Upload
truongmien
View
215
Download
1
Embed Size (px)
Citation preview
1
2012 GENERATION TECHNOLOGY ASSESSMENTGeneration Technology Cost & PerformanceTechnical Supplement to 2012 ENO IRP
JANUARY 2012 UPDATE
SPO PLANNING ANALYSIS
An understanding of generat ion technology cost and performance is a necessary input to p lanning and dec is ion support act iv i t ies . SPO P lanning Analys is monitors and assesses generat ion a l ternat ives on an on -going bas is. Th is s tudy updates technology assumptions and is intended as an input into the 2012 Integrated Resource P lan (“ IRP”) process as wel l a s other dec is ion support act iv i t ies involv ing resource p lanning and/or t ransact ion evaluat ions.
2
TABLE OF CONTENTS
Introduction …………………………………………………………………………………………….. 3
I. The Technology Landscape ………………………………………………….……………………. 5
II. Cost & Performance Assumptions ………………………………………………..……………... 31
III. Detailed Modeling ………………………………………………………………………………… 41
IV. Conclusions ………………………………………………………………………………………... 57
3
INTRODUCTION
In support of long-range planning and procurement activities System Planning & Operations (”SPO”), Planning Analysis monitors electric generation technology cost and performance. This report “2012 Generation Technology Assessment” describes current assumptions and conclusions.
The 2012 Generation Technology Assessment has been prepared in preparation of the 2012 IRP process. Results of this generation technology assessment will support IRP activities in 2012 and will provide the basis for portfolio modeling
TECHNOLOGY ASSESSMENT
4
I.
• Review the state of generation technology and identify candidate technologies that may be available to meet long-term needs.
The Technology Landscape
TECHNOLOGY ASSESSMENT
II.
• Develop cost and performance assumptions for candidate technologies.
Cost & Performance Assumptions
III.
• Model cost of candidate technologies across relevant range of operations and assess overall attractiveness including risks.
Detail Modeling
IV.
• Summarize conclusions and identify technologies to be modeled in IRP portfolio design.
Conclusions
STUDY METHODOLOGY
5
TECHNOLOGY ASSESSMENT
I. The Generation Technology Landscape
I.
• Review the state of generation technology and identify candidate technologies that may be available to meet long-term needs.
The Technology Landscape
II.
• Develop cost and performance assumptions for candidate technologies.
Cost & Performance Assumptions
III.
• Model cost of candidate technologies across relevant range of operations and assess overall attractiveness including risks.
Detail Modeling
IV.
• Summarize conclusions and identify reference technologies to be modeled in IRP portfolio design.
Conclusions
6
THE RANGE OF TECHNOLOGIES
TECHNOLOGY ASSESSMENT
The 2012 Generation Technology Assessment begins by surveying available central state electricity generation technologies, generally those that are two megawatts or greater.. The objective is to identify as wide a range of generation technologies as reasonable to consider. The initial list is subject to a screening analysis to identify generation technologies that are technologically mature and could reasonably be expected to be operational in or around the Entergy regulated service territory..
7
TECHNOLOGIES SCREENED
TECHNOLOGY ASSESSMENT
Nuclear– Advanced Boiling Water Reactor– Generation IV– Modular Reactors
Entergy Storage– Pumped Hydro– Underground Pumped Hydro– Battery– Flywheel– Compressed Air Energy Storage
Renewable Technologies– Biomass– Solar Photovoltaic– Solar Thermal– Wind Power– Municipal Solid Waste– Landfill Gas– Geothermal– Ocean & Tidal
Pulverized Coal – Subcritical Pulverized Coal– Supercritical Pulverized Coal– Ultra Supercritical Pulverized Coal
Fluidized Bed– Atmospheric Fluidized Bed– Pressurized Fluidized Bed
Integrated Gasification (“IGCC”)– Oxygen-Blown IGCC– Air-Blown IGCC– Integrated Gasification Fuel Cell Combined Cycle
Combustion Turbine / Combined Cycle / Other Natural Gas– Combustion Turbine– Combined Cycle– Small Scale Aeroderivative– Steam Boiler
Fuel Cells– Molten Carbonate– Solid Oxide– Phosphoric Acid– Proton Exchange Membrane– Fuel Cell Combined Cycle
8
PREFERENCE FOR PROVEN TECHNOLOGY
The Entergy Operating Companies prefer technologies that are proven on a commercial scale. Some technologies identified in this document lack the commercial track record to demonstrate their technical and operational feasibility. A cautious approach to technology development and deployment is therefore prudent in order to maintain System reliability and to protect Operating Company customers from undue risks. The Entergy Operating Companies generally do not plan to be the “first movers” for emerging technologies.
TECHNOLOGY ASSESSMENT
9
Technology Deployment Over Time
TECHNOLOGY LIFE CYCLE
ConceptualResearch &
Development Early Movers MatureEstablished
TECHNOLOGY ASSESSMENT
Fuel Cell CCGT Aeroderivative Combustion Turbine
Combined Cycle Gas Turbine
Heavy Duty Combustion Turbine
Gas Fired Steam Boiler
Integrated Gasification Fuel Cell CCGT
Oxygen Blown IGCC
Ultra Supercritical PC
Supercritical PC Subcritical PCAir Blown IGCC
Generation IV Nuclear
Modular Nuclear
Generation III Nuclear
Biomass –Stoker Boiler
Wind – Off-Shore
Biomass -CFBGeothermal
MSW – Plasma Torch
Ocean and Tidal Power
Wind – On-ShoreLandfill Gas MSW
Solar –Thermal
Solar –PV
FlywheelUnderground
Pumped Hydro BatteryCompressed Air Energy Storage
Pumped Storage Hydro
Proton Fuel Cell
Small CT Internal Combustion Engine
Conventional Gas Fired
Solid Fuel
Nuclear
Renewable
Energy Storage
Distributed Generation
Generation II Nuclear
10
SCREENING PROCESS
TECHNOLOGY ASSESSMENT
The following pages provide an overview of each major technology.
• Description of the technology
• The current state of maturity and extent of deployment
• Factors which may constrain additional deployment or advancement
• Potential for improvements in cost or performance
The objective is to identify technologies that merit further consideration, more detailed modeling in the following sections, and to eliminate those that do not.
11
PULVERIZED COAL
TECHNOLOGY ASSESSMENT
Background:
Pulverized Coal (“PC”) is a mature technology representing nearly 40% of installed utility capacity in the U.S.
The generation technology incorporates a boiler that burns pulverized coal producing steam that feeds into a steam turbine to produce electricity.
PC technology is categorized based on boiler pressure and temperature into three categories:
• Subcritical (2,400 psig and 1000 °F)• Supercritical (3,200 psig and 1000 °F) • Ultra Supercritical (3,400 psig and 1100 °F)
The reduction or capture of environmental emissions, particularly carbon dioxide (CO2), is the current focus for improvements in this technology.
Challenges:
Coal’s environmental footprint, especially it’s emissions profile, creates a significant challenge to future deployment and may threaten the long-term viability of existing facilities. In particular, coal fired facilities are high carbon emitters. Consequently, the imposition of a cost on CO2 emissions would negatively affect the economics of PC. Lack of a commercial scale method for economic carbon capture and storage and the risk of significant carbon compliance cost has already limited coal deployments. Finally, coal’s relatively high capital cost put it at a disadvantage to other technologies that have lower up front cost.
12
PULVERIZED COAL
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Eliminate from analysis in favor of newer more efficient technology such as supercritical boilers.
Subcritical Pulverized Coal
Subcritical cycle boilers for steam coal plants have been in use for more than 20 years. Efficiency of subcritical boilers is in the 32-36% range (9,480-10,665 btu/kWh). The technology is mature and use is expected to decline as the need for increased efficiencies to reduce emissions favor the use of more efficient technology.
Retained for detailed analysis.Supercritical Pulverized Coal
Supercritical cycle boilers have long been utilized in international markets. Higher boiler pressures and temperatures improves efficiency to between 36-40% (9,480-8,530 btu/kWh) and reduces emissions. Environmental regulations may dictate the need for higher efficiency to reduce emissions making this the PC technology of choice.
Eliminated from analysis until the technology has been commercially proven in order to understand cost and risk profile.
Ultra Supercritical Pulverized Coal
Ultra supercritical cycle boilers offer the potential of higher efficiencies and lower emissions, but these advantages come at increased operations risk and construction cost. Efficiency ranges between 40-45% (8,530-7,585 btu/kWh). The higher pressures and temperatures require higher alloy steels in the boiler resulting in higher capital cost.
13
FLUIDIZED BED
TECHNOLOGY ASSESSMENT
Background:
Fluidized bed combustion, both bubbling bed and circulating bed, are mature, having been commercially available since the 1970’s. Due to the limitations of the bubbling bed design the circulating bed (“CFB”) is the preferred technology design.
CFB boilers burn crushed coal or other carbon-based solid fuel in a mixture with blown air and limestone. More than 95 percent of the sulfur pollutants are captured inside the CFB boiler and falls out as ash.
Historically CFB boilers operated at atmospheric conditions limiting size to around 300 MW. Development is underway on pressurized circulating bed designs capable of electrical output up to 600 MW.
Challenges:
Environmental concerns associated with CO2 emissions and relatively high capital cost affect CFB technology in much the same manner as PC technology.
Other Considerations:
A CFB plant has the ability to burn a variety of solid fuels including coal, petroleum coke (“pet coke”), and other “waste” fuels resulting in lower fuel cost.
14
FLUIDIZED BED
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Retained for detailed analysis.Atmospheric Circulating Fluidized Bed (“ACFB”)
ACFB technology is mature. The ACFB boiler is suited to burn a variety of carbon-based solid fuel feedstocks, including bituminous and sub-bituminous coals, petroleum coke and waste coal. Technological limitations prevent boiler sizes much above a 300 MW limit.
Eliminated from analysis because the technology lacks sufficient commercial development at this time.
Pressurized Circulating Fluidized Bed (“PCFB”)
PCFB boilers offer the advantage of larger size and reduced environmental emissions. However, the technology is at an early stage of commercialization and not proven for wide spread deployment.
15
INTEGRATED GASIFICATION
TECHNOLOGY ASSESSMENT
Background:
Integrated Gasification Combined Cycle (“IGCC”) is an emerging technology.
An IGCC facility combines two processes or stages. First, a gasification unit converts coal or other solid fuel into a synthesis gas (“syngas”). Second, the syngas is burned in a combined cycle gas and steam power plant. Each of these processes have been widely deployed in separate applications. The uniqueness of the IGCC technology is the combining of the technologies for the purpose of electricity generation.
