2010 Squak Valley Park Restoration Project City of Issaquah. Project Overview. Originally conceived by Corps of Engineers in 1999 in Lake Washington General Investigation Identified in WRIA 8 3-year Implementation Plan list - PowerPoint PPT Presentation

Citation preview

Page 1: 2010 Squak Valley Park  Restoration Project City of Issaquah

2010 Squak Valley Park Restoration Project

City of Issaquah

Page 2: 2010 Squak Valley Park  Restoration Project City of Issaquah

Project Overview

• Originally conceived by Corps of Engineers in 1999 in Lake Washington General Investigation

• Identified in WRIA 8 3-year Implementation Plan list

• Construction completed in Fall 2010 at a total cost of $1.4 million (including acquisitions)

• Covers 8 acres of City open space and 1,100 feet of Issaquah Creek

• Benefits Chinook, Coho and Sockeye salmon; cutthroat and steelhead trout; other wildlife

Page 3: 2010 Squak Valley Park  Restoration Project City of Issaquah

Funding and Partners

• King Conservation District - $320,862

• Washington Wildlife and Recreation Program – Riparian Account - $450,000

• Salmon Recovery Funding Board - $250,000

• King County Flood Control District - $70,000

• City of Issaquah - $350,000

• Mountains to Sound Greenway Trust (volunteer coordination)

Page 4: 2010 Squak Valley Park  Restoration Project City of Issaquah

Pre-Project Condition

Page 5: 2010 Squak Valley Park  Restoration Project City of Issaquah

Pre-Project ConditionIssaquah Creek (Looking South)

Page 6: 2010 Squak Valley Park  Restoration Project City of Issaquah

Project Features

• Acquisition of 4 SFR vacant lots along creek (adjacent to city park) and one conservation easement

• Instream habitat: 19 log structures (103 logs and stumps with 154 anchors)

• Levee removal for floodplain reconnection (9500 CY)

• Invasive plant removal

• Native plants: 6,000 native trees and shrubs (700 volunteers contributing 3000 hours)

Page 7: 2010 Squak Valley Park  Restoration Project City of Issaquah

Grading in Process

Page 8: 2010 Squak Valley Park  Restoration Project City of Issaquah

Completed Grading

Page 9: 2010 Squak Valley Park  Restoration Project City of Issaquah

Installing LWD in Creek

Page 10: 2010 Squak Valley Park  Restoration Project City of Issaquah

Large LWD

Page 11: 2010 Squak Valley Park  Restoration Project City of Issaquah

One of several Mountains to Sound Greenway Trust planting events

Page 12: 2010 Squak Valley Park  Restoration Project City of Issaquah

Winter Flow Conditions

Page 13: 2010 Squak Valley Park  Restoration Project City of Issaquah

Winter Flow Conditions