30
8/12/2019 2011-2012 Phase 1 Student Design Competition http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 1/30  2011 2012  SME/NSSGA Student Design Competition PHASE ONE Treeline Construction Materials 

2011-2012 Phase 1 Student Design Competition

  • Upload
    palsy

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

Page 1: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 1/30

 

2011‐2012

 

SME/NSSGA Student Design Competition 

PHASE ONE 

Treeline Construction Materials 

Page 2: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 2/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Table of  Contents 

General Background

 Information

 .........................................................................................................

 3 

1.1  Problem Statement .....................................................................................................................  3 

1.2  Project Requirements ..................................................................................................................  4 

2  Site Location and Layout ......................................................................................................................  5 

2.1  Site Weather ................................................................................................................................  5 

2.2  General Site Layout .....................................................................................................................  6 

3  Geologic Information ...........................................................................................................................  8 

3.1  Site Geology .................................................................................................................................  8 

3.2  Drilling Logs .................................................................................................................................  8 

3.3 

Water Table

 .................................................................................................................................

 8 

4  Permit Constraints ................................................................................................................................  9 

4.1  Heber Quarry ...............................................................................................................................  9 

4.2  Charthouse Quarry ......................................................................................................................  9 

5  Processing Plant .................................................................................................................................  10 

6  Market Summary ................................................................................................................................  11 

Page 3: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 3/30

 2011- 2012 SME/NSSGA Student  Design Competition 

1  General Background Information 

This problem

 is

 intended

 to

 highlight

 the

 challenges

 associated

 with

 evaluating

 the

 operation

 of 

 multiple

 

aggregate operations in the same market area. Your  job as engineers is to determine the most profitable 

and feasible operating solution for this market area. 

This problem will use data from an actual aggregate mining company  in the United States.  This  is real 

data  and  therefore  will  represent  the  type  of   information  you  will  have  as  a  mining  engineer  of   the 

future.  The company that donated the information to create this problem has hundreds of  thousands of  

dollars  invested  in the data you will be using and  is proprietary to that company.  Therefore, the data 

should be

 respected,

 not

 reproduced

 for

 any

 other

 use,

 and

 if 

 the

 location

 is

 accidentally

 disclosed,

 the

 information should be kept to yourselves.  This is a wonderful opportunity for you as a student, so treat 

the information given in this problem appropriately. 

1.1  Problem Statement 

The  2011/2012  Student  Design  Competition  Problem  will  be  centered  on  two  quarries  located  in  the 

eastern U.S.:

 Heber

 Quarry

 and

 Charthouse

 Quarry.

 Both

 quarries

 are

 owned

 by

 Treeline

 Construction

 

Materials (TCM) and service the same market area. 

Heber  Quarry  is  located  east  of   the  market  and  has  been  operating  off ‐and‐on  for  20  years.  The 

material  resource  at  this  site  consists  of   a  granitic  deposit  with  a  significant  amount  of   overburden. 

Currently,  the  site  operates  an  aggregate  processing  plant,  and  a  portion  of   the  property  has  been 

leased  to  an  outside  company  to  produce  asphalt.  The  agreement  between  TCM  and  the  asphalt 

producer  states  that  TCM  will  be  the  sole  supplier  of   raw  aggregate  material  for  the  asphalt. 

Historically, 50%

 of 

 the

 asphalt

 aggregates

 sold

 at

 Heber

 Quarry

 go

 to

 the

 on

‐site

 asphalt

 plant.

 

Charthouse Quarry is located west of  the market and has been operating off ‐and‐on for 15 years.  The 

material  resource  at  this  site  consists  of   granitic  deposit  with  a  moderate  amount  of   overburden. 

Processing facilities onsite consist solely of  an aggregate plant. 