IGCC has attracted attention because the gasification process may facilitate the removal of carbon. Consequently, carbon capture and storage may be more feasible compared with other carbon based solid fuel technologies.
IGCC demonstration units currently in operation have only demonstrated efficiencies of between 37-41 percent (heat rates between 8,300 and 9,200 Btu/kWh) which is similar to current supercritical PC technology. However, IGCC has the potential to be more efficient than conventional PC with efficiency of 43-48 percent (heat rate between 7,100 and 7,900 Btu/kWh).
Challenges:
At this time IGCC has not been widely deployed and capital cost are higher than PC and CFB coal plants. Further, the lack of operating experience raises concerns about operating cost and performance.
16
INTEGRATED GASIFICATION
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Eliminated from analysis because of high capital cost and lack of sufficient commercial operating history..
Oxygen-Blown IGCC IGCC technology is the least mature of all solid fuel technologies. The gasifier and air separation components results in high capital cost compared to other generation technologies. If carbon capture technology is required to control emissions the cost will increase and output decrease, negatively impacting economics.
Eliminated from analysis because technology lacks sufficient commercial development to fully evaluate its cost and risk.
Air-Blown IGCC Like other IGCC technologies air-blown IGCC is immature and not proven in commercial practice. Air-blown IGCC has potential of being a lower cost alternative for IGCC by eliminating the air separation unit.
Eliminated from analysis because the technology is currently in the developmental stage and not available for deployment in commercial applications.
Integrated Gasification Fuel Cell Combined Cycle
This technology is still in the development/ bench scale phase. It is a hybrid IGCC technology combining fuel cells with gas combustion turbines to increase efficiency and reduce emissions. The technology is based on solid oxide fuel cell (SOFC) design. The current timeline estimates the commercialization of a 100 MW unit some time around 2020.
17
COMBUSTION TURBINE
TECHNOLOGY ASSESSMENT
Background:
Combustion Turbine (“CT”) generation is a mature technology first introduction into the power generation market in 1979. Aeroderivative CTs, based on aircraft engine design, are more recent having been introduced into the generation market in 1995.
Heavy Duty -Heavy Duty frame CTs with a size range of between 85-300 MW and heat rates between 9,000-11,500 Btu/kWh are broadly utilized in the power generation market with more than 3,000 units in operation accumulating nearly 100 million operating hours.
Aeroderivative -Aeroderivative CTs, as the name implies, are based on flight engines and are smaller, lighter, and more efficient than heavy duty CTs. Size ranges between 40-100 MW with heat rates in the 8,400-9,500 Btu/kWh range. New aeroderivative CTs in the 100 MW range are new to the market.
Aeroderivative turbines have higher capital and maintenance cost than heavy duty CTs resulting from the use of lighter weight exotic materials and more stringent machine tolerances.
Opportunities :
CT technology offers quick start capability, flexible siting and short construction time, low emissions footprint, and relatively low capital cost making it suited for peaking duty applications.
Challenges:
Higher heat rates make CTs less economic than CCGTs for load following and base load operations. However, CTs may be designed and constructed to provide peaking duty services in the near term yet allow for the conversion to combined cycle operations if load or other circumstances require additional load following capability.
18
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Retained for detailed analysis.Combustion Turbine –Heavy Duty
Combustion turbine (“CT”) technology, based on the heavy duty frame, is mature with thousands of units in operation around the world. Still in development are newer generation turbines with larger electrical output, better heat rates and reduced emissions.
Retained for detailed analysis.Combustion Turbine -Aeroderivatives
Aeroderivative combustion turbines are an “Established” technology. Their smaller size (50-100 MW) and higher capital and maintenance cost could potentially limit deployment to situations such as local area problems and areas with limited space.
COMBUSTION TURBINE
19
TECHNOLOGY ASSESSMENT
Background:
Combined Cycle Gas Turbine (“CCGT”) technology is mature representing over 50% of new generation capacity installed in the U.S. since 2000.
CCGT arrangements typically are combinations of one or more combustion turbines each with a dedicated heat recovery steam generator (“HRSG”) and a common steam turbine.
Development efforts currently underway focus on designs that incorporates closed-loop steam cooling and advanced coating materials allowing for higher firing temperatures and increased efficiency making CCGT more economic for baseload applications.
Opportunities
Taking into consideration moderate capital cost, low expected natural gas price forecast and flexible operating modes CCGTs are expected to be the choice technology to meet most load following roles and baseload applications over the first ten years of the planning horizon and possibly beyond.
Challenges:
CCGT cost competitiveness is driven by low to moderate natural gas prices. A sustained period of high gas prices would reduce the attractiveness of CCGTs particularly if a price is placed on carbon.
COMBINED CYCLE GAS TURBINE
20
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Retained for detailed analysis.Combined Cycle As with combustion turbines, combined cycle technology is mature with a significant number of units in operation. The development of the new CCGT designs incorporating closed loop cooling with higher pressure and firing temperature will serve to keep this technology competitive with other generation technologies for use in the power generation business during the planning horizon.
COMBINED CYCLE GAS TURBINE
21
NUCLEAR
TECHNOLOGY ASSESSMENT
Background:
No new nuclear power plant has been constructed in the U.S. in over 30 years. However, a nuclear generation alternative offers the potential benefits of no greenhouse or other air emissions, fuels diversity, and energy security.
Nuclear technology, while considered mature, continues to push new technological advances. Generation II reactors, first installed in the 1970’s, were light water reactors and represent most all of the reactors operating in the U.S. today. Since 1996, Generation III and III+ designs have been considered by developers as the design choice. Generation III includes Economically Simplified Boiling Water Reactor (“ESBWR”), Advanced Passive Nuclear Reactor (“AP-1000”), Advanced Boiling Water Reactor (“ABWR”), and Evolutionary Pressurized Water Reactor (”EPR”) designs. While most recent applications to construct and operate a new plant include one of these designs no applications have been approved by regulators at this time.
Nuclear equipment manufactures are currently designing and developing Generation IV technology. Generation IV designs include closed fuel loop cycles for more efficient fuel burn with reduced waste and cost. Generation IV is expected to include a line of smaller modular units well below the 300+ MW size currently considered. Expectations for commercial delivery of Generation IV nuclear reactors is in the 2020-2030 timeframe.
Challenges:
Among the issues facing the nuclear generation are:• The large investment required and the impact on an owner’s financial structure•Limited government support at both state and federal levels•Additional safety systems in reaction to the Fukashema Nuclear accident in Japan could raise cost.•Potentially significant increases in cost estimates being planned•Delays in NRC review and approval process•Disposition of nuclear waste•Opposition by citizen and environmental groups
Opportunities:Nuclear could become attractive if the U.S. passes a stringent greenhouse gas policy and resolves concerns around nuclear waste and safety.
22
NUCLEAR
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Advanced Boiling Water (Generation III & III+)
The design of the Generation III & III+ reactors has been around for more than 10 years but the technology must still be considered in the “Early Mover” phase since no new construction and operating permit has yet been approved by the NRC.
Eliminated from analysis due to the expectation of commercial deployment beyond the current planning horizon.
Generation IV Generation IV designs are still in the early stages of R&D with no potential deployment before the 2020-2030 time period. Generation IV technology has the potential to reduce nuclear waste and fuel cost.
Eliminated from analysis due to the expectation of commercial deployment beyond the current planning horizon.
Modular Designed A sub-set of the Generation IV these smaller modular reactors offer the potential to reduce total investment cost for a new installation, but is not expected to be available for deployment until 2020 at the earliest.
Retained for detailed analysis. Considering the long-lead time for development and construction the earliest COD for this technology is assumed to be after 2020.
23
ENERGY STORAGE
TECHNOLOGY ASSESSMENT
Background:
Energy storage technologies provide load shifting peak shaving capability for utilities. These technologies are “charged” using lower cost off-peak energy and “discharged” during periods when energy cost or demand are higher. Examples of Energy Storage technologies include pumped storage hydro, battery, flywheel and compressed air energy storage.
Pumped Storage Hydro-
Pumped storage hydro is mature and is one of the two bulk energy storage technologies commercially available.
The potential to use underground reservoirs such as old salt mines offer some opportunities for a limited number of projects in the region, but development cost are high.
Compressed Air Energy Storage-
Compressed air energy storage (“CAES”) is mature and is the second bulk energy storage technology commercially available. CAES can use old underground salt mines as storage mediums for holding compressed air. When needed the compressed air is withdrawn and mixed with a fuel such as natural gas for firing in a combustion turbine. This process reduces fuel requirements by nearly two-thirds compared to conventional combustion turbines.
Flywheel-
Flywheels stores kinetic energy in the form of a spinning mass, a rotor, which can be discharged for peak shaving or backup purposes. Currently flywheels are immature with test units ranging in size from 2-6 kW. Future plans call for scaling up to 25 kW. The discharge rate is a drawback with discharge times of up to one hour.
Battery Storage-
Large scale energy storage using batteries is still a “Developing” technology. Developers need to reduce cost, improve life cycle and reduce the use of hazardous material. Currently battery energy storage cost is high, estimates are around $3,000/kW and most battery types utilize hazardous material that can become combustible when exposed to water requiring additional protection for the battery cells. Battery energy storage may find a niche application assisting wind projects with grid integration issues.
Challenges:
Energy Storage technologies are more capital intensive than traditional technologies and are net energy users. These technologies may find specialized applications such as assisting with grid integration of intermittent renewable resources like wind.
24
ENERGY STORAGE
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Eliminated from analysis due to a lack of sufficient available sites for commercial development.
Pumped Hydro and Underground Pumped Hydro
Pumped hydro is mature with 21.5 GW in operation. The large amount of land resources required along with the proper site elevations make this a highly site specific niche deployment option. Underground pumped storage can offer limited opportunity considering the numerous underground salt caverns in the service area.
Eliminate from analysis because the technology lacks sufficient benefits or sites for widespread deployment.
Compressed Energy Storage
CAES is one of the only bulk energy storage technologies commercially available. High capital cost and acceptable sites limit deployment opportunities.
Eliminate from analysis because the technology lacks sufficient benefits for widespread deployment.
Battery Battery energy storage is a developing technology at the utility scale. Future development is needed to improve cycle life, size, and reduce cost. Useful for grid support and possibly wind integration issues.
Eliminate from analysis because the technology lacks sufficient scale for consideration.
Flywheel Flywheel’s limited capacity size and short discharge duration is not currently attractive for utility grid applications.
