ISO 21500 - 2010

Guide to Project Management 

Presentation to the Australian Computer Society

19 March 2008

James Thomson ± Standards Australia

Neville Turbit ± MB12 Project Management, Committee member 

[email protected]

Page 2: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 2/28

ISO 21500 - Guide to Project Management 

SA/AS/ISO/IS and all that! 

An Australian Standard for projectmanagement?

An International Standard for project

management

Introducing ISO 21500 (NT)

Page 3: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 3/28

SA/AS/ISO/IS and all that! 

SA = Standards Australia ± since 1922

AS = Australian Standard ± all about a process

Page 4: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 4/28

Page 5: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 5/28

SA/AS/ISO/IS and all that! 

SA = Standards Australia ± since 1922

AS = Australian Standard ± all about a process

ISO = isos Greek for ³equal´

IS = International Standard

Page 6: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 6/28

An Australian Standard for project

management (terminology) ³isn¶t there a Standard for project management

being developed?´

³what should be covered in a Standard?´

³who should be involved in the development?´

³guys we seem to be bogged down!´

Page 7: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 7/28

An International Standard for project

management The UK proposal

Six questions from Australia

Project managing a Standard on project

management

Page 8: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 8/28

MB 012 Project ManagementMirror Committee

Chair Neveen MoussaD/Chair Lloyd Carter 

P/Manager James Thomson

Working Group 1(WG 1)

Terminology15 SME from all sectors

Working Group 2(WG 2)

Processes15 SME from all sectors

Working Group 3(WG 3)

Informative Guidance15 SME from all sectors

Chairperson¶s Advisory Group(CAG)

Committee Chair, Deputy Chair,Project Manager, WG Coveners

Research Assistant, Admin supportOther experts

Construction  ±  Buildings

Construction  ±  Infrastructure

DefenceIT

Mining/MineralsOil & Gas/Energy

Finance/Banking/InsuranceGovt (Federal/State/Local)

ManufacturingPharmaceuticals

Education/TrainingR&D

Other 

Construction ± 

BuildingsConstruction  ±  Infrastructure

DefenceIT

Mining/MineralsOil & Gas/Energy

Finance/Banking/InsuranceGovt (Federal/State/Local)

ManufacturingPharmaceuticals

Education/Training

R&DOther 

Construction  ±  Buildings

Construction  ±  Infrastructure

DefenceIT

Mining/MineralsOil & Gas/Energy

Finance/Banking/InsuranceGovt (Federal/State/Local)

ManufacturingPharmaceuticals

Education/TrainingR&D

Other 

Public Consultation Panel (PCP)[email protected]

Page 9: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 9/28

An International Standard for project

management The UK proposal

Six questions from Australia

Project managing a Standard on project

management

Timeline

Page 10: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 10/28

Introducing ISO 21500 (NT)

The drivers

What it means to you

Starting positions

London resolutions Structure of the International Standard

Example

Format for process definition

Inputs ± methodologies ± outputs Example processes

What will you have to do ~

Page 11: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 11/28

ISO Standard ± The Drivers

 ± More international projects

 ± Contractual issues ± Develop a common terminology

 ± Alignment of other standards PMBOK,

BS 6079-1:2002, German Standard etc. ~

Page 12: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 12/28

What it means to You

 ± Understand the ISO standard when working on

projects (contractual, best practice issues)

 ± Changed terminology

 ± Industry standard practices

 ± Potentially skills/qualifications ~

Page 13: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 13/28

Starting Positions ± USA - recommended focus on projects, focus on

processes (what not how), generic overarchingstandard using best of all existing BOK¶s

 ± UK ± recommended the use of BS 6079-1:2002as the basis for document, generic overarchingstandard, question of when does a project start(corporate aspects).

 ± Germany ± Focus on processes, the concept of the house of processes. ~

Page 14: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 14/28

Starting Positions (cont)

 ± France - The PM corpus concept, proposal for a4th WG on competencies.

 ± Japan ± proposal to include education andtraining of personnel for project management inthe work items of WG3, established mirror committee and working groups with membersselected and funding sourced..

 ± Netherland ± program/portfolio management inor out, generic vs sector specific. ~

Page 15: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 15/28

London Resolutions

Accept the document ISO/PC 236 N0008(ANSI/PMI 99-001-2004 Glossary) as base

document for initiating the work of the WorkingGroup #1

Revision to scope of working group 2 and contentof their contribution to Standard.

Wording of first working draft of the scopestatement of the Standard ~

Page 16: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 16/28

London Resolutions (cont)

Create a draft for an annex containingrequirements and recommendations about the

competencies in project management.

Introduce in a summary form, as part of thestructure of the future standard, a paragraph inrelation to "skills and competencies in project

management". This paragraph will define themain characteristics of project managementcompetencies, and will include a reference to the

 Annex ~

Page 17: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 17/28

Structure of the Standard

Page 18: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 18/28

Structure of the Standard

Page 19: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 19/28

Structure of the Standard

Page 20: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 20/28

Example

Contractor OrganizationThe customer organization is responsible for specifying the

purpose of the project and the conditions for the

execution of a project and should ensure adequate

funding and the form of contract. The project specificationshould contain the following:

the description of context into which the purpose of the

project will be incorporated

the functionalities of this purpose

the technical solutions required

the budget

the execution time

the master quality plan

Page 21: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 21/28

Page 22: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 22/28

Page 23: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 23/28

Page 24: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 24/28

Inputs ± Methodologies - Outputs

Inputs

Project Scope Statement

Change Control System Project Scope Statement Updates

Methodologies

Work Breakdown Structure Variance Analysis

Work Breakdown Structure Updates ~

Page 25: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 25/28

Inputs ± Methodologies - Outputs

Methodologies (cont)

Scope Management Plan

Re-planning

Scope Management Plan Updates

Outputs

Approved Change Requests

Configuration Management

Project Management Plan Updates

Page 26: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 26/28

Example Processes

1.1 Develop Project Charter 

1.2 Develop Preliminary Project Scope Statement

2.1 Scope Definition

2.2 Scope Planning

2.3 Create Work Breakdown Structure

2.4 Activity Definition

2.5 Activity Resource Estimating

2.6 Activity Duration Estimating

2.7 Determine Activity Sequencing

2.8 Develop Project Schedule

Page 27: 2008_03_19_ACS_Presentation_v4-1

8/8/2019 2008_03_19_ACS_Presentation_v4-1

http://slidepdf.com/reader/full/20080319acspresentationv4-1 27/28

What will you have to do?

 ± Adapt to new terminology

 ± Change roles and responsibilities

 ± Follow the standard processes

 ± Understand legal implications