In the past, both quarries were able to operate simultaneously and profitably.  Due to a drop off  of  the 

in local market demand, both operations have been struggling to make it on their own.  Your team has 

been 

hired 

to 

put 

together 

an 

operational 

assessment 

and 

technical 

design 

to 

determine 

the 

most profitable  solution  for  TCM’s  operations  in  this  market  area.  Your  design,  assessment,  and  ultimate 

operational recommendation will be reviewed by the Board of  Directors. 

Page 4: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 4/30

 2011- 2012 SME/NSSGA Student  Design Competition 

1.2  Project Requirements 

Your  project  team  has  been  asked  to  specifically  address  the  following  in  regards  to  the  Treeline 

Construction Materials operations. 

•  Reserve Estimation: 

o  Geologic model 

o  Total mineable material 

  Total saleable material 

  Total waste material 

•  Mine Design: 

o  Overall quarry design 

o  Phasing of  reserves 

o  Phasing and location of  waste stockpiles 

•  Operating Plan:

 

o  Which site(s) will be operated 

o  Processing equipment needed 

o  Mobile equipment needed 

o  Personnel requirements 

o

 Hours required to satisfy demand 

•  Economic Analysis of  Project: 

o  Estimated operating costs for your plan 

  It  has  been  requested  that  your  team  put  annual  operating  costs  in  TCM’s 

current cost structure; cost codes and descriptions are included in Appendix F. 

o  Justification of  the site(s) your team chose to operate 

o  In order

 for

 this

 to

 be

 an

 attractive

 investment

 for

 the

 company,

 an

 IRR

 of 

 17.5%

 needs

 

to  be  achieved.  The  company  traditionally  uses  a  Cost  of   Capital  of   8%  and  the 

corporate tax rate is 34%.  A table for wage and benefits values can be seen in Appendix 

C. 

Page 5: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 5/30

 2011- 2012 SME/NSSGA Student  Design Competition 

2  Site Location and Layout 

Treeline Construction

 Materials

 (TCM)

 is

 located

 in

 a relatively

 rural

 area

 of 

 the

 eastern

 United

 States,

 with the nearest large cities of  Woodville, located 111 miles to the east with a population of  83,000; and 

Luminville, located 112 miles to the north with a population of  174,000. 

The center of  the market  is Parkersburg, a small town with a population of  1,700. According to recent 

studies, the annual population growth for the area is expected to be 1%.  There are many national parks 

and forests in the area which bring a recreational crowd in the warmer months for camping, hiking and 

whitewater rafting.  Charthouse Quarry has a 15 mile haul to the center of  the market area, and Heber 

Quarry has

 a 20

 mile

 haul.

 There

 are

 three

 other

 aggregate

 companies

 within

 the

 market.

 The

 average

 cost of  trucking in the area is $85/hr (25 ton trucks), which will vary with fuel price.  See Appendix A for 

a market map. 

2.1  Site Weather 

The  weather  at  the  quarry  is  moderate  with  an  annual  high  temperature  of   86ºF  and  an  annual  low 

temperature of  26ºF (see Figure 1).  The site experiences an annual rainfall of  approximately 55  inches 

(see Figure 2). 

Figure 1: Average Temperatures 

Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Year

Page 6: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 6/30

Page 7: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 7/30

Page 8: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 8/30

 2011- 2012 SME/NSSGA Student  Design Competition 

3  Geologic Information 

3.1  Site Geology 

The subject properties  lie within  the Blue Ridge physiographic province. The Blue Ridge physiographic 

province  is  a  mountainous  belt  extending  northeastward  from  northern  Georgia  to  southern 

Pennsylvania.  The  province  was  formed  by  tectonic  compression  resulting  in  the  uplift  of   resistant 

crystalline  bedrock  into  narrow  bands  of   medium  to  high  grade  metamorphic,  somewhat  parallel 

mountain ranges.  There are two distinct areas within this province.  The northern section consists of  an 

irregular mountain

 range,

 containing

 anywhere

 from

 one

 single

 ridge

 to

 a group

 of 

 closely

 spaced

 ridges

 

with a width of  12‐14 miles.  The southern half  of  the Section is broader, higher, and more mountainous. 

