1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit : 120 min File Version : 1.0 http://www.gratisexam.com/ 1Z0-560: Oracle Unified Business Process Management Suite 11g Essentials price: US$ 195 questions: 77 passing score: 65%

1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

  • Upload
    vantram

  • View
    240

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials

Number: 1Z0-560Passing Score: 650Time Limit: 120 minFile Version: 1.0

http://www.gratisexam.com/

1Z0-560: Oracle Unified Business Process Management Suite 11g Essentials

price: US$ 195questions: 77passing score: 65%

Page 2: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Exam A

QUESTION 1You can implement complex server-side validation logic to the task form by using a custom__________.

A. data controlB. managed beanC. EL scriptD. UI component

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 2Identify one activity that is used to create a process hierarchy as a parent child relationship.

A. Sequence FlowB. Call ActivityC. Service TaskD. Send Task

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 3Which two are true about project data objects? Select two.

A. Any process in the project can access a project data object.B. The value of a project data object does not vary between processes.C. Project data objects can be only used as input arguments to a process.D. Project data objects can be used in data associations and expressions.

Correct Answer: ADSection: (none)Explanation

Explanation/Reference:

QUESTION 4Where are the two places that you can see a visual representation of the path a running process has taken?Select two

A. BPM WorkspaceB. Enterprise ManagerC. Process ComposerD. JDeveloper MDS Explorer

Page 3: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

E. WebLogic Console

Correct Answer: ACSection: (none)Explanation

Explanation/Reference:

QUESTION 5Which start event is allowed in a subprocess?

A. Timer Start EventB. Boundary EventC. Message Start EventD. None Start Event

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 6Which three tasks need to be accomplished to allow successful publishing of process metrics to<br/>BAM?Select three.

http://www.gratisexam.com/

A. setting BPM project preferences to enable BAM as a data targetB. configuring the BAM Adapter on the SOA serverC. updating the Enterprise Manager configuration for Disable ActionD. importing BAM dashboards

Correct Answer: ABDSection: (none)Explanation

Explanation/Reference:<br/>A. setting BPM project preferences to enable BAM as a data target<br/>B. c<br/>C. updating theEnterprise Manager configuration for Disable Action<br/>D. importing BAM dashboards

QUESTION 7Which two are predefined instance attributes that can be used in data associations and expressions? Selecttwo

A. ActivationCountB. ComponentC. LoopCounter

Page 4: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

D. String

Correct Answer: ACSection: (none)Explanation

Explanation/Reference:

QUESTION 8BPM capability maturity levels describe__________

A. the capabilities of the BPM business analystB. the length of time the BPM application has been in productionC. the strategic and tactical levels of enterprise adoption of BPMD. BPM concepts, consistently applied, facilitating sharing and reuse

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 9Which two features are provided by BPM Process Analytics? Select two.

A. simulation for a BPM processB. easy-to-use process metric collectionC. easy-to-use modeling toolsD. custom reporting dashboards

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:

QUESTION 10A task form is generated as a (n) __________.

A. portlet that gets called in the BPM WorkspaceB. generic JSP page that is displayed in an I Frame in the BPM WorkspaceC. bounded task flow that is called by the BPM WorkspaceD. unbounded task flow that is called by the BPM Workspace

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 11Which three can be classified as measurement marks? Select three.

Page 5: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

A. Interval startB. SignalC. Counter markD. Single measurement

Correct Answer: ACDSection: (none)Explanation

Explanation/Reference:

QUESTION 12Which two activities are supported by BPM Studio? Select two.

A. Design BAM dashboardsB. Design user interfacesC. Design value chain modelsD. Design adapter services

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:

QUESTION 13What is the specially-seeded BPM role with business admin privileges to act on others' behalf or reassigntasks?