25
RENEWABLE GENERATION
TECHNOLOGY ASSESSMENT
Background:
Renewable generation technologies offer the potential to supplement utilities’ traditional generation portfolio. Renewable generation can provide utilities with no or neutral emission generation to assist in reducing greenhouse gas emissions.
Government Policy-
Renewable generation, especially wind power has seen rapid growth over the past decade, due in large part to government subsidies (federal and state) and state mandates often referred to as renewable portfolio standards (“PRSs”). Mandatory RPSs currently exist in about 30 states. The only state RPS in the Entergy utility service area is Texas. RPS usually require a load serving entity to obtain a certain percent of its electricity from renewable sources often utilizing a market mechanism known as renewable energy credits (“RECs”). This technology assessment does not consider government subsidies or requirements.
Wind-
Wind generation is the most mature and prevalent renewable technology. For the U.S. the best wind generation sites are in the Great Plains region of the country.
Manufactures of wind turbines and associated equipment continue working to improve wind plant availability and capacity factors through the use of variable speed turbines, larger turbines, maximized plant layout, and improved control systems.
Biomass-
Biomass is a carbon neutral renewable generation resource utilizing forest and agricultural waste as fuel sources. The dispersed nature of feedstock and large quantities required to fuel a utility scale plant generally limit the capacity of biomass plants to around 50 MW.
Solar-
Solar Photovoltaic (“PV”) employs semiconducting material to convert direct sunlight into electricity. The current generation of solar PV cells have an operating efficiency of 10-20%. Future generations of PV cells need to improve efficiency to better compete with other renewable and traditional generation technologies. Ultimately, the efficiency of solar PV installations are highly dependent on the amount of direct solar radiation making the best site location the western part of the US.
Solar thermal technology concentrates solar radiation using mirrors to heat a medium, such as molten salt, to produce steam and ultimately electricity. Land requirements are large, requiring 4-6 acres per MW of peak capacity or more for lower quality locations. As with solar PV output is highly dependent on the amount of solar radiation with the best site located in the western part of the US.
26
RENEWABLE GENERATION
TECHNOLOGY ASSESSMENT
Geothermal-
Prime geothermal sites with high-grade steam reservoirs have been largely developed, mostly in the pacific coast region. Future projects will depend on water-steam, hot water, or dry rock technologies that are less efficient. Within the region natural deposits of hot brine found in conjunction with oil and gas deposits offer options for geothermal production, albeit, expensive to develop.
Ocean and Tidal Power-
Ocean and Tidal power, both in-stream hydro and ocean wave energy are mostly still in the bench-scale phase of development with few actual operating turbines in service. Time, cost and complexity of the U.S. FERC regulatory process poses a barrier for tidal project developers.
Municipal Solid Waste and Landfill Gas-
Municipal solid waste (“MSW”) projects offer opportunities where sufficient fuel supply can be procured. Based on current estimates a 50 MW MSW facility requires approximately 2,000 tons of solid waste per day for full output. Solid waste projects require large fuels handling systems and substantial processing of solid waste to remove unwanted containments from the fuel prior to burning.
Landfill gas systems collect the naturally occurring methane gas emitted by landfill decay and processes it for burning in small combustion turbines or internal combustion engines. Issues for landfill gas are mainly associated with gas processing which includes the removal of moisture and impurities, compression, and blending the gas to achieve consistent heating values.
Challenges:
The need to meet Renewable Portfolio Standard mandates and fill the potential void left by coal retirements will pose a significant challenge for utilities in the coming years. High capital cost, low efficiencies, and intermittent nature of most renewable technologies will need to be accounted for in the planning and operations of utilities as renewables are deployed as part of generation portfolios.
27
RENEWABLE GENERATION
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Retained for detailed analysis.Biomass Biomass is a mature technology with a carbon neutral footprint. Dispersed nature of feedstock and large fuel requirements limit capacity to around 50 MW per site.
Retain for detailed analysis as an option for the second ten years of the plan horizon.
Solar Photovoltaics Solar PV technology is still maturing. The biggest improvement opportunities are 1) increase efficiency and 2) lower capital cost.
Eliminated from analysis due to lack sufficient potential at this time.
Municipal Solid Waste For MSW technology is mature. However, fuels handling and processing needs to be improved and site capacity is limited.
Eliminated from analysis due to lack of sufficient commercial sites within the region.
Solar Thermal Solar thermal technology is mature. However, most high quality site are not located near the Entergy area and capital cost remains high.
Retained for detailed analysis.Wind Power Wind technology is mature, over 35 GW of capacity installed world-wide. Best site are in the upper Great Plains states so transmission is an issue.
28
RENEWABLE GENERATION
TECHNOLOGY ASSESSMENT
DispositionTechnology Description
Eliminated from analysis due to lack sufficient potential at this time. Niche opportunities may exist in the future.
Landfill Gas The basic firing system for Landfill Gas is a mature technology. The issue for landfill gas is fuel supply is low quality with numerous contaminants that must be removed before use.Most development opportunities are under 10 MW which reduces cost competitiveness.
Eliminated from analysis due to lack sufficient commercial potential at this time within and in close proximity to the Entergy Operating Companies. The Southeast U.S. geological conditions are not well suited for this technology
Geothermal The greatest potential Geothermal generation in the Entergy region rests with the hot brine found in conjunction with oil and gas deposits. These are lower quality resources compared to the pure steam resources found in the West and will cost more to tap and operate.
Eliminated from analysis because the technology lacks sufficient commercial development at this time.
Ocean & Tidal Ocean & Tidal power has seen limited actual operating projects. Both in-stream hydro and ocean wave projects are costly and require FERC regulatory approvals.
29
RESULTS OF SCREEN
TECHNOLOGY ASSESSMENT
SPO Planning Analysis through this Technology Screen has selected certain traditional and renewable generation technology alternatives which may reasonably be expected to meet the Systems primary objectives of cost, risk mitigation, and reliability. For each selected technology Planning Analysis will develop the necessary cost and performance parameter inputs into the detailed modeling used to develop the reference technologies comprising the IRP Portfolio.
SPO Planning Analysis will monitor the technologies eliminated as a result of the initial screen and incorporate changes into future technology assessments and IRPs.
30
CANDIDATE TECHNOLOGIES
TECHNOLOGY ASSESSMENT
The following technologies are being carried forward for development of detailed planning assumptions . . .
Nuclear– Advanced Boiling Water Reactor
Renewable Technologies– Biomass– Wind Power– Solar PV
Pulverized Coal – Supercritical Pulverized Coal
Fluidized Bed– Atmospheric Fluidized Bed
Natural Gas Fired– Combustion Turbine– Combined Cycle– Small Scale Aeroderivative
31
TECHNOLOGY ASSESSMENT
II. Cost & Performance Assumptions
• Review the state of generation technology and identify candidate technologies that may be available to meet long-term needs.
The Technology Landscape
• Develop cost and performance assumptions for candidate technologies.
Cost & Performance Assumptions
• Model cost of candidate technologies across relevant range of operations and assess overall attractiveness including risks.
Detail Modeling
• Summarize conclusions and identify reference technologies to be modeled in IRP portfolio design.
Conclusions
I. II. III. IV.
32
COMBUSTION TURBINES TECHNOLOGY ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units GE 7 FA (.03)
GE 7FA (.03)
GE LM 6000
GE LM 6000
GE LMS 100
GE LMS 100
GE 7FA (.05)
GE 7FA (.05)
First Year Available from Vendor*
(Yr) 1999 1999 2009 2009 2010 2010 2012 2012
Net MW at ISO (59°F) (MW) 172 344 48 290 101 304 219 438
Number of Units (#) 1 2 1 6 1 3 1 2
Typical Development Time
(Yrs.) 1.5 1.5 1 1.5 1 1.5 1.5 1.5
Typical Construction Time
(Yrs.) 1 1 1 1 1 1 1 1
Overnight Cost ($/kW) $850 $800 $1,600 $1,100 $1,400 $1,150 $800 $760
Installed Cost ($/kW) $940 $900 $1,800 $1,200 $1,550 $1,250 $900 $840
Heat Rate (ISO) (Btu/kWh) 9,850 9,850 9,150 9,150 8,400 8,400 9,250 9,250
Typical Capacity Factor (%) 0-30 0-30 0-30 0-30 0-30 0-30 0-30 0-30
Fixed O&M ($/kW-yr) $8.50 $6.00 $16.00 $8.00 $12.00 $8.00 $7.50 $5.50
Variable O&M ($/MWh) $2.00 $2.00 $2.00 $2.00 $2.00 $2.00 $2.00 $2.00
NOx (lbs/MMBtu) 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
SO2 (lbs/MMBtu) 0 0 0 0 0 0 0 0
CO2 (lbs/MMBtu) 118.9 118.9 118.9 118.9 118.9 118.9 118.9 118.9
Hg (lbs/MMBtu) 0 0 0 0 0 0 0 0