It is nearly 70 miles wide and contains mountains of  greater elevations.  There are 46 mountain peaks in 

the southern section that have elevations above 6,000 feet.  Though high, the mountains are rounded 

and  generally  lack  prominent  angularity.  The  whole  Section  is  bounded  on  the  eastern  and  western 

margins by southwest to northeast trending thrust faults, between more faults and tight folds. 

Bedrock  is composed primarily of  Proterozoic metasediments  (quartzite, schist, and gneiss) and meta‐

igneous rocks

 (granite,

 amphibolites,

 basalt,

 and

 gabbro).

 Smaller

 areas

 underlain

 by

 Paleozoic

 granite

 

occur along the eastern and southern edge of   the Section, with  lower Cambrian sandstone, shale and 

dolomite, and broad zones of  intensely sheared and altered rock. 

The  two  quarries  owned  by  Treeline  Construction  Materials  are  mining  granitic  rock  overlain  with 

significant  thickness of  decomposed  (weathered) granite.  The weathering  is  joint controlled and as  a 

result can vary in thickness. 

3.2  Drilling Logs

 

Due  to  tightened  exploration  budgets,  the  drilling  plan  for  Heber  and  Charthouse  quarries  had  to  be 

scaled back.  Your team has been advised that additional drilling may be done at a later date, but that it 

would require cost  justification.  Drill logs are located in Appendix E. 

3.3  Water Table 

The following are the estimated water table elevations for both quarries; as determined by drilling logs 

as well

 as

 other

 nearby

 wells.

 

Heber Quarry:  2000 feet above mean sea level 

Charthouse Quarry:  2050 feet above mean sea level 

Page 9: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 9/30

 2011- 2012 SME/NSSGA Student  Design Competition 

4  Permit Constraints 

The following

 conditions

 are

 part

 of 

 the

 current

 mining

 permits

 for

 the

 two

 quarries

 

4.1  Heber Quarry 

Offsets: 

•  See Permit Boundary in AutoCAD file 

•  No  mining  may  occur  within  100ft  of   permit  boundary,  however  other  activities,  such  as 

stockpiling or road construction, are allowed. 

Slopes/Depth: 

•  Final slopes are not to exceed: 

o  Soil/Overburden: 2:1 

o  Weathered Rock: 1.5:1 

o  Fresh/Competent Rock: 0.5:1 

•  Maximum bench height: 50 ft 

•  Minimum catch bench width: 10 ft 

•  Maximum mining depth:  May not mine below water table 

Hours of  Operation: 

Excavation, processing, and  load‐out activities are allowed to take place 24 hours a day, 7 days a 

week. 

Tonnage: 

Maximum yearly tonnage allowed: NO LIMIT 

4.2  Charthouse Quarry

 

Offsets: 

•  No mining or any other activity may occur within 50 feet of  property boundary 

Slopes/Depth: 

•  Final slopes are not to exceed: 

o  Soil/Overburden: 2:1 

o  Weathered Rock:

 1.5:1

 o  Fresh/Competent Rock: 0.5:1 

•  Maximum bench height: 50 ft 

•  Minimum catch bench width:  10 ft 

•  Maximum mining depth: May not mine below water table 

Page 10: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 10/30

 2011- 2012 SME/NSSGA Student  Design Competition 

5  Processing Plant 

Due to

 the

 low

 annual

 tonnage

 of 

 both

 operations,

 each

 site

 has

 a relatively

 simple

 plant

 configuration.

 At both Heber and Charthouse Quarries, mining is done with a CAT 988 loader and 2 50‐ton haul trucks. 

A list of  the equipment at each site  is included in Appendix D.  The plant flow diagrams can be seen  in 

Appendix G. 

