Del. speed 6 6 4 3 3 3 3 3Man power 7 8 8 9 9 9 9 9
Del. speed 6 6 4 3 3 2 2Manpower 7 8 8 9 9 10 10
Available 5 8.3 10.6 11 11 11 10 6
Manpower needs
56789
101112131415
RealisticOptimisticAvailable
19/5/2004 LHC-b OTR PRR 10
Remarks to conclude
o Critical activities Critical activities o Straw productionStraw production
o More then 8 hours, extra personnelMore then 8 hours, extra personnelo Second facility plus extra personnelSecond facility plus extra personnel
o WiringWiringo Parallelism, extra personnelParallelism, extra personnel
o For this year Nikhef manpower is covered, the end of next year is For this year Nikhef manpower is covered, the end of next year is still to be solvedstill to be solved
o If assembly will run smooth may be it is possible to end up with a If assembly will run smooth may be it is possible to end up with a delivery cycle of 2 days delivery cycle of 2 days