Useful Life (Yrs.) 30 30 30 30 30 30 30 30
2012 – 2021 (First Ten Years of Planning Horizon) 2011$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
33
COMBUSTION TURBINES TECHNOLOGY ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units GE LM 6000
GE LM 6000 GE LMS 100 GE LMS 100 GE 7FA.05 GE 7FA.05
First Year Available From Vendor* (Yr) 2009 2009 2011 2011 2012 2012
Net MW at ISO (59°F) (MW) 48 290 101 304 219 438
Number of Units (#) 1 6 1 3 1 2
Typical Development Time (Yrs.) 1 1.5 1 1.5 1.5 1.5
Typical Construction Time (Yrs.) 1 1 1 1 1 1
Overnight Cost ($/kW) $2,122 $1,459 $1,856 $1,525 $1,061 $1,008
Installed Cost ($/kW) $2,388 $1,592 $2,056 $1,658 $1,194 $1,114
Heat Rate (ISO) (Btu/kWh) 9,050 9,050 8,300 8,300 9,250 9,250
Typical Capacity Factor (%) 0-30 0-30 0-30 0-30 0-30 0-30
Fixed O&M ($/kW-yr) $19.50 $9.93 $14.50 $9.75 $9.15 $7.45
Variable O&M ($/MWh) $2.48 $2.48 $2.48 $2.48 $2.48 $2.48
NOx (lbs/MMBtu) 0.03 0.03 0.03 0.03 0.03 0.03
SO2 (lbs/MMBtu) 0 0 0 0 0 0
CO2 (lbs/MMBtu) 118.9 118.9 118.9 118.9 118.9 118.9
Hg (lbs/MMBtu) 0 0 0 0 0 0
Useful Life (Yrs.) 30 30 30 30 30 30
2022 – 2031 (Second Ten Years of Planning Horizon) 2022$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
34
COMBINED CYCLE TECHNOLOGY ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units GE 7FA.03 (2x1)
GE 7FA.05 (2x1)
GE 7FA.03 (1x1)
GE 7FA.05 (1x1) GE 7H
First Year Available from Vendor* (Yr) 1999 2012 1999 2012 2008
Net MW at ISO (59°F) (MW) 502 640 237 290 404
Number of Units (#) 2 2 1 1 1
Typical Development Time (Yrs.) 2 2 2 2 2
Typical Construction Time (Yrs.) 3 3 3 3 3
Overnight Cost ($/kW) $1,200 $1,100 $1,500 $1,350 $1,550
Installed Cost ($/kW) $1,350 $1,350 $1,650 $1,650 $1,700
Heat Rate (ISO) (Btu/kWh) 6,650 6,550 6,800 6,700 6,400
Typical Capacity Factor (%) 65 65 65 65 85
Fixed O&M ($/kW-yr) $15.00 $15.00 $20.00 $20.00 $15.00
Variable O&M ($/MWh) $2.50 $2.50 $2.50 $2.50 $3.50
NOx (lbs/MMBtu) 0.015 0.015 0.015 0.015 0.015
SO2 (lbs/MMBtu) 0 0 0 0 0
CO2 (lbs/MMBtu) 118.9 118.9 118.9 118.9 118.9
Hg (lbs/MMBtu) 0 0 0 0 0
Useful Life (Yrs.) 30 30 30 30 30
2012 – 2021 (First Ten Years of Planning Horizon) 2011$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
35
COMBINED CYCLE TECHNOLOGY ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units GE 7FA.05 (2x1) GE 7FA.05 (1x1) GE 7H
First Year Available from Vendor* (Yr) 2012 2012 2008
Net MW at ISO (59°F) (MW) 640 290 404
Number of Units (#) 2 1 1
Typical Development Time (Yrs.) 2 2 2
Typical Construction Time (Yrs.) 3 3 3
Overnight Cost ($/kW) $1,478 $1814 $2,082
Installed Cost ($/kW) $1,814 $2,217 $2,284
Heat Rate (ISO) (Btu/kWh) 6,550 6,600 6,400
Typical Capacity Factor (%) 65 65 80
Fixed O&M ($/kW-yr) $18.61 $24.82 $18.61
Variable O&M ($/MWh) $3.01 $3.10 $4.34
NOx (lbs/MMBtu) 0.015 0.015 0.015
SO2 (lbs/MMBtu) 0 0 0
CO2 (lbs/MMBtu) 118.9 118.9 118.9
Hg (lbs/MMBtu) 0 0 0
Useful Life (Yrs.) 30 30 30
2022 – 2031 (Second Ten Years of Planning Horizon) 2022$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
36
COAL & NUCLEAR TECHNOLOGIES ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units PC CFB Generation III -Nuclear
First Year Available from Vendor* (Yr) 2008 2006 2006
Size (MW) 800 750 1,310
Number of Units (#) 1 3 1
Typical Development Time (Yrs.) 2 4 5
Typical Construction Time (Yrs.) 4 4 10
Overnight Cost ($/kW) $2,150 $2,500 $5,000
Installed Cost ($/kW) $2,700 $3,300 $7,500
Heat Rate (Btu/kWh) 9,250 10,600 10,200
Typical Capacity Factor (%) 85 85 85
Fixed O&M ($/kW-yr) $40.00 $45.00 $81.54
Variable O&M ($/MWh) $3.50 $10.00 $4.08
NOx (lbs/MMBtu) 0.04 0.039 0
SO2 (lbs/MMBtu) 0.05 0 0
CO2 (lbs/MMBtu) 214 212.6 0
Hg (lbs/MMBtu) 0 0 0
Useful Life (Yrs.) 40 40 40
Although there are a few nuclear projects in development around the U.S., given the long lead time to develop and construct a new nuclear plant Entergy does not believe such a facility could be online prior to 2021 at the earliest.
2012 – 2021 (First Ten Years of Planning Horizon) 2011$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
37
COAL & NUCLEAR TECHNOLOGIES ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units PC w/90% CO2 Removal CFB Generation III -
Nuclear
First Year Available from Vendor* (Yr) 2021 2006 2006
Size (MW) 800 750 1,310
Number of Units (#) 1 3 1
Typical Development Time (Yrs.) 2 4 5
Typical Construction Time (Yrs.) 4 4 10
Overnight Cost ($/kW) $4,922 $3,326 $6,625
Installed Cost ($/kW) $6,020 $4,390 $9,612
Heat Rate (Btu/kWh) 13,100 10,600 10,200
Typical Capacity Factor (%) 85 85 85
Fixed O&M ($/kW-yr) $86.87 $55.84 $101.19
Variable O&M ($/MWh) $9.93 $12.41 $5.06
NOx (lbs/MMBtu) 0.04 0.039 0
SO2 (lbs/MMBtu) 0.02 0 0
CO2 (lbs/MMBtu) 21.4 212.6 0
Hg (lbs/MMBtu) 0 0 0
Useful Life (Yrs.) 40 40 40
Generation IV New Nuclear Commercial Operation dates in the U.S. are not expected before 2030 or later, and therefore are not considered. However, this technology will be monitored and could be incorporated into future Technology Assessments and IRPs especially if it offers significant cost or time to develop and construct savings.
2022 – 2031 (Second Ten Years of Planning Horizon) 2022$
*First year of commercial operation equals First Year Available from Vendor plus construction time.
38
RENEWABLE TECHNOLOGIES ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units Biomass - Stoker Biomass – CFB Wind – On Shore
Wind – Off Shore Solar - PV
First Year Available from Vendor* (Yr) 2000 2006 2010 2011 2011
Size (MW) 50 50 75 120 50
Number of Units (#) 1 1 50 40 1
Typical Development Time (Yrs.) 2 2 1 2 2
Typical Construction Time (Yrs.) 2 3 1 2 1.5
Overnight Cost ($/kW) $3,000 $4,000 $1,850 $2,900 $4,500
Installed Cost ($/kW) $3,400 $4,700 $2,000 $3,500 $5,000
Heat Rate (Btu/kWh) 13,000 11,000 NA NA NA
Typical Capacity Factor (%) 65 85 39 41 20
Fixed O&M ($/kW-yr) $55.00 $70.00 $40.00 $90.00 $20.00
Variable O&M ($/MWh) $7.50 $3.00 $1.00 $1.00 $0.00
NOx (lbs/MMBtu) 0 0 0 0 0
SO2 (lbs/MMBtu) 0 0 0 0 0
CO2 (lbs/MMBtu) 0 0 0 0 0
Hg (lbs/MMBtu) 0 0 0 0 0
Useful Life (Yrs.) 20 30 20 20 20
Does not include any possible cost subsidization. Does not include capacity match cost or flexible capability cost to make intermittent resources consistent with dispatchable resources. Entergy Region refers to the area served by or in close proximity to the Entergy Operating Companies.
2012 – 2021 (First Ten Years of Planning Horizon) 2011$
* Lead times preclude deployment in 2012 or First Year Available from Vendor if later than 2012.
39
RENEWABLE TECHNOLOGIES ASSUMPTIONS
TECHNOLOGY ASSESSMENT
Characteristic Units Biomass – CFB Wind – On Shore Wind – Off Shore Solar - PV
First Year Available from Vendor* (Yr) 2006 2021 2021 2021
Size (MW) 50 75 120 50
Number of Units (#) 1 50 40 1
Typical Development Time (Yrs.) 2 1 2 2
Typical Construction Time (Yrs.) 3 1 2 1.5
Overnight Cost ($/kW) $5,288 $2,356 $3,263 $4,791
Installed Cost ($/kW) $6,214 $2,547 $3,868 $5,428
Heat Rate (Btu/kWh) 11,000 NA NA NA
Typical Capacity Factor (%) 85 45 60 24
Fixed O&M ($/kW-yr) $86.87 $49.64 $111.69 $24.82
Variable O&M ($/MWh) $3.72 $1.24 $1.24 $0.00
NOx (lbs/MMBtu) 0 0 0 0
SO2 (lbs/MMBtu) 0 0 0 0
CO2 (lbs/MMBtu) 0 0 0 0
Hg (lbs/MMBtu) 0 0 0 0
Useful Life (Yrs.) 30 20 20 25
Does not include any possible cost subsidization. Does not include capacity match cost or flexible capability cost to make intermittent resources consistent with dispatchable resources. Entergy Region refers to the area served by or in close proximity to the Entergy Operating Companies.
2022 – 2031 (Second Ten Years of Planning Horizon) 2022$
*First year of commercial operation equals first year available plus construction time.
40
CANDIDATE TECHNOLOGY INSTALLED CAPITAL COST PROJECTIONS (2011-2030)
TECHNOLOGY ASSESSMENT
Installed Capital Cost ($/kW)Installed Capital Cost ($/kW)
Dollars are stated in Nominal values including both Real cost changes and inflation. Does not include any cost subsidization or REC value.
2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022 … 2025… 2030
Combustion Turbines:
CT – 7F $900 $929 $974 $1,004 $1,075 $1,071 $1,076 $1,092 $1,108 $1,142 $1,170 $1,194 $1,267 $1,427
CT – LM6000 $1,200 $1,239 $1,299 $1,338 $1,434 $1,427 $1,435 $1,456 $1,478 $1,522 $1,561 $1,592 $1,689 $1,828
CT – LMS 100 $1,250 $1,291 $1,353 $1,394 $1,493 $1,487 $1,494 $1,517 $1,539 $1,586 $1,626 $1,658 $1,760 $1,943
Combined Cycle:
CCGT – 7F (2x1) $1,350 $1,395 $1,471 $1,524 $1,619 $1,635 $1,643 $1,667 $1,692 $1,734 $1,778 $1,814 $1,925 $2,125
CCGT – 7F (1x1) $1,650 $1,705 $1,798 $1,863 $1,979 $1,998 $2,008 $2,037 $2,068 $2,120 $2,173 $2,217 $2,352 $2,597
CCGT – 7H $1,700 $1,757 $1,853 $1,920 $2,039 $2,059 $2,069 $2,099 $2,130 $2,184 $2,239 $2,284 $2,424 $2,676
Solid Fuel:
PC $2,700 $2,806 $2,959 $3,066 $3,256 $3,338 $3,304 $3,353 $3,402 $3,452 $3,521 $3,592 $3,812 $4,209
PC w/Carbon Capture - - - - - - - - - - $5,902 $6,020 $6,388 $7,053
CFB $3,300 $3,429 $3,616 $3,747 $3,980 $4,079 $4,038 $4,098 $4,158 $4,220 $4,304 $4,390 $4,659 $5,144
Nuclear $7,500 $7,826 $8,043 $8,234 $8,461 $8,599 $8,738 $8,880 $9,057 $9,238 $9,423 $9,612 $10,200 $11,262
Biomass $4,700 $4,856 $5,067 $5,249 $5,658 $5,659 $5,571 $5,682 $5,826 $5,942 $6,092 $6,214 $6,594 $7,281
Wind (On-Shore) $2,000 $2,033 $2,086 $2,072 $2,355 $2,501 $2,399 $2,375 $2,420 $2,478 $2,512 $2,547 $2,656 $2,847
Wind (Off-Shore) $3,500 $3,558 $3,594 $3,511 $3,936 $4,116 $3,883 $3,782 $3,793 $3,822 $3,815 $3,868 $4,033 $4,323
Solar PV $5,000 $5,166 $5,287 $5,371 $5,682 $5,569 $5,371 $5,371 $5,400 $5,400 $5,428 $5,428 $5,428, $5,428
41
TECHNOLOGY ASSESSMENT
III. Detailed Modeling
• Review the state of generation technology and identify candidate technologies that may be available to meet long-term needs.