A. WebLogicB. BPM AdminC. Process OwnerD. Business Data

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 14The initial performer of a task is determined by the role associated with the swimlane in which the task Modeledexcept when you use___________

A. a complex taskB. a user taskC. an FYI taskD. a group task

Correct Answer: ASection: (none)

Page 6: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Explanation

Explanation/Reference:

QUESTION 15Which three actions can be performed in Process Spaces? Select three.

A. set up business rules for collaborationB. share documents such as requirement documents, feedback documents, and design specsC. discuss issuesD. define business indicators for custom dashboardsE. create a process instance space for collaboration specific to one process instance

Correct Answer: BCESection: (none)Explanation

Explanation/Reference:

QUESTION 16Human workflow notifications are implemented if through___________.

A. user written Java code called from within the BPMN/BPEL processesB. scripts included in task definitionsC. integration with the SOA User Messaging Server (UMS)D. integration with third party products

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 17Beyond process modeling, which two activities are supported by the Process Composer? Select two.

A. Defining complex data typesB. Defining business rulesC. Defining human tasksD. Defining adapter services

Correct Answer: BCSection: (none)Explanation

Explanation/Reference:

QUESTION 18Which one is not correct regarding the Process Simul-ation Model?

A. The percentage of time that a conditional or default path is executed Is captured by the Probability property.

Page 7: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

B. The rate of arrival of process instances is specified as a parameter at the Start Event.C. The cost of a process step is specified by the fixed cost and resource cost properties.D. The processing time is a constant and is specified as Days:Hours:Minutes:Seconds.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 19Which two correctly describe a Project Simulation Model?

A. It is used for simulation across multiple processes.B. It describes the simulation scenario for a process model.C. It is associated with shared resources.D. It is configured using BPMN 2.0 notation.E. It is driven by parameters provided at application deployment time.

Correct Answer: ACSection: (none)Explanation

Explanation/Reference:

QUESTION 20A task is considered overdue when__________

A. there are no more renewalsB. the current date is beyond the due dateC. the current date is beyond the expiration dateD. the current date is beyond both the expiration and the due date

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 21JavaServer Faces (JSF), JavaServer Pages (JSP), ADF Faces Rich Client (ADF Faces RC), and DataVisualization Tool (DVT) are all components that form the ADF __________.

A. Data control layerB. UI binding layerC. ControllerD. View layer

Correct Answer: DSection: (none)Explanation

Page 8: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Explanation/Reference:

QUESTION 22Which two could be used to handle exceptions thrown by a service? Select two

A. SubprocessB. event subprocessC. error end eventD. error catch event as a boundary event on the service task

Correct Answer: BDSection: (none)Explanation

Explanation/Reference:

QUESTION 23In the BPM Workspace, which two are available as ways to sort your tasks? Select two.

A. list tasks sorted by workloadB. list tasks sorted by priorityC. list tasks sorted by a value in the task like sales dollar amountD. list tasks sorted by manager

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 24Which one is semantically valid in BPMN?

A. Error Start Event for an Event SubprocessB. Message flows that connect process steps within the same poolC. Error Start Event to trigger a processD. Error Intermediate Event to catch errors in the middle of a***

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 25In Oracle BPM 1 11g, which two things can be accomplished using a script task? Select two.

A. execute Java codeB. execute XSLT transformationsC. copy data to variables or between variablesD. define new process variables

Page 9: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Correct Answer: BCSection: (none)Explanation

Explanation/Reference:

QUESTION 26Which two features do you find in decision tables? Select two

A. Sets of input data can bebucketed and reviewed for gaps.B. Data sets can be reviewed for conflicts.C. Data can be used for only one rule evaluation.D. A rule evaluation can only be used to enter new output data.

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 27In a business rule decision table, ___________ .

A. Only one rule can executeB. Rules can have only one actionC. Conflicting rules will not executeD. One rule can modify another rule outcome

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 28By default, which two task participant roles can change the outcome of a task? Select two.

