1E. Tsitrone Progress report DITS 27/04/2007
• Overview : E. Tsitrone (20 + 5 mn)
• Experimental campaign : B. Pégourié (15 + 5 mn)
• TPL analysis program : C. Brosset (25 + 5 mn)
• Integrated planning : M. Houry (10 + 5 mn)
• General discussion : all (30 mn)
Progress report on the DITS project :Agenda
2E. Tsitrone Progress report DITS 27/04/2007
Progress report on the DITS project :Overview
• What happened since the last project board ?• Management plan• Final finger selection• Erosion / redeposition (confocal microscopy)• Safety analysis
• What’s next ?• On going activities• Collaboration agreement• Planning
3E. Tsitrone Progress report DITS 27/04/2007
Internal review (CCAT, 20/12/2006) : project approved
Technical :• sample conditionning for storage• samples from other PFCs (bumpers, outboard limiter)• safety regulations regarding sample activation• measurements for erosion/redep (confocal microscopy) : critical path, funding
Management :• definition of milestones / deliverables• risk analysis• budget• regular reporting to our internal and external partners, web site• integrated in the EU PWI TF work programme
External review (08/12/2006) :Assessment from advisory board (J. Roth -EU PWI TF, M. Mayer-IPP, P. Roubin -PIIM)
• great relevance for predictions of the tritium inventory in ITER• international collaborations world-wide available expertise• preparatory discharge programme of high importance
C. Brosset
Since the last project board …
B. Pégourié
E. Tsitrone
4E. Tsitrone Progress report DITS 27/04/2007
Management plan underway
DITS : Deuterium Inventory in TS
• Compare particle balance / post mortem analysis in TS• Identify retention mechanisms (bulk diffusion)
implications for ITER
5E. Tsitrone Progress report DITS 27/04/2007
Management : project phasing
Objectives Review
Phase 0a – Definition Scientific objectives
Feasibility study
Project board 08/12/07
CCAT (20/12/2006)
Phase 0b – Organisation Budget / planning / resources, risk analysis, management plan Progress report 1 (27/04/07)
Execution phase 1 :
Experimental campaign
D loading of TPL
Monitor particle balance
Progress report 2 : experimental campaign (july)
Execution phase 2 :
Dismantling / reassembly of TPL
In situ analysis (lock in + erosion/redeposition)
Extraction of selected fingers
Progress report 3 : TPL dismantling/ in situ analysis (september)
Execution phase 3 :
Samples preparation
Samples extracted and ready for analysis
Progress report 4 : samples (november)
Execution phase 4 :
Samples analysis
Perform analysis program
Collect data
Analysis and publication of results
Intermediate meetings : partial results (tbd - 2008)
Progress report 5 : global results (tbd – 2008/2009)
Close out phase 5 Feedback Closeout review (tbd)
6E. Tsitrone Progress report DITS 27/04/2007
Management : information sharing tools
• Slides available on the EU PWI TF web site (http://www.efda-taskforce-pwi.org/) in the SEWG on particle balance
• Participative web site underway : edoc (collaborative work, file archiving)
7E. Tsitrone Progress report DITS 27/04/2007
Initial fingers selection
Fluence dependance in erosion zones
Thin / thick deposits
Fast particles in ripple
1.7 MA, no perp. flux
Courtesy of R. Mitteau, C. Brosset
8E. Tsitrone Progress report DITS 27/04/2007
Final fingers selection (satellite projects) Migration C/retention D (41 tiles, fing 5, 27, 28) Structure CFC (6 tiles) PFC (2 tiles, fing 1 et 17) IR (6 tiles, fing 4 et 26) Detritiation (fing 6 et 10)
9E. Tsitrone Progress report DITS 27/04/2007
Erosion/redeposition measurements Selected : Confocal microscopysurface mapping image difference for ero/redep. 2007 = starting point – next : in situ in TS
Budget ~ 100 kEurosCall for support from regional funding (50 kEuros)Optical part : call for tender launchedMechanical part : final design approvedIntegration and test : july 2007Measurements on sector : august 2007
on fingers : september 2007
?
ero
redep
Max resolution : 1 m in z, 20m in x-yReference inserted between fingersZones : 200 mm (radial) x 100 mm (toroidal)20° on TPL sector : 30 + 10 zones 11 days
Planning optimization :• sector equipped with new fingers• extracted fingers (no impact on shutdown)
zy
x
10E. Tsitrone Progress report DITS 27/04/2007
Sample activation Aim : TPL fingers and tiles = conventional samples
7Be (period = 53 days) : limit at 100 Bq/cm2 for surface contamination (1/10 of exemption limit)
Previous measurements : scraping on TPL : 1-5 Bq/cm2 (mobile)full deposits : < 50 Bq/cm2 (fixed + mobile)
Proposal for agreement on safety procedures underway :
• 3 phase control :On TPL sector monitored area in DRFC (sector dismantling, measurements, fingers extraction)On extracted fingers non monitored area in DRFC (tile extraction, analysis in DRFC)On tiles non monitored area outside CEA (conventional transport, sample cutting, analysis in our partners labs)
• Exchange protocol with external partners• Annual report on samples
11E. Tsitrone Progress report DITS 27/04/2007
What’s next ?