The Technology Landscape
• Develop cost and performance assumptions for candidate technologies.
Cost & Performance Assumptions
• Model cost of candidate technologies across relevant range of operations and assess overall attractiveness including risks.
Detail Modeling
• Summarize conclusions and identify reference technologies to be modeled in IRP portfolio design.
Conclusions
I. II. III. IV.
42
FUEL AND EMISSIONS ALLOWANCE CREDITS PRICES
TECHNOLOGY ASSESSMENT
Forecasts:
SPO has developed long-term forecasts for relevant fuel prices and emission allowance prices. Because these prices can have a large impact on the viability of competing technologies, where appropriate multiple forecasts have been made in order to see how robust a given technology is relative to its underlying fuel; and emissions allowance price forecasts.
Delivered Natural gas prices:
The technology assessment is based on the SPO Henry Hub natural gas price forecast dated January 19, 2012. Actual delivered gas prices to a specific plant could be a little higher or lower than the Henry Hub price. The Henry Hub, located at Erath Louisiana connects to nine interstate and four intrastate gas pipelines. There are three gas price forecasts cases used in this assessment:
Levelized Nominal Prices for the years 2012-2041Low $4.22/MMBtuReference $6.29/MMBtuHigh $8.46/MMBtu
Levelized Nominal Prices for the years 2022-2051Low $5.57/MMBtuReference $9.08/MMBtuHigh $13.40/MMBtu
Delivered Coal Prices
The technology assessment is based on the SPO Delivered Coal Reference Price forecast January 25, 2012. Actual delivered coal prices to a specific plant could be a little higher or lower than this forecast which is a volume weighted average of delivered coal prices at White Bluff, Independence, Nelson 6 and Entergy’s minority interest at Big Cajun 2, Unit 3. In order to provide for uncertainty in long-term coal prices Low and High Coal Price Forecast were also considered. These alternative forecast were $1.00 (nominal) per MMBtu higher or lower than the Reference Case.
Levelized Nominal Prices for years the 2012-2051 (PRB)Low $2.35 $/MMBtuReference $3.35 $/MMBtuHigh $4.35 $/MMBtu
Levelized Nominal Prices for the years 2022-2061 (PRB)Low $3.16 $/MMBtuReference $4.16 $/MMBtuHigh $5.16 $/MMBtu
43
FUEL AND EMISSIONS ALLOWANCE CREDITS PRICES
TECHNOLOGY ASSESSMENT
Delivered Biomass Prices Delivered Nuclear Fuel Cost
The technology assessment is based on the SPO Delivered Biomass Reference Price forecast June 4, 2010. Actual delivered biomass prices to a specific plant could be higher or lower than this forecast . SPO monitors market prices for biomass and does not believe the outlook for prices has materially changed since the 2010 forecast. The forecast is based on a market survey of Pine Pulpwood Stumpage plus forecast escalations for timber and lumber and general freight trucking through 2020. Prices beyond 2020 are held constant in real terms.
Levelized Nominal Price for the 30 years 2012-2041Reference $3.93/MMBtu
Levelized Nominal Price for the 30 years 2022-2051Reference $4.80/MMBtu
The technology assessment for long-term nuclear fuel cost is based on the SPO Generic Nuclear Fuel forecast dated December 21, 2011. This forecast is derived from a more detailed unit level long-term forecast prepared by Entergy Nuclear’s Fuel Group on August 19, 2011. Due to the relative stability of nuclear fuel cost and the small share of total cost at nuclear plants, High and Low Sensitivity cases are not necessary.
Levelized Nominal Price for the 40 years 2012-2051Reference $1.24/MMBtu
Levelized Nominal Price for the 40 years 2022-2061Reference $1.53/MMBtu
44
FUEL AND EMISSIONS ALLOWANCE CREDITS PRICES
TECHNOLOGY ASSESSMENT
CO2 Price Forecasts
The Technology Assessment ranks technologies under two different states of the world. One state is that resources are not subject to carbon constraints. The second is that resources become subject to meaningful carbon constraints in the future.
The CO2 price forecast used in the Technology Assessment assumes a cap and trade program beginning in 2023 at about $24 per ton nominal and escalating about 7 to 8 percent nominally per year through 2050. The POV assumes that price must rise faster than inflation until global goals of CO2 reduction are reached.
Levelized CO2 Nominal Prices for the years as specified below ($/Short Ton)
2012-2041 (30 Years For Use with CCGT, CT) $13.432022-2051 (30 Years For Use with CCGT, CT) $46.55
2012-2051 (40 Years for use with Coal Plants) $18.402022-2061 (40 Years for use with Coal Plants) $55.32
NOx, SO2 Price Forecasts
The Technology Assessment assumes that the Cross State Air Pollution Rule “CSAPR” as finalized by the Environmental Protection Agency “EPA” in July 2011 with October 2011 EPA proposed modifications survives court challenges. Under CSAPR AR/LA/MS are only subject to seasonal NOx restrictions. While TX is also subject to annual NOx and annual SO2 restrictions, the Technology POV will use the AR/LA/MS rules for its bus bar comparisons. Because the Technology POV focuses on new technologies which are generally lower emitting that older resources, the assumptions around CSAPR rules and allowances prices for covered emissions have only a minor impact around total bus bar cost of various resources. The Technology Assessment does not consider the impacts of EPA’s Acid Rain Program because allowance cost for this program are expected to be zero. Other currently proposed EPA rules that affect the power sector such as the proposed Mercury MACT Rule are not expected to utilize a cap and trade or emissions tax compliance mechanism.
Levelized NOX Nominal Prices for the years as specified below ($/Short Ton)
2012-2041 (30 Years For Use with CCGT, CT) $73.302022-2051 (30 Years For Use with CCGT, CT) $106.97
2012-2051 (40 Years for use with Coal Plants) $77.562022-2061 (40 Years for use with Coal Plants) $110.76
45
CCGT TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
CCGT technology is mature. However, equipment manufactures continue to push incremental technological advances. Among the expected improvements are reductions in heat rate, start up time, and emissions.
Capability:
Factoring in capital cost, heat rate, fuel cost, and operating performance CCGT technology is economically and operationally suited for dispatchable load following duty in the capacity factor range of 25 percent and higher.
Once CCGT technologies such as GE’s “H” class turbines are commercially available CCGTs are expected to be more competitive in a baseload duty applications.
Risk:
CCGT technology is economic across a wide range of operating roles and capacity factors. Favorable economics are based on reasonably low capital cost compared to solid fuel technologies and expected stable natural gas prices.
CCGTs utilizing natural gas as a fuel source emit less greenhouse gases than carbon based solid fuel technologies.
While CCGTs are well suited for dispatchable load following role operational stress may increase maintenance cost from repeated cycling.
46
$75
$85
$95
$105
$115
$125
$135
$145
$155
$165
$175
25% 35% 45% 55% 65% 75% 85%
$/M
Wh
Capacity Factor (%)
CCGT - 2x1 7F CCGT - 1x1 7F CCGT - 1x1 7H
CCGT COST ANALYSISLEVELIZED NOMINAL $ @ 9.25%, 2012-2041
TECHNOLOGY ASSESSMENT
$0 $50 $100 $150
2x1 7F
1x1 7F
1x1 7H
$/MWh @ 65% Capacity Factor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2012-2041Natural Gas - $6.29/MMBtu NOx - $73.30/short tonCO2 - $13.43/short ton SO2 - $0/short ton
47
CT TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
CT technology is mature. As with CCGTs, equipment manufactures are expected to continue to push incremental advances such as improvements in heat rate and lower emissions.
Capability:
High heat rate, compared to CCGT, and higher cost natural gas, compared to solid fuels, combine to make CTs primarily suited for peaking duty roles with a capacity factor range up to 25 percent.
Risk:
CTs are economic for peaking roles based on reasonably low capital cost, short construction lead times, flexible siting options, and low emissions rates.
While suited for a peaking role CT’s heat rates and fuel cost make the technology less economic for dispatchable load following roles.
48
$100
$150
$200
$250
$300
$350
$400
$450
$500
5% 15% 25% 35% 45%
$/M
Wh
Capacity Factor (%)
CT - 7FA CT- LM6000 CT - LMS 100
CT COST ANALYSISLEVELIZED NOMINAL $ @ 9.25% , 2012-2041
TECHNOLOGY ASSESSMENT
$0 $50 $100 $150 $200 $250
CT - 7F
CT -LM6000
CT - LMS100
$/MWh @ 15% Capacity Factor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2012-2041Natural Gas - $6.29/MMBtu NOx - $73.30/short tonCO2 - $13.43/short ton SO2 - $0/short ton
49
SOLID FUEL (PC) TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
Both PC and CFB technologies are mature technologies. Future development will focus on increased boiler efficiency and carbon capture and storage.
Increasing boiler pressure and temperature improves efficiency and reduces emissions. However, these benefits come at an increased cost. The increase in pressure and temperature requires the use of exotic alloys resulting in higher cost to building and operate supercritical and ultra supercritical units.
Capability:
Low fuel cost and high capital cost make these technologies suitable for consideration in baseload applications.
Risk:
Coal’s environmental footprint creates a significant challenge to future deployment of solid fuel burning technologies. In particular, coal fired facilities are high carbon emitters. Absent the development of an economic carbon capture and storage technology future coal deployments will be limited.