A. AdminB. ApproversC. AssigneesD. CreatorE. OwnerF. Reviewer

Correct Answer: CESection: (none)Explanation

Explanation/Reference:

Page 10: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

QUESTION 29Which two options can be used to create custom dashboards on business indicator data? Select two.

A. BPM Process WorkspaceB. WebCenter Process SpacesC. BPM StudioD. Oracle BAM

Correct Answer: ADSection: (none)Explanation

Explanation/Reference:

QUESTION 30Which two are correct about business indicators? Select two.

A. Business indicators can be captured at measurement marks.B. Dimensions allow the user to capture numerical values.C. All business indicators are captured at sampling points and a subset are captured at measurement marks.D. Counters should always be used at Interval Start and Interval Stop.

Correct Answer: ACSection: (none)Explanation

Explanation/Reference:

QUESTION 31Business Rules can be integrated with ___________, _____________ and ____________ . Select three.

A. Human workflowB. Start eventsC. BPMN processesD. BPEL processesE. Web services

Correct Answer: ACDSection: (none)Explanation

Explanation/Reference:

QUESTION 32Which three artifacts are parts of the Business Catalog in Oracle BPM Suite 11g? Select three

A. Human workflow implementationB. Organization units and rolesC. Business rules implementationD. Business exceptionsE. Business indicators

Page 11: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Correct Answer: ACDSection: (none)Explanation

Explanation/Reference:

QUESTION 33Which one of these components provides a shared work environment access multiple BPM Studio ProcessComposer clients?

A. Oracle Enterprise Repository (OER)B. Oracle Meta Data Services (MDS)C. Oracle BPM Repository (OBR)D. Oracle Business Process Analysis Suite (OBPA) Repository

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 34Human workflow is implemented as a_________.

A. service engine within the SOA infrastructureB. component within the BPEL service engineC. component within the BPMN service engineD. shared component within both BPEL and BPMN service

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 35Which one is not allowed?

A. Non-interrupting Timer EventB. Non-interrupting Error EventC. Non-interrupting Message EventD. Non-interrupting Signal Event

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Page 12: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

http://www.gratisexam.com/

QUESTION 36Which out-of-the-box dashboard would you use to determine how many instances were particular businessprocess?

A. Workload Per ProcessB. Performance Per ProcessC. Workload Per ParticipantD. Performance Per Participant

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 37In Oracle BPM 11g, a signal event is implemented as a(n)

A. JMS topicB. EDN eventC. synchronous serviceD. asynchronous service

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 38Which three levels allow for sampling point generation for a BPM process? Select three.

A. ProcessB. ProjectC. ActivityD. Simulation

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:

Page 13: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

QUESTION 39Which one of these implementations will allow a process to reply back to the calling process?

A. a Receive task followed by a Send task that implements a Service call to the calling processB. a Send task with Conversation set to Initiates In its implementationC. a Service task that implements a Process Call to the calling processD. a Receive task with Conversation set to Initiates followed by a Send task with conversation set continues

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 40Which three allow defined business indicators to be measured? Select three.

A. Sampling pointsB. Start and stop intervalC. Single measurementD. Counters

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:

QUESTION 41Which three models are supported in the BPMN 2.0 specification? Select three.

A. Value Chain ModelB. Process ModelC. Collaboration ModelD. Choreography ModelE. Event Process Chain (EPC) Model

Correct Answer: BCDSection: (none)Explanation

Explanation/Reference:

QUESTION 42Which three can you analyze using simul-ation? Select three

A. Process throughput and performanceB. Resource allocation for rolesC. Activity-based costD. End-to-end production run-time durationsE. ROI

Page 14: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:

QUESTION 43Which components are parts of BPM Suite 11g? Select two or three.

A. Oracle Business Activity Monitoring (Oracle BAM)B. Oracle Business RulesC. Oracle WebCenterD. Oracle Business IntelligenceE. Oracle Business Process Analysis

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 44When is an approval group name resolved?

A. Design timeB. During compileC. During deploymentD. At run time

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 45Which one is not a list builder used to determine the actual list of approvers in a management task?