At Heber Quarry, the two haul  trucks dump the blasted material  into a Telsmith 3648  jaw crusher  for 

primary  crushing.  Once  the  material  passes  through  the  crusher,  it  is conveyed  to  the  primary surge 

pile.  The  material  is  then conveyed  to  a secondary circuit which begins  with  a double deck vibrating 

screen. 

The 

undersize 

is 

screened 

off  

as 

ABC 

stone 

and 

the 

oversize 

is 

crushed 

with 

Telsmith 

SBS 

52 

C/C  cone  crusher.  The  material  which  is  not  screened  off   as  ABC  stone  can  be  stock  piled  as  3’s  or 

conveyed to the tertiary circuit.  The tertiary circuit consists of  two triple deck vibrating screens and two 

side‐by‐side Nordberg Symons 4 ¼  ft S/M cone crushers.  This circuit  is designed to produce 78’s and 

57’s.  In addition, an Eagle Sand Screw is used to make sand from the undersize 

At  the  Charthouse  Quarry,  the  two  haul  trucks  dump  the  blasted  material  into  a  Telsmith  3648  jaw 

crusher  for  primary  crushing.  Once  the  material  falls  goes  through  the  crusher,  it  is  conveyed  to  a 

double 

deck 

vibrating 

screen. 

The 

undersize 

is 

screened 

off  

as 

ABC 

stone 

and 

the 

oversize 

is 

crushed 

with a Telsmith SBS 52 C/C cone crusher.  The material which  is not screened off  as ABC stone can be 

stock piled as 3’s or conveyed to the secondary surge pile.  The tertiary circuit begins with two side‐by‐

side Nordberg Symons 4 ¼  ft S/M cone crushers.  The tertiary crushers  feed  two  triple deck vibrating 

screens.  This circuit is designed to produce 78’s and 57’s.  In addition, an Eagle Sand Screw is used to 

make sand from the undersize. 

Page 11: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 11/30

 2011- 2012 SME/NSSGA Student  Design Competition 

6  Market Summary 

The economy

 surrounding

 the

 TCM

 operations

 is

 at

 a stand

‐still.

 The

 economic

 outlook

 suggests

 that

 the  aggregates  market  will  remain  flat  for  the  next  three  years  and  then  increase  at  a  rate  of   2% 

annually.  Tables  2  and  3  contain  the  projected  tons  and  price  for  each  product  at  the  Heber  and 

Charthouse  Quarries,  respectively,  for  years  2012–2014.  The  table  for  Heber  quarry  includes  the 

demand from the on‐site asphalt plant. 

The  market  growth  data  was  taken  from  a market  study  done  by  Treeline  Construction  Materials;  be 

aware  that  sales  forecasts  are  subject  to  change  with  macro‐economic  conditions  and  local  market 

variables. 

copy 

of  

the 

current 

gradation 

targets/specifications 

for 

these 

products 

can 

be 

found 

in 

Appendix B. 

Table 2:  Heber Quarry Annual Sales Projections, 2012‐2014 

Product Sales Projection 

(tons) 

Average 

Sales Price 

($) 

#57  15,000  $14.50 

#78 

12,000 

$13.75 

Base (ABC)  60,000  $10.50 

Class 1 Rip Rap  7,000  $16.00 

#3  2,000  $14.75 

Manufactured Sand  4,000  $14.50 

TOTAL  100,000  ‐‐‐

Table 3:  Charthouse Quarry Annual Sales Projections, 2012‐2014 

Product Sales Projection 

(tons) 

Average 

Sales Price 

($) 

#57  20,000  $16.00 

#78M  19,000  $19.00 

Base (ABC)  30,000  $9.50 

#3 

4,000 

$14.50 

Class 1 Rip Rap  2,000  $17.00 

Manufactured Sand  19,000  $14.00 

TOTAL  94,000  ‐‐‐

Page 12: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 12/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix   A

 

Market   Map 

 

Page 13: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 13/30

Page 14: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 14/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  B

 