The ultimate cost of carbon capture technology is unknown but preliminary estimates including the cost of parasitic load loss are included in this technology assessment. Based on these projections and given the CO2 cost under cap and trade in this analysis (starting at about $24 per short ton in 2023 (nominal dollars) and escalating at about 7% each year until 2050 (with inflation, post 2050) , it would be more economic to purchase allowances than to invest in carbon capture technology.
50
$100$110$120$130$140$150$160$170$180$190$200$210$220
50% 55% 60% 65% 70% 75% 80% 85%
$/M
Wh
Capacity Factor (%)
PC PC w/CCS CFB
SOLID FUEL COST ANALYSIS(LEVELIZED NOMINAL $ @ 9.25% ,2012-2051)
TECHNOLOGY ASSESSMENT
$0 $50 $100 $150 $200
PC
PC w/CCS
CFB
$/MWh @ 85% Capacity Factor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Commodity Cost Input Assumptions40 Year Levelized Nominal Prices Covering Years 2012-2051PRB Coal- $3.35/MMBtu NOx - $77.56/short tonCO2 - $18.40/short ton SO2 - $0/short ton
51
RENEWABLES (INTERMITTENT) TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
Wind turbine technology is the most mature of the Renewable technologies. Future incremental technology improvements will focus on larger turbine size and improved control systems with a goal of achieving capacity factors of nearing 50% in the most attractive wind speed sites. The highest on shore capacity factors achievable in and around the Entergy Operating Companies is expected to be 36% over the 2012-2021 planning horizon and 43% over the 2022-2031 planning horizon. Off shore wind capacity factors are expected to be about 30% and 50% respectively.
Solar PV is an established technology with improvements focused on increasing conversion efficiency and reducing capital cost. Over the next two decades conversion efficiency is expected to improve In the most attractive solar .regions (the Desert Southwest capacity factors currently average 20%. Capacity factor in and around the Entergy Operating Companies are expected to be 13% over the 2012-2021 planning horizon and 16% over the 2022-2031 planning horizon due to lower solar radiation intensity.
Capability:
Intermittent renewable technologies are highly dependent on wind and solar radiation as “fuel” sources and as such are considered “as available” resources providing limited energy and little peak capacity.
Risk:
The intermittent nature of wind and solar PV resources impact planning and operational activities due to the utility’s need to provide back-up and flexible capable resources to support wind and solar PV generation.
Additionally, most suitable sites for wind and solar PV are remote to the region and are expected to require additional transmission resources to deliver the energy. This Technology Assessment does not consider incremental transmission investment spending in its cost estimates.
When comparing intermittent resources to dispatchable resources capacity match up cost and flexible capability cost are included to make economic comparisons meaningful.
52
$100
$300
$500
$700
$900
$1,100
$1,300
$1,500
$1,700
$1,900
5% 10% 15% 20% 25% 30% 35% 39% 45%
$/M
Wh
Capacity Factor (%)
Wind Solar PV
RENEWABLES (INTERMITTENT) COST ANALYSISLEVELIZED NOMINAL $ @ 9.25% , WIND 2012-2031, SOLAR 2012-2036
TECHNOLOGY ASSESSMENT
$0 $100 $200 $300 $400 $500
Wind
Solar PV
$/MWh @ 20% Capacity Factor
Fixed Cost Fuel VOM Matchup Flex. Cap.
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Does not include any cost subsidization or REC price value Include capacity match cost and flexible capability cost to make intermittent resources consistent with dispatchable resources.
53
RENEWABLES (BASELOAD) TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
Biomass technology is mature. Environmental concerns are expected to cause stoker boiler technology to decline in use in favor of CFB technology.
Capability:
With a stable fuel supply biomass units can operate as a baseload resource with capacity factors approaching 80% or more.
Risk:
High capital cost for biomass plants will mean developers will need government incentives to compete with other generation technologies.
Stable fuel supply and/or co-firing with carbon based fuels will improve unit availability.
54
$100
$150
$200
$250
$300
$350
25% 35% 45% 55% 65% 75%
$/M
Wh
Capacity Factor (%)
Biomass (CFB)
RENEWABLES (BASELOAD) COST ANALYSISLEVELIZED NOMINAL @ 9.25% ,2012-2041)
TECHNOLOGY ASSESSMENT
$0 $50 $100 $150
Biomass
$/MWh @ 80% Capacity Factor
Fixed Cost Fuel VOM Matchup Flex. Cap.
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Does not include any cost subsidization or REC price value
Biomass Fuel Cost Assumptions: (30 Year Levelized Nominal 2012-2041)$3.93/MMBtu
55
NUCLEAR TECHNOLOGY
TECHNOLOGY ASSESSMENT
State of Technology:
Nuclear technology is mature, accounting for nearly 20% of U.S. electricity generation. Nuclear generation produces no greenhouse gas emissions and does not rely on fossil fuels there by providing energy security.
Capability:
Nuclear generation’s high capital cost and low operating cost makes it best suited for baseload operations so as to minimize cost on a dollar-per-megawatt-hour basis.
Risk:
Large investment, the potential for significant cost overruns, and long lead times for permitting and construction limit utility interest in nuclear generation.
Delays in NRC review and approval of new construction and operating permits are likely prevent any new nuclear units from completing construction during the first ten years of the planning horizon.
56
$130
$140
$150
$160
$170
$180
$190
$200
$210
65% 70% 75% 80% 85% 90%
$/M
Wh
Capacity Factor (%)
Nuclear
NUCLEAR COST ANALYSISLEVELIZED NOMINAL $ @ 9.25%, 2012-2051
TECHNOLOGY ASSESSMENT
$0 $25 $50 $75 $100 $125 $150
Nuclear
$/MWh @ 90% Capacity Factor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)Screening Curves (2012 COD)Screening Curves (2012 COD)
Fuel Cost Assumptions: (40 Year Levelized Nominal 2012-2051) $1.24/MMBtu
Does not include any cost subsidization.
57
TECHNOLOGY ASSESSMENT
IV. Conclusions
• Review the state of generation technology and identify candidate technologies that may be available to meet long-term needs.
The Technology Landscape
• Develop cost and performance assumptions for candidate technologies.
Cost & Performance Assumptions
• Model cost of candidate technologies across relevant range of operations and assess overall attractiveness including risks.
Detail Modeling
• Summarize conclusions and identify reference technologies to be modeled in IRP portfolio design.
Conclusions
I. II. III. IV.
58
PEAKING GENERATION
TECHNOLOGY ASSESSMENT
Resources operating as Peaking resources should be able start quickly, operate for relatively short periods of time and then shut down on a daily, or intra-day basis. Expectations are that resources serving this role will experience utilization factors of 15% or less.
To be economic, Peaking resources will have relatively low capital cost and higher variable cost. In this case the lower capital cost is spread across fewer megawatt hours (“MWh”). Among the technologies considered CT and CCGT technologies offer the best fit for the peaking role.
Considering the low capital cost, short deployment period, and quick start capability Combustion Turbines, CT, are the preferred technology for new capacity serving in the Peaking role for both the ten year planning period starting in 2012 and the second ten year planning period starting in 2022. Under most peaking roles a CT with General Electric 7F technology (or similar technology from a different vendor ) is preferred due to lower capital cost, on a dollar per kW basis, than aero-derivative CTs.
59
PEAKING GENERATIONLevelized Nominal $ @ 9.25%, 2012-2041
TECHNOLOGY ASSESSMENT
$100
$150
$200
$250
$300
$350
$400
$450
$500
$550
5% 10% 15% 20% 25% 30%
$/M
Wh
Capacity Factor (%)CCGT - 2x1 7F CT - LMS 100 CT - LM6000 CT - 7F
Screening Curves (2012 COD)Screening Curves (2012 COD)
$0
$50
$100
$150
$200
$250
CT - 7FA CT - LM6000 CT - LMS 100 CCGT - 2 7FA$/
MW
h @
15%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2012-2041Natural Gas - $6.29/MMBtu NOx - $73.30/short tonCO2 - $13.43/short ton SO2 - $0/short ton
60
PEAKING GENERATION (SENSITIVITY)LEVELIZED NOMINAL $ @ 9.25%, 2012-2041
TECHNOLOGY ASSESSMENT
$100
$150
$200
$250
$300
$350
$400
$450
$500
$550
5% 10% 15% 20% 25% 30%
$/M
Wh
Capacity Factor (%)CCGT - 2x1 7F CT - LMS 100 CT - LM6000 CT - 7F
High Gas Price Sensitivity (2012 COD)High Gas Price Sensitivity (2012 COD)
$100
$150
$200
$250
$300
$350
$400
$450
$500
$550
5% 10% 15% 20% 25% 30%$/
MW
h
Capacity Factor (%)CCGT - 2x1 7F CT - LMS 100 CT - LM6000 CT - 7F
Low Gas Price Sensitivity (2012 COD)Low Gas Price Sensitivity (2012 COD)
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2012-2041Natural Gas Low- $4.22/MMBtu NOx - $73.30/short tonNatural Gas High- $8.46/MMBtu SO2 - $0/short ton CO2 - $13.43/short ton
61
PEAKING GENERATIONLEVELIZED NOMINAL $ @ 9.25%, 2022-2051
TECHNOLOGY ASSESSMENT
$150
$200
$250
$300
$350
$400
$450
$500
$550
$600
$650
$700
5% 10% 15% 20% 25% 30%
$/M
Wh
Capacity Factor (%)CCGT - 2x1 7F CT - LMS 100 CT - LM6000 CT - 7F
Screening Curves (2022 COD)Screening Curves (2022 COD)
$0
$50
$100
$150
$200
$250
$300
CT - 7FA CT - LM6000 CT - LMS 100 CCGT - 2 7FA$/
MW
h @
15%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2022 COD)Cost Elements (2022 COD)
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2022-2051Natural Gas - $9.08/MMBtu NOx - $106.97/short tonCO2 - $46.55/short ton SO2 - $0/short ton
62
DISPATCHABLE LOAD FOLLOWING GENERATION
TECHNOLOGY ASSESSMENT
Resources operating in the Dispatchable Load Following Role should be to react to the dynamics of ever changing and unpredictable load as well as the physical and mechanical capabilities of other units used to serve load. Expectations are that resources in the Dispatchable Load Following Role will see utilization factors that could range from as low as 20% to as high as 80% with 50% to 65% seen as a typical load factor range.
To be economic, Dispatchable Load Following resources need to have both moderate capital cost and variable cost. Among the technologies considered, CT, CCGT, PC, and CFB technologies offer the best fit for load following.
