Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1/16/2020
1
1
HMA Pavingfor Inspectors
2020
2
Topics of Discussion
Hot Mix Asphalt “HMA” (Section 402)
HMA Series (50, 60, 70, and 80)
Prep
Joint Adhesive
Tack Coat
HMA Paver
HMA Paving Defects
Documentation
3
Section 402
Seasonal Limits for Top Course
Upstate – April 15 to October 31
Downstate – April 1 to November 30
Surface Temperature 50°F and rising for layer thickness 1.0 inch or less
45°F and rising for greater than 1.0 - 3.0 inches thick
40°F and rising for layer thickness greater than 3.0 inches
Guidelines for measuring surface temperature
4
HMA Series
50 Series – Expressways
60 Series – High Volume Hwy >2000 tons of top
70 Series – High Volume Hwy <2000 tons of top or Low Volume Hwy >2000 tons of top
80 Series – Specified for miscellaneous placements, shoulders, bridge approaches (regardless of the project location), True & Leveling, Shim, 6.3mm etc.
5
Methods to Check Density
6
HMA Series Compaction
50 Series - Daily Coring
60 Series - Coring for test section and additional coring every 3rd day of mainline placement
70 Series - No coring, construct a test section and monitor density with a nuclear gauge
80 Series – No coring or nuclear gauge; compaction determined by number of roller passes (see Table 402-6)
1/16/2020
2
7
50 Series Construct a Test Section (Option 1), or Proceed with Routine
Paving (Option 2) (Contractor’s Choice)
Routine Density Monitoring via Daily Coring Mainline Paving, Ramps >1250 feet
Cores Results Used to Determine Pavement Density Quality Adjustment Factor (QAF) QAF Range 0.60 - 1.05
8
60 Series Construct a Test Section - Project Target Density “PTD”
Option 1 (Test Strip Only) or Option 2 (Continue Paving)
Contractor uses a gauge to monitor density every 200 ft
≥96% and ≤103% of PTD
Moving average of last 10 tests ≥98% of PTD
See MP 402-02 for density monitoring using a gauge
Engineer or Inspector checks BR Form 5 times signs off
96% or 103%Average of last 10 98%
200 ft
9
60 Series Compaction
Additional Cores for Density Verification One set of 4 cores every 3rd day of
mainline paving Cores Assigned QAF Applied to
Mainline tonnage only. Maximum QAF = 1.0
Multiple Paving SitesNew Test Section Not RequiredFirst Day of PavingUse Previously Established PTDTake 4 cores over entire day's
placement for PTD verification
10
11
70 Series Compaction
Test section is 1500 ft max in one lane
PTD is the average of highest densities at each of
3 random locations
150 ft 1350 ft
1500 ft
Lane 1
Lane 2
Excluded Area
12
70 Series Construct a Test Section and
determine the PTD by “peak” method using a nuclear gauge
1/16/2020
3
13
70 Series Compaction Contractor uses a gauge to monitor density Each test location ≥96% and ≤103% of PTD Moving average of last10 tests ≥98% of PTD See MP 402-02 for density monitoring using a
gauge Engineer or Inspector checks BR Form 5 times
signs off
�96% or 103%Average of last 10 98%
200 ft
14
80 Series Compaction
This method is used for
6.3 HMA
Small Placements
Bridge Approaches, Culvert Replacements, etc.
T&L (where thickness is not specified)
Misc. Paving, i.e., repairs
Number of Passes per Table 402-6
15
80 Series CompactionTABLE 402-6 NUMBER OF PASSES1
Pavement Courses
Static Compaction Vibratory Compaction
Steel WheelRollers
PneumaticRollers
VibratoryPasses
StaticPasses
37.5 Base (Each Lift)
8 3 6 4
25 Binder 8 3 6 4
19 Binder 6 3 4 2
12.5 Top 6 3 4 2
9.5 Top 4 3 4 2
Permeable Base2 - - - 2
Vibratory Pass Movement of Roller with Both Drums Vibrating
Static Pass Movement of Roller with Both Drums Not Vibrating
16
80 Series Compaction
Check Number of Passes
Engineer may modify if damage occurs Determine Impacts per Foot
VPM / FT PER MINUTE Verify
Spec Requires 12 Minimum Modify roller settings if necessary
17
80 Series Table 402-6 includes recommended number of roller
passes
Follow table it is not the contractor’s choice
Requires approved rollers (from approved List)
18
Definition of a Roller Pass
Vibratory PassOne vibrating drum passes over a point
Static PassA roller (non-vibrating mode) passes over a point
1/16/2020
4
19
80 Series
Where will this method be used?