Product  Gradations 

(by   percent   passing) 

Page 15: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 15/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Class 1 Rip Rap: 

Minimum Stone Size  – 5” 

Midrange Stone

 Size

  –

 10”

 Maximum Stone Size  – 17” 

ASTM SPECIFICATIONS 

PRODUCT: #57 #3 Base (ABC) #67 #78 #89 Manufac. Sand

% Passing: Min Max Min Max Min Max Min Max Min Max Min Max Min Max

2" 80 100 100 1001 1/2" 100 100 35 70

1" 90 100 0 15 94 100 100 100

3/4" 90 100 100 100

1/2" 26 60 0 5 90 100 100 100

3/8" 63 72 20 55 90 100 100 100

#4 0 7 0 10 5 25 20 55 94 100

#8 0 3 0 5 0 10 5 30

#10 32 41#16 0 5 0 10

#40 14 24

#50 0 5

#100 6 12 0 10

#200 0 5

Page 16: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 16/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  C  

Wages and  Benefits 

Page 17: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 17/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Wages and Benefits 

Classification 

Wage &

 Benefits

 

Mine Foreman  29.00 $/hr 

Blast Overseer/Driller Overseer 25.00 $/hr 

Driller  20.00 $/hr 

Haul Truck Operator  18.00 $/hr 

Over Road Driver  15.00 $/hr 

Loader Operator  22.00 $/hr 

Plant Operator

 20.00

 $/hr

 

Plant Laborer  15.00 $/hr 

Plant Mechanic  21.00 $/hr 

Mechanic  20.10 $/hr 

Electrician  25.00 $/hr 

Scale operator  14.00 $/hr 

Engineer  85,000 $/year 

Site Manager

 120,000

 $/year

 Quality Engineer  75,000 $/year 

Safety Professional  70,000 $/year 

Page 18: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 18/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  D 

Plant  Equipment  

Page 19: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 19/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Heber Quarry

Page 20: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 20/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Charthouse Quarry

Page 21: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 21/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  E 

 

Drill  Logs 

Page 22: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 22/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Heber Quarry 

(all  measurements in  feet) 

COLLAR 

HOLEID  X COORD  Y COORD  Z COORD 

HQ11‐1  547931  490433  2425 

HQ11‐2  550585  489089  2895 

HQ11‐3  550468  490021  2560 

HQ11‐4  548567  487992  2150 

HQ11‐5 

549991 

489050 

2450 

LITHOLOGY 

HOLEID  FROM  TO  LITHOLOGY 

HQ11‐1  0  2  SOIL 

HQ11‐1  2  33  CLAYEY SAND 

HQ11‐1  33  72  DG 

HQ11‐1  72  150  GRANITE 

HQ11‐2  0  1  SOIL 

HQ11‐2  1  30  CLAYEY SAND 

HQ11‐2  30  67  DG 

HQ11‐2  67  200  GRANITE 

HQ11‐3  0  1  SOIL 

HQ11‐3  1  35  CLAYEY SAND 

HQ11‐3  35  60  DG 

HQ11‐3  60  150  GRANITE 

HQ11‐4  0  2  SOIL 

HQ11‐4  2  40  CLAYEY SAND 

HQ11‐4  40  70  DG 

HQ11‐4  70  150  GRANITE 

HQ11‐5  0  300  GRANITE 

Page 23: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 23/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Charthouse Quarry (all  measurements in  feet) 

COLLAR 

HOLEID  X COORD Y COORD Z COORD

CHQ11‐1 436099  498404  2680 

CHQ11‐2 434614  499930  2360 

CHQ11‐3 436586  501285  2025 

CHQ11‐4 434796  497850  2120 

CHQ11‐5 435503  496909  2230 

CHQ11‐6 435497  499523  2411 

LITHOLOGY 

HOLEID  FROM  TO  LITHOLOGY

CHQ11‐1 0  2  SOIL 

CHQ11‐1 2

 65

 DG

 