Factoring in low capital cost, short deployment period, and suitability for the load following, CCGT is the preferred technology for the dispatchable load following role. Additional analysis indicates that CCGT is still the economic under a high gas price scenario. Under most load following roles a CCGT in a 2X1 configuration with General Electric 7FA technology combustion turbines (or similar technology from a different vendor) is preferred due to lower cost and performance than other CCGT Technologies.
63
DISPATCHABLE LOAD FOLLOWING GENERATIONNOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB 40 YEARS)
TECHNOLOGY ASSESSMENT
$50
$100
$150
$200
$250
$300
30% 40% 50% 60% 70% 80%
$/M
Wh
Capacity Factor (%)CT - 7F CCGT -2x1 PC CFB
Screening Curves (2012 COD)Screening Curves (2012 COD)
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
CT - 7FA CCGT - 2x1 PC CFB$/
MW
h @
65%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx SO2
Cost Elements (2012 COD)Cost Elements (2012 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2012-2041)-Natural Gas - $6.29/MMBtuCO2 - $13.43/tonNOX - $73.30/tonSO2 - $0/ton
40 year Levelized Nominal (2012-2051)–Coal - $3.35/MMBtuCO2 - $18.40/tonNOX - $77.56/tonSO2 - $0/ton
64
DISPATCHABLE LOAD FOLLOWING GENERATIONNOMINAL LEVELIZED $ @9.25% OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB 40 YEARS)
TECHNOLOGY ASSESSMENT
$50
$100
$150
$200
$250
$300
30% 40% 50% 60% 70% 80%
$/M
Wh
Capacity Factor (%)CT - 7F CCGT -2x1 PC CFB
Levelized Nominal $ Over Expected Life of Resource
High Gas Price Sensitivity (2012 COD)High Gas Price Sensitivity (2012 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2012-2041) -Natural Gas – (Ref) $6.29/MMBtu
(High) $8.46/MMBtuCO2 - $13.43/tonNOX - $73.30/tonSO2 - $0/ton
40 year Levelized Nominal (2012-2051)–Coal – (Ref) $3.35/MMBtu
(Low) $2.35/MMBtuCO2 - $18.40/tonNOX - $77.56/tonSO2 - $0/ton
No Carbon Cost Sensitivity (2012)No Carbon Cost Sensitivity (2012)
Low Coal Price Sensitivity (2012 COD)Low Coal Price Sensitivity (2012 COD)
$50
$100
$150
$200
$250
$300
30% 40% 50% 60% 70% 80%
$/M
Wh
Capacity Factor (%)CT - 7F CCGT -2x1 PC CFB
Levelized Nominal $ Over Expected Life of Resource
$50
$100
$150
$200
$250
$300
30% 40% 50% 60% 70% 80%
$/M
Wh
Capacity Factor (%)CT - 7F CCGT -2x1 PC CFB
Levelized Nominal $ Over Expected Life of Resource
65
DISPATCHABLE LOAD FOLLOWING GENERATIONNOMINAL LEVELIZED $ @ 9.25 OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB 40 YEARS)
TECHNOLOGY ASSESSMENT
$100
$150
$200
$250
$300
$350
$400
30% 40% 50% 60% 70% 80%
$/M
Wh
Capacity Factor (%)CT - 7F CCGT -2x1 PC CFB
Screening Curves (2022 COD)Screening Curves (2022 COD)
$0
$50
$100
$150
$200
$250
CT - 7FA CCGT - 2x1 PC w/CarbonCap.
CFB$/
MW
h @
65%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx SO2
Cost Elements (2022 COD)Cost Elements (2022 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2022-2051)-Natural Gas - $9.08/MMBtuCO2 - $46.55/tonNOX - $106.97/tonSO2 - $0/ton
40 year Levelized Nominal (2022-2061) –Coal - $4.16/MMBtuCO2 - $55.32/tonNOX - $110.76/tonSO2 - $0/ton
66
BASE LOAD GENERATION
TECHNOLOGY ASSESSMENT
Resources operating in the Base Load Role should be available to serve load most hours of the year. Expectations are that resources in the Base Load will see utilization factors exceeding 85%.
Base Load resources can be expected to cost more to construct but operate at fairly low cost. The combination of capital and operating cost is economic since operating at a high utilization factor allows capital cost to be spread over more MWh. Technologies offering the best fit for the Base Load role are: CCGT, PC, CFB, and nuclear. . In regards to CCGTs a 2x1 configuration with General Electric 7FA technology combustion turbines (or similar technology from a different vendor) is preferred during the first ten year planning period (2012-2021) due to lower cost and performance than other CCGT technologies. However, by the second ten years of the planning period 2022-2031 the GE H Class CCGT in a 2x1 configuration is expected to offer the lowest cost and performance in a base load operating role. In regards to coal PC is generally believed to be lower cost than CFB, however, proximity to alternative fuel sources like petroleum coke more advantages in some settings.
The ideal choice of baseload technology is currently CCGT. Declines in the long-term outlook for natural gas prices has been the biggest single driver.
This technology assessment has stressed that assumption under eighteen different combinations of future natural gas, coal and CO2 prices. In a large majority of cases, including the Reference Case scenarios for these inputs the CCGT is preferred. In the few cases the CCGT was not preferred the cost difference between it and the preferred choice was small.
This technology assessment has stressed that assumption under eighteen different combinations of future natural gas, coal and CO2 prices. In a large majority of cases, including the Reference Case scenarios for these inputs the CCGT is preferred. In the few cases the CCGT was not preferred the cost difference between it and the preferred choice was small.
In addition to lower forecasted total supply cost per MWh CCGTs also offer the following advantages over coal and nuclear resources:
-Lower upfront capital cost-Shorter development and construction time meaning lower financing cost-Easier siting and smaller environmental footprint-Likely to have less environmental group opposition-Shorter payback period in case operating conditions or fuel and emissions allowance cost change.-Able to operate under a wide range of operating roles and contributes to flexible capability
67
BASE LOAD GENERATIONNOMINAL LEVELIZED $ @9.25 OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB/NUCLEAR 40 YEARS)
TECHNOLOGY ASSESSMENT
$75
$100
$125
$150
$175
$200
70% 75% 80% 85% 90% 95%
$/M
Wh
Capacity Factor (%)
CCGT -2x1 CCGT - 7H PC CFB Nuclear
Screening Curves (2012 COD)Screening Curves (2012 COD)
$0
$20
$40
$60
$80
$100
$120
$140
$160
CCGT - 2x1 CCGT - 7H PC CFB Nuclear$/
MW
h @
90%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx SO2
Cost Elements (2012 COD)Cost Elements (2012 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2012-2041)Natural Gas - $6.29/MMBtu CO2 - $13.43/tonNOX - $73.30/tonSO2 - $0/ton
40 year Levelized Nominal (2012-2051) –Coal - $3.35/MMBtuNuclear - $1.24/MMBtuCO2 - $18.40/tonNOX - $77.56/tonSO2 - $0/ton
68
BASE LOAD GENERATION (SENSITIVITIES)NOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB/NUCLEAR 40 YEARS)
TECHNOLOGY ASSESSMENT
$80
$130
$180
70% 80% 90%
$/M
Wh
Capacity Factor (%)CCGT -2x1 CCGT -7H PCCFB Nuclear
High Gas Price Sensitivity (2012 COD)High Gas Price Sensitivity (2012 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2012-2041) -Natural Gas – (Ref) $6.29/MMBtu
(High) $8.46/MMBtuCO2 - $13.43/tonNOX - $73.30/tonSO2 - $0/ton
40 year Levelized Nominal (2012-2051) –Coal – (Ref) $3.35/MMBtu
(Low) $2.35/MMBtuNuclear - $1.24/MMBtuCO2 - $18.40/tonNOX - $77.56/tonSO2 - $0/ton
No Carbon Cost Sensitivity (2012 COD)No Carbon Cost Sensitivity (2012 COD)
Low Coal Price Sensitivity (2012 COD)Low Coal Price Sensitivity (2012 COD)
$50
$100
$150
$200
70% 80% 90%
$/M
Wh
Capacity Factor (%)CCGT -2x1 CCGT -7H PCCFB Nuclear
$50
$100
$150
$200
70% 80% 90%
$/M
Wh
Capacity Factor (%)CCGT -2x1 CCGT -7H PCCFB Nuclear
Levelized Nominal $ Over Expected Life of Resource Levelized Nominal $ Over Expected
Life of Resource
Levelized Nominal $ Over Expected Life of Resource
69
BASE LOAD GENERATIONNOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (CT/CCGT 30 YEARS , PC/CFB/NUCLEAR 40 YEARS)
TECHNOLOGY ASSESSMENT
$100
$125
$150
$175
$200
$225
$250
$275
$300
70% 75% 80% 85% 90% 95%
$/M
Wh
Capacity Factor (%)
CCGT - 7H PC CFB Nuclear
Screening Curves (2022 COD)Screening Curves (2022 COD)
$0
$50
$100
$150
$200
$250
CCGT PC CFB Nuclear$/
MW
h @
90%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2022 COD)Cost Elements (2022 COD)
Commodity Price Assumptions:30 year Levelized Nominal (2022-2051)-Natural Gas - $9.08/MMBtuCO2 - $46.55/tonNOX - $106.97/tonSO2 - $0/ton
40 year Levelized Nominal (2022-2061)–Coal - $4.16/MMBtuNuclear - $1.53/MMBtuCO2 - $55.32/tonNOX - $110.76/tonSO2 - $0/ton
70
RENEWABLES VERSUS CONVENTIONAL GENERATION
TECHNOLOGY ASSESSMENT
In and around the area served by the Entergy Operating Companies absent government subsidies or mandates the cost of power from renewable generation alternatives continues to be above that of a CCGT given Reference Case assumptions. This is currently forecasted to hold true for new resource installations over the next twenty years. This conclusion is made in light of recent and expected future improvements to both CCGT and renewable technologies.
Of the renewable technologies wind power is likely to be the most cost competitive with natural gas fired generation. However, the continued decline in the long-term outlook for natural gas prices has put pressure on wind’s economics relative to natural gas fired resources. The realization that started in late 2008 that shale and other non conventional gas resources would have profound affects on supply and demand fundamentals has had led the power industry to gravitate to CCGT and CTs as the resource of choice.
Furthermore, the current federal political climate has shifted away from supporting renewable technologies. Current federal tax incentives for renewables could expire as soon as year-end 2012.
Finally the outlook for near-term CO2 regulation has also dimmed improving the relative economics of CCGT and CTs versus renewable generation.