A. Approval groupsB. Business rulesC. Job levelD. BPM role

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 46Which three options does process tracking provide?

Page 15: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

A. It is available from the Process Tracking tab in Workspace.B. It is available to any user participating in a process.C. It shows data entered at each point in the process.D. It shows the path taken during process execution.E. It allows any user participating in the process to modify the process execution.

Correct Answer: ADSection: (none)Explanation

Explanation/Reference:

QUESTION 47Which three are addressed by BPMN 2.0? Select three.

A. XMI-based and XML-based interchange formatsB. Process choreographyC. Organization modelsD. Event composition and correlationE. Data and information models (logical, physical, and conceptual)F. Business strategy

Correct Answer: ABDSection: (none)Explanation

Explanation/Reference:

QUESTION 48Which ADF technology binds UI components, such as input fields, to human task details?

A. Managed beansB. Data controlsC. Bounded task flowD. Human workflow Web services

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 49Which one empowers the business user to model the business process?

A. BPM StudioB. BPM ComposerC. Enterprise ManagerD. BPM Analytics

Page 16: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 50Which three activities are most likely performed by a Business Analyst? Select three

A. model business processesB. design and implement user interfacesC. simulate and analyze business processesD. create services for system interactionsE. design and implement BAM dashboards

Correct Answer: ACESection: (none)Explanation

Explanation/Reference:

QUESTION 51Process instance data is made available to task instances via___________.

A. data associations defined on the activity's implementation tabB. transformations defined as part of the task metadataC. script tasks implemented before and after the activityD. references to global process variables from inside the task definition

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 52Which three measurement marks can be identified on a sequence flow? Select three.

A. Interval startB. Interval stopC. Counter markD. Single measurement

Correct Answer: ABDSection: (none)Explanation

Explanation/Reference:

QUESTION 53Which statement is false about a Process Simul-ation Model?

Page 17: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

A. It does not execute actual code of a process.B. It captures time and cost parametersC. It computes business rulesD. There can be multiple Process Simulation Models for a business process model in BPM Studio.

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 54Which two actions can you perform on a task in your Inbox? Select two.

A. You can reassign the task to a colleagueB. You can delegate the task to your managerC. You can postpone a due date to a later dateD. You can re-open a completed task

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 55Only the process owner of a process can ____________ .

A. cancel a process instanceB. view the details of a process instanceC. associate comments with a process instanceD. change the columns of a process view

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 56Which one cannot be used as a start point to initiate a new instance of a process?

A. Initiator User TaskB. Call TaskC. Receive TaskD. Message Start Event

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

Page 18: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

QUESTION 57Which one is a gateway type used in the context of process interactions?

A. Exclusive GatewayB. Event Based GatewayC. Inclusive GatewayD. Parallel Gateway

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 58Which end event should you use at the end of your process to send a message to a specific process?

A. None End EventB. Terminate End EventC. Signal End EventD. Message End Event

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 59Which one of these tools would you use to see the detail information, like source component and about faultsgenerated by a running process?

A. BPM WorkspaceB. Enterprise ManagerC. Process ComposerD. JDeveloper MDS Explorer

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 60Which two are true about a bounded task flow? Select two.

A. A user can navigate to any page in a bounded task flow.B. A bounded task flow can participate in a database transaction.C. A bounded task flow can be called by another bounded task flow.D. A bounded task flow is stateless.

Page 19: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Correct Answer: BCSection: (none)Explanation

Explanation/Reference:

QUESTION 61In the ADF model-view-controller architecture, the controller is the ADF____________.

A. binding layerB. data control layerC. controllerD. faces

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 62Which two statements are true? Select two.

A. In Oracle BPM 11g, a BPMN process can have only one start and one end event.B. A process started with a Timer Start Event can end with a message end event.C. A None Start Event is required when using a Human task of Initiator type to start a process.D. A Timer Start Event is used to automatically initiate a new instance of a process.