12E. Tsitrone Progress report DITS 27/04/2007
On going activities …• WP0 : Management :• Management plan, information sharing tool (E. Tsitrone, L. Jourdheuil)• Integrated planning (M. Houry, echange/DITS/PLANNING)
• Safety aspects : ok for conventional operation (K. Zunino), agreement on specific procedures for sample activation (F. Saint Laurent)
• WP1 : Experimental campaign : • Preparatory experiment (11/05/2007), diagnostics strategy (P. Moreau)• Dedicated campaign manning (B. Pégourié)
• WP2 : TPL dismantling :• Specific tooling for TPL sector and fingers protection (A. Martinez)• SATIR test (new fingers selection) (J. Schlosser)• Planning / human resources for summer shutdown (F. Samaille, M. Houry)
• WP3 : TPL analysis :• Preparation for confocal microscopy (E. Gauthier, H. Roche)• Validation of tile extraction process (J. Schlosser)• Integrated analysis program (C. Brosset)• Sampling from other PFCs (C. Brosset)
13E. Tsitrone Progress report DITS 27/04/2007
WP4 : Satellite projects
Dust :Characterisation + effect of maintenance, sampling location, analysis program (MEB)
IR : low cost option• Thermal properties of deposited layers (power balance for IR on TPL) : with available laser (Speckle)• IR monitoring of neutralisers : simple fiber replacement• Cancelled : upgrade of calorimetry, active thermography, TPL cleaning procedure
PFCs :• Lock in thermography on extracted sector• Analysis of defective tiles on Q6A• Oxydation of cooling channels• Cancelled : finger repair• Added : acoustic sensor for CHF detection (feasibility)
Detritiation :Test on deposited layers + gaps : • laser cleaning (CEA) : lab through safety procedures before commisionning• oxydation/scavengers : CIEMAT, MEPHI
14E. Tsitrone Progress report DITS 27/04/2007
Collaboration agreement for analysis
• Integrated into EU PWI TF (STAC), preferential support in 2008 for EU participating labs ?
NRA NRA SIMS TDS Structure Porosity
Detritiation
CEA-DRFC (JY Pascal, H. Roche)
X X
CEA-LECA (L. Desgranges)
X
CEA-LPS (H. Khodja)
X
CP2M – Tecsen (W. Saikaly, F. Boquet)
X
PIIM (P. Roubin)
X
IPP (M. Mayer)
X
IPP (W. Jacobs)
X
FZ Juelich (A. Kreter)
X ? X ? X ?
JSI (P. Pelicon)
X
VTT-Tekes (J. Likonen)
X
VR (M. Rubel)
?
CIEMAT (P. Tabares)
X
Sandia R. Causey
X (virgin CFC)
MEPHI (L. Begranbekov)
X X
• Call for interest after last project board : all needed measurements covered
• Collaboration agreement :• Integrated analysis program• Sample preparation / identification• Experimental protocol for all measurements involved• Data collection (data format, intermediate reports …)• Strategy for global analysis• Publication policy : editorial board (TS + participating labs)
Suggestions welcome !
15E. Tsitrone Progress report DITS 27/04/2007
Provisionnal planning for TS
Jan Feb.Jan Feb. March April May June July. Aug. Sept. Oct. Nov. Dec.
Arrêt hiver 06/073 4,5 2 1 5 4
AIA (V+T)AIA (PA)
Winter shutdown Winter SD07/06 Summer Shutdown 01/10
Cat.1Dismantling
3D Meas.
Install ICRH Iter-like
12/06 DITS 12/09
3 4,5 23 4,5 2 1 5 4 1 5 5 3 4
SpecConsult.
Real.Assemb.
3D Diagnostic manufact.
16E. Tsitrone Progress report DITS 27/04/2007
Provisionnal planning for DITS
11/05/07 Validation of plasma scenario
23/05/07 Carbonisation + boronisation
24/05/07 up to 07/06/07
Dedicated campaign (10 days, long shift)
June 2007 •TS openingControl TS + TPL sector
• TPL dismantling• Lock in Thermography
• Extraction selected fingers
Control on fingers Replacement by new fingers
July 2007 Leakage test of TPL sector
August 2007 Confocal microscopy on TPL sector
September 2007
• Confocal microscopy on extracted fingers• Tile extractionControl on tiles
• Samples cutting from tiles
TPL reassembly in TS
October 2007
• Samples characterization• Sample ready for analysis
TS restart
DITS TS