71
RENEWABLES VS. CONVENTIONAL (PEAKING)NOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CT, 25 YEARS SOLAR, 20 YEARS WIND)
TECHNOLOGY ASSESSMENT
Screening Curves (2012 COD)Screening Curves (2012 COD)
$0
$100
$200
$300
$400
$500
$600
$700
CT - 7F Wind Solar PV$/
MW
h @
15%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx Matchup Flex Cap
Cost Elements (2012 COD)Cost Elements (2012 COD)
Does not include any cost subsidization or REC price value. Includes capacity match cost and flexible capability cost to make intermittent resources comparable with dispatchable resources.
$100
$350
$600
$850
$1,100
$1,350
$1,600
5% 10% 15% 20% 25% 30% 35% 40%
$/M
Wh
Capacity Factor (%)CT - 7F Wind Solar PV
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2012-2041Natural Gas - $6.29/MMBtu NOx - $73.30/short tonCO2 - $13.43/short ton SO2 - $0/short ton
72
RENEWABLES VS. CONVENTIONAL (PEAKING)NOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CT, 25 YEARS SOLAR, 20 YEARS WIND)
TECHNOLOGY ASSESSMENT
Screening Curves (2022 COD)Screening Curves (2022 COD) Cost Elements (2022 COD)Cost Elements (2022 COD)
Does not include any cost subsidization or REC price value. Includes capacity match cost and flexible capability cost to make intermittent resources comparable with dispatchable resources.
$0
$100
$200
$300
$400
$500
$600
$700
CT - 7F Wind Solar PV$/
MW
h @
15%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx Matchup Flex Cap
$100
$350
$600
$850
$1,100
$1,350
$1,600
$1,850
5% 10% 15% 20% 25% 30% 35% 40% 45%
$/M
Wh
Capacity Factor (%)CT - 7F Wind Solar PV
Commodity Cost Input Assumptions30 Year Levelized Nominal Prices Covering Years 2022-2051Natural Gas - $9.08/MMBtu NOx - $106.97/short tonCO2 - $46.55/short ton SO2 - $0/short ton
73
RENEWABLES VS. CONVENTIONAL GENERATIONNOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CCGT, 25 YEARS SOLAR, 20 YEARS WIND)
TECHNOLOGY ASSESSMENT
$50
$150
$250
$350
$450
$550
15% 25% 35% 45% 55% 65%
$/M
Wh
Capacity Factor (%)CCGT -2x1 Wind Solar PV
Screening Curves (2012 COD)Screening Curves (2012 COD) Cost Elements (2012 COD)Cost Elements (2012 COD)
Does not include any cost subsidization or REC price value. Includes capacity match cost and flexible capability cost to make intermittent resources comparable with dispatchable resources.
$0
$50
$100
$150
$200
$250
$300
$350
$400
$450
$500
CCGT (65% CF) Wind (39% CF) Solar PV (20% CF)$/
MW
h @
Indi
cate
d Ca
paci
ty F
acto
r
Fixed Cost Fuel VOM CO2 NOx Matchup Flex Cap
Capacity Factors for Wind and Solar PV are their expected maximum
capacity factors
Assumptions: 30 Year Levelized Nominal (2012-2041)Natural Gas – $6.29/MMBtu
CO2 - $13.43/tonNOX - $73.30/ton
SO2 - $0/ton
74
RENEWABLES VS. CONVENTIONAL GENERATIONNOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CCGT, 25 YEARS SOLAR, 20 YEARS WIND)
TECHNOLOGY ASSESSMENT
Screening Curves (2022 COD)Screening Curves (2022 COD) Cost Elements (2022 COD)Cost Elements (2022 COD)
Does not include any cost subsidization or REC price value. Includes capacity match cost and flexible capability cost to make intermittent resources comparable with dispatchable resources.
$0
$50
$100
$150
$200
$250
$300
$350
$400
$450
CCGT (65% CF) Wind (45% CF) Solar PV (24% CF)$/
MW
h @
Indi
cate
d Ca
paci
ty F
acto
r
Fixed Cost Fuel VOM CO2 NOx Matchup Flex Cap
Capacity Factors for Wind and Solar PV are their expected maximum
capacity factors
$50
$150
$250
$350
$450
$550
$650
15% 25% 35% 45% 55% 65%
$/M
Wh
Capacity Factor (%)CCGT -2x1 Wind Solar PV
Assumptions: 30 Year Levelized Nominal (2022-2051)Natural Gas - $9.08/MMBtu
CO2 - $46.55/tonNOX - $106.97/ton
SO2 - $0/ton
75
RENEWABLES VS. CONVENTIONAL GENERATIONNOMINAL LEVELIZED $ @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CCGT & BIOMASS CFB)
TECHNOLOGY ASSESSMENT
$50
$75
$100
$125
$150
$175
$200
60% 65% 70% 75% 80% 85%
$/M
Wh
Capacity Factor (%)CCGT -2x1 Biomass
Screening Curves (2012 COD)Screening Curves (2012 COD)
$0
$20
$40
$60
$80
$100
$120
$140
$160
CCGT - 2x1 Biomass$/
MW
h @
75%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx
Cost Elements (2012 COD)Cost Elements (2012 COD)
Does not include any cost subsidization or REC price value. Biomass assumed to be fully dispatchable.
Assumptions: 30 Year Levelized Nominal (2012-2041)Natural Gas – $6.29/MMBtu
Biomass - $3.93/MMBtuCO2 - $13.43/ton
NOX - $73.30/tonSO2 - $0/ton
76
RENEWABLES VS. CONVENTIONAL GENERATIONNOMINAL LEVELIZED @ 9.25% OVER EXPECTED LIFE OF RESOURCE (30 YEARS CCGT & BIOMASS CFB)
TECHNOLOGY ASSESSMENT
Screening Curves (2022 COD)Screening Curves (2022 COD) Cost Elements (2022 COD)Cost Elements (2022 COD)
$100
$125
$150
$175
$200
$225
$250
60% 65% 70% 75% 80% 85%
$/M
Wh
Capacity Factor (%)CCGT -7H Biomass
$0
$20
$40
$60
$80
$100
$120
$140
$160
$180
$200
CCGT - 7H Biomass$/
MW
h @
75%
Cap
acity
Fac
tor
Fixed Cost Fuel VOM CO2 NOx
Does not include any cost subsidization or REC price value. Biomass assumed to be fully dispatchable.
Assumptions: 30 Year Levelized Nominal (2022-2051)Natural Gas – $9.08/MMBtu
Biomass - $4.80/MMBtuCO2 - $46.55/ton
NOX - $106.97/tonSO2 - $0/ton
7777
LEVELIZED COST OF ELECTRICITY FOR VARIOUS TECHNOLOGIES
0
50
100
150
200
250
300
CT-7FA
LM6000
CT-LM
S 100
CC
GT-2 7FA
CT - 7FA
CC
GT - 2x1
CC
GT - 2x1
CC
GT - 7H
PC CFB
Nuclear (G
en III)
Wind (39%
CF)
Solar PV (20% C
F)
Biomass (75%
CF)
Peaking (15% CF) LoadFollowing(65% CF)
Base Load (90% CF) Renewables
Fixed Cost Fuel VOM NOx CO2 Integration
$438
Notes:• Costs not adjusted to
include subsidies (ITC/PTC)• Jan. 2012 Technology
Assessment for 2012 IRP.• Reference case
assumption for newtechnologies ifdeployed in 2012.
• 30-year levelized(2012-2041) cost assumption Nominal $:
– Natural gas $6.29/MMBtu
– Biomass :$3.93/MMBtu– CO2: $13.43/ton– NOx :$73.30/ton– SO2: $0/ton
• 40-year levelized(2012-2051) cost assumption Nominal $:
– Coal: $3.35/MMBtu– Nuclear: $1.24/MMBtu– CO2: $18.40/ton
NOx :$77.56/ton– SO2 :$0/ton
• Useful life:– CCGT, CT & Biomass 30
years– Coal & Nuclear 40 years– Wind 20 years– Solar PV 25 years
$/MWh
TECHNOLOGY ASSESSMENT
78
CONVENTIONAL ALTERNATIVES
TECHNOLOGY ASSESSMENT
182
107
98
55
19
Nuclear
Coal
CCGT w/o CO2
CO2
50
100
150
200
250
300
10% 15% 20% 25% 30% 35% 40% 45% 50% 55% 60%
And in 2022For base load CCGT is low cost alternative now . . .
CT is preferred over CCGT below about 30% Capacity FactorGas Fired CT / CCGT offers Lowest Capital Cost
900 1,350 2,700
7,500
CT CCGT Coal Nuclear
148
85
72
18
6
Nuclear
Coal
CCGT
w/o CO2
CO2
Installed Cost (2011$/kW) $/MWh (2012 Installation)*
Bus Bar Cost $/MWh (90% Capacity Factor)*Bus Bar Cost/MWh (90% Capacity Factor)*
*Bus bar cost levelized in nominal $/MWh over expected life of resource (30 years CCGT & CT, 40 years coal and nuclear). CO2compliance cost begins in 2023 and escalates over time.
CCGT
CT
79
(5)
(6)
(10)
(16)
5
8
10
16
SENSITIVITIES
TECHNOLOGY ASSESSMENT
*Bus bar cost levelized in nominal $/MWh over expected life of resource (30 years CCGT & CT, 40 years coal and nuclear). CO2compliance cost begins in 2023 and escalates over time.
(12)
(13)
0
(6)
12
16
0
6
(3)
(5)
(4)
(22)
3
6
4
22
± 10$/Ton CO2
± 10% Installed Cost
± 50% Fuel Cost
± 10% Capacity Factor
NuclearGas-Fired CCGT Coal
Gas-fired CCGT economics remain favorable across range of assumptions*
65% 90%80%
80
RENEWABLE ALTERNATIVES
TECHNOLOGY ASSESSMENT
*Bus bar cost levelized in nominal $/MWh over expected life of resource (30 years CCGT & CT, 40 years coal and nuclear). CO2compliance cost begins in 2023 and escalates over time.
2022 In Service Date
$308
$123
$141
Solar
Wind
Biomass
$404
$151
$173
Solar
Wind
Biomass
$327
$112
$113
Solar
Wind
Biomass
$438
$137
$138
Solar
Wind
Biomass
$/MWh Without Incentives* $/MWh With Incentives*
$/MWh Without Incentives* $/MWh With Incentives*
CCGT w/o CO2 CCGT with CO2CCGT w/o CO2 CCGT with CO2
CCGT w/o CO2 CCGT with CO2 CCGT w/o CO2 CCGT with CO2