6.3 HMA paving
Small placements, i.e., bridge approaches, culvert replacements etc
Some T&L paving, repairs
20
Inspector Responsibilities
Attend Pre-Pave Meeting
Identify Mix Type
Check Mix Temperature
Check Mat Quality
Check Mat Density
21
CIM Paving
Checklist
22
Asphalt
Paving CheckList
23
Gauge Inspector Certification
Gauge operators must be certified
50, 60, and 70 series specification
Nuclear and non-nuclear gauges
Discuss with Contractor
Pre-construction
Pre-pave
24
Binder Grade
Gyration Level
1/16/2020
5
25
Identify Mix Type Too many possibilities
Mix codes
Mix Codes are printed on the delivery tickets
Example: 12.F2.2.H.C
TABLE 401-7 DELIVERY TICKET MIX CODINGMix
TypeCode
FrictionCode
Design ESAL Code Mix Type CodePG Binder
TypeCode
9.5 09 F1 <0.3 million 1 HMA H PG 58E-34 A
12.5 12 F2 <30 million 2 WMA W PG 64S-22 B
19.0 19 F3 ≥30 million 3 PG 64V-22 C
25.0 25 F9 PG 64H-22 D
37.5 37 ----- PG 64E-22 E
OTHER G
26
27
The Paving Day
28
Inspector Supplies
29
Review Plans and Specifications
30
Check Equipment
1/16/2020
6
31
Tack Coat Tack provides a bond between layers
No tack on permeable base
Prior to tack application, surface must be clean
Must be evenly applied
Must break (brown to black)
Application rate may be adjusted
32
33 34
35 36
Bad Good
1/16/2020
7
37 38
39 40
41 42
1/16/2020
8
43
Self Propelled Paving Machine
HMA Flow
44
Forces on Screed
45
There are two primary forces acting on the paver screed as the paver places the mix.
The first force is the F3 - it varies as the speed of the tractor increases or decreases.
The second force on the screed is the head of the material pushing against the screed
Paver Screed
The speed of the paver needs to remain constant.
If the speed changes the mat thickness changes and this will affect the HMA mat quality
46
It takes 5 lengths of the leveling or tow arm to attain 99% of the change in the mat thickness.
A paver with a10 foot tow arm will need to travel 50 feet
before the change in the mat thickness is achieved
Paver Screed Reaction Time
After the desired mat thickness is obtained, there should be no need to make adjustments throughout the day…
47
Mix Temperature
Why check temperature?
Helps maintain consistent densities
Check temperature at the hopper
Use either Infra Red gun or dial type thermometers
Insure the Temperature is between 325°F and 250°F ±20°F (To reject trucks, use only dial types)
Should not exceed the maximum of 325°F unless PG Binder is polymer modified
48
It is essential to have a continuous operation…
Continuous does not mean the paver never stops…
Quality HMA Pavement…
Continuous refers to the supply of HMA from the plant so that trucks are arriving one at a time instead of in groups.
1/16/2020
9
49
After the truck is emptied, the paver can continue placing the mat as long as there is sufficient material in the hopper, i.e. slat conveyors are not visible.
High Quality HMA Pavement…
50
51 52
53
Common Problems
54
Common Problems
1/16/2020
10
55
Safety
56
57 58
Segregation and Mat Problems
59
Pavement Defects
§402-3.07 Compaction
...Upon completion of the HMA placement, there shall be no visible defects in the pavement, such as shallow ruts,
ridges, roller marks, cracking, tearing, segregation,
bleeding, or any other irregularities. Any defects that
become apparent shall be corrected, or the defective
pavement replaced, to the satisfaction of the Engineer,
at no additional cost to the State.
60
Quality HMA Pavement
A continuous supply of
HMA also minimizes
segregation of the mix.
Therefore, it is important
not to empty the hopper
If you can see the slat conveyors the hopper is empty…don’t let this happen
1/16/2020
11
61
Mat Quality
Bleeding (flushing)
Mix related
Too much asphalt
Too much fines
Construction related
Traffic put on too early
Spilling fuel, etc
62
Mat Quality
Segregation
Improper loading at the plants
Broken or missing auger (sometime more than one)
Unnecessary emptying of paver hopper
63
Missing Auger Extension• can cause segregation or
irregularities in the mat
64
Mat Quality
Pavement tears
Generally associated with Tender Zone
Caused by rollers
Wait for Temperature to drop below the tender zone before finishing the rolling
Tear
GaugeReading
65
Mat Quality Bumps
Due to excessive compaction effort
Mat moving
Poor paving practice
Check roller speed
Not to exceed 2 ½ mph
For Vibratory Rollers
66
DO NOT WALK ONTOP COURSE!!!!!!!!!!!!!!
1/16/2020
12
67
Joint Failures
68
Why Do Joints Fail?
Lack of densification
Bad joint construction practice
Lack of enough material at the joint
Lack of bond between hot and cold joints
Bad paving practice, e.g., not a straight line
All these leads to moisture penetration
69
Specification Objective
To improve joint performance
Make contractor pay attention
Inspire innovation
Let contractors select the best way to construct joints i.e., Use best construction practice
Use mechanical tools
Cutting a joint with “pizza cutter”
Joint heaters
Use of joint makers
70
Joint Core Location
71
Joint Adhesive
Provides a sealer between joints
Application of joint adhesive Butt joint - entire vertical face
Wedge joint – entire 1 inch vertical face and 3-4 inches on the wedge.
First Pass
First Pass Second Pass
Second Pass
Joint adhesive
72
Documentation
1/16/2020
13
73 74
BR 340 & 341
Filled daily
A copy will be submitted to Engineer at the end of each day
60 Series Compaction
75
BR 340 & 341
filled daily
A copy will be submitted to Engineer at the end of the day
70 Series Method
76
77 78
1/16/2020
14
79