CHQ11‐1 65  200  GRANITE 

CHQ11‐2 0  1  SOIL 

CHQ11‐2 1  62  DG 

CHQ11‐2 62  150  GRANITE 

CHQ11‐3 0  1  SOIL 

CHQ11‐3 1  57  DG 

CHQ11‐3 57  65  GRANITE 

CHQ11‐4 0  2  SOIL 

CHQ11‐4 2  59  DG 

CHQ11‐4 59  150  GRANITE 

CHQ11‐5 0  2  SOIL 

CHQ11‐5 2  55  DG 

CHQ11‐

5 55 

200 

GRANITE 

CHQ11‐6 0  300  GRANITE 

Page 24: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 24/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  F  

Cost  Codes 

Page 25: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 25/30

 2011- 2012 SME/NSSGA Student  Design Competition 

[Note:  all  cost  codes may  not  apply  to the quarries outlined  in this  problem] 

Cost Code Description1101 Personnel - Labor

1102 Labor - Hourly

1103 Labor - Hourly Overtime

1104 Labor - Salary

1105 Labor - Salary Overtime

1106 Labor - Vacation

1107 Labor - Holiday

1108 Labor - Sick1200 Personnel - Safety

1201 Safety Training

1203 Health and Safety Equipment

1204 MSHA Fines

1205 Medical Injury Cost

1300 Personnel - Employ Related

1301 Drug Screening

1302 Employee Physical

1306 Employee Training

1307 Tuition Reimbursement

1308 Relocation Expense

1400 Energy

1401 Electric

1402 Gasoline

1403 Diesel

1500 Supplies1501 Hydraulic Hammer Parts

1502 Explosives

1503 Drill Steel

1504 Tires & Tubes

1505 Welding & Cutting

1506 Oil & Lubricant

1507 Manganese

1508 Conveyor Belts

1509 Screen Cloth

1510 Filters

1511 Wire Rope

1512 Ground Engaging Tools

1513 Other

Page 26: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 26/30

 2011- 2012 SME/NSSGA Student  Design Competition 

1608 Loader

1609 Conveyor

1610 Drill

1611 Shove/Crane/Excavator

1612 Truck

1613 Crusher

1614 Screen

1615 Electric

1616 Truck Scale

1617 Other

1700 Contract Services

1701 Contract Svcs - Crushing

1702 Contract Svcs - Grading

1703 Contract Svcs - Drilling

1704 Contract Svcs - Blasting

1705 Contract Svcs - Towing

1706 Contract Svcs - Materials Handling

1707 Contract Svcs - Crane

1800 Depr, Depletion & Amor t

1801 Depreciation

1802 Depletion

1803 Amort - Goodwill

1900 Property Related

1901 Heat & Water

1902 Janitorial

1903 Security

1904 Landscaping

1905 Maintenance

1906 Other

2000 Office Expense

2101 Telephone

2102 Internet Access

2103 Computer Software

2104 Computer Hardware

2105 Office Supplies

2106 Membership & Subscriptions

2107 Other

2200 Professional Services

2201 Engineering

2202 Legal

Page 27: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 27/30

 2011- 2012 SME/NSSGA Student  Design Competition 

2500 Equipment Rental

2501 Rental - Long Term

2502 Rental - Short Term2600 Travel & Entertainment

2601 Travel

2602 Meals

2603 Entertainment

Page 28: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 28/30

 2011- 2012 SME/NSSGA Student  Design Competition 

 Appendix  G

 

Plant  Flow  

Page 29: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 29/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Heber Quarry 

Plant Flow 

Page 30: 2011-2012 Phase 1 Student Design Competition

8/12/2019 2011-2012 Phase 1 Student Design Competition

http://slidepdf.com/reader/full/2011-2012-phase-1-student-design-competition 30/30

 2011- 2012 SME/NSSGA Student  Design Competition 

Charthouse Quarry 

Plant Flow