Correct Answer: CDSection: (none)Explanation

Explanation/Reference:

QUESTION 63Which two are available using BPM Workspace? Select two.

A. Administration of user groupsB. Administration of vacation rulesC. Administration of the BPM process life cycleD. Administration of end-user passwords

Correct Answer: BCSection: (none)Explanation

Explanation/Reference:

QUESTION 64Which task should be accomplished to enable metrics data to be sent to Oracle BAM?

Page 20: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

A. "BAM" is checked as a data target for one or more processes.B. All deployed projects on the BPM server must be configured for "Enable BAM."C. "Enable Cubes (Process)" setting is disabled as data targets.D. Cube Update Frequency is established in Enterprise Manager.

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 65Which human task pattern would be best suited for single approver scenario where the role is resolved throughgroup membership?

A. UserB. GroupC. InitiatorD. FYIE. Management

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 66Process data objects can be accessed from_________.

A. any process in a projectB. any task within a processC. a subprocess onlyD. a user task form

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 67Which human task pattern would be best suited for a voting-based approval scenario where the role isrestricted to participants who are managers?

A. UserB. GroupC. FYID. Management

Correct Answer: BSection: (none)

Page 21: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Explanation

Explanation/Reference:

QUESTION 68What is the purpose of measures?

A. Capture a KPI-relevant numeric valueB. Slice data for analysisC. Count exception flowsD. Acquire audit information

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

QUESTION 69Which one of the user personas is least likely to use Process Composer?

A. Process DeveloperB. Business UserC. Business AnalystD. Line of Business Owner

Correct Answer: BSection: (none)Explanation

Explanation/Reference:

QUESTION 70When you create a swimlane role, the artifact that's created is a (n) __________ .

A. virtual userB. approval groupC. LDAP groupD. application role

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 71Which one is a BPMN flow object that is used to represent process interactions?

A. Sequence flowB. Association

Page 22: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

C. Default flowD. Message flowE. Conditional flow

Correct Answer: DSection: (none)Explanation

Explanation/Reference:

QUESTION 72Business Process Management (BPM) is more than just orchestration of activities. Which three are key aspectsof BPM? Select three.

A. Process TransparencyB. Process IntelligenceC. Continuous Process ImprovementD. Web Services InteroperabilityE. Identity Management

Correct Answer: ABCSection: (none)Explanation

Explanation/Reference:

QUESTION 73Which two business indicators should be created to identify a value like "Sales Total by Region"? Select two.

A. MeasureB. DimensionC. CounterD. Counter Mark

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 74Which two are true about BPM roles? Select two

A. BPM roles are concrete roles defined in the enterprise directory.B. BPM roles are abstract roles.C. Application roles can be defined as members of a BPM role.D. BPM roles are private to a process.

Correct Answer: BCSection: (none)Explanation

Page 23: 1Z0-560 Oracle Unified Business Process Management Suite ... · 1Z0-560 Oracle Unified Business Process Management Suite 11g Essentials Number : 1Z0-560 Passing Score : 650 Time Limit

Explanation/Reference:

QUESTION 75A Send activity is the same as a_________.

A. Message Start Event of an Event SubprocessB. Message Boundary EventC. Throw Message Intermediate EventD. Catch Message Intermediate Event

Correct Answer: CSection: (none)Explanation

Explanation/Reference:

QUESTION 76In which two ways can BPMN processes use rules? Select two.

A. Rules are used to define process flow.B. Rules are used to describe human task assignments.C. Rules are used to modify past actionsD. Rules are used to change completed task activities.

Correct Answer: ABSection: (none)Explanation

Explanation/Reference:

QUESTION 77Which event type cannot be used as a trigger at the start of a BPMN process?

A. Error Start EventB. Message Start EventC. Signal Start EventD. None Start Event

Correct Answer: ASection: (none)Explanation

Explanation/Reference:

http://www.gratisexam.com/